# Nevada Data Center Investment Tracker
Source: https://savrn.com/data-center-capital-atlas/nevada
Markdown alternate of the page above; the site index is https://savrn.com/llms.txt

---

Named sites

8

Site-level commitments the atlas records in Nevada

Disclosed capital floor

$7.2B

Sum of sites with a stated dollar figure. Sites without one are listed, not counted

Disclosed capacity

243 MW

Sum of sites with a stated megawatt figure

Blocked, delayed or restricted

12

$1.0B of announced capital in those projects

Who is investing

## Who is investing in data centers in Nevada?

The largest disclosed commitments in Nevada are n.a. (Fleet Data Centers Reno-area hyperscale facility (SV RNO), $3.8B); DigitalBridge (Switch Nevada AI campus, $3.0B); Alphabet / Google (Nevada campuses (Storey and Clark counties), ≥$400M). Together the 8 named sites here carry a disclosed floor of $7.2B; sites with no dollar figure are listed but not counted.

[DigitalBridge 1 site · $3.0B](https://savrn.com/data-center-capital-atlas/company/digitalbridge)[Alphabet / Google 1 site · $400M](https://savrn.com/data-center-capital-atlas/company/alphabet)

Named sites

## Named data center sites in Nevada

Each row is one site-level commitment with its capital provider, the figure the source states, and the status the source gives it. Capital is shown as one compact figure; the verbatim wording is in the row's sources.

| Site | Capital provider | Place | Capital | MW | Status | Sources |
| --- | --- | --- | --- | --- | --- | --- |
| Fleet Data Centers Reno-area hyperscale facility (SV RNO) | n.a.with Fleet Data Centers | Storey County | $3.8B | 200 | construction |  |
| Switch Nevada AI campus | [DigitalBridge](https://savrn.com/data-center-capital-atlas/company/digitalbridge)with IFM Investors | n.a. | $3.0B | n.a. | announced |  |
| Nevada campuses (Storey and Clark counties)In-year investment; cumulative since 2019 | [Alphabet / Google](https://savrn.com/data-center-capital-atlas/company/alphabet) | Storey and Clark counties | ≥$400M | n.a. | expansion |  |
| Colovore Reno 1 data centerGOED approval announced Wednesday 5 August 2026; reported 7 August 2026; single-outlet report (Las Vegas Sun) | Colovore | Near Tahoe Reno Industrial Center, Storey County | $30M | n.a. | incentive approved |  |
| Webb Data Center (9710 and 9730 N. Virginia Street, North Valleys)Approved December 2024; appeal denied January 2025; under construction; single outlet (Reno Gazette-Journal) | Webb Data Center (developer not named in source; Colovore lists pre-leasing)with Colovore | Reno, Washoe County | n.a. | 28 | under construction |  |
| Oppidan Data Center (9630 N. Virginia Street, North Valleys)Application November 2024; approved March 2025; under construction; single outlet (Reno Gazette-Journal) | Oppidan | Reno, Washoe County | n.a. | 8 | under construction |  |
| Keystone Data Center (265 Keystone Avenue)Application November 2024; approved January 2025; under construction; single outlet (Reno Gazette-Journal) | Centra | Reno, Washoe County | n.a. | 7 | under construction |  |
| Monarch Data CenterApproved 3-1 on 6 August 2026; reported 6 and 7 August 2026 | Copia Power | Yerington, Lyon County | n.a. | n.a. | approved |  |

Capital at risk

## Blocked, delayed or restricted in Nevada

Every project in Nevada on the atlas's capital-at-risk record: the action taken, who took it, and the announced capital affected. Restarts and reversals are recorded with the same weight as blocks.

| Project | Developer | Jurisdiction | Action | Capital | Sources |
| --- | --- | --- | --- | --- | --- |
| Tract Northern Nevada portfoliolitigation 2026; disqualification motion argued before Judge Scott Freeman, reported 30 September 2026 (single outlet), no ruling yet | Tract | Storey County / Washoe County | Tract has purchased more than 12,000 acres across northern Nevada; company says it never sought subsidized costs and committed nearly $1B toward NV Energy infrastructure. Related to Tract's earlier land dispute victory against Switch in Reno. Washoe County District Judge Scott Freeman heard arguments on Tract's motion to disqualify NV Energy attorney Adam Hosmer-Henner from the utility's lawsuit against Tract; Tract claims the attorney's firm previously obtained its confidential data. No ruling was reported. | $1.0B |  |
| Fallon Paiute-Shoshone Tribe data center moratoriummoratorium Enacted May 2026 | n.a. | Fallon Paiute-Shoshone Tribe | Fallon Paiute-Shoshone Tribe, Nevada, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated May 2026. First tribe in Northern Nevada to ban data centers on tribal lands; resolution brought by tribal council secretary Philip Johnson. The measure has no end date by design. | n.a. |  |
| Henderson 180-day data center moratorium proposal (declined)other Moratorium declined 21 July 2026 | n.a. | City of Henderson | On 21 July 2026 the Henderson City Council declined a proposed 180-day moratorium on new data center applications. Council instead directed staff to strengthen the development agreement framework so future applicants must address water consumption, electrical demand, noise and site-specific concerns. Officials noted new projects could see effective delays while the framework is developed. | n.a. |  |
| Humboldt County data center moratoriummoratorium Enacted July 2026 | n.a. | Humboldt County | Humboldt County, Nevada, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated July 2026. Temporary moratorium on data center applications through 13 July 2027 while the county updates land-use rules on water, power and infrastructure; multiple developers had approached the county and its code did not address data centers. The measure runs to 13 July 2027. | n.a. |  |
| Hyperscale data center and natural gas plant on BLM land near Henderson (Paradise Hills area)withdrawn Application filed November 2025; withdrawal announced 24 September 2026 | Skylar Opportunities LLC (affiliate of Skylar Capital Management) | Bureau of Land Management / City of Henderson | A Texas-based developer canceled a proposed 1,000 MW hyperscale data center and natural gas plant on 680 acres of BLM land near the southeastern tip of Henderson, close to the Paradise Hills community. In a statement on Thursday 24 September 2026 the developer said it had consulted with the city and BLM and withdrew its application because of the city's planned urban development in the same area. Skylar Opportunities LLC is an affiliate of Skylar Capital Management, the company behind the Boulder City Townsite project on BLM land (row 180). | n.a. |  |
| Pahrump Valley data center ban (Nye County Bill No. 2026-11)moratorium Adopted 18 August 2026; developer petition for judicial review filed September 2026 (reported 24 and 25 September 2026) | n.a. | Nye County | County commissioners voted 5-0 on 18 August 2026 to adopt Bill No. 2026-11, amending Nye County Code Title 17 to prohibit data center development in the Pahrump Valley and Hydrographic Basin 162, an over-appropriated basin. A separate motion setting a 14 September 2026 public hearing on land use standards for data centers elsewhere in the county passed 4-1. A proposal to put the ban to a special election died without a motion. Earlier in September 2026 CDDC, LLC and 9 of a Kind, LLC, which own nearly 911 acres along Carpenter Canyon Road and State Route 160 planned for the Manse Technology Campus (MTC Project), petitioned the Nye County district court to reverse the ban (Ordinance No. 631), allow the project to proceed and award attorney's fees, arguing the ordinance disregarded their investment made in reliance on existing zoning and violated their property rights. Commissioner Ian Bayne, who proposed the ban, said he remained confident in it. No initial court date had been scheduled as of 25 September 2026. | n.a. |  |
| Pyramid Lake Paiute Tribe data center moratoriummoratorium Enacted August 2026 | n.a. | Pyramid Lake Paiute Tribe | Pyramid Lake Paiute Tribe, Nevada, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated August 2026. Tribal Council passed permanent ban on data centers on tribal homelands; Chairman Steven Wadsworth cited water sovereignty and protecting endangered cui-ui fish. Part of Water Over Data Alliance tribal coalition demanding free, prior, and informed consent for data centers in Truckee River watershed. The measure has no end date by design. | n.a. |  |
| Reno citywide data center moratoriummoratorium Final moratorium approved 6-1, reported 1 June 2026; runs through 31 August 2027 | n.a. | City of Reno | The Reno City Council voted 6-1 to adopt a pending moratorium at a 14 May 2026 special meeting, then approved the final moratorium 6-1 in early June 2026. The moratorium runs through 31 August 2027 and cannot be lifted until new regulations are adopted. Council directed staff to draft rules on water and energy use, noise, air quality, community benefits and allowed locations. Already permitted data centers are not affected. | n.a. |  |
| Townsite Data Centercourt halt BLM right-of-way amendment approved 26 June 2026; IBLA stay issued 1 September 2026; BLM motion to set aside and remand filed 21 September 2026; Boulder City response due 5 October 2026 | Townsite Solar 2 LLC | Boulder City area, Clark County | The Interior Board of Land Appeals stayed construction of the Townsite Data Center on 1 September 2026, an 88.5-acre facility the Bureau of Land Management approved on public land roughly 25 miles southeast of Las Vegas near Boulder City, and reported as the first AI data center approved on federal public land. The board found BLM likely acted unlawfully when it amended an existing right-of-way grant in June 2026 to permit a data center without a project-specific environmental review. Opponents cited projected electricity and water demand, soil disruption, light pollution and habitat loss for the Mojave desert tortoise. BLM had until 21 September 2026 to respond. This is an interim stay, not a final decision, and no capital figure has been disclosed. In a filing on Monday 21 September 2026, BLM asked Interior Board of Land Appeals Administrative Judge David Gunter, who granted the stay, to set aside its approval of the right-of-way amendment so the agency can conduct additional review of the application. Townsite Solar 2 LLC supports the motion, the Center for Biological Diversity and the Sierra Club are neutral, and Boulder City opposes it, with its response due 5 October 2026; the city said the motion does not commit BLM to an environmental assessment or public involvement and its approval would lift the stay. | n.a. |  |
| Trammell Crow Bentonite Avenue data center complex (Henderson)withdrawn City notified March 2026; reported 3 August 2026 | Trammell Crow Co. | City of Henderson | Henderson officials said a data center complex approved by the Planning Commission in November 2025 is no longer moving forward. Trammell Crow Co. had received a conditional use permit and design review with a six-year approval period for five buildings on 157.3 acres. The city said a real estate agent told it in March 2026 that the project was off and the owner, Eldorado Hills LLC, was looking to sell for traditional industrial development. No further data center applications have been filed for the site. | n.a. |  |
| Wells data center moratoriummoratorium Enacted June 2026 | n.a. | Wells | Wells, Nevada, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated June 2026. Small rural city (Elko County) approved moratorium on data center approvals pending staff recommendations. The measure has no documented term. | n.a. |  |
| White Pine County data center moratoriummoratorium Enacted July 2026 | n.a. | White Pine County | White Pine County, Nevada, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated July 2026. Resolution 2026-18: 180-day moratorium on accepting, processing or approving land-use applications for data center development while staff draft zoning standards; renewable. End date is 180 days from adoption. The measure runs to 18 January 2027. | n.a. |  |

Financing

## Financing transactions tied to Nevada sites

Transactions the atlas ties to a named site in Nevada: joint ventures, project bonds, credit facilities, leases and power agreements. Amounts are as stated; overlapping commitments are never summed.

| Parties | Instrument | Amount | Date | Site | Sources |
| --- | --- | --- | --- | --- | --- |
| Fleet Data Centers + SV RNO Property Owner I, LLCFleet Data Centers announced the pricing of $3.8 billion aggregate principal amount of 5.875% senior secured notes due 1 March 2031, issued by SV RNO Property Owner I, LLC. Proceeds finance a portion of the development and construction of a 230 MW utility capacity (200 MW critical IT capacity) turnkey data center and electrical substation on a 252-acre property in Storey County, Nevada, plus associated fees and expenses. The release states the facility is 100% leased under a 197-month triple net lease to a tenant it describes only as an AA- investment grade rated tenant with a market capitalization in excess of $3 trillion. The tenant is not named in the release and is not named here. | project bond | $3.8B | Priced 13 February 2026 | Fleet Data Centers Reno-area hyperscale facility (SV RNO) |  |
| Nevada Governor's Office of Economic Development + Colovore Reno 1 LLCGOED approved $17.6 million in abatements for nine companies, including $4.08 million for Colovore's Storey County data center. The abatements are performance-based and must be repaid if commitments are not met | incentive | $4M | Announced Wednesday 5 August 2026 | Colovore Reno 1 data center |  |

Policy context

## What governs a data center in Nevada

Nevada (Executive Order 2026-005)state

Conditions on new tax abatement applications not yet reviewed by the GOED Board; existing abatements unchanged. Not a moratorium

Governor Joe Lombardo signed Executive Order 2026-005, setting the Nevada Standard for Responsible Data Center Development, on 17 September 2026 bars GOED abatement applications from going to the Board unless the developer pays the Local School Support Tax in full and signs a Nevada Community Support Commitment covering local water standards, paying the full cost of service without shifting it to ratepayers, and curtailing load in grid emergencies. GOED is to publish standard terms by 6 November 2026 and the Nevada Office of Energy a Responsible Speed to Power Plan by 31 December 2026. The Nevada Independent reported $236 million in missed school support taxes and $461 million in expected breaks over 11 years

The policy layer for Nevada lives in three companion references: the [Nevada Data Center Moratorium Tracker](https://savrn.com/data-center-moratorium-tracker/nevada) for every state measure and local moratorium on record, the [Water Tracker](https://savrn.com/data-center-water-tracker) for the water rules that touch a site, and the [Grid Operator Watchlist](https://savrn.com/data-center-grid-operator-watchlist) for the large-load rules of the RTO or utility that decides whether it can energize.

Next door

## States next door

California

10 sites

35 blocked, delayed or restricted

Utah

11 sites · $13.0B disclosed

12 blocked, delayed or restricted

Arizona

11 sites · $25.4B disclosed

11 blocked, delayed or restricted

Oregon

1 site

8 blocked, delayed or restricted

Idaho

2 sites · $1.2B disclosed

2 blocked, delayed or restricted

On the map

## Data centers in Nevada

The US Data Center Map identifies 61 facilities run by 27 operators in Nevada, each one placed from primary sources and listed by city and by operator, with this atlas record beside it.

Nevada data centers

61 facilities · 27 operators

Map, locations, operators, rules

Nevada power and local economy

Generation, utilities and county records

Explore the power supply chain and local conditions behind the build-out

US Data Center Map

Every state, one page each

The national map and the operator directory

Sources

## Sources for Nevada

Every source cited on this page, once each. The full atlas source register is at [Capital Atlas sources](https://savrn.com/data-center-capital-atlas/sources).

- fleetdatacenters.com[Fleet Data Centers](https://fleetdatacenters.com/news/fleet-data-centers-announces-pricing-of-3-8-billion-of-senior-secured-notes-for-hyperscale-facility-in-rapidly-growing-reno-hub/)
- einpresswire.com[EIN Presswire](https://www.einpresswire.com/article/892161131/fleet-data-centers-announces-pricing-of-3-8-billion-of-senior-secured-notes-for-hyperscale-facility-in-growing-reno-hub)
- yahoo.com[Nevada Current via Yahoo](https://www.yahoo.com/news/us/articles/private-gas-plants-power-data-120039669.html)
- yahoo.com[Nevada Current via Yahoo News](https://www.yahoo.com/news/us/articles/public-utility-commission-approves-gas-115403579.html)
- nevadacurrent.com[Nevada Current](https://nevadacurrent.com/2026/09/18/public-utility-commission-approves-gas-plants-to-power-data-centers/)
- thenevadaindependent.com[The Nevada Independent](https://thenevadaindependent.com/article/why-a-northern-nevada-data-center-wants-to-build-its-own-temporary-natural-gas-power-plant)
- nnbw.com[Northern Nevada Business Weekly](https://www.nnbw.com/news/2026/jun/02/fleet-data-centers-breaks-ground-on-2-facilities/)
- msn.com[Las Vegas Review-Journal via MSN](https://www.msn.com/en-us/news/other/nevada-data-center-growth-drives-approval-of-temporary-gas-plants/ar-AA2cP0Er)
- datacenterdynamics.com[DCD](https://www.datacenterdynamics.com/en/news/digitalbridge-has-54gw-of-data-center-capacity-in-operation-or-under-construction/)
- thenevadaindependent.com[The Nevada Independent](https://thenevadaindependent.com/article/google-to-spend-400-million-to-expand-nevada-data-centers)
- lasvegassun.com[Las Vegas Sun](https://lasvegassun.com/news/2026/aug/07/nine-companies-secure-tax-breaks-while-promising-m/)
- msn.com[Reno Gazette-Journal (via MSN)](https://www.msn.com/en-us/news/other/3-reno-data-centers-under-construction-in-october-here-s-where/ar-AA2dq2KT)
- mynews4.com[KRNV News 4](https://mynews4.com/news/local/lyon-county-commissioners-approve-monarch-data-center-near-yerington)
- kolotv.com[KOLO 8 News Now](https://www.kolotv.com/2026/08/07/lyon-county-commissioners-approve-monarch-data-center/)
- thenevadaindependent.com[Thenevadaindependent](https://thenevadaindependent.com/article/nevadas-electric-utility-is-suing-a-major-data-center-company-heres-why)
- tract.com[Tract](https://www.tract.com/news/tract-achieves-major-court-victory-against-switch-in-reno-data-center-land-dispute/)
- thisisreno.com[This Is Reno](https://thisisreno.com/2026/09/utility-attorney-disqualification-hearing/)
- kunr.org[kunr.org](https://www.kunr.org/energy-and-environment/2026-09-02/northern-nevada-tribes-speak-out-against-data-centers)
- news3lv.com[News 3 Las Vegas](https://news3lv.com/news/local/henderson-to-revise-data-center-rules-instead-of-approving-moratorium)
- 8newsnow.com[KLAS 8 News Now](https://www.8newsnow.com/news/local-news/henderson-halts-data-center-applications-for-180-days-officials-said-they-need-more-data/)
- thenevadaindependent.com[thenevadaindependent.com](https://thenevadaindependent.com/article/how-has-your-city-or-county-regulated-data-centers-heres-the-latest-in-nevada)
- reviewjournal.com[Las Vegas Review-Journal](https://www.reviewjournal.com/news/environment/developer-pulls-out-of-hyperscale-data-center-natural-gas-plant-proposed-on-blm-land-in-henderson-3890611/)
- msn.com[Las Vegas Review-Journal via MSN](https://www.msn.com/en-us/money/technology/developer-pulls-out-of-hyperscale-data-center-natural-gas-plant-proposed-on-blm-land-in-henderson/ar-AA2cUIWx)
- pvtimes.com[Pahrump Valley Times](https://pvtimes.com/news/data-centers-banned-in-pahrump-189671/)
- ktnv.com[KTNV](https://www.ktnv.com/news/companies-sue-nye-county-over-data-center-development-ban)
- reviewjournal.com[Las Vegas Review-Journal](https://www.reviewjournal.com/news/politics-and-government/nevada/developer-asks-judge-to-toss-pahrump-data-center-ban-amid-water-fight-3891110/)
- mynews4.com[News 4 (KRNV)](https://mynews4.com/news/local/no-new-data-centers-in-reno-as-city-council-adopts-final-moratorium-starts-drafting-new-regulations-rules-ordinances)
- datacenterbans.com[Data Center Bans](https://www.datacenterbans.com/state/nevada)
- outdoorlife.com[Outdoor Life](https://www.outdoorlife.com/conservation/public-land-data-center-paused/)
- nationofchange.org[NationofChange](https://www.nationofchange.org/2026/09/02/federal-panel-halts-first-data-center-planned-for-us-public-land/)
- alaska-native-news.com[Alaska Native News](https://alaska-native-news.com/federal-panel-halts-what-would-be-first-data-center-on-public-lands/86009/)
- reviewjournal.com[Las Vegas Review-Journal](https://www.reviewjournal.com/news/environment/blm-asks-judge-to-set-aside-boulder-city-data-center-approval-3889402/)
- reviewjournal.com[Las Vegas Review-Journal](https://www.reviewjournal.com/local/henderson/data-center-project-in-henderson-no-longer-moving-forward-3858426/)
- elynews.com[elynews.com](https://elynews.com/2026/07/30/joint-white-pine-county-commission-road-commission-and-liquor-board-meeting/)
- gov.nv.gov[Governor of Nevada, Executive Order 2026-005](https://gov.nv.gov/executive-actions/executive-orders/2026-executive-orders/eo-2026-005/)
- news3lv.com[News3LV](https://news3lv.com/news/local/nevada-governor-signs-executive-order-setting-new-rules-for-state-data-center-development)
- thenevadaindependent.com[The Nevada Independent](https://thenevadaindependent.com/article/lombardo-curtails-nevada-data-center-tax-break-program-in-executive-order)
- kolotv.com[KOLO](https://www.kolotv.com/2026/09/18/lombardo-signs-order-placing-restrictions-data-centers/)

### Every state, one page each

[Alabama 9 / 21](https://savrn.com/data-center-capital-atlas/alabama)[Alaska 1 / 1](https://savrn.com/data-center-capital-atlas/alaska)[Arizona 11 / 11](https://savrn.com/data-center-capital-atlas/arizona)[Arkansas 2 / 8](https://savrn.com/data-center-capital-atlas/arkansas)[California 10 / 35](https://savrn.com/data-center-capital-atlas/california)[Colorado 6 / 21](https://savrn.com/data-center-capital-atlas/colorado)[Connecticut 0 / 6](https://savrn.com/data-center-capital-atlas/connecticut)[Delaware 0 / 5](https://savrn.com/data-center-capital-atlas/delaware)[Florida 0 / 46](https://savrn.com/data-center-capital-atlas/florida)[Georgia 23 / 57](https://savrn.com/data-center-capital-atlas/georgia)[Hawaii 0 / 0](https://savrn.com/data-center-capital-atlas/hawaii)[Idaho 2 / 2](https://savrn.com/data-center-capital-atlas/idaho)[Illinois 10 / 35](https://savrn.com/data-center-capital-atlas/illinois)[Indiana 14 / 44](https://savrn.com/data-center-capital-atlas/indiana)[Iowa 3 / 22](https://savrn.com/data-center-capital-atlas/iowa)[Kansas 5 / 19](https://savrn.com/data-center-capital-atlas/kansas)[Kentucky 6 / 26](https://savrn.com/data-center-capital-atlas/kentucky)[Louisiana 7 / 3](https://savrn.com/data-center-capital-atlas/louisiana)[Maine 0 / 20](https://savrn.com/data-center-capital-atlas/maine)[Maryland 1 / 22](https://savrn.com/data-center-capital-atlas/maryland)[Massachusetts 0 / 11](https://savrn.com/data-center-capital-atlas/massachusetts)[Michigan 4 / 55](https://savrn.com/data-center-capital-atlas/michigan)[Minnesota 3 / 31](https://savrn.com/data-center-capital-atlas/minnesota)[Mississippi 7 / 5](https://savrn.com/data-center-capital-atlas/mississippi)[Missouri 10 / 25](https://savrn.com/data-center-capital-atlas/missouri)[Montana 1 / 10](https://savrn.com/data-center-capital-atlas/montana)[Nebraska 3 / 16](https://savrn.com/data-center-capital-atlas/nebraska)[Nevada 8 / 12](https://savrn.com/data-center-capital-atlas/nevada)[New Hampshire 0 / 5](https://savrn.com/data-center-capital-atlas/new-hampshire)[New Jersey 4 / 61](https://savrn.com/data-center-capital-atlas/new-jersey)[New Mexico 3 / 10](https://savrn.com/data-center-capital-atlas/new-mexico)[New York 6 / 21](https://savrn.com/data-center-capital-atlas/new-york)[North Carolina 10 / 45](https://savrn.com/data-center-capital-atlas/north-carolina)[North Dakota 6 / 4](https://savrn.com/data-center-capital-atlas/north-dakota)[Ohio 24 / 80](https://savrn.com/data-center-capital-atlas/ohio)[Oklahoma 11 / 20](https://savrn.com/data-center-capital-atlas/oklahoma)[Oregon 1 / 8](https://savrn.com/data-center-capital-atlas/oregon)[Pennsylvania 16 / 42](https://savrn.com/data-center-capital-atlas/pennsylvania)[Rhode Island 0 / 5](https://savrn.com/data-center-capital-atlas/rhode-island)[South Carolina 6 / 20](https://savrn.com/data-center-capital-atlas/south-carolina)[South Dakota 1 / 6](https://savrn.com/data-center-capital-atlas/south-dakota)[Tennessee 6 / 26](https://savrn.com/data-center-capital-atlas/tennessee)[Texas 106 / 35](https://savrn.com/data-center-capital-atlas/texas)[Utah 11 / 12](https://savrn.com/data-center-capital-atlas/utah)[Vermont 0 / 3](https://savrn.com/data-center-capital-atlas/vermont)[Virginia 33 / 50](https://savrn.com/data-center-capital-atlas/virginia)[Washington 9 / 22](https://savrn.com/data-center-capital-atlas/washington)[Washington, DC 0 / 0](https://savrn.com/data-center-capital-atlas/washington-dc)[West Virginia 4 / 3](https://savrn.com/data-center-capital-atlas/west-virginia)[Wisconsin 4 / 45](https://savrn.com/data-center-capital-atlas/wisconsin)[Wyoming 11 / 5](https://savrn.com/data-center-capital-atlas/wyoming)

Figures beside each state are named sites and blocked, delayed or restricted projects.

Part of the [North American Data Center Capital Atlas](https://savrn.com/data-center-capital-atlas), refreshed every Tuesday, Thursday and Saturday. Announced commitments overlap one another and overlap reported capital expenditure, so this page shows disclosed floors and never adds them into a single deployment figure. Informational, not investment or legal advice.

The SAVRN reference set

## Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.

Delay Watchlist

Project-level slippage: named projects, jurisdictional actions, utility and federal dockets, SEC disclosures, and the interconnection queue.

[Open the watchlist →](https://savrn.com/data-center-delay-tracker)

Moratorium Tracker

The policy layer: every state measure and local moratorium mapped and cited, with one page per state.

Open the tracker →

Water Tracker

Every federal, state, local and interstate water measure that touches a data center, plus a fifty-state water ledger.

Open the water tracker →

Grid Operator Watchlist

ERCOT, PJM, MISO, CAISO, SPP, NYISO, ISO-NE and FERC: the large-load rules, filings and queue positions that decide whether a site can energize.

Open the watchlist →

Permits and Power Development

Data center and substation permits, large loads in the interconnection queues, and the power plants planned to serve them, refreshed hourly from public records.

Open the permits tracker →

SAVRN Scarcity Tracker

Eleven primary-sourced indicators of AI infrastructure scarcity, one composite index, read against the token index, SAVRN's own cost basis and the frontier ceiling.

Open the scarcity tracker →

Have a specific address? Site Intelligence reads all seven references against one location, county, utility and grid operator included, and cites every finding.

[Check an address →](https://savrn.com/site-intelligence)