# Brookfield Data Center Capex and Sites
Source: https://savrn.com/data-center-capital-atlas/company/brookfield
Markdown alternate of the page above; the site index is https://savrn.com/llms.txt

---

Named sites

2

Site-level commitments the atlas ties to Brookfield (BAM / Brookfield Infrastructure Partners)

Disclosed site capital

$110B

Sum of named sites with a stated dollar figure. Not a capex total; see the spending table

Disclosed capacity

2,300 MW

Sum of named sites with a stated megawatt figure

Financing transactions

12

Transactions naming Brookfield (BAM / Brookfield Infrastructure Partners) or tied to one of its sites

Spending

## Reported and guided spending

Audited, reported and guided figures as the filing or release states them. Reported lines are what was spent; guidance is what management said it expects. They are shown side by side and never combined.

| Period | Kind | Amount | As stated | Sources |
| --- | --- | --- | --- | --- |
| May 2026 disclosure | backlog | $9.6B | BIP capital backlog $9.6 billion; enterprise value $64 billion |  |
| 2026 | aum | ≥$1.00T | BAM AUM over $1 trillion (cited in NVIDIA financing-partner announcement and French commitment release) |  |
| next three years (per disclosure) | guidance | n.a. | plans to build roughly 1GW of data center capacity over three years; more than 485MW operating plus 775MW contracted, exceeding 1.25GW |  |

Named sites

## Where Brookfield (BAM / Brookfield Infrastructure Partners) builds

Kentucky

1 site · $100B disclosed

Open the Kentucky investment tracker →

Mississippi

1 site · $10.0B disclosed

Open the Mississippi investment tracker →

| Site | State | Place | Capital | MW | Status | Sources |
| --- | --- | --- | --- | --- | --- | --- |
| Paducah American Energy Hubwith Brookfield, NextEra Energy, US Department of Energy, Big Rivers Electric Power Corporation, Jackson Purchase Energy Cooperative, Paducah Power System | [Kentucky](https://savrn.com/data-center-capital-atlas/kentucky) | Paducah, McCracken County | ≥$100B | 1,800 | announced |  |
| Compass Datacenters Meridian hyperscale campuswith Ontario Teachers' Pension Plan | [Mississippi](https://savrn.com/data-center-capital-atlas/mississippi) | Meridian, Lauderdale County | $10.0B | 500 | announced |  |

Financing

## Financing transactions

Transactions that name Brookfield (BAM / Brookfield Infrastructure Partners) as a party or attach to one of its named sites. Amounts are as stated; overlapping commitments are never summed.

| Parties | Instrument | Amount | Date | Site | Sources |
| --- | --- | --- | --- | --- | --- |
| Nvidia + Apollo + BlackRock + Blackstone + Brookfield + Goldman Sachs + KKROn August 10, 2026 Nvidia announced strategic partnerships with Apollo, BlackRock, Blackstone, Brookfield, Goldman Sachs and KKR to establish AI compute infrastructure financing platforms intended to mobilize over $500 billion of third-party capital over time. | platform | ≥$500B | August 10, 2026 | n.a. |  |
| US Department of Energy + Brookfield + NextEra Energy + Big Rivers Electric Power Corporation + Jackson Purchase Energy Cooperative + Paducah Power SystemThe US Department of Energy selected Brookfield to develop and operate a 1.8 GW AI data center campus on federally owned land at the Paducah Gaseous Diffusion Plant in western Kentucky, with NextEra Energy building and owning the generation and storage. Brookfield leases approximately 600 acres on the site. Reported as the largest economic development project in Kentucky's history. | platform | $100B | Announced 29-30 July 2026 | Paducah American Energy Hub (KY) |  |
| United States Government + Westinghouse Electric Company + Brookfield Asset Management + Cameco CorporationThe United States Government announced a strategic partnership with Westinghouse and its owners Brookfield Asset Management and Cameco to deploy a fleet of AP1000 reactors, with a minimum aggregate value of $80 billion. Reporting on the terms describes a government participation interest entitling it to 20% of cash distributions above $17.5 billion following issuance. Westinghouse cited 45,000 manufacturing and engineering jobs per two-unit project across 43 states. | platform | ≥$80.0B | Announced 28 October 2025 | n.a. |  |
| Brookfield + Data4Brookfield's French commitment sits within a global AI infrastructure initiative of $100 billion and a dedicated AI infrastructure fund of $10 billion; the €10 billion increase is corroborated by Baxtel. | platform | ~$34.0B | initial €20 billion commitment subsequently raised by €10 billion | n.a. |  |
| Brookfield Infrastructure + Ontario Teachers' Pension Plan + RedBird Capital Partners + Azrieli Group + RedBird Capital Partners (seller) + Azrieli Group (seller)OTPP co-acquired Compass Datacenters with Brookfield Infrastructure from RedBird Capital Partners and Azrieli Group in June 2023. Reuters put the deal at approximately $5.5 billion. | acquisition | ~$5.5B | June 2023 | n.a. |  |
| Brookfield + Bloom EnergyBrookfield agreed to invest up to $5 billion to deploy Bloom Energy solid oxide fuel cell systems as onsite generation for AI data centers globally. Bloom stated it had deployed 1.5 GW across more than 1,200 installations at the time of announcement, with systems already operating at American Electric Power, Equinix and Oracle facilities. | platform | ~$5.0B | Announced 13 October 2025 | n.a. |  |
| NVIDIA + Brookfield Artificial Intelligence Infrastructure Fund + Kuwait Investment AuthorityBloomberg reported on 17 September 2026 that investor documents show NVIDIA committed $2 billion to the Brookfield Artificial Intelligence Infrastructure Fund, revealing the size of a previously disclosed investment. The fund targets $10 billion, has NVIDIA and the Kuwait Investment Authority as anchor investors, and invests globally in AI factories, dedicated behind-the-meter power and compute infrastructure. The commitment is a fund pledge, not deployed North American capital | fund commitment | $2.0B | Reported 17 September 2026 from investor documents. Reported by Bloomberg | n.a. |  |
| Brookfield Infrastructure + Cyxtera + EvoqueBrookfield acquired substantially all of Cyxtera's assets through portfolio company Evoque after Cyxtera's June 2023 Chapter 11; the combined platform was rebranded Centersquare. | acquisition | $1.3B | asset purchase agreement dated November 1, 2023; completed January 16, 2024 | n.a. |  |
| Csquare, Inc. + Brookfield + Morgan Stanley + TD Securities + Wells Fargo Securities + BofA Securities + BMO Capital Markets + ScotiabankBrookfield-backed Csquare priced its NYSE IPO under ticker CSQR. The company runs carrier-neutral colocation and interconnection data centers across U.S., Canadian and U.K. markets. Net proceeds go to repaying debt and offering costs The sale of 50,000,000 shares closed on 17 July 2026 with net proceeds of $1,010.0 million after underwriting discounts, per the company 8-K | equity raise | ~$1.1B | Priced 15 July 2026; closed 17 July 2026 | n.a. |  |
| 5C Group + Brookfield Asset ManagementAI data center developer 5C secured $605 million of debt led by Brookfield Asset Management. 5C said the money will fund acquisition and construction of a campus in Memphis, Tennessee, and development of campuses in Phoenix, Arizona, and Ohio. The company reports more than 1.5 GW in its pipeline | debt facility | $605M | Announced 10 August 2026 | n.a. |  |
| Brookfield + Data4Brookfield acquired France's Data4, covering 31 data centers in six countries. | acquisition | n.a. | 2023 | n.a. |  |
| Brookfield Asset Management + American Real Estate Partners (AREP) + Rothschild & Co (AREP adviser)Brookfield affiliates agreed to buy a minority interest in AREP, a Washington DC-area investor with more than $30 billion deployed or committed. AREP has 32 million square feet of hyperscale data centers in development across the United States | acquisition | n.a. | Announced 14 September 2026; expected to close Q4 2026 | n.a. |  |

The record

## Sourced facts on Brookfield (BAM / Brookfield Infrastructure Partners)

- Cyxtera had filed for Chapter 11 in June 2023; the combined Centersquare platform holds 400MW of capacity and 1.9 million sq ft, with 200MW of potential expansion, 320MW brought to market across more than 50 locations and 100MW of near-term under-roof expansion.
- Brookfield's thesis paper sizes the AI infrastructure opportunity at over $7 trillion over the next decade, split $2T AI factories, $0.5T power and transmission, $4T compute and $0.5T adjacencies.
- Ascenty is a Latin American joint venture with Digital Realty; figures n.a. (page not fetched in this session).
- A specific $10B French AI campus at Cadarache is n.a. on the evidence gathered.
- Compass is co-named on the cancelled PW Digital Gateway, valued at $24.7 billion in blocked/delayed capital.

Sources

## Sources for Brookfield (BAM / Brookfield Infrastructure Partners)

Every source cited on this page, once each. The full atlas source register is at [Capital Atlas sources](https://savrn.com/data-center-capital-atlas/sources).

- lpm.org[Louisville Public Media](https://www.lpm.org/news/2026-07-30/100b-data-center-gas-fired-power-plant-to-be-developed-around-paducah-doe-site)
- power-eng.com[Power Engineering](https://www.power-eng.com/gas/federal-government-to-turn-a-kentucky-uranium-plant-into-an-ai-data-center-and-gas-power-complex/)
- governorreeves.ms.gov[Office of Governor Reeves](https://governorreeves.ms.gov/compass-datacenters-project-generates-10-billion-investment-in-lauderdale-county/)
- nvidianews.nvidia.com[Nvidia Newsroom](https://nvidianews.nvidia.com/news/nvidia-partners-with-apollo-blackrock-blackstone-brookfield-goldman-sachs-and-kkr-to-establish-ai-compute-infrastructure-financing-platforms-to-mobilize-over-500-billion-of-third-party-capital)
- cnbc.com[CNBC](https://www.cnbc.com/2026/08/10/nvidia-wall-street-asset-managers-500-billion-ai-push.html)
- energy.gov[US Department of Energy](https://www.energy.gov/articles/energy-department-announces-partnership-expand-reliable-affordable-energy-access-and-power)
- westinghousenuclear.com[Westinghouse / Brookfield](https://westinghousenuclear.com/strategic-partnership/press-releases/brookfield/)
- utilitydive.com[Utility Dive](https://www.utilitydive.com/news/westinghouse-cameco-brookfield-nuclear/803999/)
- mlq.ai[MLQ](https://mlq.ai/news/brookfield-raises-french-data-center-commitment-to-30b-adding-two-northern-campuses/)
- baxtel.com[Baxtel](https://baxtel.com/news/brookfield-increases-french-data-center-investment-by-10-billion)
- bam.brookfield.com[BAM](https://bam.brookfield.com/press-releases/brookfield-invest-eu20-billion-frances-ai-infrastructure)
- reuters.com[Reuters](https://www.reuters.com/markets/deals/brookfield-canadian-pension-fund-buy-compass-datacenters-2023-06-20/)
- compassdatacenters.com[Compass Datacenters](https://www.compassdatacenters.com/news/brookfield-infrastructure-and-ontario-teachers-to-acquire-compass-datacenters-from-redbird-capital-partners-and-azrieli-group/)
- otpp.com[OTPP](https://www.otpp.com/en-ca/about-us/news-and-insights/2023/brookfield-infrastructure-and-ontario-teachers--to-acquire-compass-datacenters-from-redbird-capital-partners-and-azrieli-group/)
- investor.bloomenergy.com[Bloom Energy investor relations](https://investor.bloomenergy.com/press-releases/press-release-details/2025/Brookfield-and-Bloom-Energy-Announce-5-Billion-Strategic-AI-Infrastructure-Partnership/default.aspx)
- datacenterdynamics.com[DCD](https://www.datacenterdynamics.com/en/news/bloom-energy-signs-5bn-partnership-with-brookfield-to-deploy-fuel-cell-tech-across-ai-data-centers/)
- finance.yahoo.com[Bloomberg via Yahoo Finance](https://finance.yahoo.com/technology/ai/articles/nvidia-committed-2-billion-brookfield-171728893.html)
- mccarthy.ca[McCarthy Tétrault](https://www.mccarthy.ca/en/experience/brookfield-infrastructure-partners-closes-us-1-3b-acquisition-of-cyxtera-technologies-through-its-portfolio-company-evoque-data-center-solutions)
- datacenterdynamics.com[DCD](https://www.datacenterdynamics.com/en/news/brookfield-combines-cyxtera-and-evoque-under-new-centersquare-brand/)
- prnewswire.com[PR Newswire](https://www.prnewswire.com/news-releases/csquare-inc-announces-pricing-of-initial-public-offering-302827109.html)
- sec.gov[SEC Form 424B4 (Csquare)](https://www.sec.gov/Archives/edgar/data/2105398/000110465926084293/tm264837-15_424b4.htm)
- sec.gov[SEC Form 8-K (Csquare)](https://www.sec.gov/Archives/edgar/data/2105398/000110465926084616/tm264837d22_8k.htm)
- datacenterdynamics.com[Data Center Dynamics](https://www.datacenterdynamics.com/en/news/ai-data-center-developer-5c-secures-half-a-billion-dollars-in-new-financing/)
- prnewswire.com[Company press release (5C Group, PR Newswire)](https://www.prnewswire.com/news-releases/5c-secures-more-than-usd-1-4-billion-to-power-north-americas-ai-infrastructure-302847289.html)
- reuters.com[Reuters](https://www.reuters.com/markets/deals/brookfield-agrees-acquire-frances-data-centre-firm-data4-2023-04-11/)
- finance.yahoo.com[Yahoo Finance](https://finance.yahoo.com/real-estate/articles/brookfield-acquire-minority-interest-american-110000521.html)
- bisnow.com[Bisnow](https://www.bisnow.com/news/national/data-center-capital-markets/brookfield-buys-minority-stake-in-hyperscale-data-center-developer-arep)
- bip.brookfield.com[BIP](https://bip.brookfield.com/sites/brookfield-bip-v2/files/Brookfield-BIP-IR-V2/corporate-profile-may-2026.pdf)
- datacenterdynamics.com[DCD](https://www.datacenterdynamics.com/en/news/brookfield-infrastructure-partners-to-develop-nearly-one-gigawatt-of-data-center-capacity-over-the-next-three-years/)
- datacenterfrontier.com[Data Center Frontier](https://www.datacenterfrontier.com/colocation/article/55016615/brookfield-infrastructures-evoque-cyxtera-data-center-collaboration-emerges-as-centersquare)
- brookfield.com[Brookfield](https://www.brookfield.com/sites/default/files/documents/Brookfield_Building_the_Backbone_of_AI.pdf)
- digitalrealty.com[Digital Realty](https://www.digitalrealty.com/about/newsroom/press-releases/122908/digital-realty-announces-closing-of-joint-venture-with-brookfield-infrastructure)
- datacenterwatch.org[DataCenterWatch](https://www.datacenterwatch.org/report)

### Private equity and infrastructure: one page each

[Antin Infrastructure Partners 0](https://savrn.com/data-center-capital-atlas/company/antin)[Apollo Global Management 0](https://savrn.com/data-center-capital-atlas/company/apollo)[Ares Management 2](https://savrn.com/data-center-capital-atlas/company/ares)[BlackRock / GIP / AI Infrastructure Partnership 0](https://savrn.com/data-center-capital-atlas/company/blackrock-gip-aip)[Blackstone 5](https://savrn.com/data-center-capital-atlas/company/blackstone)[Brookfield (BAM / Brookfield Infrastructure Partners) 2](https://savrn.com/data-center-capital-atlas/company/brookfield)[Copenhagen Infrastructure Partners 1](https://savrn.com/data-center-capital-atlas/company/cip)[DigitalBridge 5](https://savrn.com/data-center-capital-atlas/company/digitalbridge)[EQT 1](https://savrn.com/data-center-capital-atlas/company/eqt)[Global Infrastructure Partners (as a distinct platform) 0](https://savrn.com/data-center-capital-atlas/company/gip)[I Squared Capital 0](https://savrn.com/data-center-capital-atlas/company/i-squared)[IPI Partners / Blue Owl 1](https://savrn.com/data-center-capital-atlas/company/ipi-blue-owl)[KKR 3](https://savrn.com/data-center-capital-atlas/company/kkr)[Macquarie Asset Management 1](https://savrn.com/data-center-capital-atlas/company/macquarie-am)[Oaktree Capital Management 1](https://savrn.com/data-center-capital-atlas/company/oaktree)[Pensions & Sovereign Wealth Funds (CalPERS, CPPIB, CDPQ/La Caisse, OTPP, PSP, ADIA, GIC, Mubadala, MGX) 0](https://savrn.com/data-center-capital-atlas/company/pensions-swfs)[Silver Lake 0](https://savrn.com/data-center-capital-atlas/company/silver-lake)[Stonepeak 2](https://savrn.com/data-center-capital-atlas/company/stonepeak)[The Carlyle Group 2](https://savrn.com/data-center-capital-atlas/company/carlyle)

The figure beside each provider is its count of named sites in the atlas.

Part of the [North American Data Center Capital Atlas](https://savrn.com/data-center-capital-atlas), refreshed every Tuesday, Thursday and Saturday. Site commitments overlap reported capital expenditure and overlap one another, so this page shows each figure as its source states it and never adds them into a single deployment number. Informational, not investment advice.

The SAVRN reference set

## Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.

Delay Watchlist

Project-level slippage: named projects, jurisdictional actions, utility and federal dockets, SEC disclosures, and the interconnection queue.

[Open the watchlist →](https://savrn.com/data-center-delay-tracker)

Moratorium Tracker

The policy layer: every state measure and local moratorium mapped and cited, with one page per state.

Open the tracker →

Water Tracker

Every federal, state, local and interstate water measure that touches a data center, plus a fifty-state water ledger.

Open the water tracker →

Grid Operator Watchlist

ERCOT, PJM, MISO, CAISO, SPP, NYISO, ISO-NE and FERC: the large-load rules, filings and queue positions that decide whether a site can energize.

Open the watchlist →

Permits and Power Development

Data center and substation permits, large loads in the interconnection queues, and the power plants planned to serve them, refreshed hourly from public records.

Open the permits tracker →

SAVRN Scarcity Tracker

Eleven primary-sourced indicators of AI infrastructure scarcity, one composite index, read against the token index, SAVRN's own cost basis and the frontier ceiling.

Open the scarcity tracker →

Have a specific address? Site Intelligence reads all seven references against one location, county, utility and grid operator included, and cites every finding.

[Check an address →](https://savrn.com/site-intelligence)