# Alaska Data Center Investment Tracker
Source: https://savrn.com/data-center-capital-atlas/alaska
Markdown alternate of the page above; the site index is https://savrn.com/llms.txt

---

Named sites

1

Site-level commitments the atlas records in Alaska

Disclosed capital floor

n.a.

Sum of sites with a stated dollar figure. Sites without one are listed, not counted

Disclosed capacity

100 MW

Sum of sites with a stated megawatt figure

Blocked, delayed or restricted

1

Projects on the capital-at-risk record here

Who is investing

## Who is investing in data centers in Alaska?

The named commitments in Alaska carry no disclosed dollar figure yet. The record is .

Named sites

## Named data center sites in Alaska

Each row is one site-level commitment with its capital provider, the figure the source states, and the status the source gives it. Capital is shown as one compact figure; the verbatim wording is in the row's sources.

| Site | Capital provider | Place | Capital | MW | Status | Sources |
| --- | --- | --- | --- | --- | --- | --- |
| Cook Inlet Subsea-Compute and Infrastructure Hub (East Foreland corridor)FERC notice of accepted preliminary permit application 4 September 2026 (Peninsula Clarion, 14 September 2026) | DeepGreen Cook Inlet SPV LLC | Offshore Nikiski (landing in the Nikiski industrial corridor), Kenai Peninsula Borough | n.a. | 100 | proposed |  |

Capital at risk

## Blocked, delayed or restricted in Alaska

Every project in Alaska on the atlas's capital-at-risk record: the action taken, who took it, and the announced capital affected. Restarts and reversals are recorded with the same weight as blocks.

| Project | Developer | Jurisdiction | Action | Capital | Sources |
| --- | --- | --- | --- | --- | --- |
| Anchorage data center moratoriummoratorium Enacted March 2026 | n.a. | Anchorage | Anchorage, Alaska, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated March 2026. AO 2026-27: defines data centers (20+ MW) in zoning code, restricts to commercial/industrial zones, bans from residential, requires conditional use review, utility capacity statement, landscaping buffers and enclosed power equipment. The measure has no end date by design. | n.a. |  |

Policy context

## What governs a data center in Alaska

The policy layer for Alaska lives in three companion references: the [Alaska Data Center Moratorium Tracker](https://savrn.com/data-center-moratorium-tracker/alaska) for every state measure and local moratorium on record, the [Water Tracker](https://savrn.com/data-center-water-tracker) for the water rules that touch a site, and the [Grid Operator Watchlist](https://savrn.com/data-center-grid-operator-watchlist) for the large-load rules of the RTO or utility that decides whether it can energize.

On the map

## Data centers in Alaska

The US Data Center Map identifies 6 facilities run by 4 operators in Alaska, each one placed from primary sources and listed by city and by operator, with this atlas record beside it.

Alaska data centers

6 facilities · 4 operators

Map, locations, operators, rules

Alaska power and local economy

Generation, utilities and county records

Explore the power supply chain and local conditions behind the build-out

US Data Center Map

Every state, one page each

The national map and the operator directory

Sources

## Sources for Alaska

Every source cited on this page, once each. The full atlas source register is at [Capital Atlas sources](https://savrn.com/data-center-capital-atlas/sources).

- peninsulaclarion.com[Peninsula Clarion](https://www.peninsulaclarion.com/2026/09/14/federal-review-advances-for-subsea-data-center-off-nikiski/)
- adn.com[adn.com](https://www.adn.com/alaska-news/anchorage/2026/03/27/anchorage-assembly-preemptively-adopts-data-center-regulations/)

### Every state, one page each

[Alabama 9 / 21](https://savrn.com/data-center-capital-atlas/alabama)[Alaska 1 / 1](https://savrn.com/data-center-capital-atlas/alaska)[Arizona 11 / 11](https://savrn.com/data-center-capital-atlas/arizona)[Arkansas 2 / 8](https://savrn.com/data-center-capital-atlas/arkansas)[California 10 / 35](https://savrn.com/data-center-capital-atlas/california)[Colorado 6 / 21](https://savrn.com/data-center-capital-atlas/colorado)[Connecticut 0 / 6](https://savrn.com/data-center-capital-atlas/connecticut)[Delaware 0 / 5](https://savrn.com/data-center-capital-atlas/delaware)[Florida 0 / 46](https://savrn.com/data-center-capital-atlas/florida)[Georgia 23 / 57](https://savrn.com/data-center-capital-atlas/georgia)[Hawaii 0 / 0](https://savrn.com/data-center-capital-atlas/hawaii)[Idaho 2 / 2](https://savrn.com/data-center-capital-atlas/idaho)[Illinois 10 / 35](https://savrn.com/data-center-capital-atlas/illinois)[Indiana 14 / 44](https://savrn.com/data-center-capital-atlas/indiana)[Iowa 3 / 22](https://savrn.com/data-center-capital-atlas/iowa)[Kansas 5 / 19](https://savrn.com/data-center-capital-atlas/kansas)[Kentucky 6 / 26](https://savrn.com/data-center-capital-atlas/kentucky)[Louisiana 7 / 3](https://savrn.com/data-center-capital-atlas/louisiana)[Maine 0 / 20](https://savrn.com/data-center-capital-atlas/maine)[Maryland 1 / 22](https://savrn.com/data-center-capital-atlas/maryland)[Massachusetts 0 / 11](https://savrn.com/data-center-capital-atlas/massachusetts)[Michigan 4 / 55](https://savrn.com/data-center-capital-atlas/michigan)[Minnesota 3 / 31](https://savrn.com/data-center-capital-atlas/minnesota)[Mississippi 7 / 5](https://savrn.com/data-center-capital-atlas/mississippi)[Missouri 10 / 25](https://savrn.com/data-center-capital-atlas/missouri)[Montana 1 / 10](https://savrn.com/data-center-capital-atlas/montana)[Nebraska 3 / 16](https://savrn.com/data-center-capital-atlas/nebraska)[Nevada 8 / 12](https://savrn.com/data-center-capital-atlas/nevada)[New Hampshire 0 / 5](https://savrn.com/data-center-capital-atlas/new-hampshire)[New Jersey 4 / 61](https://savrn.com/data-center-capital-atlas/new-jersey)[New Mexico 3 / 10](https://savrn.com/data-center-capital-atlas/new-mexico)[New York 6 / 21](https://savrn.com/data-center-capital-atlas/new-york)[North Carolina 10 / 45](https://savrn.com/data-center-capital-atlas/north-carolina)[North Dakota 6 / 4](https://savrn.com/data-center-capital-atlas/north-dakota)[Ohio 24 / 80](https://savrn.com/data-center-capital-atlas/ohio)[Oklahoma 11 / 20](https://savrn.com/data-center-capital-atlas/oklahoma)[Oregon 1 / 8](https://savrn.com/data-center-capital-atlas/oregon)[Pennsylvania 16 / 42](https://savrn.com/data-center-capital-atlas/pennsylvania)[Rhode Island 0 / 5](https://savrn.com/data-center-capital-atlas/rhode-island)[South Carolina 6 / 20](https://savrn.com/data-center-capital-atlas/south-carolina)[South Dakota 1 / 6](https://savrn.com/data-center-capital-atlas/south-dakota)[Tennessee 6 / 26](https://savrn.com/data-center-capital-atlas/tennessee)[Texas 106 / 35](https://savrn.com/data-center-capital-atlas/texas)[Utah 11 / 12](https://savrn.com/data-center-capital-atlas/utah)[Vermont 0 / 3](https://savrn.com/data-center-capital-atlas/vermont)[Virginia 33 / 50](https://savrn.com/data-center-capital-atlas/virginia)[Washington 9 / 22](https://savrn.com/data-center-capital-atlas/washington)[Washington, DC 0 / 0](https://savrn.com/data-center-capital-atlas/washington-dc)[West Virginia 4 / 3](https://savrn.com/data-center-capital-atlas/west-virginia)[Wisconsin 4 / 45](https://savrn.com/data-center-capital-atlas/wisconsin)[Wyoming 11 / 5](https://savrn.com/data-center-capital-atlas/wyoming)

Figures beside each state are named sites and blocked, delayed or restricted projects.

Part of the [North American Data Center Capital Atlas](https://savrn.com/data-center-capital-atlas), refreshed every Tuesday, Thursday and Saturday. Announced commitments overlap one another and overlap reported capital expenditure, so this page shows disclosed floors and never adds them into a single deployment figure. Informational, not investment or legal advice.

The SAVRN reference set

## Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.

Delay Watchlist

Project-level slippage: named projects, jurisdictional actions, utility and federal dockets, SEC disclosures, and the interconnection queue.

[Open the watchlist →](https://savrn.com/data-center-delay-tracker)

Moratorium Tracker

The policy layer: every state measure and local moratorium mapped and cited, with one page per state.

Open the tracker →

Water Tracker

Every federal, state, local and interstate water measure that touches a data center, plus a fifty-state water ledger.

Open the water tracker →

Grid Operator Watchlist

ERCOT, PJM, MISO, CAISO, SPP, NYISO, ISO-NE and FERC: the large-load rules, filings and queue positions that decide whether a site can energize.

Open the watchlist →

Permits and Power Development

Data center and substation permits, large loads in the interconnection queues, and the power plants planned to serve them, refreshed hourly from public records.

Open the permits tracker →

SAVRN Scarcity Tracker

Eleven primary-sourced indicators of AI infrastructure scarcity, one composite index, read against the token index, SAVRN's own cost basis and the frontier ceiling.

Open the scarcity tracker →

Have a specific address? Site Intelligence reads all seven references against one location, county, utility and grid operator included, and cites every finding.

[Check an address →](https://savrn.com/site-intelligence)