# South Dakota Data Center Investment Tracker
Source: https://savrn.com/data-center-capital-atlas/south-dakota
Markdown alternate of the page above; the site index is https://savrn.com/llms.txt

---

Named sites

1

Site-level commitments the atlas records in South Dakota

Disclosed capital floor

n.a.

Sum of sites with a stated dollar figure. Sites without one are listed, not counted

Disclosed capacity

50 MW

Sum of sites with a stated megawatt figure

Blocked, delayed or restricted

6

$17.9B of announced capital in those projects

Who is investing

## Who is investing in data centers in South Dakota?

The named commitments in South Dakota carry no disclosed dollar figure yet. The record is .

Named sites

## Named data center sites in South Dakota

Each row is one site-level commitment with its capital provider, the figure the source states, and the status the source gives it. Capital is shown as one compact figure; the verbatim wording is in the row's sources.

| Site | Capital provider | Place | Capital | MW | Status | Sources |
| --- | --- | --- | --- | --- | --- | --- |
| Leola Data CenterPUC approval reported 8 to 9 September 2026; county conditional use permit deferred | Leola Data Centerwith Montana-Dakota Utilities | Leola, McPherson County | n.a. | 50 | utility service approved; county permit pending |  |

Capital at risk

## Blocked, delayed or restricted in South Dakota

Every project in South Dakota on the atlas's capital-at-risk record: the action taken, who took it, and the announced capital affected. Restarts and reversals are recorded with the same weight as blocks.

| Project | Developer | Jurisdiction | Action | Capital | Sources |
| --- | --- | --- | --- | --- | --- |
| Applied Digital Torontocancelled January 6, 2026 | Applied Digital | Toronto | Applied Digital confirmed its proposed $5B, 430MW data center campus near Toronto, SD is 'unlikely to go forward' after the legislature rejected tax incentives. | $16.0B |  |
| Sioux Falls Hyperscale Data Centermoratorium February 24, 2026 | Gemini Data Center SD LLC (Gemini Capital) | Lincoln County | Lincoln County Commissioner Joel Arends proposed a one-year moratorium on hyperscale data centers requiring 100+ MW, calling it an opportunity to 'press pause and further research' the impacts of projects like Gemini | $1.9B |  |
| Aberdeen data center permit moratoriummoratorium Passed July 2026 (exact date not stated); runs to 18 November 2026; extension to 1 July 2027 set for a hearing on 19 October 2026 at the Monday 5 October 2026 council meeting | n.a. | Aberdeen City Council | Aberdeen passed a moratorium on data center building and zoning permits in July 2026, under which city officials may not issue permits authorizing construction, expansion or operation of a data center within city limits; it runs to 18 November 2026. The council's Monday 5 October 2026 agenda set a public hearing for 19 October 2026 on Resolution 26-07-04R, which would extend it to 1 July 2027, citing water supply and noise. | n.a. |  |
| Applied Digital Toronto data center campuspaused Company statement 13 March 2026 that the project is unlikely to go forward | Applied Digital | Deuel County / State of South Dakota | Applied Digital told KELOLAND News on 13 March 2026 that its proposed data center near Toronto, South Dakota, is unlikely to go forward, after the 2026 Legislature declined to pass a sales and use tax exemption for data center equipment (House Bill 1005 failed in committee). CEO Wes Cummins said later in March that he does not expect any projects in the state for now. | n.a. |  |
| Lincoln County data center moratorium amendment (failed; Gemini Sioux Falls data center)other Moratorium amendment failed 3-2 on 25 August 2026; regulation hearing set for 27 October 2026 | Gemini (Sioux Falls data center) | Lincoln County Commission | At a joint meeting with the Sioux Falls City Council on Tuesday 25 August 2026, the Lincoln County Commission voted 3-2 against Commissioner Joel Arends' amendment to schedule a hearing on a data center moratorium, attached to adoption of the Sioux Falls 2050 comprehensive plan. A companion amendment barring non-disclosure agreements on zoning proposals also failed. The commission instead approved a public hearing on data center regulation for 27 October 2026. The Sioux Falls City Council had approved the controversial Gemini data center. | n.a. |  |
| Yankton County six-month data center and bitcoin mining moratoriummoratorium Approved unanimously 21 July 2026; six months, extendable six months | n.a. | Yankton County Commission | Yankton County commissioners voted unanimously on Tuesday 21 July 2026 to pass a six-month moratorium on data center and bitcoin mining facility permits, shorter than the 12 months on the agenda. The commission may extend it another six months if no ordinance is drafted. The pause gives the county time to study economic and environmental effects and write regulations. The vote followed nearly an hour of public comment. | n.a. |  |

Policy context

## What governs a data center in South Dakota

The policy layer for South Dakota lives in three companion references: the [South Dakota Data Center Moratorium Tracker](https://savrn.com/data-center-moratorium-tracker/south-dakota) for every state measure and local moratorium on record, the [Water Tracker](https://savrn.com/data-center-water-tracker) for the water rules that touch a site, and the [Grid Operator Watchlist](https://savrn.com/data-center-grid-operator-watchlist) for the large-load rules of the RTO or utility that decides whether it can energize.

Next door

## States next door

Minnesota

3 sites

31 blocked, delayed or restricted

Iowa

3 sites · $7.0B disclosed

22 blocked, delayed or restricted

Nebraska

3 sites

16 blocked, delayed or restricted

Wyoming

11 sites · $57.8B disclosed

5 blocked, delayed or restricted

Montana

1 site

10 blocked, delayed or restricted

North Dakota

6 sites · $26.9B disclosed

4 blocked, delayed or restricted

On the map

## Data centers in South Dakota

The US Data Center Map identifies 11 facilities run by 5 operators in South Dakota, each one placed from primary sources and listed by city and by operator, with this atlas record beside it.

South Dakota data centers

11 facilities · 5 operators

Map, locations, operators, rules

South Dakota power and local economy

Generation, utilities and county records

Explore the power supply chain and local conditions behind the build-out

US Data Center Map

Every state, one page each

The national map and the operator directory

Sources

## Sources for South Dakota

Every source cited on this page, once each. The full atlas source register is at [Capital Atlas sources](https://savrn.com/data-center-capital-atlas/sources).

- sdpb.org[SDPB](https://www.sdpb.org/politics/2026-09-09/leola-data-center-electricity-to-be-served-by-mdu-next-faces-county-permitting)
- datacenterdynamics.com[datacenterdynamics.com](https://www.datacenterdynamics.com/en/news/applied-digital-says-data-center-near-toronto-south-dakota-unlikely-to-go-forward/)
- southdakotasearchlight.com[southdakotasearchlight.com](https://southdakotasearchlight.com/2026/04/02/one-data-center-project-unchanged-while-another-doesnt-make-sense-after-rejected-incentives/)
- mitchellrepublic.com[mitchellrepublic.com](https://www.mitchellrepublic.com/news/south-dakota/lincoln-county-backs-down-on-hyperscale-data-center-moratorium)
- dakotanewsnetwork.com[dakotanewsnetwork.com](https://www.dakotanewsnetwork.com/2026/02/27/lincoln-county-commissioners-discuss-moratorium-on-building-data-centers)
- kelo.com[kelo.com](https://kelo.com/2026/02/26/889056/)
- siouxfalls.business[siouxfalls.business](https://siouxfalls.business/hyperscale-data-center-seeking-city-approvals-to-build-northeast-of-sioux-falls/)
- sdpb.org[sdpb.org](https://www.sdpb.org/business-economics/2025-08-15/la-based-company-looking-to-build-data-center-in-sioux-falls)
- siouxfalls.business[siouxfalls.business](https://siouxfalls.business/sioux-falls-data-center-developers-detail-next-steps/)
- siouxfallslive.com[siouxfallslive.com](https://www.siouxfallslive.com/news/sioux-falls/sioux-falls-group-wants-citywide-vote-on-data-center-rezone)
- keloland.com[keloland.com](https://www.keloland.com/news/local-news/where-to-sign-petitions-to-bring-data-center-to-a-vote/)
- siouxfallslive.com[siouxfallslive.com](https://www.siouxfallslive.com/news/sioux-falls/planned-data-center-sparks-outrage-in-downtown-sioux-falls)
- sdnewswatch.org[sdnewswatch.org](https://www.sdnewswatch.org/gemini-data-center-power-usage-sioux-falls-sd-ai-electricty/)
- keloland.com[KELOLAND News, 5 October 2026](https://www.keloland.com/keloland-com-original/aberdeen-considers-data-center-moratorium-extension/amp/)
- aberdeeninsider.com[Aberdeen Insider, 6 October 2026](https://aberdeeninsider.com/council-sets-oct-19-hearing-to-discuss-data-center-moratorium-extension/)
- keloland.com[KELOLAND (13 March 2026)](https://www.keloland.com/news/local-news/deuel-county-data-center-unlikely-to-go-forward/amp/)
- keloland.com[KELOLAND (23 March 2026)](https://www.keloland.com/keloland-com-original/applied-digital-says-sd-data-center-future-unclear/amp)
- yahoo.com[Argus Leader via Yahoo News](https://www.yahoo.com/news/us/articles/data-center-moratorium-shot-down-162241974.html)
- lennoxnews.com[Lennox News](https://www.lennoxnews.com/single-post/lincoln-county-sioux-falls-approve-2050-plan-data-center-moratorium-rejected)
- ktiv.com[KTIV](https://www.ktiv.com/2026/07/22/data-center-moratorium-passes-yankton-county-south-dakota/)
- yankton.net[Yankton Press & Dakotan](https://www.yankton.net/community/article_77f0cd48-dbbc-4f5d-9f5b-56b709da8a36.html)

### Every state, one page each

[Alabama 9 / 21](https://savrn.com/data-center-capital-atlas/alabama)[Alaska 1 / 1](https://savrn.com/data-center-capital-atlas/alaska)[Arizona 11 / 11](https://savrn.com/data-center-capital-atlas/arizona)[Arkansas 2 / 8](https://savrn.com/data-center-capital-atlas/arkansas)[California 10 / 35](https://savrn.com/data-center-capital-atlas/california)[Colorado 6 / 21](https://savrn.com/data-center-capital-atlas/colorado)[Connecticut 0 / 6](https://savrn.com/data-center-capital-atlas/connecticut)[Delaware 0 / 5](https://savrn.com/data-center-capital-atlas/delaware)[Florida 0 / 46](https://savrn.com/data-center-capital-atlas/florida)[Georgia 23 / 57](https://savrn.com/data-center-capital-atlas/georgia)[Hawaii 0 / 0](https://savrn.com/data-center-capital-atlas/hawaii)[Idaho 2 / 2](https://savrn.com/data-center-capital-atlas/idaho)[Illinois 10 / 35](https://savrn.com/data-center-capital-atlas/illinois)[Indiana 14 / 44](https://savrn.com/data-center-capital-atlas/indiana)[Iowa 3 / 22](https://savrn.com/data-center-capital-atlas/iowa)[Kansas 5 / 19](https://savrn.com/data-center-capital-atlas/kansas)[Kentucky 6 / 26](https://savrn.com/data-center-capital-atlas/kentucky)[Louisiana 7 / 3](https://savrn.com/data-center-capital-atlas/louisiana)[Maine 0 / 20](https://savrn.com/data-center-capital-atlas/maine)[Maryland 1 / 22](https://savrn.com/data-center-capital-atlas/maryland)[Massachusetts 0 / 11](https://savrn.com/data-center-capital-atlas/massachusetts)[Michigan 4 / 55](https://savrn.com/data-center-capital-atlas/michigan)[Minnesota 3 / 31](https://savrn.com/data-center-capital-atlas/minnesota)[Mississippi 7 / 5](https://savrn.com/data-center-capital-atlas/mississippi)[Missouri 10 / 25](https://savrn.com/data-center-capital-atlas/missouri)[Montana 1 / 10](https://savrn.com/data-center-capital-atlas/montana)[Nebraska 3 / 16](https://savrn.com/data-center-capital-atlas/nebraska)[Nevada 8 / 12](https://savrn.com/data-center-capital-atlas/nevada)[New Hampshire 0 / 5](https://savrn.com/data-center-capital-atlas/new-hampshire)[New Jersey 4 / 61](https://savrn.com/data-center-capital-atlas/new-jersey)[New Mexico 3 / 10](https://savrn.com/data-center-capital-atlas/new-mexico)[New York 6 / 21](https://savrn.com/data-center-capital-atlas/new-york)[North Carolina 10 / 45](https://savrn.com/data-center-capital-atlas/north-carolina)[North Dakota 6 / 4](https://savrn.com/data-center-capital-atlas/north-dakota)[Ohio 24 / 80](https://savrn.com/data-center-capital-atlas/ohio)[Oklahoma 11 / 20](https://savrn.com/data-center-capital-atlas/oklahoma)[Oregon 1 / 8](https://savrn.com/data-center-capital-atlas/oregon)[Pennsylvania 16 / 42](https://savrn.com/data-center-capital-atlas/pennsylvania)[Rhode Island 0 / 5](https://savrn.com/data-center-capital-atlas/rhode-island)[South Carolina 6 / 20](https://savrn.com/data-center-capital-atlas/south-carolina)[South Dakota 1 / 6](https://savrn.com/data-center-capital-atlas/south-dakota)[Tennessee 6 / 26](https://savrn.com/data-center-capital-atlas/tennessee)[Texas 106 / 35](https://savrn.com/data-center-capital-atlas/texas)[Utah 11 / 12](https://savrn.com/data-center-capital-atlas/utah)[Vermont 0 / 3](https://savrn.com/data-center-capital-atlas/vermont)[Virginia 33 / 50](https://savrn.com/data-center-capital-atlas/virginia)[Washington 9 / 22](https://savrn.com/data-center-capital-atlas/washington)[Washington, DC 0 / 0](https://savrn.com/data-center-capital-atlas/washington-dc)[West Virginia 4 / 3](https://savrn.com/data-center-capital-atlas/west-virginia)[Wisconsin 4 / 45](https://savrn.com/data-center-capital-atlas/wisconsin)[Wyoming 11 / 5](https://savrn.com/data-center-capital-atlas/wyoming)

Figures beside each state are named sites and blocked, delayed or restricted projects.

Part of the [North American Data Center Capital Atlas](https://savrn.com/data-center-capital-atlas), refreshed every Tuesday, Thursday and Saturday. Announced commitments overlap one another and overlap reported capital expenditure, so this page shows disclosed floors and never adds them into a single deployment figure. Informational, not investment or legal advice.

The SAVRN reference set

## Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.

Delay Watchlist

Project-level slippage: named projects, jurisdictional actions, utility and federal dockets, SEC disclosures, and the interconnection queue.

[Open the watchlist →](https://savrn.com/data-center-delay-tracker)

Moratorium Tracker

The policy layer: every state measure and local moratorium mapped and cited, with one page per state.

Open the tracker →

Water Tracker

Every federal, state, local and interstate water measure that touches a data center, plus a fifty-state water ledger.

Open the water tracker →

Grid Operator Watchlist

ERCOT, PJM, MISO, CAISO, SPP, NYISO, ISO-NE and FERC: the large-load rules, filings and queue positions that decide whether a site can energize.

Open the watchlist →

Permits and Power Development

Data center and substation permits, large loads in the interconnection queues, and the power plants planned to serve them, refreshed hourly from public records.

Open the permits tracker →

SAVRN Scarcity Tracker

Eleven primary-sourced indicators of AI infrastructure scarcity, one composite index, read against the token index, SAVRN's own cost basis and the frontier ceiling.

Open the scarcity tracker →

Have a specific address? Site Intelligence reads all seven references against one location, county, utility and grid operator included, and cites every finding.

[Check an address →](https://savrn.com/site-intelligence)