# Fuel Cell Powered AI Data Centers: Projects and Vendors
Source: https://savrn.com/ai-index/categories/fuel-cell-powered-ai-data-centers
Markdown alternate of the page above; the site index is https://savrn.com/llms.txt

---

[SAVRN Index.](https://savrn.com/ai-index)

Explore the IndexCategories

## Data center sites with fuel cell power on record

| # | Developer | Site | State | Capacity | Status | Power arrangement, as recorded | Sources |
| --- | --- | --- | --- | --- | --- | --- | --- |
| 1 | [Alphabet / Google](https://savrn.com/data-center-capital-atlas/company/alphabet) | Project Tembo (formerly Project Jade), Switchgrass Industrial Park | Wyoming | 2,700 MW | approved | Tallgrass Energy to combine energy resources from Black Hills Energy, fuel cells and its power plant to serve the campus | [cowboystatedaily.com](https://cowboystatedaily.com/2026/07/08/google-revealed-as-owner-of-wyomings-largest-data-center-now-project-tembo/)[datacenterknowledge.com](https://www.datacenterknowledge.com/data-center-construction/new-data-center-developments-august-2026)[oilcity.news](https://oilcity.news/business-feature-2/2026/09/11/google-stepping-in-for-crusoe-pitches-700-acre-data-center-campus-to-laramie-county-on-wednesday/) |
| 2 | Volition | Volition data center, former Fingerhut warehouse (4000 E. U.S. 6), Spanish Fork Canyon | Utah | 250 MW | proposed | Self-generated, fuel cell powered; the city amendment requires energy grid isolation; air permits sought from the Utah Division of Air Quality | [msn.com](https://www.msn.com/en-us/news/other/will-a-data-center-join-the-wind-turbines-at-spanish-fork-canyon-the-city-just-cleared-a-path/ar-AA2cTjHM)[sltrib.com](https://www.sltrib.com/news/2026/09/24/spanish-fork-changes-zoning-allow/)[fox13now.com](https://www.fox13now.com/news/local-news/northern-utah/spanish-fork-passes-amendment-opens-door-to-volition-data-center-project) |
| 3 | [Amazon (AWS)](https://savrn.com/data-center-capital-atlas/company/amazon) | AWS data center campus, Scioto Darby Road (Hilliard area) with AEP Ohio fuel cell plant | Ohio |  | under construction | 72.9 MW AEP Ohio fuel cell facility using 228 Bloom Energy units, supplied by natural gas | [msn.com](https://www.msn.com/en-us/news/other/hilliard-withdraws-appeal-of-fuel-cell-power-for-amazon-data-center/ar-AA2cjwCt)[wosu.org](https://www.wosu.org/politics-government/2026-09-16/hilliard-drops-appeal-on-permit-for-natural-gas-fuel-cells-for-data-center) |
| 4 | DataOne | DataOne AI factory campus (Logix Innovation Campus) | Indiana |  | announced | 350 MW of utility power through IMPA plus 175 MW from Bloom Energy natural gas fuel cells, per the project electrical engineer at the 21 September 2026 open house | [clintoncountydailynews.com](https://clintoncountydailynews.com/634943-2/)[jconline.com](https://www.jconline.com/story/news/local/indiana/2026/09/16/french-company-plans-7-5-billion-ai-factory-data-center-in-frankfort/91795708007/)[clintoncountydailynews.com](https://clintoncountydailynews.com/635328-2/) |

Questions this page answers

Which AI data centers are powered by fuel cells?

4 named sites in the SAVRN Capital Atlas record fuel cell generation: Alphabet / Google at Project Tembo (formerly Project Jade), Switchgrass Industrial Park, Wyoming; Volition at Volition data center, former Fingerhut warehouse (4000 E. U.S. 6), Spanish Fork Canyon, Utah; Amazon (AWS) at AWS data center campus, Scioto Darby Road (Hilliard area) with AEP Ohio fuel cell plant, Ohio; DataOne at DataOne AI factory campus (Logix Innovation Campus), Indiana.

Why fuel cells instead of gas turbines?

A fuel cell converts fuel electrochemically, without combustion, so it runs quiet, emits no NOx and can be permitted and sited where a turbine plant cannot. It produces firm baseload rather than variable output, which is what a constant compute load needs.

How does SAVRN use fuel cells?

SAVRN's Proton plant is the on-site baseload for an Atom block: fuel cells sized to the block's 13.2 MW envelope, with grid-forming storage for transients, islanding and black start, so the campus never waits on a utility interconnection queue. Proton is a reference design verified per site; it is described on its solutions page, not ranked against operating sites here.

How much fuel cell capacity is planned nationally?

The permits tracker's EIA-860M read has no planned fuel cell generators on file at the moment.

Keep going

- [SAVRN Proton: fuel-cell power for an Atom block →](https://savrn.com/solutions/fuel-cell-power)
- [Fuel cell versus grid reliability →](https://savrn.com/blog/fuel-cell-vs-grid-reliability)
- [Self-powered and off-grid AI data center companies →](https://savrn.com/ai-index/categories/self-powered-ai-data-center-companies)
- [Permits and power development tracker →](https://savrn.com/data-center-permits-tracker)

The SAVRN reference set

## Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.

Capital Atlas

Who is funding AI data centers: capital providers, named sites, financing transactions, and the blocked-and-delayed record, state by state and company by company.

[Open the atlas →](https://savrn.com/data-center-capital-atlas)

Delay Watchlist

Project-level slippage: named projects, jurisdictional actions, utility and federal dockets, SEC disclosures, and the interconnection queue.

Open the watchlist →

Moratorium Tracker

The policy layer: every state measure and local moratorium mapped and cited, with one page per state.

Open the tracker →

Water Tracker

Every federal, state, local and interstate water measure that touches a data center, plus a fifty-state water ledger.

Open the water tracker →

Grid Operator Watchlist

ERCOT, PJM, MISO, CAISO, SPP, NYISO, ISO-NE and FERC: the large-load rules, filings and queue positions that decide whether a site can energize.

Open the watchlist →

Permits and Power Development

Data center and substation permits, large loads in the interconnection queues, and the power plants planned to serve them, refreshed hourly from public records.

Open the permits tracker →

SAVRN Scarcity Tracker

Eleven primary-sourced indicators of AI infrastructure scarcity, one composite index, read against the token index, SAVRN's own cost basis and the frontier ceiling.

Open the scarcity tracker →

Have a specific address? Site Intelligence reads all seven references against one location, county, utility and grid operator included, and cites every finding.

[Check this address →](https://savrn.com/site-intelligence)