# Florida Data Center Permits Tracker
Source: https://savrn.com/data-center-permits-tracker/florida
Markdown alternate of the page above; the site index is https://savrn.com/llms.txt

---

SAVRN Tracker

# Florida Data Center Permits Tracker

Florida has 2,436 MW of generation planned within 36 months. Every row below links to its primary source.

Last checked Oct 25, 2026

0

Data center & substation permits

of 2 total utility-scale permits tracked here

0MW

In the interconnection queue

0 active generation and storage positions

2,436MW

Planned generation

28 EIA-860M generators due within 36 months

#14

of 51 states with anything on record

Ranked by data center & substation permit count

## Where the activity is

Ranked by row count. Counts are never mixed with the MW figures above.

### Permit categories

Site plan or rezoning 1

zoning 1

## Permits in Florida

2 building and land-use permits tracked in Florida.

| Date | Category | Address | Applicant | Source |
| --- | --- | --- | --- | --- |
| Sep 22, 2026 | Site plan or rezoning | Village of Indiantown (news report) | Panatonni and Ferreira |  |
| Sep 18, 2026 | Zoning | 10050 Midway Road at I-95, Fort Pierce, FLFort Pierce Planning Board (news report) | Willow Lakes Development |  |

## Planned generation in Florida

2,436 MW across 28 EIA-860M generators scheduled to enter service within 36 months.

| Plant | Technology | MW | Planned | Status | Source |
| --- | --- | --- | --- | --- | --- |
| Shady Hills Combined Cycle FacilityPasco County | Natural Gas Fired Combined Cycle | 612 MW | Nov 2026 | Under construction, more than 50 percent complete |  |
| Powerline Energy StorageCitrus County | Batteries | 100 MW | Mar 2027 | Planned for installation, but regulatory approvals not initiated |  |
| Highland Solar SouthHighlands County | Solar Photovoltaic | 75 MW | Aug 2026 | Under construction, more than 50 percent complete |  |
| Bailey Mill SolarJefferson County | Solar Photovoltaic | 75 MW | Aug 2026 | Under construction, less than or equal to 50 percent complete |  |
| Highland Solar NorthHighlands County | Solar Photovoltaic | 75 MW | May 2027 | Regulatory approvals pending. Not under construction |  |
| Lonesome Camp Solar PlantOsceola County | Solar Photovoltaic | 75 MW | Apr 2027 | Under construction, more than 50 percent complete |  |
| Turnpike Solar PlantOsceola County | Solar Photovoltaic | 75 MW | Feb 2027 | Under construction, more than 50 percent complete |  |
| Middle LakeMadison County | Solar Photovoltaic | 74 MW | Apr 2027 | Under construction, less than or equal to 50 percent complete |  |
| PineconeCalhoun County | Solar Photovoltaic | 74 MW | Oct 2027 | Under construction, less than or equal to 50 percent complete |  |
| SaddleCalhoun County | Solar Photovoltaic | 74 MW | Oct 2027 | Under construction, less than or equal to 50 percent complete |  |
| Spanish MossSt Lucie County | Solar Photovoltaic | 74 MW | Oct 2027 | Under construction, less than or equal to 50 percent complete |  |
| TangeloOkeechobee County | Solar Photovoltaic | 74 MW | Jan 2027 | Under construction, less than or equal to 50 percent complete |  |
| AmbersweetIndian River County | Solar Photovoltaic | 74 MW | Apr 2027 | Under construction, less than or equal to 50 percent complete |  |
| CatfishOkeechobee County | Solar Photovoltaic | 74 MW | Jul 2027 | Under construction, less than or equal to 50 percent complete |  |
| CocoplumHendry County | Solar Photovoltaic | 74 MW | Jul 2027 | Under construction, less than or equal to 50 percent complete |  |
| County LineDeSoto County | Solar Photovoltaic | 74 MW | Apr 2027 | Under construction, less than or equal to 50 percent complete |  |
| Hardwood HammockWalton County | Solar Photovoltaic | 74 MW | Jul 2027 | Under construction, less than or equal to 50 percent complete |  |
| HendryHendry County | Solar Photovoltaic | 74 MW | Jan 2027 | Under construction, less than or equal to 50 percent complete |  |
| Joshua CreekDeSoto County | Solar Photovoltaic | 74 MW | Oct 2027 | Under construction, less than or equal to 50 percent complete |  |
| Maple TrailBaker County | Solar Photovoltaic | 74 MW | Jul 2027 | Under construction, less than or equal to 50 percent complete |  |
| Keene Branch SolarHillsborough County | Solar Photovoltaic | 74 MW | Dec 2026 | Under construction, more than 50 percent complete |  |
| FRP Miller SolarDuval County | Solar Photovoltaic | 74 MW | Dec 2026 | Under construction, less than or equal to 50 percent complete |  |
| Mattaniah SolarPolk County | Solar Photovoltaic | 52 MW | Dec 2026 | Under construction, less than or equal to 50 percent complete |  |
| FRP Forest Trail SolarDuval County | Solar Photovoltaic | 50 MW | Dec 2026 | Under construction, less than or equal to 50 percent complete |  |
| FRP Miller SolarDuval County | Batteries | 50 MW | Dec 2026 | Under construction, less than or equal to 50 percent complete |  |
| Brewster SolarPolk County | Solar Photovoltaic | 43 MW | Dec 2026 | Under construction, less than or equal to 50 percent complete |  |
| Pace Road Battery StoragePolk County | Batteries | 20 MW | Oct 2027 | Regulatory approvals received. Not under construction |  |
| Pasco Cnty Solid Waste Resource RecoveryPasco County | Municipal Solid Waste | 17 MW | Apr 2027 | Under construction, less than or equal to 50 percent complete |  |

### Where Florida stands

Across the whole tracker, 738 data center and substation permits are on record in 51 states and DC. Florida accounts for 0 of them, ranking #14 by that count. Ranking measures documented permit activity, not the size of the eventual buildout.

[← PreviousDelaware](https://savrn.com/data-center-permits-tracker/delaware) [Next →Georgia](https://savrn.com/data-center-permits-tracker/georgia)

The SAVRN reference set

## Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.

Capital Atlas

Who is funding AI data centers: capital providers, named sites, financing transactions, and the blocked-and-delayed record, state by state and company by company.

[Open the atlas →](https://savrn.com/data-center-capital-atlas)

Delay Watchlist

Project-level slippage: named projects, jurisdictional actions, utility and federal dockets, SEC disclosures, and the interconnection queue.

Open the watchlist →

Moratorium Tracker

The policy layer: every state measure and local moratorium mapped and cited, with one page per state.

Open the tracker →

Water Tracker

Every federal, state, local and interstate water measure that touches a data center, plus a fifty-state water ledger.

Open the water tracker →

Grid Operator Watchlist

ERCOT, PJM, MISO, CAISO, SPP, NYISO, ISO-NE and FERC: the large-load rules, filings and queue positions that decide whether a site can energize.

Open the watchlist →

SAVRN Scarcity Tracker

Eleven primary-sourced indicators of AI infrastructure scarcity, one composite index, read against the token index, SAVRN's own cost basis and the frontier ceiling.

Open the scarcity tracker →