# CPP Investments Data Center Capex and Sites
Source: https://savrn.com/data-center-capital-atlas/company/cpp-investments
Markdown alternate of the page above; the site index is https://savrn.com/llms.txt

---

Named sites

1

Site-level commitments the atlas ties to CPP Investments (CPPIB)

Disclosed site capital

n.a.

Sum of named sites with a stated dollar figure. Not a capex total; see the spending table

Disclosed capacity

54 MW

Sum of named sites with a stated megawatt figure

Financing transactions

7

Transactions naming CPP Investments (CPPIB) or tied to one of its sites

Spending

## Reported and guided spending

Audited, reported and guided figures as the filing or release states them. Reported lines are what was spent; guidance is what management said it expects. They are shown side by side and never combined.

| Period | Kind | Amount | As stated | Sources |
| --- | --- | --- | --- | --- |
| as of March 31, 2025 | aum | n.a. | CPP Fund totalled C$714.4 billion (Canadian dollars, no USD figure given) |  |
| as of September 30, 2025 | aum | n.a. | CPP Fund totalled C$777.5 billion (Canadian dollars, no USD figure given) |  |

Named sites

## Where CPP Investments (CPPIB) builds

Ontario

1 site

| Site | State | Place | Capital | MW | Status | Sources |
| --- | --- | --- | --- | --- | --- | --- |
| Cambridge, Ontario hyperscale data centerwith Related Digital, TowerBrook, Ascent | Ontario | Cambridge | n.a. | 54 | construction |  |

Financing

## Financing transactions

Transactions that name CPP Investments (CPPIB) as a party or attach to one of its named sites. Amounts are as stated; overlapping commitments are never summed.

| Parties | Instrument | Amount | Date | Site | Sources |
| --- | --- | --- | --- | --- | --- |
| Equinix + GIC + CPP InvestmentsEquinix agreed to form a greater-than-$15B xScale joint venture with GIC and CPP Investments targeting more than 1.5 GW in the United States, with 750+ MW committed as of the 2025 Analyst Day. | jv equity | $15.0B | agreement announced; as of 2025 Analyst Day $15B planned, ~$6B invested | n.a. |  |
| Ares + CPP InvestmentsAres closed the fund outside North America. | equity raise | $2.4B | n.a. | n.a. |  |
| CPP Investments + EQT + EdgeConneXCPP Investments commitment into the EdgeConneX build-out; Sixth Street took a minority stake in 2024. CPP Investments announced the investment on 3 July 2026 and said the transaction had closed following customary approvals. EdgeConneX plans more than 10 GW of additional data centers | equity raise | $1.8B | Announced and closed 3 July 2026 | n.a. |  |
| CPP Investments + Ares ManagementCPPIB committed $1.3 billion to Ares' US$2.4 billion Japan data center fund. | platform | $1.3B | n.a. in source | n.a. |  |
| CPPIBCPPIB commitment in Ontario recorded in the private capital summary table. | equity raise | n.a. | n.a. | n.a. | n.a. |
| CPP Investments + Related Digital + TowerBrook + AscentCPPIB committed C$225 million of construction financing for a 54MW hyperscale data center in Cambridge, Ontario developed with Related Digital, TowerBrook and Ascent. | debt facility | n.a. | disclosed with CPP Fund at C$714.4 billion as of March 31, 2025 | Cambridge, Ontario hyperscale data center (Ontario) |  |
| CPP Investments + GoodmanCPPIB and Goodman launched an A$14 billion (€8 billion) European data centre partnership with an initial A$3.9 billion (€2.2 billion) commitment, covering 435 MW of primary power and 282 MW of IT load. Disclosed when the CPP Fund totalled C$777.5 billion as of September 30, 2025. | jv equity | n.a. | launched December 23, 2025 | n.a. |  |

The record

## Sourced facts on CPP Investments (CPPIB)

- CPPIB committed C$225 million of construction financing for a 54MW hyperscale data center in Cambridge, Ontario developed with Related Digital, TowerBrook and Ascent.
- CPPIB committed US$1.75 billion to the EQT/EdgeConneX AI data center build-out.
- CPPIB committed $1.3 billion to Ares' US$2.4 billion inaugural Japan data center development fund.
- CPPIB formed a greater than $15 billion Equinix xScale JV with GIC on October 1, 2024.
- On December 23, 2025 CPPIB and Goodman launched an A$14 billion (€8 billion) European data centre partnership with an initial A$3.9 billion (€2.2 billion) commitment, 435 MW of primary power and 282 MW of IT load.

Sources

## Sources for CPP Investments (CPPIB)

Every source cited on this page, once each. The full atlas source register is at [Capital Atlas sources](https://savrn.com/data-center-capital-atlas/sources).

- cppinvestments.com[CPP Investments](https://www.cppinvestments.com/newsroom/cpp-investments-commits-to-225-million-in-construction-financing-for-ontario-data-centre/)
- investor.equinix.com[Equinix](https://investor.equinix.com/news-events/press-releases/detail/1053/equinix-agrees-to-form-greater-than-15b-jv-to-expand)
- d1io3yog0oux5.cloudfront.net[Equinix Analyst Day 2025](https://d1io3yog0oux5.cloudfront.net/_61ce85944b338f3e09395ba2ce8fd459/equinix/files/Equinix_Analyst_Day_2025_Building_Bolder_and_xScale_Kiosk_-_vF.pdf)
- cppinvestments.com[CPP Investments](https://www.cppinvestments.com/newsroom/ares-management-closes-inaugural-us2-4-billion-data-center-development-fund-in-japan/)
- datacenterdynamics.com[DCD](https://www.datacenterdynamics.com/en/news/cpp-investments-to-pump-175-billion-into-eqt-and-edgeconnexs-ai-data-center-build-out/)
- newswire.ca[CPP Investments press release (Canada Newswire)](https://www.newswire.ca/news-releases/cpp-investments-partners-with-eqt-to-support-global-digital-infrastructure-growth-826226428.html)
- investmentexecutive.com[The Canadian Press via Investment Executive](https://www.investmentexecutive.com/news/cpp-investments-spends-2-4b-with-eqt-to-build-ai-infrastructure/)
- cppinvestments.com[CPP Investments](https://www.cppinvestments.com/newsroom/cpp-investments-and-goodman-launch-a14-billion-european-data-centre-partnership/)

### Pension and sovereign wealth: one page each

[ADIA (Abu Dhabi Investment Authority) 0](https://savrn.com/data-center-capital-atlas/company/adia)[CalPERS 0](https://savrn.com/data-center-capital-atlas/company/calpers)[CDPQ / La Caisse 2](https://savrn.com/data-center-capital-atlas/company/cdpq-la-caisse)[CPP Investments (CPPIB) 1](https://savrn.com/data-center-capital-atlas/company/cpp-investments)[GIC 0](https://savrn.com/data-center-capital-atlas/company/gic)[Kuwait Investment Authority 0](https://savrn.com/data-center-capital-atlas/company/kuwait-investment-authority)[MGX 0](https://savrn.com/data-center-capital-atlas/company/mgx)[Mubadala 0](https://savrn.com/data-center-capital-atlas/company/mubadala)[Ontario Teachers' Pension Plan (OTPP) 1](https://savrn.com/data-center-capital-atlas/company/otpp)[PSP Investments 0](https://savrn.com/data-center-capital-atlas/company/psp-investments)[Qatar Investment Authority 0](https://savrn.com/data-center-capital-atlas/company/qatar-investment-authority)[Temasek 0](https://savrn.com/data-center-capital-atlas/company/temasek)

The figure beside each provider is its count of named sites in the atlas.

Part of the [North American Data Center Capital Atlas](https://savrn.com/data-center-capital-atlas), refreshed every Tuesday, Thursday and Saturday. Site commitments overlap reported capital expenditure and overlap one another, so this page shows each figure as its source states it and never adds them into a single deployment number. Informational, not investment advice.

The SAVRN reference set

## Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.

Delay Watchlist

Project-level slippage: named projects, jurisdictional actions, utility and federal dockets, SEC disclosures, and the interconnection queue.

[Open the watchlist →](https://savrn.com/data-center-delay-tracker)

Moratorium Tracker

The policy layer: every state measure and local moratorium mapped and cited, with one page per state.

Open the tracker →

Water Tracker

Every federal, state, local and interstate water measure that touches a data center, plus a fifty-state water ledger.

Open the water tracker →

Grid Operator Watchlist

ERCOT, PJM, MISO, CAISO, SPP, NYISO, ISO-NE and FERC: the large-load rules, filings and queue positions that decide whether a site can energize.

Open the watchlist →

Permits and Power Development

Data center and substation permits, large loads in the interconnection queues, and the power plants planned to serve them, refreshed hourly from public records.

Open the permits tracker →

SAVRN Scarcity Tracker

Eleven primary-sourced indicators of AI infrastructure scarcity, one composite index, read against the token index, SAVRN's own cost basis and the frontier ceiling.

Open the scarcity tracker →

Have a specific address? Site Intelligence reads all seven references against one location, county, utility and grid operator included, and cites every finding.