# Compass Datacenters Data Center Capex and Sites
Source: https://savrn.com/data-center-capital-atlas/company/compass-datacenters
Markdown alternate of the page above; the site index is https://savrn.com/llms.txt

---

Named sites

3

Site-level commitments the atlas ties to Compass Datacenters

Disclosed site capital

$326M

Sum of named sites with a stated dollar figure. Not a capex total; see the spending table

Disclosed capacity

180 MW

Sum of named sites with a stated megawatt figure

Financing transactions

4

Transactions naming Compass Datacenters or tied to one of its sites

Spending

## Reported and guided spending

Audited, reported and guided figures as the filing or release states them. Reported lines are what was spent; guidance is what management said it expects. They are shown side by side and never combined.

| Period | Kind | Amount | As stated | Sources |
| --- | --- | --- | --- | --- |
| n.a. | raise | $326M | $326M refinancing on five Red Oak, Texas facilities with Wilmington Trust and KeyBank, maturing 2050 |  |

Named sites

## Where Compass Datacenters builds

Texas

1 site · $326M disclosed

Open the Texas investment tracker →

Illinois

1 site

Open the Illinois investment tracker →

North Carolina

1 site

Open the North Carolina investment tracker →

| Site | State | Place | Capital | MW | Status | Sources |
| --- | --- | --- | --- | --- | --- | --- |
| Compass Red Oak facilitiesmaturing 2050 | [Texas](https://savrn.com/data-center-capital-atlas/texas) | Red Oak | $326M | 180 | operating |  |
| Compass Hoffman Estates brownfield project | [Illinois](https://savrn.com/data-center-capital-atlas/illinois) | Hoffman Estates | n.a. | n.a. | announced |  |
| Compass Statesville project | [North Carolina](https://savrn.com/data-center-capital-atlas/north-carolina) | Statesville | n.a. | n.a. | announced |  |

Financing

## Financing transactions

Transactions that name Compass Datacenters as a party or attach to one of its named sites. Amounts are as stated; overlapping commitments are never summed.

| Parties | Instrument | Amount | Date | Site | Sources |
| --- | --- | --- | --- | --- | --- |
| Compass DatacentersCompass Datacenters priced a green $413 million ABS under series CMDC 2026-2. Only the headline could be read. Collateral, ratings and bookrunners were not visible in the fetched page | abs | $413M | Priced 24 July 2026 per IFR headline | n.a. |  |
| Compass DatacentersAn asset-backed securitization by Compass Datacenters noted alongside its 2023 $5.5 billion value and the $10 billion Meridian campus. | other | $326M | cited as deal context in the KKR-Compass reporting | n.a. |  |
| Compass Datacenters + Wilmington Trust + KeyBankCompass closed a $326M refinancing on five Red Oak, Texas facilities with Wilmington Trust and KeyBank, across 5 data centers and 180 MW. | debt facility | $326M | maturing 2050 | Compass Red Oak facilities (TX) |  |
| KKR + Compass DatacentersKKR agreed to invest in Compass Datacenters, the Brookfield- and OTPP-backed platform. | equity raise | n.a. | agreed December 5, 2025 | n.a. |  |

The record

## Sourced facts on Compass Datacenters

- Compass formally withdrew from the $24.7B Prince William Digital Gateway on April 29, 2026.
- Compass is a named target of organized opposition in Statesville, North Carolina.

Sources

## Sources for Compass Datacenters

Every source cited on this page, once each. The full atlas source register is at [Capital Atlas sources](https://savrn.com/data-center-capital-atlas/sources).

- connectcre.com[Connect CRE](https://www.connectcre.com/stories/compass-datacenters-lands-refi-on-5-red-oak-facilities-to-add-three-more/)
- asreport.americanbanker.com[Asset Securitization Report](https://asreport.americanbanker.com/news/compass-datacenters-raises-326-million-from-five-buildings)
- michaelbommarito.com[Bommarito](https://michaelbommarito.com/wiki/datacenters/risks/cancellations/)
- floridadatacenters.org[Florida Data Centers tracker](https://floridadatacenters.org/news)
- ifre.com[International Financing Review](https://www.ifre.com/deal/securitisation/2459576/abs-compass-data-center-cmdc-2026-2-green-us413m-priced)
- bisnow.com[Bisnow](https://www.bisnow.com/news/national/data-center-capital-markets/kkr-invests-billions-in-portfolio-of-brookfield-backed-compass-datacenters-132236)
- bloomberg.com[Bloomberg](https://www.bloomberg.com/news/articles/2025-12-05/kkr-to-invest-in-assets-of-brookfield-backed-compass-datacenters)
- datacenterfrontier.com[Data Center Frontier](https://www.datacenterfrontier.com/hyperscale/article/55392482/when-buildability-breaks-what-prince-william-and-new-york-signal-for-data-center-development)

### REIT and developer: one page each

[Aligned Data Centers 1](https://savrn.com/data-center-capital-atlas/company/aligned-data-centers)[Cloverleaf Infrastructure 1](https://savrn.com/data-center-capital-atlas/company/cloverleaf-infrastructure)[Cologix 0](https://savrn.com/data-center-capital-atlas/company/cologix)[Compass Datacenters 3](https://savrn.com/data-center-capital-atlas/company/compass-datacenters)[CRG (Clayco) 1](https://savrn.com/data-center-capital-atlas/company/crg-clayco)[CyrusOne 7](https://savrn.com/data-center-capital-atlas/company/cyrusone)[DataBank 4](https://savrn.com/data-center-capital-atlas/company/databank)[Digital Realty Trust 8](https://savrn.com/data-center-capital-atlas/company/digital-realty)[EdgeConneX 0](https://savrn.com/data-center-capital-atlas/company/edgeconnex)[Equinix 2](https://savrn.com/data-center-capital-atlas/company/equinix)[Fermi Inc. (Fermi America) 1](https://savrn.com/data-center-capital-atlas/company/fermi-inc)[Flexential 0](https://savrn.com/data-center-capital-atlas/company/flexential)[H5 Data Centers 2](https://savrn.com/data-center-capital-atlas/company/h5-data-centers)[Iron Mountain 3](https://savrn.com/data-center-capital-atlas/company/iron-mountain)[Novva Data Centers 1](https://savrn.com/data-center-capital-atlas/company/novva-data-centers)[Prime Data Centers 4](https://savrn.com/data-center-capital-atlas/company/prime-data-centers)[QTS Realty Trust (Blackstone) 7](https://savrn.com/data-center-capital-atlas/company/qts-realty-trust)[Rowan Digital Infrastructure 1](https://savrn.com/data-center-capital-atlas/company/rowan-digital-infrastructure)[Sabey Data Centers 3](https://savrn.com/data-center-capital-atlas/company/sabey-data-centers)[SB Energy 4](https://savrn.com/data-center-capital-atlas/company/sb-energy)[STACK Infrastructure 4](https://savrn.com/data-center-capital-atlas/company/stack-infrastructure)[Tract 6](https://savrn.com/data-center-capital-atlas/company/tract)[Vantage Data Centers 7](https://savrn.com/data-center-capital-atlas/company/vantage-data-centers)

The figure beside each provider is its count of named sites in the atlas.

Part of the [North American Data Center Capital Atlas](https://savrn.com/data-center-capital-atlas), refreshed every Tuesday, Thursday and Saturday. Site commitments overlap reported capital expenditure and overlap one another, so this page shows each figure as its source states it and never adds them into a single deployment number. Informational, not investment advice.

The SAVRN reference set

## Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.

Delay Watchlist

Project-level slippage: named projects, jurisdictional actions, utility and federal dockets, SEC disclosures, and the interconnection queue.

[Open the watchlist →](https://savrn.com/data-center-delay-tracker)

Moratorium Tracker

The policy layer: every state measure and local moratorium mapped and cited, with one page per state.

Open the tracker →

Water Tracker

Every federal, state, local and interstate water measure that touches a data center, plus a fifty-state water ledger.

Open the water tracker →

Grid Operator Watchlist

ERCOT, PJM, MISO, CAISO, SPP, NYISO, ISO-NE and FERC: the large-load rules, filings and queue positions that decide whether a site can energize.

Open the watchlist →

Permits and Power Development

Data center and substation permits, large loads in the interconnection queues, and the power plants planned to serve them, refreshed hourly from public records.

Open the permits tracker →

SAVRN Scarcity Tracker

Eleven primary-sourced indicators of AI infrastructure scarcity, one composite index, read against the token index, SAVRN's own cost basis and the frontier ceiling.

Open the scarcity tracker →

Have a specific address? Site Intelligence reads all seven references against one location, county, utility and grid operator included, and cites every finding.

[Check an address →](https://savrn.com/site-intelligence)