# Michigan Data Center Investment Tracker
Source: https://savrn.com/data-center-capital-atlas/michigan
Markdown alternate of the page above; the site index is https://savrn.com/llms.txt

---

Named sites

4

Site-level commitments the atlas records in Michigan

Disclosed capital floor

$23.4B

Sum of sites with a stated dollar figure. Sites without one are listed, not counted

Disclosed capacity

2,340 MW

Sum of sites with a stated megawatt figure

Blocked, delayed or restricted

55

$20.9B of announced capital in those projects

Who is investing

## Who is investing in data centers in Michigan?

The largest disclosed commitments in Michigan are Oracle (Saline Township campus, $16.3B); OpenAI (Stargate) (Stargate Saline Township (Michigan), ~$7.0B); Hyperscale Data (Hyperscale Data Michigan AI data center (Alliance Cloud Services), ≥$70M). Together the 4 named sites here carry a disclosed floor of $23.4B; sites with no dollar figure are listed but not counted.

[Oracle 1 site · $16.3B](https://savrn.com/data-center-capital-atlas/company/oracle)[OpenAI (Stargate) 1 site · $7.0B](https://savrn.com/data-center-capital-atlas/company/openai-stargate)[Alphabet / Google 1 site](https://savrn.com/data-center-capital-atlas/company/alphabet)

Named sites

## Named data center sites in Michigan

Each row is one site-level commitment with its capital provider, the figure the source states, and the status the source gives it. Capital is shown as one compact figure; the verbatim wording is in the row's sources.

| Site | Capital provider | Place | Capital | MW | Status | Sources |
| --- | --- | --- | --- | --- | --- | --- |
| Saline Township campus | [Oracle](https://savrn.com/data-center-capital-atlas/company/oracle)with PIMCO, Related Digital Infrastructure, Blackstone, OpenAI | Saline Township, Washtenaw area | $16.3B | n.a. | announced |  |
| Stargate Saline Township (Michigan)announced October 2025; construction expected to begin early 2026; DTE contract approved December 2025 | [OpenAI (Stargate)](https://savrn.com/data-center-capital-atlas/company/openai-stargate)with Oracle, Related Digital, DTE | Saline Township | ~$7.0B | 1,000 | announced |  |
| Hyperscale Data Michigan AI data center (Alliance Cloud Services)Update announced 17 September 2026; investor day and strategic alternatives, including a possible campus sale, announced 5 October 2026 | Hyperscale Datawith Alliance Cloud Services, Sentinum | Dowagiac, Cass County | ≥$70M | 340 | under construction |  |
| Project Cannoli data center (east of Haggerty Road, north of the I-94 North Service Drive)Preliminary approval February 2026; Google confirmed March 2026; township incentives late May 2026; county incentive veto 25 September 2026, overridden 13-0 on 1 October 2026; DTE contracts approved by the Michigan PSC 1 October 2026; final site plan vote expected 14 October 2026 | [Alphabet / Google](https://savrn.com/data-center-capital-atlas/company/alphabet)with Panattoni (developer), DTE Energy (proposed 2.7 GW renewable and storage portfolio) | Van Buren Township, Wayne County | n.a. | 1,000 | proposed |  |

Capital at risk

## Blocked, delayed or restricted in Michigan

Every project in Michigan on the atlas's capital-at-risk record: the action taken, who took it, and the announced capital affected. Restarts and reversals are recorded with the same weight as blocks.

| Project | Developer | Jurisdiction | Action | Capital | Sources |
| --- | --- | --- | --- | --- | --- |
| Saline Township campusother Oct 2025-2026 | Related Digital / Oracle (Green Chile Ventures LLC) / OpenAI | Washtenaw County | MPSC conditionally approved DTE special contracts (Case U-21990) Dec 18 2025; residents voted against; construction began weeks later. Oracle, OpenAI and Related broke ground on the campus, described as a $16 billion project that would eventually use more than a gigawatt, on 1 June 2026. | $16.0B |  |
| U. Michigan / Los Alamos DCmoratorium Mar 2025-2026; the $100M figure is a state grant, not total project capital | UM / LANL | Ypsilanti | 60-day emergency moratorium; renewed 2026. Ypsilanti City Council passed a resolution opposing the $1.2 billion project, and the Ypsilanti Community Utilities Authority passed a yearlong halt on water and sewer connections for data centers in April 2026. | $1.2B |  |
| Howell Township campusmoratorium Nov 21 2025 | Meta | Livingston County | Six-month moratorium (expired) | $1.0B |  |
| Meta Howell Townshipmoratorium November 20, 2025 | Meta | Howell Township | Township enacted a unanimous six-month moratorium on Nov. 20, 2025 after ~2 hours of public comment. | $1.0B |  |
| Microsoft / Franklin Partners Covenant Parkpaused Dec 1 2025 | Microsoft / Franklin Partners | Township adjacent to Lowell (Kent County) | Estimated $500M-$1B investment over 3-5 years. Site needs rezoning from industrial PUD to light industrial. | $1.0B |  |
| Gotion Green Township plantcancelled Jan 1 2026 | Gotion | Green Township, near Big Rapids | Gotion abandoned its planned Green Township facility after legal challenges, environmental issues, and backlash over the company's China ties; Michigan had committed a $715M incentive package ($175M grants plus a 30-year tax exemption valued at $540M), which the state is now working to recover. | $715M |  |
| Allendale Township data center moratoriummoratorium Enacted June 2026 | n.a. | Allendale Township | Allendale Township, Michigan, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated June 2026. Ordinance 2026-07, one-year moratorium on data centers, battery storage, large-scale solar, and wind farms. Township board voted to study and implement ordinance revisions. The measure runs to 8 June 2027. | n.a. |  |
| Alterra Marshall data center (Brooks Industrial Park)moratorium Moratorium 3 August 2026, 365 days | Alterra Development | City of Marshall | Alterra Development bought 270 acres in Marshall's Brooks Industrial Park in October 2025 for a data center originally planned at about 1 GW with an on-site gas plant, later cut to about 400 MW without the plant. The Marshall City Council approved a 365-day moratorium on 3 August 2026, delaying any approval until at least August 2027. The council cited electricity and water uncertainty, heat discharge, low-frequency noise and proximity to wetlands and a lake. | n.a. |  |
| Ann Arbor Township 12-month data center moratoriummoratorium Passed 16 February 2026; 12 months; single outlet | n.a. | Ann Arbor Township Board of Trustees | The Ann Arbor Township Board of Trustees passed a 12-month moratorium on data centers on Monday 16 February 2026. Supervisor Diane O'Connell said no developer had approached the township and the pause is to study water and electricity impacts. A subcommittee will review the master plan and zoning ordinance, with a report expected in about nine months. | n.a. |  |
| Big Rapids Charter Township data center moratoriummoratorium Enacted February 2026 | n.a. | Big Rapids Charter Township | Big Rapids Charter Township, Michigan, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated February 2026. One-year moratorium on permitting, consideration, approval, location, construction, and installation of data center facilities. The measure runs to 23 February 2027. | n.a. |  |
| Brighton Township data center moratoriummoratorium Adopted, reported 21 September 2026; six-month review period requested | n.a. | Brighton Township Board | Brighton Township adopted a moratorium on new data center applications. Township Manager Brian Vick said it was a housekeeping item, with no project proposed, requested for a six-month period to review an ordinance that does not specifically mention data centers, following Michigan Townships Association guidance. | n.a. |  |
| City of Portage data center moratoriummoratorium Enacted February 2026 | n.a. | City of Portage | City of Portage, Michigan, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated February 2026. In City of Portage, Michigan, Portage enacted a temporary moratorium on data centers and battery energy storage facilities through end of year to allow the city to review zoning rules and potential impacts. A public hearing on new ordinance amendments was scheduled for March 2026, Part of a broader trend of at least 27 Michigan communities pausing data center development. | n.a. |  |
| Dearborn six-month data center moratoriummoratorium Planning Commission recommended after 10 August 2026 hearing; first reading 8 September 2026; adopted 7-0 on 22 September 2026; expected effective October 2026 through end of March 2027 | n.a. | Dearborn City Council | The Dearborn City Council voted 7-0 on 22 September 2026, on second and final reading, to adopt a six-month moratorium on new data centers while the city writes permanent regulations. It is expected to take effect in October and run through the end of March 2027. Applications will still be accepted but forwarded to the legal department, and applicants will be told they must reapply. | n.a. |  |
| Delta County data center moratoriummoratorium Enacted January 2026 | n.a. | Delta County | Delta County, Michigan, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated January 2026. 12-month moratorium on data centers and cryptocurrency mining; county board approved unanimously after planning commission forwarded recommendation; county to develop zoning standards during pause. The measure runs to 23 July 2027. | n.a. |  |
| Dexter Township data center moratoriummoratorium Enacted February 2026 | n.a. | Dexter Township | Dexter Township, Michigan, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated February 2026. Dexter Township adopted a 180-day moratorium on data center applications via Resolution #26-705, joining at least 19 Michigan communities that have paused data center development. Residents and officials raised concerns about massive water and energy demands, potential cost increases for existing ratepayers, and industrialization of rural landscapes. The moratorium gives the township time to study impacts and draft appropriate zoning regulations. | n.a. |  |
| East Lansing data center moratoriummoratorium Enacted August 2026 | n.a. | East Lansing | East Lansing, Michigan, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated August 2026. 6-month extension, unanimous, running to 17 March 2027. Extends the moratorium adopted March 2026, which would have lapsed September 2026. Preemptive, no data center has been proposed in the city; the city's zoning ordinance does not address data centers at all and staff expect to bring draft language in Sep/October 2026. The measure runs to 17 March 2027. | n.a. |  |
| Elmwood Township (Tuscola County) nine-month data center moratoriummoratorium Adopted 18 February 2026; nine months; single outlet | n.a. | Elmwood Township Board | The Elmwood Township Board adopted an ordinance enacting a temporary moratorium on data centers at its regular meeting on 18 February 2026. The proposal called for 12 months, and trustees amended it to nine months before a unanimous roll call vote. The board had tabled the measure at its 21 January 2026 meeting. | n.a. |  |
| Erie Township (Monroe County) limited data center moratoriummoratorium Enacted 10 February 2026 per WKAR tracker of 27 February 2026; single outlet; term not stated | n.a. | Erie Township | WKAR's Michigan data center tracker lists Erie Township as having enacted a limited moratorium on 10 February 2026. The source gives no duration, vote count or project. | n.a. |  |
| Filer Charter Township one-year data center moratoriummoratorium Adopted 2 June 2026; one year; reported 10 August 2026; single outlet | n.a. | Filer Charter Township | Filer Charter Township adopted a one-year moratorium on data center development on 2 June 2026, according to township records cited by the Ludington Daily News. Neighboring Stronach Township separately adopted a six-month moratorium after a landowner discussed a possible data center on about 150 acres. | n.a. |  |
| Flint one-year data center moratoriummoratorium Passed 8 June 2026; one year | n.a. | City of Flint | The Flint City Council passed a one-year moratorium on data centers on 8 June 2026. During the moratorium permits cannot be issued for a data center, and the council required an independent study with public input on its findings. Planning and legal staff are to recommend data center regulations. | n.a. |  |
| Forsyth Township data center moratoriummoratorium Enacted January 2026 | n.a. | Forsyth Township | Forsyth Township, Michigan, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated January 2026. 12-month moratorium on data center construction; board passed at crowded meeting; township lacks data center zoning regulations and has no pending applications. The measure runs to 25 June 2027. | n.a. |  |
| Garfield Township data center and crypto mining moratoriummoratorium Adopted 25 August 2026 | n.a. | Garfield Township, Grand Traverse County | Township trustees voted unanimously on 25 August 2026 to impose a one-year moratorium on data centers and cryptocurrency mining facilities, with an option to extend six months for a maximum of 18 months, while the township updates its zoning ordinance. The moratorium places on hold a small-scale data center proposed on Sybrandt Road. The township board chair stated that no data center regulations have yet been drafted and that the measure was written with legal counsel to be defensible after other Michigan communities saw restrictions challenged in court. | n.a. |  |
| Genoa Township data center and cryptocurrency mining moratorium (extended)moratorium Six-month extension approved 17 August 2026; original adoption date not stated in source; single outlet | n.a. | Genoa Township Board of Trustees | The Genoa Township Board of Trustees on Monday 17 August 2026 approved a one-time, six-month extension of its temporary moratorium on accepting, processing and approving applications for data centers and cryptocurrency mining facilities. The board had earlier adopted a six-month moratorium whose resolution allowed a single six-month extension. Township staff said the extra time is needed to finish a noise study and draft enforceable sound provisions in the zoning ordinance. | n.a. |  |
| Google Project Cannoli county tax incentives and community benefits agreement (Van Buren Township)approved after delay Veto announced 25 September 2026; overridden 13-0 by the Wayne County Commission on 1 October 2026; township final site plan review expected 14 October 2026 | Google (Panattoni developer) | Wayne County Executive | On 25 September 2026 Wayne County Executive Warren Evans vetoed the tax incentives and community benefits agreement the Wayne County Commission had approved for Google's Project Cannoli data center, saying Google pressed the county to act within about two weeks and the process did not allow public input or independent analysis. The veto covers the county incentive and benefits package, not the project itself. Commission Chair Alisha Bell called the package lucrative and said the commission would take it up again the following week. The township's final site plan vote is expected 14 October 2026. On 30 September 2026 Commission Chair Alisha Bell said the commission would take up the Project Cannoli agreements at its 1 October 2026 meeting, without saying what action it would take; overriding the veto of the $125 million in local tax incentives needs a two-thirds vote of the 15-member commission. The county had approved the packages on 15 September 2026. Van Buren Township's planning commission is scheduled to vote on final site approval in October. On Thursday 1 October 2026 the Wayne County Commission overrode County Executive Warren Evans's veto by 13-0, with two commissioners absent (FOX 2 Detroit), giving final county approval to the tax incentive and community benefits package. Commissioners said the vote was not an approval of the data center itself. The Van Buren Township Planning Commission is expected to review the final site plan on 14 October 2026. | n.a. |  |
| Hagar Township (Berrien County) data center moratoriummoratorium Approved 13 July 2026 (reported 16 July 2026); term not stated; single outlet, paywalled | n.a. | Hagar Township Board | The Tri-City Record reported that the Hagar Township board approved a data center moratorium at its meeting on Monday 13 July 2026. The article is behind a paywall, and the duration and vote are not available in the accessible text. | n.a. |  |
| Haring Township six-month data center moratoriummoratorium Approved unanimously, reported 14 July 2026; six months | n.a. | Haring Charter Township | The Haring Township Board of Trustees unanimously approved a six-month moratorium on data center construction in July 2026. Legal consultants advised that an outright exclusionary ban is not allowed in Michigan. The board directed the planning commission to work with counsel on permanent standards such as decommissioning requirements and environmental impact studies. | n.a. |  |
| Hart six-month moratorium on data centers and digital miningmoratorium Adopted 26 May 2026; six months; reported 10 August 2026; single outlet | n.a. | Hart City Council | The Hart City Council unanimously adopted a six-month moratorium on data centers and digital mining uses on 26 May 2026, according to city records cited by the Ludington Daily News. City officials described the action as proactive rather than a response to a specific proposal. | n.a. |  |
| Houghton data center moratoriummoratorium Enacted January 2026 | n.a. | Houghton | Houghton, Michigan, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated January 2026. One-year moratorium on permitting, approval, or installation of data center facilities; city council voted unanimously; no proposals pending but city acted proactively to develop regulations. The measure runs to 9 July 2027. | n.a. |  |
| Huron County data center moratoriummoratorium Enacted January 2026 | n.a. | Huron County | Huron County, Michigan, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated January 2026. Three-year (36-month) moratorium on data centers; planning commission unanimously extended original 6-month proposal to 36 months at April 1 hearing after public demand; county commissioners approved in May; concerns center on farmland preservation and resource use. The measure runs to 27 May 2029. | n.a. |  |
| Kalamazoo one-year data center moratoriummoratorium Resolution adopted August 2026; zoning code moratorium given final approval 5 October 2026; one year from 5 October 2026 | n.a. | Kalamazoo | The City Commission approved a resolution pausing data center development for one year in August 2026; some residents pressed for a permanent ban instead. On 21 September 2026 the commission took up for first reading zoning code changes that write the moratorium into the city's zoning and development code, and set a public hearing and final vote for its next meeting. Assistant City Planner Bobby Durkee said the earlier action was only a resolution and the code change makes the pause enforceable under the zoning code and the state enabling act. WKZO reported that the moratorium is in effect and City Hall is not accepting data center applications. On Monday 5 October 2026 the City Commission held the final public hearing and vote on the zoning code amendment establishing the one-year moratorium on data centers and large battery energy storage systems; Assistant City Planner Bobby Durkee said the one-year clock begins with that approval, and staff will set up a working group to help draft regulations. WZZM reported on 6 October 2026 that Kalamazoo paused data center planning and development for one year. | n.a. |  |
| Lincoln Township data center moratoriummoratorium Enacted June 2026 | n.a. | Lincoln Township | Lincoln Township, Michigan, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated June 2026. 10-month moratorium on data center development. Allows planning commission time to study noise, water and electrical consumption, and community impacts. The measure runs to 11 April 2027. | n.a. |  |
| Lyndon Township data center moratoriummoratorium Enacted May 2026 | n.a. | Lyndon Township | Lyndon Township, Michigan, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated May 2026. Resolution 26-06, 12-month moratorium on issuance of permits, licenses, or approvals for data centers, or until permanent regulations adopted. The measure runs to 22 May 2027. | n.a. |  |
| Lyon Township six-month data center moratorium (Project Flex not affected)moratorium Enacted 2 March 2026; six months to 8 September 2026; single outlet | n.a. | Lyon Township Board of Trustees | Lyon Township trustees voted on Monday 2 March 2026, after nearly three hours of public comment, to enact a six-month moratorium on new data center applications through 8 September 2026. Officials said the pause is to study zoning changes on land, water and energy consumption. WHMI reported the moratorium is unlikely to affect Project Flex, which had already received preliminary approval from the township Planning Commission. | n.a. |  |
| New Buffalo Township one-year data center moratorium (Kluver Road parcel)moratorium Approved 8 April 2026; one year; single outlet | n.a. | New Buffalo Township Board | New Buffalo Township officials approved a one-year moratorium on data center development by resolution at a special meeting on 8 April 2026, halting permits, licenses and approvals while the township reviews its zoning ordinance. The move followed the sale of a 114-acre parcel at 19701 Kluver Road to an entity tied to the investment group behind the Project Maize data center in Michigan City, Indiana. Township officials said no formal proposal has been submitted for the site and its intended use is unclear. | n.a. |  |
| Niles Charter Township 12-month data center moratoriummoratorium Zoning ordinance amendment approved 5 October 2026; 12 months; single outlet | n.a. | Niles Charter Township Board of Trustees | On Monday 5 October 2026 the Niles Charter Township Board of Trustees approved an amendment to the township zoning ordinance establishing a 12-month data center moratorium. An earlier Herald-Palladium report says trustees had approved a 12-month moratorium on data center permits on 1 June and the planning commission began the zoning amendment on 9 June (year not shown on that page). | n.a. |  |
| Parma Township data center moratoriummoratorium Enacted February 2026 | n.a. | Parma Township | Parma Township, Michigan, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated February 2026. Ordinance 2026-3, data center moratorium. Jackson County township. The measure has no documented term. | n.a. |  |
| Penn Township (Cass County) one-year data center moratoriummoratorium 30-day moratorium 11 May 2026; one-year moratorium approved 21 May 2026 | n.a. | Penn Township Board | The Penn Township Board approved a 30-day moratorium on data center projects on Monday 11 May 2026, with Trustee Scott Peters casting the only no vote because he favored a longer pause. Supervisor Oli Olafsson said multiple developers had contacted the township about data centers. On 21 May 2026 the Planning Commission unanimously recommended, and the Township Board approved, a one-year general law (non-zoning) moratorium that stops new data center applications while zoning amendments are drafted. | n.a. |  |
| Pontiac data center moratorium (second six-month term)moratorium First moratorium adopted early 2026; second six-month term in effect, expiring January 2027; adoption date of the second term not confirmed | n.a. | City of Pontiac | Pontiac is under its second six-month moratorium on data centers, which expires in January 2027, according to WXYZ. A special council committee on data centers is drafting an ordinance covering utilities, backup generators, water, air quality and noise before the pause lapses. There are no known plans for a data center in the city. | n.a. |  |
| Port Huron Township data center moratoriummoratorium Adopted the week of 21 September 2026 (reported by the Times Herald 22 September and WGRT 24 September 2026); up to 12 months | n.a. | Port Huron Township Board | The Port Huron Township Board unanimously passed a temporary moratorium blocking new applications for data centers and other high-demand power users while it writes rules on noise, lighting and safety. Officials said no applications are on file. The pause lasts up to 12 months or until permanent zoning rules take effect, and the board may extend it. | n.a. |  |
| Porter Township data center moratoriummoratorium Enacted May 2026 | n.a. | Porter Township | Porter Township, Michigan, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated May 2026. 12-month moratorium on data center development, unanimous vote. Enacted to establish data center guidelines before developers arrive. Multiple Cass County townships have enacted similar moratoriums. The measure runs to 19 May 2027. | n.a. |  |
| Raeden data center at former McLouth steel mill site (Gibraltar moratorium lawsuit)litigation Moratorium adopted 9 March 2026; suit filed 17 August 2026; city response reported 21 September 2026 | Raeden Acquisitions, LLC (with property owner CAL Realty, LLC) | U.S. District Court for the Eastern District of Michigan | Raeden submitted a site plan on 17 February 2026, and on 9 March 2026 the Gibraltar City Council unanimously adopted a one-year moratorium on data centers by resolution. Raeden and CAL Realty sued the city on 17 August 2026 in federal court (CAL Realty, LLC et al v. Gibraltar, 2:26-cv-12893), alleging the moratorium was adopted to defeat review of their pending application and seeking to have it declared invalid and the site plan approved. Law360 reported on 21 September 2026 that the city told the court the suit is premature. | n.a. |  |
| Rochester Hills data center moratoriummoratorium Enacted August 2026 | n.a. | Rochester Hills | Rochester Hills, Michigan, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated August 2026. 180-day moratorium adopted March 2026, extended through mid-March 2027; studying noise, vibration, light pollution, water, electricity demand. The measure runs to 15 March 2027. | n.a. |  |
| Rocklocker Kalkaska data center (state land near Island Lake and South River roads)withdrawn Withdrawn 20 November 2025; single outlet | Rocklocker (Matt Rine) with Kalkaska Go | Kalkaska County / Michigan DNR land | Rocklocker's Matt Rine said on Thursday 20 November 2025 that his company and Kalkaska Go would end their pursuit of a data center proposed on 1,440 acres of state land, and cancelled a community forum set for that night. An overflow crowd had opposed the project at the first forum that Monday, and several legislators said it would not happen on DNR land. Rocklocker said concerns about developing on public lands were decisive. | n.a. |  |
| Rocklocker LLC Kalkaska Countycancelled November 1, 2025 | Rocklocker LLC | Kalkaska County | Rocklocker LLC (headed by Traverse City geologist Matt Rine) proposed a gigawatt-scale hyperscale data center on 1,440 acres of state-owned land near Island Lake and South River roads, with its own natural gas power | n.a. |  |
| Saginaw data center moratoriummoratorium Moratorium approved January 2026, runs through 31 December 2026; regulating ordinance approved 28 September 2026, effective 9 October 2026 | n.a. | Saginaw City Council | The Saginaw City Council approved a moratorium on data center development spanning all of 2026 in January 2026 and directed staff to draft regulations. On Monday 28 September 2026 the council unanimously approved the resulting ordinance, which makes data centers special land uses in light and general industrial districts, requires reports on water, wastewater, energy and noise, sets 500-foot residential setbacks and a 55-decibel limit near homes, and takes effect 9 October 2026. The moratorium remains in place through the end of 2026. | n.a. |  |
| Sault Ste. Marie Tribe of Chippewa Indians data center moratoriummoratorium Enacted January 2026 | n.a. | Sault Ste. Marie Tribe of Chippewa Indians | Sault Ste. Marie Tribe of Chippewa Indians, Michigan, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated January 2026. Indefinite moratorium prohibiting development, approval, or operation of AI data centers on tribal lands; board of directors voted unanimously; remains in effect unless lifted by subsequent resolution; concerns about resource strain and long-term land use impacts. The measure has no end date by design. | n.a. |  |
| Springfield Township campus (84 acres, 2-3 buildings)moratorium Jan 7 2026; dollar value n.a. | n.a. | Oakland County | 180-day moratorium | n.a. |  |
| Stargate / The Barndenied August 12, 2025 | Related Digital / Oracle | Saline Township Planning Commission | After an August 5, 2025 first public hearing dominated by opposition, the Saline Township Planning Commission tabled Related Digital's 'conditional rezoning' application for 575 acres from A-1 Agricultural to I-1 | n.a. |  |
| Texas Township data center moratoriummoratorium Enacted June 2026 | n.a. | Texas Township | Texas Township, Michigan, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated June 2026. Resolution 26-12, 12-month moratorium on data center developments including AI and cryptocurrency mining facilities. Planning commission to evaluate impacts on farmland preservation, infrastructure capacity, and environmental factors. The measure runs to 5 July 2027. | n.a. |  |
| Warren 12-month data center moratoriummoratorium Approved unanimously 25 August 2026; 12 months | n.a. | Warren City Council | The Warren City Council unanimously approved a 12-month moratorium on data centers at its 25 August 2026 meeting, giving the city time to define the facilities in its zoning ordinance and decide where and under what conditions they should be allowed. Council Secretary Mindy Moore had called for a pause after July storms knocked down more than 60 power lines in the city. The moratorium does not affect existing facilities or previously approved uses, and excludes server rooms of less than 2,500 square feet that are related to another permitted use. The council's attorney said he was not aware of any hyperscale data center operating in Warren. | n.a. |  |
| Washington Township (Macomb Co.) data center moratoriummoratorium Enacted May 2026 | n.a. | Washington Township (Macomb Co.) | Washington Township (Macomb Co.), Michigan, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated May 2026. 6-month pause or until zoning ordinance amendments take effect; passed after Prologis withdrew a 312-acre 'technical campus' application. The measure runs to 23 November 2026. | n.a. |  |
| Webster Township data center moratoriummoratorium Enacted January 2026 | n.a. | Webster Township | Webster Township, Michigan, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated January 2026. Ordinance 26-02: 1-year moratorium on data centers and battery energy storage systems (BESS). Washtenaw County township. The measure runs to 21 April 2027. | n.a. |  |
| Wixom data center moratorium (ended early) and Midwinds Park proposalrestarted Restrictions adopted 26 August 2026, effective no later than 6 September 2026 | Wixom Industrial One, LLC (Sansone Group) | City of Wixom | Wixom's six-month data center moratorium ended early. On 26 August 2026 the city council adopted data center restrictions in its zoning ordinance, requiring a 1,500-foot setback from residential areas, parks and K-12 schools, prohibiting the use of well water, and requiring a 48-hour Monday-to-Friday sound study as part of an application. The council then passed a resolution making the restrictions effective no later than 6 September 2026, ending the moratorium roughly two and a half weeks before its scheduled expiration. Wixom Industrial One, LLC, operating under the Missouri-based Sansone Group, has sued the city, claiming the moratorium is illegal and was intended to permanently kill its proposed Midwinds Park data center of three buildings totaling 519,400 square feet at 30625 S. Wixom Road. | n.a. |  |
| Ypsilanti Township 180-day moratorium on major electric utility infrastructuremoratorium Adopted August 2026 | n.a. | Ypsilanti Township | The Board of Trustees voted unanimously on Aug. 18, 2026 for a six-month moratorium on major electric utility infrastructure serving high-energy-demand uses, expressly including hyperscale and mid-sized data centers and AI computing facilities. The township, which had already paused water service for data centers, is seeking to slow a proposed University of Michigan and Los Alamos computing project and an associated 110 MW DTE substation. | n.a. |  |
| Zeeland Township moratorium and PA 233 challengemoratorium Moratorium reported 1 September 2026; PA 233 suit filed July 2026, removed to federal court August 2026 | RWE Americas (Silver Maple Solar) | Zeeland Township, Ottawa County | The Zeeland Township board unanimously approved a one-year moratorium on data centers and energy facilities, repealing and replacing an earlier moratorium at the same meeting, to allow the township to review and update its master plan. Supervisor Kerri Bosma said the township had no pending data center or energy facility applicants. The township sued in July 2026 challenging Michigan's PA 233 siting law as unconstitutional; RWE Americas filed a notice of removal in August 2026 transferring the case from Ottawa County Circuit Court to the U.S. District Court for the Western District of Michigan, and the township moved to remand. RWE's Silver Maple Solar application before the Michigan Public Service Commission was suspended in July 2026 at the company's request. | n.a. |  |

Financing

## Financing transactions tied to Michigan sites

Transactions the atlas ties to a named site in Michigan: joint ventures, project bonds, credit facilities, leases and power agreements. Amounts are as stated; overlapping commitments are never summed.

| Parties | Instrument | Amount | Date | Site | Sources |
| --- | --- | --- | --- | --- | --- |
| Oracle + PIMCO + Related Digital Infrastructure + BlackstoneOracle closed a $16.3 billion financing for the Saline Township, Michigan campus, the largest single-facility technology debt package on record, with bonds carrying a 7.5% coupon and 19.5-year maturity, structured with six years of interest-only payments followed by 13 years of amortisation. | project bond | ~$16.3B | Closed; part of the Stargate joint venture program | Saline Township campus |  |
| Ault & Company + Hyperscale DataAult & Company, controlled by Milton 'Todd' Ault III, said it has invested $55 million of direct capital in Hyperscale Data through Series H convertible preferred stock and retains the right to buy up to an additional $96 million. Ault & Company and affiliates beneficially own about 62% of Hyperscale Data. The release cites Hyperscale Data's investment of more than $70 million in its Michigan AI data center operated by subsidiary Alliance Cloud Services. | preferred | $55M | Cumulative investment announced 25 September 2026 (PR Newswire); purchase dates not stated | Hyperscale Data Michigan AI data center (Alliance Cloud Services) |  |
| Hyperscale Data, Inc. + Morpho Protocol lendersHyperscale Data said it had implemented a bitcoin-backed decentralized finance borrowing program through the Morpho Protocol, with about $30 million outstanding as of 2 August 2026 at a variable rate of about 4.9 percent. Proceeds support development of its Michigan AI data center campus under a master services agreement with a neocloud provider, plus working capital and general corporate purposes. | debt facility | ~$30M | Announced 3 August 2026; about $30 million outstanding as of 2 August 2026 | Hyperscale Data Michigan AI data center (Alliance Cloud Services) |  |
| The debt package for the Saline Township, Michigan Stargate site is described in the atlas's §5.4. | debt facility | n.a. | described in atlas §5.4 | Stargate Saline Township (Michigan) |  |
| DTE + Stargate (Saline Township data center)Michigan regulators approved a 19-year DTE contract for 1.4 GW serving the Stargate AI data center in Saline Township. | ppa | n.a. | approved December 2025 | Stargate Saline Township (Michigan) |  |
| Hyperscale Data + Alliance Cloud Services + SentinumHyperscale Data's board began a strategic review including a possible sale of its Michigan AI data center, a minority sale through an IPO of subsidiary Sentinum, or continued ownership. The campus has a 10-year master services agreement with a California-based neocloud for an initial 20 MW, expandable to 52 MW. The company said it had invested more than $70 million in the facility as of 15 September 2026 | other | n.a. | Strategic review announced 11 August 2026; $750 million threshold announced 14 September 2026 | Hyperscale Data Michigan AI data center (Alliance Cloud Services) |  |
| Google + DTE Energy (DTE Electric)Google announced plans for a new data center in DTE Energy's Michigan service territory, served by 2.7 GW of new clean resources under a Clean Capacity Acceleration Agreement with DTE (the same structure as Google's Clean Transition Tariff), plus a $10 million Energy Impact Fund; Google said it is evaluating a site in Van Buren Township. Planet Detroit reports the project is 1 GW, with DTE promising 1.6 GW of renewables, up to 480 MW of storage and demand response, a 20-year contract, and the first contested case for a hyperscale data center before the Michigan Public Service Commission. DTE's investor presentation lists the 1 GW Google agreement as executed and in the MPSC approval process, as upside to its capital plan. On Thursday 1 October 2026 the Michigan Public Service Commission unanimously approved, with conditions, DTE Electric's special contracts with Google LLC in Case No. U-22058: a primary supply agreement with a 20-year term, a minimum billing demand of 80% of contract capacity, an early termination payment ensuring at least 15 years of minimum monthly charges, and credit and collateral requirements; and a clean capacity accelerator agreement under which Google pays for DTE Electric to develop up to 1,600 MW of renewable energy and 480 MW of battery storage. DTE Electric expects service to begin in December 2027 and maximum load by December 2028. It is the first hyperscale data center contract in Michigan decided through a contested case; Attorney General Dana Nessel had sought a 90% minimum billing demand. No contract value was disclosed. | power supply agreement | n.a. | Announced 17 March 2026 (Google blog); DTE special contracts approved with conditions by the Michigan Public Service Commission on 1 October 2026 (Case No. U-22058) | Project Cannoli data center (east of Haggerty Road, north of the I-94 North Service Drive) |  |
| Hyperscale Data (Sentinum) + Undisclosed California-based neocloud providerMaster services agreement with an undisclosed California-based neocloud for an initial 20 MW of critical AI compute capacity at Hyperscale Data's Michigan campus in Dowagiac, with rights to a further 32 MW (52 MW total). On 5 October 2026 the company said it will hold an investor day on 12 November 2026 to discuss the campus and strategic alternatives, including a possible sale of the Michigan campus or an IPO of its Sentinum subsidiary, and reiterated 2027 guidance of $300 million to $350 million in revenue. | compute lease | n.a. | MSA previously disclosed by the company; potential contract value restated in the company release of Monday 5 October 2026 | Hyperscale Data Michigan AI data center (Alliance Cloud Services) |  |

Policy context

## What governs a data center in Michigan

Michigan (statewide)state

Most heavily restricted state in the country with 73 tracked actions. C.4 floors: 1,383 MW (Saline, conditionally approved); $8.1B-$17.1B ($7-16B Saline + $1B Howell + $0.1B Ypsilanti); 4 named projects.

Michigan carries 73 tracked actions, the most of any state, spanning Detroit (proposed), Flint, and dozens of townships. The Saline Township campus was conditionally approved by the MPSC (Case U-21990) on December 18, 2025 despite residents voting against it.

Michigan (MPSC order on Consumers Energy large-load tariff)state

Applies to new data centers and other loads above 100 MW in Consumers Energy's territory; approved Thursday 6 November 2025. Conditions on service, not a moratorium

The Michigan Public Service Commission approved on Thursday 6 November 2025 Consumers Energy's rules for new data centers and other loads above 100 MW: a 15-year minimum contract term, a minimum bill of 80% of expected monthly demand regardless of use, and a ramp-up period of up to five years. The commission required Consumers to show that costs caused by each new large load are not subsidized by other customers, saying it aimed to make large loads fully pay for the costs to serve them and to guard against stranded assets if load fails to materialize. CMS Energy cited a 9 GW pipeline of potential data center, semiconductor and manufacturing projects.

The policy layer for Michigan lives in three companion references: the [Michigan Data Center Moratorium Tracker](https://savrn.com/data-center-moratorium-tracker/michigan) for every state measure and local moratorium on record, the [Water Tracker](https://savrn.com/data-center-water-tracker) for the water rules that touch a site, and the [Grid Operator Watchlist](https://savrn.com/data-center-grid-operator-watchlist) for the large-load rules of the RTO or utility that decides whether it can energize.

Next door

## States next door

Ohio

24 sites · $47.3B disclosed

80 blocked, delayed or restricted

Indiana

14 sites · $69.5B disclosed

44 blocked, delayed or restricted

Wisconsin

4 sites · $37.0B disclosed

45 blocked, delayed or restricted

On the map

## Data centers in Michigan

The US Data Center Map identifies 59 facilities run by 32 operators in Michigan, each one placed from primary sources and listed by city and by operator, with this atlas record beside it.

Michigan data centers

59 facilities · 32 operators

Map, locations, operators, rules

Michigan power and local economy

Generation, utilities and county records

Explore the power supply chain and local conditions behind the build-out

US Data Center Map

Every state, one page each

The national map and the operator directory

Sources

## Sources for Michigan

Every source cited on this page, once each. The full atlas source register is at [Capital Atlas sources](https://savrn.com/data-center-capital-atlas/sources).

- thenextweb.com[The Next Web](https://thenextweb.com/news/oracle-data-centre-16-billion-financing-stargate)
- wxyz.com[WXYZ](https://www.wxyz.com/news/data-centers/saline-township-board-approves-oracle-tax-abatement-cap-it-at-original-4-8b-project-cost)
- yahoo.com[GOLF via Yahoo](https://www.yahoo.com/news/articles/golf-courses-owners-building-16-054535295.html)
- msn.com[MLive via MSN](https://www.msn.com/en-us/news/other/public-hearing-set-on-openai-oracle-data-center-s-proposal-to-discharge-wastewater-into-saline-river/ar-AA2c5p7Q)
- openai.com[OpenAI](https://openai.com/index/expanding-stargate-to-michigan/)
- apnews.com[AP](https://apnews.com/article/openai-inc-joi-harris-data-management-and-storage-microsoft-corp-oracle-corp-f25196fca5865ed79d94c972249a272c)
- mgrid.org[mgrid](https://mgrid.org/2025/12/18/michigan-regulators-approve-dte-19-year-contract-for-1-4-gw-stargate-ai-data-center-in-saline-township/)
- tmcnet.com[TMCnet (PR Newswire)](https://www.tmcnet.com/usubmit/2026/09/17/10447347.htm)
- abc57.com[ABC57](https://www.abc57.com/news/bitcoin-mining-ceases-at-dowagiac-data-center-consistent-humming-no-longer-heard)
- datacenterdynamics.com[Data Center Dynamics](https://www.datacenterdynamics.com/en/news/hyperscale-data-ends-cryptomining-operations-at-michigan-data-center/)
- prnewswire.com[Hyperscale Data release (PR Newswire), 5 October 2026](https://www.prnewswire.com/news-releases/hyperscale-data-sets-november-12-as-investor-day-to-discuss-michigan-ai-expansion-and-strategic-alternatives-across-its-portfolio-302897945.html)
- msn.com[The Detroit News (via MSN), 25 September 2026](https://www.msn.com/en-us/news/other/wayne-co-exec-vetoes-van-buren-twps-125m-data-center-tax-break/ar-AA2cZlzV)
- msn.com[Morning Overview (via MSN), 18 March 2026](https://www.msn.com/en-us/news/us/google-confirms-it-is-behind-the-project-cannoli-data-center-plan/ar-AA1YV7Ds)
- blog.google[Google blog](https://blog.google/innovation-and-ai/infrastructure-and-cloud/global-network/clean-energy-reliability-michigan/)
- planetdetroit.org[Planet Detroit](https://planetdetroit.org/2026/09/google-dte-van-buren-data-center-contracts/)
- sec.gov[DTE Energy investor presentation (SEC)](https://www.sec.gov/Archives/edgar/data/936340/000093634026000159/dtebusinessupdate92826fi.htm)
- planetdetroit.org[Planet Detroit, 1 October 2026](https://planetdetroit.org/2026/10/dte-google-data-center-contract-approval/)
- wxyz.com[WXYZ Detroit, 1 October 2026](https://www.wxyz.com/news/wayne-county-commissioners-override-veto-to-approve-google-data-center-tax-incentives-in-van-buren-township)
- fox2detroit.com[FOX 2 Detroit](https://www.fox2detroit.com/news/wayne-county-overrides-evans-veto-tax-breaks-van-buren-data-center)
- cbsnews.com[CBS News Detroit, 1 October 2026](https://www.cbsnews.com/detroit/news/wayne-county-commissioners-warren-evans-data-center-tax-incentives/)
- thealpenanews.com[The Alpena News (MPSC release), 1 October 2026](https://www.thealpenanews.com/news/local-news/2026/10/mpsc-approves-dte-electric-contracts-for-google-data-center/)
- msn.com[CBS Detroit (via MSN)](https://www.msn.com/en-us/news/other/wayne-county-commissioners-override-warren-evans-veto-on-van-buren-township-data-center-tax-breaks/ar-AA2do96h)
- michigan.gov[MPSC](https://www.michigan.gov/mpsc/commission/news-releases/2025/12/18/mpsc-approves-dte-electric-energy-contracts-for-data-center)
- planetdetroit.org[Planet Detroit](https://planetdetroit.org/2025/12/dte-data-center-contract-decision/)
- fortune.com[Fortune](https://fortune.com/2026/05/18/communities-are-blocking-billions-in-data-centers-big-tech-has-wagered-1-trillion-otherwise/)
- michiganpublic.org[Michigan Public](https://www.michiganpublic.org/economy/2026-06-01/company-leaders-optimistic-responsible-development-of-saline-data-center-will-set-example)
- interconnectedcapital.com[Interconnected Capital](https://www.interconnectedcapital.com/research/data-center-moratoriums)
- planetdetroit.org[Planetdetroit](https://planetdetroit.org/2025/10/ypsilanti-council-data-center-vote/)
- wxyz.com[WXYZ](https://www.wxyz.com/news/data-centers/residents-and-officials-push-back-on-1-25b-university-of-michigan-data-center-plan)
- static1.squarespace.com[Wins against DCs](https://static1.squarespace.com/static/662008fbe1c43d29c0122d8a/t/6980f39a65fc747facd340aa/1770058650648/Wins+against+DCs.pdf)
- planetdetroit.org[planetdetroit.org](https://planetdetroit.org/2025/12/billion-dollar-data-center-paused/)
- michiganadvance.com[michiganadvance.com](https://michiganadvance.com/2025/11/21/local-michigan-township-trustee-says-meta-is-behind-data-center-project-planned-near-howell/)
- planetdetroit.org[planetdetroit.org](https://planetdetroit.org/2025/11/meta-data-center-howell-township/)
- fractracker.org[fractracker.org](https://www.fractracker.org/2026/01/howell-township-data-center-win/)
- michiganadvance.com[michiganadvance.com](https://michiganadvance.com/2025/12/08/rezoning-request-for-rural-michigan-data-center-project-pulled-from-consideration/)
- change.org[change.org](https://www.change.org/p/stop-the-construction-of-michigan-s-largest-data-center-in-howell)
- datacenterdynamics.com[datacenterdynamics.com](https://www.datacenterdynamics.com/en/news/meta-reportedly-the-company-behind-1bn-data-center-in-howell-county-michigan/)
- wilx.com[wilx.com](https://www.wilx.com/2025/11/21/meta-is-behind-proposed-howell-twp-data-center-trustee-says/)
- cnbc.com[CNBC](https://www.cnbc.com/2026/01/07/microsoft-behind-controversial-data-center-in-michigan-township.html)
- mlive.com[Mlive](https://www.mlive.com/news/grand-rapids/2026/06/west-michigan-residents-protest-data-centers-in-front-of-developer-roundtable.html)
- hollander.news[hollander.news](https://www.hollander.news/article/allendale-to-approve-a-moratorium-on-data-and-energy-projects)
- wwmt.com[WWMT](https://wwmt.com/news/local/marshall-data-center-moratorium-delays-development-one-year-alterra-brooks-industrial-park-acres-wetland-lake-energy-environment-calhoun-county-west-michigan)
- wemu.org[WEMU](https://www.wemu.org/wemu-news/2026-02-17/ann-arbor-township-passes-12-month-moratorium-on-data-centers)
- bigrapidstownshipmi.gov[bigrapidstownshipmi.gov](https://bigrapidstownshipmi.gov/2026/02/27/data-center-moratorium-ordinance/)
- whmi.com[WHMI](https://www.whmi.com/news/article/51280)
- portagemi.gov[portagemi.gov](https://www.portagemi.gov/m/newsflash/home/detail/1831)
- yahoo.com[MLive via Yahoo News](https://www.yahoo.com/news/us/articles/dearborn-approves-6-month-pause-145407949.html)
- miningjournal.net[miningjournal.net](https://www.miningjournal.net/news/local/2026/07/delta-county-board-oks-moratorium-on-data-centers/)
- dextertownshipmi.gov[dextertownshipmi.gov](https://www.dextertownshipmi.gov/resolution-26-705-resolution-adopting-data-center-application-moratorium-2/)
- wilx.com[wilx.com](https://www.wilx.com/2026/08/12/east-lansing-city-council-votes-extend-data-center-moratorium/)
- tuscolatoday.com[Tuscola County Advertiser](https://www.tuscolatoday.com/news/elmwood-acts-on-data-center-moratorium/article_989c5d64-6088-4222-8f1c-e9d099776f71.html)
- wkar.org[WKAR](https://www.wkar.org/wkar-news/2026-02-27/michigan-data-center-tracker-moratoria-legislation-and-grid-impact)
- shorelinemedia.net[Ludington Daily News](https://www.shorelinemedia.net/ludington_daily_news/news/west-michigan-communities-move-to-regulate-data-centers/article_924d511a-66a7-4f94-ab63-ac9b984546ee.html)
- midmichigannow.com[Mid-Michigan NOW](https://midmichigannow.com/news/local/flint-city-council-passes-data-center-moratorium-other-key-resolutions)
- wnem.com[WNEM](https://www.wnem.com/2026/06/08/flint-city-council-consider-data-center-moratorium/)
- uppermichiganssource.com[uppermichiganssource.com](https://www.uppermichiganssource.com/2026/06/26/forsyth-township-board-passes-moratorium-regarding-data-centers-crowded-meeting/)
- 9and10news.com[9&10 News](https://www.9and10news.com/2026/08/25/garfield-township-enacts-data-center-moratorium-to-buy-time-for-research-on-restrictions/)
- upnorthlive.com[UpNorthLive](https://upnorthlive.com/news/local/garfield-township-approves-12-month-moratorium-on-data-centers-after-unanimous-vote-grand-traverse-county)
- interlochenpublicradio.org[Interlochen Public Radio](https://www.interlochenpublicradio.org/2026-08-26/garfield-township-puts-a-1-year-ban-on-data-centers-cryptocurrency-mining)
- whmi.com[WHMI](https://www.whmi.com/news/article/genoa-data-center-crypto-currency-mining-moratorium-extended)
- crainsdetroit.com[Crain's Detroit Business, 25 September 2026 (walled)](https://www.crainsdetroit.com/technology/cdb-data-center-van-buren-google-20260925/)
- msn.com[The Detroit News (via MSN), 30 September 2026](https://www.msn.com/en-us/news/other/wayne-county-commission-to-revisit-van-buren-township-data-center-tax-breaks-after-veto/ar-AA2dioEd)
- msn.com[The Detroit News (via MSN), 1 October 2026](https://www.msn.com/en-us/news/other/wayne-co-commissioners-override-evans-van-buren-data-center-veto/ar-AA2dmV3C)
- tricityrecord.com[Tri-City Record](https://www.tricityrecord.com/post/hagar-township-board-approves-data-center-moratorium-hears-concerns-over-drain-district-assessments)
- cadillacnews.com[Cadillac News](https://www.cadillacnews.com/news/crowd-comes-out-in-support-of-banning-data-centers-in-haring-township/article_b816e06c-d974-43b1-b274-b87bf761e337.html)
- uppermichiganssource.com[uppermichiganssource.com](https://www.uppermichiganssource.com/2026/07/09/houghton-city-council-approves-temporary-data-center-moratorium/)
- huroncountyview.com[huroncountyview.com](https://huroncountyview.com/articles/huron-county-planners-advance-moratorium-on-data-centers/)
- fox17online.com[Source](https://www.fox17online.com/news/local-news/kzoo-bc/kalamazoo/kalamazoo-city-commission-votes-in-favor-of-data-center-pause)
- wkzo.com[WKZO](https://wkzo.com/2026/09/21/971915/)
- wkzo.com[WKZO](https://wkzo.com/2026/09/22/972292/)
- wkzo.com[WKZO](https://wkzo.com/2026/10/05/976615/)
- wzzm13.com[WZZM 13 (video; 403 to fetch)](https://www.wzzm13.com/video/news/local/kalamazoo-pauses-data-center-planning-development-for-one-year/69-592bfb7e-ca51-4c86-9b4e-ad0f3dc2ed63)
- wsbt.com[wsbt.com](https://wsbt.com/news/local/lincoln-township-trustees-agree-to-moratorium-on-data-centers-state-water-noise-electrical-consumption-impacts-communities-built-lincoln-township-michigan)
- thesuntimesnews.com[thesuntimesnews.com](https://thesuntimesnews.com/lyndon-twp-notice-of-resolution-26-06/)
- whmi.com[WHMI](https://www.whmi.com/news/article/lyon-twp-board-enacts-six-month-moratorium-on-new-data-center-projects)
- heraldpalladium.com[The Herald-Palladium](https://www.heraldpalladium.com/communities/new_buffalo/new-buffalo-township-moves-to-pause-data-centers/article_ae807e06-310b-5d6e-a346-f4952041d0a6.html)
- heraldpalladium.com[The Herald-Palladium](https://www.heraldpalladium.com/leaderpub/communities/niles/niles-township-board-approves-data-center-moratorium-marijuana-ordinance/article_0760c873-bf41-55bd-886e-781171c62dd5.html)
- heraldpalladium.com[The Herald-Palladium (June report)](https://www.heraldpalladium.com/communities/niles/niles-township-approves-data-center-moratorium/article_578eca9c-08f1-5f09-b3df-7945d152258d.html)
- parmatwp.gov[parmatwp.gov](https://parmatwp.gov/2026/02/23/notice-of-data-center-moratorium-adoption-2026-3/)
- wndu.com[WNDU](https://www.wndu.com/2026/05/12/officials-approve-30-day-moratorium-data-center-penn-township-residents-request-longer-term-option/)
- wsbt.com[WSBT](https://wsbt.com/news/local/penn-township-mi-approves-one-year-pause-on-data-centers-zoning-ordinance-heated-debate-planning-board-michigan-cass-county-ai-hyperscale-infrastructure)
- wxyz.com[WXYZ 7 News Detroit](https://www.wxyz.com/news/pontiacs-data-center-moratorium-expires-in-january-and-the-city-is-racing-to-set-rules)
- wgrt.com[WGRT](https://wgrt.com/township-hits-pause-button-on-data-center-boom/)
- thetimesherald.com[Times Herald (Port Huron; blocked to fetch, headline only)](https://www.thetimesherald.com/story/news/local/2026/09/22/port-huron-township-michigan-approves-12-month-moratorium-on-data-centers/91886381007/)
- yahoo.com[Michigan Advance via Yahoo (Weekly Download)](https://www.yahoo.com/news/us/articles/michigan-data-centers-weekly-download-100003134.html)
- wsbt.com[wsbt.com](https://wsbt.com/news/local/porter-township-passes-one-year-moratorium-pause-data-center-pause-ordinance-town-residents-developer-law-michigan-board-members-zoning-comment-public-meetings-approval-extension-cass-county-michigan)
- mlive.com[MLive via MSN](https://www.mlive.com/news/detroit/2026/08/data-center-developer-sues-michigan-city-challenging-one-year-pause-on-projects.html)
- cbsnews.com[CBS Detroit](https://www.cbsnews.com/detroit/news/raedan-acquisition-sues-gibraltar-data-center-moratorium/)
- law360.com[Law360](https://www.law360.com/real-estate-authority/articles/2528093/mich-city-says-data-center-moratorium-suit-is-premature)
- detroitnews.com[detroitnews.com](https://www.detroitnews.com/story/news/local/oakland-county/2026/08/11/rochester-hills-extends-data-center-moratorium/91256551007/)
- traverseticker.com[The Ticker (Traverse City)](https://www.traverseticker.com/news/developer-pulls-plug-on-kalkaska-data-center/)
- datacenterdynamics.com[datacenterdynamics.com](https://www.datacenterdynamics.com/en/news/opposition-leads-developer-to-withdraw-data-center-proposal-in-kalkaska-county-michigan/)
- 9and10news.com[9and10news.com](https://www.9and10news.com/2025/11/20/kalkaska-county-data-center-project-halted-after-public-opposition/)
- interlochenpublicradio.org[interlochenpublicradio.org](https://www.interlochenpublicradio.org/2025-11-20/after-chilly-response-from-public-rocklocker-calls-off-plans-for-kalkaska-data-center)
- themidwesterner.news[themidwesterner.news](https://www.themidwesterner.news/2025/11/were-gonna-fight-like-hell-local-opposition-kills-hyperscale-data-center-in-kalkaska/)
- mlive.com[MLive](https://www.mlive.com/news/2026/09/saginaw-council-approves-data-center-ordinance-after-months-of-planning.html)
- wnem.com[WNEM](https://www.wnem.com/2026/09/29/saginaw-approves-new-rules-future-data-centers-moratorium-nears-end/)
- myupnow.com[myupnow.com](https://www.myupnow.com/news/sault-tribe-directors-vote-in-indefinite-pause-on-data-center-development/article_51356dac-7efb-4e02-b7fd-6802f439cfd8.html)
- planetdetroit.org[planetdetroit.org](https://planetdetroit.org/2025/09/saline-denies-data-center/)
- salinetownship.org[salinetownship.org](https://salinetownship.org/uploads/minutes/1761140618_August%205.pdf)
- salinetownship.org[salinetownship.org](https://salinetownship.org/uploads/notices/QA%20Data%20Center%20Proposal.pdf)
- wkzo.com[wkzo.com](https://wkzo.com/2026/06/26/942683/)
- candgnews.com[C & G Newspapers (Warren Weekly)](https://www.candgnews.com/articles/government-news/warren-city-council-votes-to-approve-12-month-data-center-moratorium/)
- web.archive.org[Michigan Advance (archived copy)](https://web.archive.org/web/2026/https://michiganadvance.com/2026/09/14/michigan-data-centers-the-weekly-download-4-2-2-2/)
- detroitnews.com[detroitnews.com](https://www.detroitnews.com/story/news/local/macomb-county/2026/05/23/washington-township-passes-six-month-moratorium-on-data-centers/90213646007/)
- cms9files.revize.com[cms9files.revize.com](https://cms9files.revize.com/webstertwpmi/2026-04-21%20Ordinance%20No.%2026-02%20Data%20Center%20Moratorium%20Notice%20of%20Adoption.pdf)
- yahoo.com[Detroit News](https://www.yahoo.com/news/us/articles/wixom-moves-forward-data-center-040140663.html)
- wxyz.com[WXYZ](https://www.wxyz.com/news/data-centers/wixom-city-council-takes-steps-to-regulate-data-centers-as-6-month-moratorium-nears-end)
- wemu.org[Source](https://www.wemu.org/wemu-news/2026-08-19/ypsilanti-township-passes-moratorium-on-new-major-electric-infrastructure)
- fox17online.com[FOX 17 West Michigan](https://www.fox17online.com/news/local-news/holland-zeeland-grand-haven/zeeland-township-approves-new-data-center-and-energy-facility-moratorium-to-protect-local-planning)
- prnewswire.com[Ault & Company release (PR Newswire)](https://www.prnewswire.com/news-releases/ault--company-has-invested-55-million-in-capital-to-hyperscale-data-302890089.html)
- prnewswire.com[Hyperscale Data release (PR Newswire), 3 August 2026](https://www.prnewswire.com/news-releases/hyperscale-data-establishes-bitcoin-backed-defi-financing-program-through-morpho-protocol-current-borrowings-approximately-30-million-at-4-9-to-support-michigan-ai-data-center-expansion-302840711.html)
- morningstar.com[Morningstar (PR Newswire)](https://www.morningstar.com/news/pr-newswire/20260811sf23587/hyperscale-data-board-considers-all-options-to-maximize-stockholder-value-including-potential-sale-of-its-michigan-data-center)
- tmcnet.com[TMCnet (PR Newswire)](https://www.tmcnet.com/usubmit/2026/09/14/10444444.htm)
- clickondetroit.com[ClickOnDetroit (WDIV), 2 October 2026](https://www.clickondetroit.com/news/local/2026/10/02/state-regulators-approve-dte-contracts-for-google-data-center-in-wayne-county/)
- dimetrics.ai[Dimetrics Michigan](https://www.dimetrics.ai/datacenter-risk/michigan)
- utilitydive.com[Utility Dive](https://www.utilitydive.com/news/kansas-michigan-data-center-large-load-evergy-consumers/805115/)

### Every state, one page each

[Alabama 9 / 21](https://savrn.com/data-center-capital-atlas/alabama)[Alaska 1 / 1](https://savrn.com/data-center-capital-atlas/alaska)[Arizona 11 / 11](https://savrn.com/data-center-capital-atlas/arizona)[Arkansas 2 / 8](https://savrn.com/data-center-capital-atlas/arkansas)[California 10 / 35](https://savrn.com/data-center-capital-atlas/california)[Colorado 6 / 21](https://savrn.com/data-center-capital-atlas/colorado)[Connecticut 0 / 6](https://savrn.com/data-center-capital-atlas/connecticut)[Delaware 0 / 5](https://savrn.com/data-center-capital-atlas/delaware)[Florida 0 / 46](https://savrn.com/data-center-capital-atlas/florida)[Georgia 23 / 57](https://savrn.com/data-center-capital-atlas/georgia)[Hawaii 0 / 0](https://savrn.com/data-center-capital-atlas/hawaii)[Idaho 2 / 2](https://savrn.com/data-center-capital-atlas/idaho)[Illinois 10 / 35](https://savrn.com/data-center-capital-atlas/illinois)[Indiana 14 / 44](https://savrn.com/data-center-capital-atlas/indiana)[Iowa 3 / 22](https://savrn.com/data-center-capital-atlas/iowa)[Kansas 5 / 19](https://savrn.com/data-center-capital-atlas/kansas)[Kentucky 6 / 26](https://savrn.com/data-center-capital-atlas/kentucky)[Louisiana 7 / 3](https://savrn.com/data-center-capital-atlas/louisiana)[Maine 0 / 20](https://savrn.com/data-center-capital-atlas/maine)[Maryland 1 / 22](https://savrn.com/data-center-capital-atlas/maryland)[Massachusetts 0 / 11](https://savrn.com/data-center-capital-atlas/massachusetts)[Michigan 4 / 55](https://savrn.com/data-center-capital-atlas/michigan)[Minnesota 3 / 31](https://savrn.com/data-center-capital-atlas/minnesota)[Mississippi 7 / 5](https://savrn.com/data-center-capital-atlas/mississippi)[Missouri 10 / 25](https://savrn.com/data-center-capital-atlas/missouri)[Montana 1 / 10](https://savrn.com/data-center-capital-atlas/montana)[Nebraska 3 / 16](https://savrn.com/data-center-capital-atlas/nebraska)[Nevada 8 / 12](https://savrn.com/data-center-capital-atlas/nevada)[New Hampshire 0 / 5](https://savrn.com/data-center-capital-atlas/new-hampshire)[New Jersey 4 / 61](https://savrn.com/data-center-capital-atlas/new-jersey)[New Mexico 3 / 10](https://savrn.com/data-center-capital-atlas/new-mexico)[New York 6 / 21](https://savrn.com/data-center-capital-atlas/new-york)[North Carolina 10 / 45](https://savrn.com/data-center-capital-atlas/north-carolina)[North Dakota 6 / 4](https://savrn.com/data-center-capital-atlas/north-dakota)[Ohio 24 / 80](https://savrn.com/data-center-capital-atlas/ohio)[Oklahoma 11 / 20](https://savrn.com/data-center-capital-atlas/oklahoma)[Oregon 1 / 8](https://savrn.com/data-center-capital-atlas/oregon)[Pennsylvania 16 / 42](https://savrn.com/data-center-capital-atlas/pennsylvania)[Rhode Island 0 / 5](https://savrn.com/data-center-capital-atlas/rhode-island)[South Carolina 6 / 20](https://savrn.com/data-center-capital-atlas/south-carolina)[South Dakota 1 / 6](https://savrn.com/data-center-capital-atlas/south-dakota)[Tennessee 6 / 26](https://savrn.com/data-center-capital-atlas/tennessee)[Texas 106 / 35](https://savrn.com/data-center-capital-atlas/texas)[Utah 11 / 12](https://savrn.com/data-center-capital-atlas/utah)[Vermont 0 / 3](https://savrn.com/data-center-capital-atlas/vermont)[Virginia 33 / 50](https://savrn.com/data-center-capital-atlas/virginia)[Washington 9 / 22](https://savrn.com/data-center-capital-atlas/washington)[Washington, DC 0 / 0](https://savrn.com/data-center-capital-atlas/washington-dc)[West Virginia 4 / 3](https://savrn.com/data-center-capital-atlas/west-virginia)[Wisconsin 4 / 45](https://savrn.com/data-center-capital-atlas/wisconsin)[Wyoming 11 / 5](https://savrn.com/data-center-capital-atlas/wyoming)

Figures beside each state are named sites and blocked, delayed or restricted projects.

Part of the [North American Data Center Capital Atlas](https://savrn.com/data-center-capital-atlas), refreshed every Tuesday, Thursday and Saturday. Announced commitments overlap one another and overlap reported capital expenditure, so this page shows disclosed floors and never adds them into a single deployment figure. Informational, not investment or legal advice.

The SAVRN reference set

## Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.

Delay Watchlist

Project-level slippage: named projects, jurisdictional actions, utility and federal dockets, SEC disclosures, and the interconnection queue.

[Open the watchlist →](https://savrn.com/data-center-delay-tracker)

Moratorium Tracker

The policy layer: every state measure and local moratorium mapped and cited, with one page per state.

Open the tracker →

Water Tracker

Every federal, state, local and interstate water measure that touches a data center, plus a fifty-state water ledger.

Open the water tracker →

Grid Operator Watchlist

ERCOT, PJM, MISO, CAISO, SPP, NYISO, ISO-NE and FERC: the large-load rules, filings and queue positions that decide whether a site can energize.

Open the watchlist →

Permits and Power Development

Data center and substation permits, large loads in the interconnection queues, and the power plants planned to serve them, refreshed hourly from public records.

Open the permits tracker →

SAVRN Scarcity Tracker

Eleven primary-sourced indicators of AI infrastructure scarcity, one composite index, read against the token index, SAVRN's own cost basis and the frontier ceiling.