# Groq Data Center Capex and Sites
Source: https://savrn.com/data-center-capital-atlas/company/groq
Markdown alternate of the page above; the site index is https://savrn.com/llms.txt

---

Named sites

1

Site-level commitments the atlas ties to Groq

Disclosed site capital

$1.5B

Sum of named sites with a stated dollar figure. Not a capex total; see the spending table

Disclosed capacity

n.a.

Sum of named sites with a stated megawatt figure

Financing transactions

6

Transactions naming Groq or tied to one of its sites

Spending

## Reported and guided spending

Groq has no reported or guided spending line in the atlas. Its position is recorded through its named sites, its transactions and its sourced facts below.

Named sites

## Where Groq builds

Saudi Arabia

1 site · $1.5B disclosed

| Site | State | Place | Capital | MW | Status | Sources |
| --- | --- | --- | --- | --- | --- | --- |
| Dammam data centerwith Saudi Arabia | Saudi Arabia | Dammam | $1.5B | n.a. | announced |  |

Financing

## Financing transactions

Transactions that name Groq as a party or attach to one of its named sites. Amounts are as stated; overlapping commitments are never summed.

| Parties | Instrument | Amount | Date | Site | Sources |
| --- | --- | --- | --- | --- | --- |
| Nvidia + GroqNvidia agreed to buy AI chip startup Groq for about $20 billion, structured as an asset purchase with a non-exclusive license, an approximately $20 billion asset purchase. Nvidia held $60.6B cash at end-October per the same report. | acquisition | ~$20.0B | December 24, 2025 | n.a. |  |
| Groq + Saudi ArabiaSaudi commitment tied to a Dammam data center, with approximately $500 million of Saudi contract revenue expected per the later Reuters page. | other | ~$1.5B | announced February 10, 2025 | Dammam data center (Saudi Arabia) |  |
| Groq + Disruptive + BlackRock + Neuberger Berman + Samsung + Cisco + Altimeter + 1789 CapitalRound led by Disruptive with BlackRock, Neuberger Berman, Samsung, Cisco, Altimeter and 1789 Capital participating. | equity raise | $750M | September 17, 2025 | n.a. |  |
| Groq + Disruptive + InfinitumRaise to scale Groq's AI inference cloud business, with 13 data centers and a 200MW target by end-2027. | equity raise | $650M | June 22, 2026 | n.a. |  |
| Groq + BlackRock Private Equity Partners + Cisco + Samsung CatalystRound led by BlackRock Private Equity Partners with Cisco and Samsung Catalyst. | equity raise | $640M | August 2024 | n.a. |  |
| Groq + Disruptive + NvidiaGroq raised $350 million to fund its pivot from AI chip design to operating a cloud of Nvidia systems, following a $650 million round in June 2026. Groq said it operates 13 data centers across North America, Europe, the Middle East and Asia Pacific and intends to scale from 54 MW to more than 200 MW in 2027 | equity | $350M | Announced 17 August 2026 | n.a. |  |

The record

## Sourced facts on Groq

- The two Reuters figures for the Saudi commitment conflict ($1.5 billion originally, '$15 billion' on a later page); the atlas flags the discrepancy in-line and treats $1.5B as originally reported.
- Groq operates 13 data centers with a 200MW target by end-2027, following a December 2025 non-exclusive Nvidia licensing agreement; it had been targeting $500 million of revenue for the year, with approximately $500 million of Saudi contract revenue expected per Reuters.
- Groq's North American data center-level MW and site names beyond the 13-facility/200MW aggregate are n.a.

Sources

## Sources for Groq

Every source cited on this page, once each. The full atlas source register is at [Capital Atlas sources](https://savrn.com/data-center-capital-atlas/sources).

- reuters.com[Reuters](https://www.reuters.com/technology/artificial-intelligence/ai-chip-startup-groq-secures-15-billion-commitment-saudi-arabia-2025-02-10/)
- reuters.com[Reuters](https://www.reuters.com/business/groq-more-than-doubles-valuation-69-billion-investors-bet-ai-chips-2025-09-17/)
- cnbc.com[CNBC](https://www.cnbc.com/2025/12/24/nvidia-buying-ai-chip-startup-groq-for-about-20-billion-biggest-deal.html)
- groq.com[Groq](https://groq.com/newsroom/groq-raises-usd650m-to-scale-its-ai-inference-cloud-business)
- techcrunch.com[TechCrunch](https://techcrunch.com/2026/08/17/groq-raises-350m-to-fuel-its-pivot-from-ai-chips-to-neocloud/)

### NeoCloud and GPU cloud: one page each

[Applied Digital 5](https://savrn.com/data-center-capital-atlas/company/applied-digital)[Bitdeer Technologies Group 2](https://savrn.com/data-center-capital-atlas/company/bitdeer)[Cerebras Systems 6](https://savrn.com/data-center-capital-atlas/company/cerebras)[Cipher Digital Inc. 0](https://savrn.com/data-center-capital-atlas/company/cipher-digital)[Core Scientific 2](https://savrn.com/data-center-capital-atlas/company/core-scientific)[CoreWeave 4](https://savrn.com/data-center-capital-atlas/company/coreweave)[Corvex, Inc. 0](https://savrn.com/data-center-capital-atlas/company/corvex)[Crusoe Energy 5](https://savrn.com/data-center-capital-atlas/company/crusoe-energy)[Fluidstack 2](https://savrn.com/data-center-capital-atlas/company/fluidstack)[Galaxy Digital Inc. 1](https://savrn.com/data-center-capital-atlas/company/galaxy-digital)[Groq 1](https://savrn.com/data-center-capital-atlas/company/groq)[Hut 8 Corp. 1](https://savrn.com/data-center-capital-atlas/company/hut8)[IREN 1](https://savrn.com/data-center-capital-atlas/company/iren)[Lambda (Lambda Labs) 2](https://savrn.com/data-center-capital-atlas/company/lambda)[Nebius Group 4](https://savrn.com/data-center-capital-atlas/company/nebius-group)[Nscale 2](https://savrn.com/data-center-capital-atlas/company/nscale)[Poolside 1](https://savrn.com/data-center-capital-atlas/company/poolside)[SambaNova Systems 0](https://savrn.com/data-center-capital-atlas/company/sambanova)[Sesterce 3](https://savrn.com/data-center-capital-atlas/company/sesterce)[TeraWulf 1](https://savrn.com/data-center-capital-atlas/company/terawulf)[Together AI 0](https://savrn.com/data-center-capital-atlas/company/together-ai)[Voltage Park 6](https://savrn.com/data-center-capital-atlas/company/voltage-park)[Vultr 1](https://savrn.com/data-center-capital-atlas/company/vultr)[WhiteFiber, Inc. 2](https://savrn.com/data-center-capital-atlas/company/whitefiber)

The figure beside each provider is its count of named sites in the atlas.

Part of the [North American Data Center Capital Atlas](https://savrn.com/data-center-capital-atlas), refreshed every Tuesday, Thursday and Saturday. Site commitments overlap reported capital expenditure and overlap one another, so this page shows each figure as its source states it and never adds them into a single deployment number. Informational, not investment advice.

The SAVRN reference set

## Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.

Delay Watchlist

Project-level slippage: named projects, jurisdictional actions, utility and federal dockets, SEC disclosures, and the interconnection queue.

[Open the watchlist →](https://savrn.com/data-center-delay-tracker)

Moratorium Tracker

The policy layer: every state measure and local moratorium mapped and cited, with one page per state.

Open the tracker →

Water Tracker

Every federal, state, local and interstate water measure that touches a data center, plus a fifty-state water ledger.

Open the water tracker →

Grid Operator Watchlist

ERCOT, PJM, MISO, CAISO, SPP, NYISO, ISO-NE and FERC: the large-load rules, filings and queue positions that decide whether a site can energize.

Open the watchlist →

Permits and Power Development

Data center and substation permits, large loads in the interconnection queues, and the power plants planned to serve them, refreshed hourly from public records.

Open the permits tracker →

SAVRN Scarcity Tracker

Eleven primary-sourced indicators of AI infrastructure scarcity, one composite index, read against the token index, SAVRN's own cost basis and the frontier ceiling.

Open the scarcity tracker →

Have a specific address? Site Intelligence reads all seven references against one location, county, utility and grid operator included, and cites every finding.