# Vultr Data Center Capex and Sites
Source: https://savrn.com/data-center-capital-atlas/company/vultr
Markdown alternate of the page above; the site index is https://savrn.com/llms.txt

---

Named sites

1

Site-level commitments the atlas ties to Vultr

Disclosed site capital

$1.0B

Sum of named sites with a stated dollar figure. Not a capex total; see the spending table

Disclosed capacity

50 MW

Sum of named sites with a stated megawatt figure

Financing transactions

2

Transactions naming Vultr or tied to one of its sites

Spending

## Reported and guided spending

Audited, reported and guided figures as the filing or release states them. Reported lines are what was spent; guidance is what management said it expects. They are shown side by side and never combined.

| Period | Kind | Amount | As stated | Sources |
| --- | --- | --- | --- | --- |
| Dec 2025 | guidance | ≥$1.0B | More than $1 billion investment in the Springfield, Ohio 50MW AI cluster |  |

Named sites

## Where Vultr builds

Ohio

1 site · $1.0B disclosed

Open the Ohio investment tracker →

| Site | State | Place | Capital | MW | Status | Sources |
| --- | --- | --- | --- | --- | --- | --- |
| Springfield AI clusterwith AMD | [Ohio](https://savrn.com/data-center-capital-atlas/ohio) | Springfield | ≥$1.0B | 50 | announced |  |

Financing

## Financing transactions

Transactions that name Vultr as a party or attach to one of its named sites. Amounts are as stated; overlapping commitments are never summed.

| Parties | Instrument | Amount | Date | Site | Sources |
| --- | --- | --- | --- | --- | --- |
| Vultr + Hewlett Packard Enterprise + AMDHPE announced at its networking investor day that it secured a $1.2 billion order from Vultr, which it calls the world's largest privately held cloud infrastructure company, to deploy AMD Helios AI Rack by HPE systems with HPE networking hardware and software. The release does not say where the systems will be deployed. | equipment order | $1.2B | Announced 30 September 2026 (HPE release, Form 8-K Exhibit 99.1) | n.a. |  |
| Vultr + LuminArx Capital Management + AMD VenturesFinancing with LuminArx Capital Management and AMD Ventures. | equity raise | $333M | December 2024 | n.a. |  |

The record

## Sourced facts on Vultr

- The atlas notes the brief's '$3.5B Series A' conflates valuation with round size; the December 2024 round was reported at $333 million at a $3.5 billion valuation.
- Anchor customer contract values are n.a. in the fetched record.

Sources

## Sources for Vultr

Every source cited on this page, once each. The full atlas source register is at [Capital Atlas sources](https://savrn.com/data-center-capital-atlas/sources).

- reuters.com[Reuters](https://www.reuters.com/business/vultr-invest-1-billion-ohio-ai-cluster-using-amd-chips-2025-12-02/)
- wvxu.org[WVXU (WYSO)](https://www.wvxu.org/2026-08-14/springfields-1-3b-data-center-brings-economic-hope-and-environmental-skepticism)
- daytondailynews.com[Dayton Daily News](https://www.daytondailynews.com/local/state-local-data-center-tax-breaks-total-billions-for-trillion-dollar-tech-companies/article_61697bd7-06a5-56ae-8d62-ee63177111f4.html)
- sec.gov[HPE release, Form 8-K Exhibit 99.1 (SEC)](https://www.sec.gov/Archives/edgar/data/1645590/000164559026000084/hpenetworkinginvestorday20.htm)
- blogs.vultr.com[Vultr](https://blogs.vultr.com/financing2024)
- wsj.com[WSJ](https://www.wsj.com/articles/cloud-ai-startup-vultr-raises-333-million-at-3-5-billion-valuation-7f35f1a9)

### NeoCloud and GPU cloud: one page each

[Applied Digital 5](https://savrn.com/data-center-capital-atlas/company/applied-digital)[Bitdeer Technologies Group 2](https://savrn.com/data-center-capital-atlas/company/bitdeer)[Cerebras Systems 6](https://savrn.com/data-center-capital-atlas/company/cerebras)[Cipher Digital Inc. 0](https://savrn.com/data-center-capital-atlas/company/cipher-digital)[Core Scientific 2](https://savrn.com/data-center-capital-atlas/company/core-scientific)[CoreWeave 4](https://savrn.com/data-center-capital-atlas/company/coreweave)[Corvex, Inc. 0](https://savrn.com/data-center-capital-atlas/company/corvex)[Crusoe Energy 5](https://savrn.com/data-center-capital-atlas/company/crusoe-energy)[Fluidstack 2](https://savrn.com/data-center-capital-atlas/company/fluidstack)[Galaxy Digital Inc. 1](https://savrn.com/data-center-capital-atlas/company/galaxy-digital)[Groq 1](https://savrn.com/data-center-capital-atlas/company/groq)[Hut 8 Corp. 1](https://savrn.com/data-center-capital-atlas/company/hut8)[IREN 1](https://savrn.com/data-center-capital-atlas/company/iren)[Lambda (Lambda Labs) 2](https://savrn.com/data-center-capital-atlas/company/lambda)[Nebius Group 4](https://savrn.com/data-center-capital-atlas/company/nebius-group)[Nscale 2](https://savrn.com/data-center-capital-atlas/company/nscale)[Poolside 1](https://savrn.com/data-center-capital-atlas/company/poolside)[SambaNova Systems 0](https://savrn.com/data-center-capital-atlas/company/sambanova)[Sesterce 3](https://savrn.com/data-center-capital-atlas/company/sesterce)[TeraWulf 1](https://savrn.com/data-center-capital-atlas/company/terawulf)[Together AI 0](https://savrn.com/data-center-capital-atlas/company/together-ai)[Voltage Park 6](https://savrn.com/data-center-capital-atlas/company/voltage-park)[Vultr 1](https://savrn.com/data-center-capital-atlas/company/vultr)[WhiteFiber, Inc. 2](https://savrn.com/data-center-capital-atlas/company/whitefiber)

The figure beside each provider is its count of named sites in the atlas.

Part of the [North American Data Center Capital Atlas](https://savrn.com/data-center-capital-atlas), refreshed every Tuesday, Thursday and Saturday. Site commitments overlap reported capital expenditure and overlap one another, so this page shows each figure as its source states it and never adds them into a single deployment number. Informational, not investment advice.

The SAVRN reference set

## Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.

Delay Watchlist

Project-level slippage: named projects, jurisdictional actions, utility and federal dockets, SEC disclosures, and the interconnection queue.

[Open the watchlist →](https://savrn.com/data-center-delay-tracker)

Moratorium Tracker

The policy layer: every state measure and local moratorium mapped and cited, with one page per state.

Open the tracker →

Water Tracker

Every federal, state, local and interstate water measure that touches a data center, plus a fifty-state water ledger.

Open the water tracker →

Grid Operator Watchlist

ERCOT, PJM, MISO, CAISO, SPP, NYISO, ISO-NE and FERC: the large-load rules, filings and queue positions that decide whether a site can energize.

Open the watchlist →

Permits and Power Development

Data center and substation permits, large loads in the interconnection queues, and the power plants planned to serve them, refreshed hourly from public records.

Open the permits tracker →

SAVRN Scarcity Tracker

Eleven primary-sourced indicators of AI infrastructure scarcity, one composite index, read against the token index, SAVRN's own cost basis and the frontier ceiling.