Data Center Capital Atlas Update: September 17, 2026

98 capital providers, 346 named sites, 437 financing transactions and 740 blocked or delayed projects, each linked to its source.

SAVRN·Sep 17, 2026 ·88 min read
Data Center Capital Atlas Update: September 17, 2026

Would you like the atlas update?

The atlas is re-verified and republished on Tuesday, Thursday and Saturday. You get one email when it goes out, with what changed. Nothing else.

Also send me

One email when it publishes. Unsubscribe in one click. Privacy ·

You're on the list. The next atlas update will land in your inbox when it publishes.
You are subscribed. Read the latest tracker

This data center capital atlas update records what changed in the North American Data Center Capital Atlas, SAVRN’s primary-sourced record of who is funding data center capacity in North America, in what structure, at which site, and how much of that capital has been stopped. The atlas is refreshed every Tuesday, Thursday, and Saturday, and each refresh publishes a note like this one recording exactly what changed.

Where the record stands

Measure Previous Current Change
Capital providers 98 98 no change
Named sites 197 346 up 149
Financing transactions 307 437 up 130
Blocked or delayed projects 196 740 up 544
Source citations 2,424 4,049 up 1625
States with a blocked or delayed project 43 49 up 6

Announced capital across the tracked cohort is reported as disclosed and is never summed into a single deployment figure: site commitments overlap one another and overlap reported capital expenditure. Blocked-and-delayed totals from different trackers cover different windows and definitions and are shown side by side rather than added.

Capital at risk, added this period

  • Statesville 180-day data center moratorium, City of Statesville (NC). Citywide pause on data center applications. No megawatt or dollar figure; previously approved data centers, including the Compass Data Center project on Stamey Farm Road approved the prior year, are not affected. Statesville City Council unanimously approved the second reading of a 180-day moratorium on data centers on 14 September 2026, and the moratorium took effect that day. It covers the acceptance, processing and approval of development applications for data centers and does not affect previously approved data centers. The original proposal called for 150 days and was lengthened to 180 days; council approved the first reading unanimously in August 2026. The pause gives staff time to review development regulations, which do not currently address data centers. (WBTV)
  • Clarendon County data center moratorium (Project 59), Clarendon County (SC). Countywide pause. Project 59 in the county industrial park has no building and no confirmed operator; a Santee Electric Co-op proposal on co-op land would use closed-loop cooling. No megawatt or dollar figure disclosed. Clarendon County Council passed the third and final reading of a moratorium pausing future data center development unanimously, with no one opposed, at its meeting on 14 September 2026. Council said the measure closes existing loopholes before a new project can proceed and that research on data centers will continue during the pause. Council members said an outright ban would be discriminatory and is not planned. Public concern centered on Project 59 and a Santee Electric Co-op proposal, along with tourism, environmental and water-use impacts. The duration was not stated in the reporting. (WIS News 10)
  • Lima 18-month data center and outside-water moratorium, City of Lima (OH). Citywide pause on new data center construction and on new requests for city-supplied water to developments in outside municipalities. The existing agreement to supply water to the Google data center under construction in American Township is not affected. No megawatt or dollar figure. Lima City Council approved an ordinance at its Monday meeting (14 September 2026) enacting an 18-month moratorium on data center construction in the city and on new requests for city-supplied water to developments in outside municipalities. The vote was 6-0 with one abstention (Third Ward Councilor Jesse Lowe) and one member absent. The city said the ordinance does not affect its agreement to supply water to the Google data center being developed in American Township. Development directors will evaluate standards on land use, setbacks, electric demand, community benefits and infrastructure costs, and the moratorium can end early if council adopts standards. (Government Technology)
  • Pioneer six-month moratorium (former AquaBounty site data center), Village of Pioneer (OH). Proposed 20 MW data center on property owned by AquaBounty Technologies near the Ohio-Indiana line. No dollar figure disclosed. Pioneer Village Council voted 6-0 on 14 September 2026 to adopt a six-month moratorium on data centers. Tom Cervenka of Cervenka Development Partners had told the planning commission he intended to buy the former AquaBounty Technologies property to build a 20 MW data center. The village will conduct studies during the pause, including a new electrical study, and council members said they did not want anything fast-tracked. (The Village Reporter)
  • Richmond 45-day data center moratorium, City of Richmond (CA). Citywide pause; Richmond has no data centers and no pending data center applications. No megawatt or dollar figure. Richmond City Council voted 6-1 on Tuesday 15 September 2026 to adopt a 45-day moratorium on new data center development, making Richmond the third Bay Area city to do so after Oakley and Gilroy. As amended, the city may continue accepting applications during the moratorium but may not approve them or issue permits. Staff outlined a timeline that includes a moratorium report and extension within the 45 days. There are no pending data center applications in the city. (Contra Costa News)
  • Gilroy 45-day data center moratorium, City of Gilroy (CA). Citywide pause. The Amazon data center under construction on a 56-acre site at 8050 Camino Arroyo is exempt; a second project at Highway 152 and Camino Arroyo was only at pre-application and would be subject to the pause. No megawatt or dollar figure. Gilroy City Council voted unanimously on 14 September 2026 to adopt a 45-day interim urgency ordinance barring the city from accepting, processing or approving applications and entitlements for new data centers. The moratorium expires 29 October 2026 unless renewed and can be extended to a total of two years under California Government Code Section 65858. It does not apply to the Amazon data center under construction on a 56-acre site at 8050 Camino Arroyo, approved in 2025 by the community development director. Staff will return with objective zoning, development and operational standards covering water, grid capacity, backup generator emissions and noise. (San Jose Spotlight)
  • Marysville 12-month data center moratorium, City of Marysville (KS). Citywide pause on data center applications. No specific project, megawatt or dollar figure reported. Marysville City Council unanimously adopted a 12-month moratorium on data center development at its Monday meeting (14 September 2026). No applications for data center development will be accepted or processed during the moratorium. The pause gives the Planning Commission and city staff time to examine zoning changes and hear from residents and stakeholders. The ordinance defines data centers broadly to include cloud computing and AI infrastructure. (Marysville Advocate)
  • Woodburn 120-day data center moratorium, City of Woodburn (OR). Citywide pause; the city has no pending or active data center applications. No megawatt or dollar figure. Woodburn City Council adopted Resolution 2267 on 14 September 2026 declaring a 120-day moratorium on the acceptance, review and approval of city permits and development proposals for new data centers. Other industrial development is not affected. During the pause the city will review zoning and siting criteria and study water, energy, noise and environmental impacts. The vote count was not published in the sources reviewed. (City of Woodburn)
  • Loudoun County 12-month pause on legislative data center applications, Loudoun County (VA). County hosts 233 data centers. Pause would apply to new legislative data center and substation applications, not projects already in the pipeline. No megawatt or dollar figure. The Loudoun County Board of Supervisors voted 7-1-1 on 15 September 2026 directing staff to draft a resolution pausing data center applications for 12 months while new regulations are written. Supervisor Kristen Umstattd voted against and Supervisor Caleb Kershner abstained. As described, each application would be paused for one year from its submission date. Board Chair Phyllis Randall said the measure is not a ban or a moratorium. A separate vote is still required to adopt the resolution. Loudoun Now reported that staff will bring the resolution back in October 2026 for a final board decision, that County Attorney Leo Rogers advised a moratorium is not legal in Virginia so the measure relies on the 12-month review deadlines for legislative applications, that by-right applications (an estimated 18.2 million sq ft of data center space) are not affected, and that new data center regulations are expected to be completed in July 2027 (NBC4 Washington)
  • Texas enforcement directive on data center water-use reporting, State of Texas (TX). Statewide. The Texas Water Development Board surveyed 329 data centers in 2025 and about 30% responded; 22.5% of 267 new facilities responded. No megawatt or dollar figure. Gov. Greg Abbott announced on 14 September 2026 that he directed the Texas Water Development Board to use its enforcement authority against data centers that fail to complete the state’s mandatory water use survey, both for past failures and future noncompliance. Existing law makes failure to respond a Class C misdemeanor, and the directive includes referring violations to county or district attorneys. Response rates were 32% of 22 surveyed data centers in 2023, 28% of 67 in 2024 and about 30% of 329 in 2025. Abbott asked the board for a compliance and enforcement update by 14 October 2026. (Texas Tribune)
  • QLevr Carmen Avenue data center (moratorium carve-out), City of Inver Grove Heights (MN). 54,000-square-foot data center on Carmen Avenue East. Inver Grove Heights City Council voted 3-1 at its Monday meeting (14 September 2026) to exempt QLevr LLC’s proposed data center from the one-year citywide moratorium the council adopted 3-2 in June 2026. QLevr had sued the city in Dakota County District Court in July 2026 calling the moratorium unlawful, and its attorneys offered to dismiss the suit without damages if the project was carved out; the city attorney cited potential liability of at least $20 million against $1 million of insurance. The council is set to vote on the major site plan on 28 September 2026. The moratorium remains in place for all other data center projects. The underlying one-year citywide moratorium was approved 3-2 on 26 June 2026, after QLevr had threatened legal action if the project was put on hold. Residents also filed a petition with more than 700 signatures seeking an environmental assessment worksheet. (MPR News)
  • Chillicothe moratorium repeal (Alignment Engine former paper mill data hall), City of Chillicothe (OH). Proposed data hall in the Chilpaco division of the former US Paper Mill site at Eastern Avenue and Canal Street. No project megawatt or dollar figure disclosed. Chillicothe City Council voted 8-1 on Monday 14 September 2026 to reconsider and strike down the 60-day data center moratorium it had adopted unanimously on 24 August 2026. Council members cited a newly surfaced city letter from earlier in 2026 telling the paper mill owner that the Unified Development Code did not prevent a data center on the property. The vote clears a hurdle for Alignment Engine’s proposed data hall, which the company says will not seek tax abatements or draw more power or water than the former mill. A companion report says a revised moratorium grandfathering the project and setting standards, including a 100 MW cap, will be redrafted and returned to council. (WCHI Easy 1350)
  • Former Star Tribune printing facility data center (North Loop), City of Minneapolis (MN). Proposed 20 MW data center at the former Star Tribune Heritage Printing Facility. No dollar figure or square footage disclosed. Virginia-based Legacy Investing withdrew its land use application for a 20 MW data center at the former Star Tribune printing facility in Minneapolis’s North Loop, a city spokesperson confirmed on 11 September 2026. The proposal drew heavy opposition from North Loop residents over environmental impacts and doubts about job creation. Minneapolis City Council had passed a six-month ban on data centers larger than 350,000 square feet in May 2026. The Star Tribune still owns the site. (MPR News)
  • DC Rapids former paper mill data center, City of Wisconsin Rapids (WI). Redevelopment of the former paper mill site into a data center. No megawatt, acreage or dollar figure disclosed. The Wisconsin Rapids Plan Commission voted 7-0 on 16 September 2026 to recommend that the Common Council deny DC Rapids LLC’s conditional use and site review applications to redevelop the former paper mill site as a data center. Staff identified 33 shortcomings, including missing electric utility approval, employment and shift projections and construction traffic details. The recommendation goes to the Common Council, reported for 20 October 2026, and the company may reapply. The city is separately drafting a data center moratorium. This is a recommendation, not a final denial. (WSAW)
  • Spring Valley Technology Park, Loudoun County (VA). 325 acres / 3.54M sq ft / 780 MW. The Loudoun County Planning Commission voted 5-0 on 23 July 2026 to recommend denial of Active Infrastructure’s rezoning (LEGI-2024-0074) for a 780 MW, 3.54 million sq ft campus on 325 acres near Beaverdam Reservoir. County staff had also recommended denial, calling the rezoning a fundamental departure from planned land uses. More than 500 residents attended the hearing. As of September 2026 the application awaits a final Board of Supervisors decision. (MLQ.ai)
  • Nebius Oxmoor Valley data center, Jefferson County Circuit Court / City of Birmingham (AL). 80-acre site. Neighbors sued Nebius, Hoar Construction and the City of Birmingham, alleging the city issued permits for a hyperscale data center on land not zoned for that use. On 10 July 2026 Circuit Judge Javan Patton Crayton ruled the case can proceed without first going to the Zoning Board of Adjustment. On 14 August 2026 the judge granted the plaintiffs’ request to skip the preliminary injunction and go to the merits, with the next hearing set for 8 March 2027. Construction continues, with completion projected for 2028. Additional suits filed: the Greater Birmingham Humane Society sued the City of Birmingham, Alabama ADC Holdings LLC and 201 Milan Birmingham LLC in Jefferson County Circuit Court on 10 July 2026, seeking review of permits and approvals for the project next to its planned animal campus. On 5 September 2026 Regions Bank shareholder James Anderson filed a derivative suit alleging Nebius affiliates defrauded the bank of $66.3 million in the 30 September 2025 sale of 201 Milan Parkway. Former school board member Terri Michal sued (filed on a Thursday afternoon, reported 11 September 2026) Birmingham’s Industrial Development Board, its chairman and Nebius, asking a judge to cancel the $3.2 billion in 30-year tax abatements approved 29 May 2026 under the Open Meetings Act; AL.com described the project as $36 billion and 300 MW on about 75 acres (WBHM)
  • West Mahanoy Township 180-day data center and solar farm moratorium, West Mahanoy Township (PA). No specific project named; size, capital, and capacity not applicable; township solicitor said no data center application has been filed. West Mahanoy Township supervisors voted unanimously to approve a resolution invoking a six-month moratorium on data centers and solar farms. The township used the curative amendment process to declare its zoning ordinance deficient on those uses. Siana Law was hired as special counsel to draft ordinance updates covering noise, buffers, power sources, and community benefits. (The Shenandoah Sentinel)
  • Colquitt County data center moratorium extension, Colquitt County (GA). No specific project named; size, capital, and capacity not applicable. Colquitt County commissioners extended the county’s moratorium on data center development for another 180 days after a discussion on 1 September 2026. Residents raised water use and environmental concerns. The county administrator said the board would use the period to draft zoning regulations, potentially modeled on Floyd County’s ordinance. (Moultrie Observer)
  • Tarrant 12-month data center moratorium, City of Tarrant (AL). No specific project named; size, capital, and capacity not applicable; mayor said no developer has approached the city. Tarrant city officials approved a 12-month moratorium on data centers. Mayor Tracie Threadford said the decision was made out of caution. She noted several buildings for sale in the city could fit a smaller data center project. (ABC 33/40)
  • Foley six-month data center and cryptocurrency mining moratorium, City of Foley (AL). No specific project named; size, capital, and capacity not applicable; mayor said no data centers have been proposed. The Foley City Council approved on final reading an ordinance establishing a six-month moratorium on accepting, processing, or approving applications for data centers, cryptocurrency mining facilities, and server farms. The vote was held Tuesday, 8 September 2026. Mayor Ralph Hellmich said the city-owned utility already has some protections on water, noise, and electricity use. (FOX10 News)
  • Edgewater permanent AI data center ban, City of Edgewater (FL). No specific project named; size, capital, and capacity not applicable. The Edgewater City Council unanimously approved a permanent ban on artificial intelligence data centers on 14 September 2026. The ordinance took effect immediately. Voters will decide in November whether to add the prohibition to the city charter as Charter Amendment 4. The Daytona Beach News-Journal reported that the ordinance, described by the city as a permanent moratorium, carries a 12-month sunset and bars accepting, processing or approving development orders and permits for data centers, hyperscale data centers and cryptocurrency mining facilities. (FOX 35 Orlando)
  • Orange County proposed AI data center moratorium, Orange County (FL). No specific project named; size, capital, and capacity not applicable. Orange County commissioners expressed support on 15 September 2026 for a temporary moratorium on large AI data centers, but no formal moratorium vote was reported. The proposal calls for a pause of at least one year on prospective applications while staff study water, electric load, noise, and zoning impacts. The commission could take up the item again in early December. (WUSF)
  • Gorham 180-day data center moratorium, Town of Gorham (ME). No specific project named; size, capital, and capacity not applicable; councilor said no data centers are planned. The Gorham Town Council voted 7-0 to adopt a 180-day moratorium on large-scale data center proposals, with an option to extend another 180 days. In September 2026 the council voted unanimously to send a proposed permanent ban to the planning board for a public hearing. (Portland Press Herald)
  • Hendersonville 12-month data center moratorium, City of Hendersonville (NC). No specific project named; size, capital, and capacity not applicable; city officials said no data centers were seeking approval. Hendersonville City Council unanimously adopted a 12-month moratorium on data center development after a public hearing scheduled for 3 September 2026. The pause covers city building, zoning, and special use permits for data centers. Staff presented a research plan for the year. (Hendersonville Times-News)
  • Quiet Data Centers Halifax AI data center (301 Industrial Site), Halifax County (NC). About 251 acres of county-owned property off Trestle Road in Enfield Township, sold for $1.7 million; at least $250 million taxable investment in years 1 to 10 and 50 jobs required; company described an 88 MW ceiling. Halifax County commissioners voted 5-1 to schedule a 19 October 2026 legislative hearing on a possible data center moratorium. The county previously approved a $1.7 million land sale to Quiet Data Centers Halifax for an 88 MW AI data center on 251 acres. The county attorney cautioned that a moratorium before site plan submission could expose the county to interference claims. No moratorium has been adopted. (The Daily Herald (Roanoke Rapids))

Capital at risk, added this period, newly verified from earlier periods

These entries were added in this cycle but their own dates fall before the current month. They are documentation catching up, not new activity.

  • Diode Ventures Cedar Creek Lake data center, Henderson County (TX). 12-year build-out; water use of 5 million gallons per day by year five (Texas Tribune); MW and capital not disclosed. Kansas-based Diode Ventures withdrew its proposed data center near Cedar Creek Lake in Henderson County on 23 July 2026, saying it would not advance the site beyond preliminary planning. The Governor’s office said the project did not meet the five data center standards Gov. Greg Abbott set in June 2026 directives to the PUC and ERCOT. A volunteer Save Cedar Creek Lake coalition had gathered thousands of petition signatures over water supply concerns. Henderson County has no zoning rules, so the county had no approval to deny. (Office of the Texas Governor)
  • Dulles South Innovation Center (Dulles Cloud South), Prince William County (VA). ~1,940 acres / 252 parcels / 43M sq ft. The Prince William Board of County Supervisors voted 8-0 on 7 July 2026 to deny the rezoning for roughly 43 million sq ft of data centers on about 1,940 acres along Sanders Lane near the Loudoun County line. The site lies outside the county’s Data Center Opportunity Zone Overlay District. Supervisors cited conflict with the 2040 Comprehensive Plan, emissions from roughly 6,000 planned diesel generators, and Occoquan watershed protection. The vote followed the collapse of the Prince William Digital Gateway. (WTOP)
  • Mountain Road Technology Park, Hanover County (VA). ~430 acres. The Hanover County Board of Supervisors voted 4-3 on 28 May 2026 to deny Tract’s rezoning for a data center park on nearly 430 acres. Opponents cited estimated water use of 600,000 gallons per day, described as about 90 percent of the zone’s water supply, along with power demand, noise and rural character. Tract had offered a $15 million commitment toward county water infrastructure. (The Cool Down)
  • Pine Island data center (Project Skyway), Goodhue County District Court / City of Pine Island (MN). Up to 3M sq ft / up to 2,700 MW. The Minnesota Center for Environmental Advocacy sued the City of Pine Island and Ryan Companies in October 2025, arguing the Project Skyway environmental review covered a generic technology center rather than the Google data center. On 22 May 2026 Goodhue County District Judge Patrick Biren enjoined all construction and pre-construction activity, finding MCEA likely to succeed on the merits, with a $2,000 bond. The court also denied the city and developer’s request to rule the review adequate. The case has moved to discovery, and the next hearing is reported for 22 February 2027. (FOX 9)
  • Hexa Builders data center, 3043 Black Horse Pike, Monroe Township (NJ). 1M sq ft data center plus warehouse. Monroe Township adopted ordinances in April 2026 removing data centers as a permitted use on Hexa’s redevelopment site and banning them townwide. Hexa Builders sued the township in New Jersey Superior Court on 5 June 2026 seeking $300 million in damages. The case was moved to federal court, where the township filed a motion to dismiss on 28 July 2026. As of early August 2026 no ruling had been issued. Monroe Township moved Hexa Builders’ $300 million complaint from state to federal court and, on 28 July 2026, its attorney filed a letter asking that the suit be dismissed, rejecting the First Amendment and equal protection claims. Hexa’s attorney then asked U.S. District Judge Edward Kiel to send the non-constitutional land-use claims back to New Jersey state court and to reject the dismissal request. The judge had not acted as of early August 2026 (Philadelphia Inquirer)
  • Former Newton Airport data center site, Andover Township (NJ). ~97 acres at 248 Stickles Pond Road. Andover Township had amended zoning to allow data centers in September 2025, then moved to ban them townwide in May 2026 after heated public meetings. National Land Developers LLC sued in New Jersey Superior Court on 10 July 2026 to overturn the ban for its roughly 97-acre former Newton Airport property. The suit argues nothing changed in the five days between the township introducing data center standards and reversing to a full prohibition. (GovTech)
  • DC Blox Nashville Zoo-area data center, Metro Nashville-Davidson County (TN). 23+ acre former Asurion office and data center site. Metro Nashville adopted a temporary data center moratorium and new regulations in July 2026, and DC Blox’s permits were put on hold. On 5 August 2026 Metro Council authorized the city to negotiate for or potentially acquire the property through eminent domain. DC Blox filed a federal lawsuit on 11 August 2026 alleging the moratorium is a targeted attack that violates due process, equal protection and takings protections, and seeks to block enforcement plus damages. (Nashville Banner)
  • Eagan Capital data center moratorium challenge, City of Eagan (MN). Moratorium covers new data centers over 20 MW or within 500 ft of homes. The Eagan City Council adopted an interim data center moratorium on 17 February 2026, running through 17 February 2027. Eagan Capital sued the city on 15 June 2026, arguing only the Minnesota Public Utilities Commission may regulate electricity demand, and seeks to void the moratorium plus damages over $50,000. The city said it will defend the moratorium, noting the company had installed trailer-mounted chillers without permits, which led to denial of an interim use permit. (CBS Minnesota)
  • Bristow Campus (NVA02 expansion), Prince William County (VA). 58 acres. STACK Infrastructure sought to rezone 58 acres of agricultural land near Nokesville Road for a campus outside the county’s Data Center Opportunity Zone. The Board of County Supervisors hearing was deferred several times starting in November 2024, most recently 24 June 2025. On 9 September 2025 the board voted 4-2 to deny the rezoning. (InsideNoVa)
  • Oaklawn data center rezoning, Town of Leesburg (VA). 145-acre Oaklawn site; up to 450,000 sq ft of data center use sought. Leesburg Town Council denied Oaklawn LLC’s application in late January 2025, which sought up to 450,000 sq ft of data center use alongside affordable housing units. In February 2025 Oaklawn LLC and Oaklawn Development Partners sued the town in Loudoun County Circuit Court seeking a declaratory judgment. The town attorney said the council followed the zoning ordinance standards. A trial outcome has not been confirmed in the reporting reviewed. (Loudoun Times-Mirror)
  • Gigaland data center campus, Fauquier County (VA). Original: 202 acres / 2.2M sq ft; revised plan ~847,000 sq ft. Gigaland sought to rezone land near Remington for a large data center campus. After the Planning Commission recommended denial, the developer withdrew in August 2025 and a scheduled September 2025 Board of Supervisors hearing was canceled. A scaled-down resubmission followed, and in August 2026 the developers withdrew their comprehensive plan amendment, rezoning and special exception requests again, acknowledging they lacked the votes. The applicant could return as soon as January 2027. (Piedmont Environmental Council (2025))
  • Cabin Field Road data center site, Campbell County (VA). ~57 acres. On 7 October 2025 the Campbell County Board of Supervisors voted 5-2 to deny MESH Capital’s request to remove a protective proffered site plan from 2000 on about 57 acres, and a motion to require special use permits for data centers failed 6-1. MESH then submitted three scaled-back concept plans that county staff found consistent with the original proffer, keeping a by-right path open. An adjacent owner petitioned for review on 25 November 2025, and the board scheduled a hearing for 20 January 2026. The outcome of that hearing was not confirmed in the reporting reviewed. (Campbell County)
  • New Kent Technology Overlay District, New Kent County (VA). 1,800-acre proposed overlay. New Kent County staff spent more than a year drafting a 1,800-acre Technology Overlay District along the Route 33 corridor where data center applications could be approved without public hearings. On 14 July 2026 the Board of Supervisors ended the overlay effort after widespread public opposition. The same night the board voted 3-2 to rezone about 343 acres for The Curtis Group’s Eltham Business Park, described as commercial and light-industrial use. Staff were directed to draft a data center ordinance with strict performance standards. (Richmond BizSense)
  • Frederick County data center application pause (Quantum Frederick expansion context), Frederick County (MD). Quantum Frederick campus expanded from ~1,600 to ~2,600 acres by December 2025 ordinance. The Frederick County Council passed an ordinance in December 2025 expanding the Quantum Frederick campus by about 1,000 acres, and a citizen committee gathered over 21,000 signatures to put it to referendum. The Maryland Supreme Court blocked the referendum, and in a 28 July 2026 opinion held that zoning ordinances are not subject to referendum under the county charter. County Executive Jessica Fitzwater paused new applications for data centers and related substations through 31 December 2026, exempting projects approved before 17 June 2025 and those under construction. (The Daily Record)
  • Charles County Zoning Text Amendment 25-187, Charles County (MD). Would have permitted data centers in general and heavy industrial zones. ZTA 25-187 would have defined and permitted data centers under conditions in Charles County’s industrial zones. The Planning Commission recommended against it twice, most recently after a 1 June 2026 hearing where opponents chanted no data centers. On 21 July 2026 the county commissioners reached consensus not to move forward and asked staff for a task force and outside consultant framework. Data centers remain a non-permitted use in the county. (Southern Maryland Chronicle)
  • Pennhurst data center, East Vincent Township (PA). 125-acre parcel / 1.9M sq ft. The East Vincent Township Board of Supervisors unanimously rejected the conditional use application for a 1.9 million sq ft data center with power generation and battery storage on the former Pennhurst State School site. The vote came in May 2026 at the second conditional use hearing. The developer’s attorney said the company would appeal to the Chester County Court of Common Pleas, arguing Pennsylvania law requires zoning accommodation for data centers. State Sen. Katie Muth is proposing a data center moratorium. (Philadelphia Inquirer)
  • King of Prussia data center campus, Upper Merion Township (PA). Five data centers, more than 4.5M sq ft. Developer Brian O’Neill sued Upper Merion Township, its supervisors and planning commission seeking review extensions, and a Montgomery County judge enjoined township action on his applications on 12 August 2026. The judge vacated the injunction the next day. On 13 August 2026 the Board of Supervisors denied two extension requests and several preliminary land development plans, citing missing architectural, traffic and engineering information. O’Neill said he will appeal. (6abc)
  • Triangle Innovation Park West (TIP West), Chatham County (NC). 750 MW. Chatham County adopted a 12-month countywide moratorium on new data centers on 11 February 2026. ECO TIP West, which says it received a zoning permit in October 2025 confirming a data center as a use by right, sued the county in Chatham County Superior Court. The suit seeks to invalidate the moratorium, confirm vested rights or an exemption, and recover damages and fees. The company says it spent $11 million in development costs. (North State Journal)
  • Clinton County data center, precast plant and hydroponic farm rezoning, Clinton County (IN). ~714.55 acres. The Clinton County Board of Commissioners voted 3-0 on 20 January 2026 to deny rezoning about 714.55 acres from A-1 agricultural to I-1 light industrial for a combined data center, precast plant and hydroponic farm. Commissioners cited the lack of signed, matching commitments from the developer and landowner and impacts on nearby property owners. The parcels remain agricultural. (Citizen Portal)
  • Madison County data center moratorium extension, Madison County (IN). County-wide. Madison County commissioners unanimously approved a one-year extension of the county’s data center moratorium on 4 August 2026. A new committee of planning commissioners and citizen appointees will draft zoning rules, which could include a permanent ban. Residents cited resource use, utility bills and noise. (Indiana Public Radio)
  • Minneapolis data center moratorium, City of Minneapolis (MN). City-wide; downtown projects under 350,000 sq ft exempt. The Minneapolis City Council approved a six-month interim moratorium on new data center development in May 2026, which does not require the mayor’s signature. Downtown data centers with less than 350,000 sq ft of new or expanded space are exempt. Council supporters said the pause allows the city to write permanent regulations. (MPR News)
  • Alterra Marshall data center (Brooks Industrial Park), City of Marshall (MI). 270 acres; originally ~1 GW with gas plant, now ~400 MW without it. Alterra Development bought 270 acres in Marshall’s Brooks Industrial Park in October 2025 for a data center originally planned at about 1 GW with an on-site gas plant, later cut to about 400 MW without the plant. The Marshall City Council approved a 365-day moratorium on 3 August 2026, delaying any approval until at least August 2027. The council cited electricity and water uncertainty, heat discharge, low-frequency noise and proximity to wetlands and a lake. (WWMT)
  • Project Cardinal, City of Yorkville (IL). 1,034 acres / 14 buildings / 17M sq ft. Yorkville approved Project Cardinal on 10 March 2026. On 29 April 2026 Preserve Our Yorkville & Community LLC and several neighbors sued the city, alleging it failed to notify nearby residents before annexing and rezoning the land. A separate suit by resident John Bryan, filed in late 2025, was in settlement talks as of April 2026. (Shaw Local)
  • Project Steel (Eldamain Corridor), City of Yorkville (IL). Not specified. Preserve Our Yorkville and Community filed a second lawsuit in Kendall County Court in May 2026, this time over the rezoning for Project Steel. The suit alleges the city failed to mail proper notice to residents and that the rezoning conflicts with the comprehensive plan, and asks the court to void it. A case management hearing was set for August 2026. (WSPY News)
  • Meyer data center rezoning, City of Yorkville (IL). ~80 acres as originally proposed; later redesigned. The Yorkville Planning and Zoning Commission unanimously voted down Green Door Capital’s rezoning for a data center near the Caledonia subdivision. The developer redesigned the plan but withdrew it on 14 April 2026 before a City Council vote. Mayor John Purcell said the council had no support for data centers at that location, citing proximity to homes and the three projects already approved. (Shaw Local)

Sites added this period

  • CleanSpark Sandersville data center (Sandersville, GA). 175 MW, under_construction. CleanSpark signed a 20-year lease with two 5-year extension options for 175 MW of critical IT load at Sandersville with an unnamed high investment-grade global technology company, with deliveries expected to begin in Q4 2027. On 17 September 2026 a CleanSpark subsidiary proposed $2.227 billion of senior secured notes to fund the remaining build-out. The same tenant signed a letter of intent covering CleanSpark’s 885 MW Texas portfolio (Sealy and Brazoria). 20-year triple-net lease for 175 MW of critical IT load with an undisclosed high-investment-grade technology company announced 14 July 2026, valued at approximately $6.6 billion; deliveries expected to begin Q4 2027 (CleanSpark investor relations (lease release))
  • Bell AI Fabric Saskatchewan hub (R.M. of Sherwood) (Rural Municipality of Sherwood, Saskatchewan). 1200 MW, under_construction. Bell Canada and the Government of Saskatchewan signed a non-binding MOU to expand Bell AI Fabric in Saskatchewan by up to 900 MW, building on a 300 MW campus already under construction near Regina. Additional phases are contingent on customer commitments, commercial agreements, permits and environmental assessments. The expansion was announced at Canada’s Investment Summit. On 14 to 15 September 2026, at the Canada Investment Summit, Bell announced a non-binding memorandum of understanding with Saskatchewan to expand the R.M. of Sherwood campus from 300 MW to 1.2 GW, adding up to 900 MW powered by new natural gas generation to be developed by an operating partner, while the original 300 MW draws on the SaskPower grid. Bell describes total investment of C$50 billion to C$52 billion, with about 500 permanent jobs plus 3,000 additional roles and a Bell AI Fabric head office near Regina. Expansion depends on customers, power and approvals (Bell Canada press release (Newswire.ca))
  • Site Layer 4 Goshen Hole data center and energy campus (near Wheatland, WY). rezoning approved. Platte County commissioners unanimously rezoned 5,344 acres of ranchland in Goshen Hole, northeast of Wheatland, to industrial for a utility-scale energy generation, storage and data center campus proposed by Site Layer 4, LLC. Conditions include reversion to prior zoning if construction does not begin within five years and a special-use permit for any use. At a 2 September 2026 public hearing, Platte County commissioners approved rezoning 5,344 acres of Lazy V6 Ranch land along the Goshen Hole rim from RAM to Industrial for the Site Layer 4 energy and data center campus, with conditions: a five-year sunset reverting the zoning if construction does not begin, county review of any subdivision, and a required Special Use Permit with full engineering, environmental, water and traffic studies before construction. The developer said it expects to use about 15 acre-feet of water a year with closed-loop cooling from a private commercial supplier (Cowboy State Daily (rezoning vote))
  • Google potential Lea County data center (Lea County, NM). exploring. Google said it is exploring a potential data center in Lea County, New Mexico and began community engagement, noting many details remain outstanding and no final decision has been made. No investment amount, capacity or timeline was disclosed. (Google blog)
  • Project Tembo (formerly Project Jade), Switchgrass Industrial Park (Cheyenne (8 miles south), WY). $17.0B, 2700 MW, approved. A site-plan amendment filed 30 June 2026 with Laramie County Planning and Development identified Google, through Jupiter Star Holdings LLC, as the owner of the 716-acre campus previously known as Project Jade. The plan covers four data center halls, an office hub, logistics and network buildings, new access roads off U.S. 85 and on-site wastewater lagoons. The original Project Jade received a conditional-use permit in January 2026, and a public hearing on the amendment was scheduled for 13 August 2026. The outcome of that hearing was not confirmed in the fetched sources At a community meeting in Cheyenne on 9 September 2026 Google said Project Tembo represents a $17 billion investment. The resubmitted, scaled-back site plan has four data center buildings instead of five with about 1 million fewer square feet and was handled administratively by the county; Google added a two-story office building that requires a conditional use permit. Related Digital is lead developer managing construction, Tallgrass will develop adjacent power generation keeping the campus off the local Cheyenne grid, and Google said it did not pursue local incentives. Site development may begin by the end of 2026, with some data halls operating in the second half of 2028 and full build-out near the end of 2031, and the project is expected to employ up to 2,500 construction workers and about 250 operations staff (Cowboy State Daily)
  • Crusoe and Lancium Childress AI data center campus (Childress, TX). 1000 MW, announced. Crusoe and Lancium announced a 1.0 GW AI data center campus on 270 acres in Childress, Texas, their second joint site after Abilene. Construction is scheduled to begin in Q3 2026, with thousands of construction jobs and more than 100 permanent positions expected. The tenant was not named. This is a separate project from the existing IREN Childress campus record Three Project Hyper - Childress buildings at 525 A, B and C County Road 23 were registered with the Texas Department of Licensing and Regulation on 11 September 2026 by Childress DC1, DC2 and DC3 LLCs, each a single-story data center of 806,359 sq ft with an estimated cost of $2.4 billion, designed by HKS, with estimated starts of 6 July, 1 September and 5 October 2026 and completions from 28 February to 31 May 2028. The owner contact on the filings, Nader Pakfar, is Crusoe’s General Counsel, Real Estate. No tenant is listed (Crusoe)
  • CleanSpark Sealy campus (Sealy, TX). announced. Part of CleanSpark’s 718-acre, up to 885 MW Texas portfolio placed under a letter of intent and exclusivity arrangement with the Sandersville tenant The Sandersville tenant holding the Texas LOI was disclosed on 17 September 2026 as Anviran, LLC, a wholly owned Meta subsidiary (CleanSpark)
  • CleanSpark Brazoria campus (Not disclosed, TX). 300 MW, announced. Part of CleanSpark’s Texas portfolio placed under a letter of intent and exclusivity arrangement with the Sandersville tenant. Map point is the county seat, Angleton The Sandersville tenant holding the Texas LOI was disclosed on 17 September 2026 as Anviran, LLC, a wholly owned Meta subsidiary (CleanSpark)
  • Sabey Decatur Township data center (Indianapolis (Decatur Township), IN). $4.0B, approved. Indianapolis approved $240 million in tax breaks on 16 September 2026. The site also appears in the at-risk list under a March 2026 moratorium entry (Indianapolis Business Journal)
  • Digital Realty Hawthorne Race Course site (Stickney, IL). announced. 119-acre former racetrack at 3501 South Laramie Avenue bought out of bankruptcy. The Chicago Sun-Times headline reports the Stickney mayor and board oppose a data center there Stickney trustees passed a six-month moratorium on data center development after the purchase (Yahoo Finance)
  • Digital Realty Rolling Meadows Atrium Campus (Rolling Meadows, IL). announced. 40-acre office campus with a 485,000-square-foot building at 3800 Golf Road planned for data center conversion (The Real Deal)
  • Terra Nexus Rockingham data center (316 Old Cheraw Highway) (Rockingham, NC). $1.2B, 460 MW, approved. Rockingham City Council approved 4-1 a conditional rezoning of 165.07 acres from high-density residential (R-7) to conditional light industrial for Terra Nexus, with Councilwoman Holly Howe dissenting. The Planning Board had unanimously recommended the rezoning and the council public hearing was set for 8 September 2026. The city projects about $6.6 million in annual property tax revenue and about 30 full-time jobs, with completion anticipated within six years (Richmond County Daily Journal)
  • Starwood Digital Ventures Mason County High Impact Data Center (Mason County, WV). $12.0B, 2160 MW, approved. West Virginia granted the project High Impact Data Center certification, announced by Governor Patrick Morrisey at the West Virginia Business Summit alongside the Nscale certification. The governor’s office cites about 1,500 jobs. The governor said infrastructure costs are covered by developers rather than passed to ratepayers The project is dubbed Project Tamarack, about 20 miles north of the Nscale Monarch campus, and would use closed-loop cooling with grid power (West Virginia Office of the Governor)
  • Gateway Digital Campus (Diamond Farms, Villa Ridge) (Villa Ridge, MO). approved. The Franklin County Commission approved rezoning from agricultural to industrial for the Gateway Digital Campus near Villa Ridge, off I-44 by the Shaw Nature Reserve. The Planning and Zoning Commission had recommended approval 8-1 in April 2026. The commission also considered county data center regulations including a $20,000 daily fine provision and a $10 million escrow requirement (KMOV First Alert 4)
  • Meramec Valley Technology Park (Crooked Creek farm) (Pacific, MO). approved. The Franklin County Commission approved rezoning for the Meramec Valley Technology Park on the Crooked Creek farm south of Pacific along Highway O, even though the Planning and Zoning Commission had recommended denial 4-5 in April 2026 (KMOV First Alert 4)
  • Alpha Compute northern Pennsylvania AI data center campus (Tioga County, PA). 200 MW, announced. Alpha Compute (NASDAQ: ALP) announced a binding term sheet on 11 August 2026 and a first amendment adding seller financing on 10 September 2026 for about 350 surface and pore-space acres plus Marcellus mineral rights in Tioga County, and about 107 acres in Beaver County for future development. The company says the project still needs county planning commission review, Board of Commissioners approval, environmental and water studies, and Pennsylvania DEP and Susquehanna River Basin Commission permits (FinanzNachrichten.de (company release))
  • Project Brookwood data center campus (Youngwoo & Associates) (Brookwood, AL). approved. Brookwood City Council voted 5-0 to annex and rezone about 374 acres along Brookwood Industrial Parkway for a data center campus tied to New York firm Youngwoo & Associates. Tuscaloosa Thread reports it is one of three data center projects near Brookwood Middle School, alongside an Applied Digital site of about 1,300 acres holding a state environmental permit and a Provident Data Centers site of more than 500 acres. Residents raised concerns about power demand, noise and proximity to the school (Tuscaloosa Thread)
  • Pollard Land Company McCormick County data center (McCormick County, SC). approved. McCormick County Council voted to rezone land for Pollard Land Company’s proposed data center and rejected a proposed pause on data center development at a contentious meeting. The developer had held a public meeting in August 2026 on the roughly 1,000-acre request. The council chairman said the county retains control over environmental issues and could stop the project if misled (WRDW)
  • DataOne AI factory campus (Logix Innovation Campus) (Frankfort, IN). $7.5B, announced. DataOne, a data center operator with US and French operations, is asking the City of Frankfort to approve an AI factory campus on 115 acres at the Logix Innovation Campus. The company scheduled public open houses for 21 and 22 September 2026. Incentive requests and job counts were not reported in the fetched coverage The company release cites about 200 permanent on-site jobs. Mayor Judy Sheets said the project goes before the city council on 28 September 2026. It follows a larger Clinton County data center plan that died in January 2026 for lack of commissioner support (Clinton County Daily News)
  • Project Horizon data center (Kearney) (Kearney, NE). 368 MW, approved. Kearney City Council unanimously approved the Project Horizon redevelopment plan by Starwood Digital Ventures and MARA Holdings in northeast Kearney after months of resident debate and questions. The city cites 59 jobs, community benefit agreements, closed-loop cooling using 2 million to 5 million gallons of water a year and a 55 dBA noise standard. Construction could begin in November or December 2026 with Phase 1 operating by spring 2028 (Nebraska TV)
  • Project Cayman energy project and co-located data center campus (Ascension Parish, LA). announced. One Nuclear Energy executed a binding letter of intent with a Louisiana landowner group for Project Cayman near the 17,000-acre RiverPlex MegaPark on the west bank of the Mississippi River, pairing a 2.88 GW gas-fired plant and battery storage with a co-located data center campus. The company plans public information meetings through the end of 2026. One Nuclear announced a separate 1 GW small modular reactor campus, Project Amberjack, on 9 September 2026 (POWER Magazine)
  • Project Taurus data center (former Intel plant) (Colorado Springs, CO). 50 MW, approved. The Colorado Springs planning department approved Raeden’s Project Taurus at the former Intel microchip plant off Garden of the Gods Road and Centennial Boulevard in June 2026, and the Planning Commission denied appeals in July 2026. City Council scheduled a special session on 17 September 2026 to hear the remaining appeals. Raeden has proposed a 30-foot sound wall and closed-loop cooling in response to noise, energy and water concerns (KOAA News5)
  • Accokeek Center data center complex (Stafford County, VA). $2.0B, announced. The Stafford County Planning Commission recommended approval of Falmouth Tech’s Accokeek Center data center complex near the Rappahannock Regional Jail between I-95 and Route 1, which would be the sixth data center approved in the county. Some commissioners raised concerns about setbacks and environmental impacts, and neighbors cited pollution, noise and property values. The Board of Supervisors makes the final decision (FOX 5 DC via Yahoo News)
  • SpaceXAI Tulane Road data center (MZX Tech) (Southaven, MS). approved. Southaven’s Board of Aldermen approved design review and a subdivision combining parcels into one heavy industrial lot for a roughly 660,000 sq ft SpaceXAI data center on Tulane Road, with Alderman Charlie Hoots dissenting after a unanimous Planning Commission vote; data centers are allowed by right in the city’s industrial zoning. The city traded a 51-acre site near the power plant serving Colossus 2 for the 69-acre site. The Commercial Appeal counts it as SpaceXAI’s fifth planned hyperscale data center in the Memphis and Southaven area. The DeSoto Times gives the address as 8325 Tulane Road and the Commercial Appeal as 8425 Tulane Road (DeSoto Times-Tribune)
  • Project River energy and data center campus (Cleveland, TN). $11.3B, announced. The Wright family, through Wright Industrial Group, proposes an $11.3 billion industrial campus on about 850 acres west of I-75 and north of Old Lower River Road near the Hiwassee River, with gas and biomass power plants that could host a data center. The project needs rezoning and annexation by the City of Cleveland, which is drafting a planned unit development ordinance with conditions that the family said on 15 September 2026 it would accept. Developers held a community meeting on 1 September 2026 to gauge neighbor sentiment, and WUTC reported planning commission and council votes were expected later in September 2026 (Chattanooga Times Free Press)

Sites added this period, newly verified from earlier periods

These entries were added in this cycle but their own dates fall before the current month. They are documentation catching up, not new activity.

  • AWS northwest Louisiana campuses (Caddo and Bossier parishes, incl. third campus at Resilient Technologies Park, Shreveport) (Shreveport, LA). $18.0B, announced. On 18 August 2026 AWS announced a third data center campus at Resilient Technologies Park in west Shreveport, a $6 billion investment that lifts its planned northwest Louisiana total to $18 billion across three campuses in Caddo and Bossier parishes. Amazon cited up to 750 full-time jobs across the campuses and targeted mid-2028 construction completion for the third campus. (About Amazon)
  • Project Eagle campus, Boling (Boling, TX). $1.2B, 75 MW, announced. Amazon Data Services filed four Texas Department of Licensing and Regulation applications for identical 189,060 sq ft buildings at about $300 million each near FM 1301 and FM 442 in Boling, on roughly 2,700 acres. The filings list construction starting 1 August 2026, with three buildings completing in January 2027 and the fourth in August 2027. Reporting in August 2026 said site preparation was underway but additional county permits were still required and the schedule was affected by new state audit requirements for data center power hookups. Wharton County officials signed a nondisclosure agreement with Amazon consultant VisionFirst Advisors (US Data Center Projects (TDLR filings))
  • Cortex 1 and Cortex 2 AI training clusters, Gigafactory Texas (Austin, TX). 205 MW, operational. Tesla’s Q2 2026 shareholder update said it more than doubled onsite compute in Texas, measured in MW, during the first half of 2026. Cortex 2 at Gigafactory Texas began running training workloads by April 2026 and supports vehicle and humanoid robot autonomy software. Tesla guided to 2026 capital expenditures of more than $25 billion, with AI compute among the main uses (EVwire)
  • Justified Data Campus (Hawesville, KY). 401 MW, announced. Former Century Aluminum Hawesville facility redeveloped by TeraWulf. Anthropic signed a 20-year lease with initial capacity in the second half of 2027 and full capacity by early 2028 (TeraWulf)
  • Chesapeake campus (Morgantown generating station) (Morgantown, MD). announced. FERC authorized TeraWulf’s acquisition of the Morgantown generating station on 29 July 2026. Data center operations are currently contemplated for 2030 (SEC EDGAR (TeraWulf 8-K))
  • Apollo site (Near San Antonio (within 25 miles), TX). 900 MW, announced. Cipher acquired an option on an approximately 288-acre site within 25 miles of San Antonio, Texas (SEC EDGAR (Cipher Digital 8-K))
  • Rockdale campus AI data center (Rockdale, TX). 191 MW, announced. Riot’s existing Rockdale bitcoin mining campus, where a 20-year lease with a frontier AI lab was signed after 30 June 2026 (Riot Platforms)
  • Matagorda County powered land site (Approximately 90 miles southwest of Houston, TX). 2000 MW, announced. More than 1,200 acres planned as a digital infrastructure campus for HPC workloads and bitcoin mining. Phased construction is expected to begin in 2026, contingent on regulatory approvals (SEC EDGAR (MARA 8-K))
  • Merlin campus, McGregor Industrial Park (McGregor, TX). 74 MW, announced. Galaxy disclosed a 500-acre site in the McGregor Industrial Park alongside two further Texas pipeline sites, Caspian (about 700 MW potential) and Selene (about 900 MW potential), subject to ERCOT interconnection (PR Newswire (Galaxy))
  • QTS Fayetteville campus (Project Odyssey buildings DC1-2) (Fayetteville, GA). 300 MW, operational. Campus leased to Microsoft. Commercial operations began in late 2025 per AFII, and the SPV issued investment-grade secured notes in August 2026 to fund expansion. QTS also has $4.6 billion of 5.7% notes due April 2036 on this campus per NordSip (NordSip)
  • Nexus Data Centers Hubbard AI campus (Hubbard, TX). $16.0B, under_construction. 2,900-acre multi-phase campus about 70 miles south of Dallas with Anthropic as expected anchor tenant. W.Media dates Building 1 construction from January 2026 to October 2027 and Building 2 from June 2026 to January 2028. Final investment decision reached with the August 2026 financing (W.Media)
  • Coravel Dallas-Fort Worth campus (Dallas-Fort Worth, TX). 140 MW, announced. First anchor campus of the Coravel platform, with staggered service dates through 2028. Exact city and county not disclosed (Yahoo Finance)
  • Yondr and Cerberus Manassas data center (Manassas, VA). 72 MW, announced. 40-acre site in Manassas; Yondr is developer, owner and operator. Expected operational by 2029. County not stated in source (Yahoo Finance)
  • Digital Realty Ad Astra Enterprise Park campus (De Soto, KS). announced. Nine-building campus on about 1,400 acres in two phases (281 acres and about 1,155 acres) near the Panasonic EV plant. No tenant identified (Yahoo News (Kansas City Star))
  • Crow Holdings North Stemmons data center campus (Market Hall) (Dallas, TX). 245 MW, announced. 40-acre campus on the North Stemmons Freeway corridor that may replace the Dallas Market Hall exhibition building, which has stopped booking events (NBC DFW (Dallas Morning News))
  • PowerHouse Hillwood Joliet campus (Joliet, IL). $20.0B, 1800 MW, announced. PowerHouse Hillwood asked FERC to reject ComEd’s cancellation of its transmission security agreement in a dispute over security deposit timing The project is branded the Joliet Technology Center on a 795-acre site (Utility Dive)
  • CyrusOne Castroville data center (Castroville, TX). $500M, under_construction. One-story facility at 3397 U.S. 90 West, CyrusOne’s sixth San Antonio-area facility and first in Castroville. CyrusOne owns at least 244 acres in Medina County. Completion expected June 2027 CyrusOne’s project page says early earth-moving and grading are under way and puts expected capital investment at about $4 billion to $6 billion across multiple phases, using closed-loop cooling (Yahoo Finance (San Antonio Express-News))
  • T5 @ Chicago IV (Grayslake, IL). $18.0B, 1550 MW, approved. 472 acres with up to 10.1 million square feet. First permit issued 31 August 2026 for an initial 800,000-square-foot building while a resident lawsuit continues. Also tracked in the at-risk list (Lake and McHenry County Scanner)
  • Tract Tuckahoe Creek Technology Park (Goochland County (eastern, near West Creek), VA). 900 MW, announced. 871-acre proposed campus. Most residents at a 23 July 2026 community meeting opposed it (Yahoo News)
  • STACK Culpeper Technology Park (Culpeper, VA). announced. 71-acre site at 15140 Keyser Road in the Culpeper Tech Zone with by-right data center zoning (Commercial Observer)
  • Flexential Parker data center (Parker, CO). $205M, 22.5 MW, under_construction. Douglas County commissioners unanimously approved a $19.3 million incentive agreement rebating 100% of the county’s share of business personal property tax on the facility over 35 years. The rebate covers equipment, machinery and certain leasehold improvements, not land and buildings, and Flexential continues to pay real property, school district and fire district taxes. County documents estimate 16 permanent jobs. The Town of Parker approved the project in 2024 (Denver Gazette)
  • RELLIS Data and Research Center (Bryan, TX). $700M, under_construction. Brazos County commissioners voted 4-0, with one absent, to transfer the tax abatement agreement for the nearly complete RELLIS Campus data center to ThisWay Global, which emerged from the bankruptcy of the prior developer, RELLIS Campus Data and Research Center, LLC. KBTX reports the county receives 50% of taxable valuation for the first 10 years and 100% for the remaining 30 years of a 40-year agreement (KBTX)
  • Kinetic Infrastructure Solutions (Google) Columbia County data center (Harlem, GA). $17.0B, approved. The Economic Development Authority of Columbia County approved a memorandum of understanding with Kinetic Infrastructure Solutions, an Alphabet subsidiary, under a bond-for-title financing structure. Townhall, citing the authority, reports expected property tax payments of about $40 million a year, and a November referendum will decide whether data center revenue is dedicated to homeowner property tax relief. The county’s Data Center zoning district requires 500-foot residential buffers, a 65-decibel noise limit, closed-loop cooling, a ban on private wells and decommissioning obligations (WRDW)
  • Salem 3 data center campus (Salem Township, Luzerne County, PA). announced. The Salem Township Planning Commission voted 4-0-1, with member Susan Lynn abstaining as a participating landowner, to recommend that supervisors approve 4-3 Glenbrook Group’s Special Data Center Overlay expansion for the 4,000-plus-acre Salem 3 campus. The vote was a re-hearing of an approval first given on 23 July 2026. The matter moves to the Board of Supervisors, and at least 80% of the assembled land is intended to remain green space (Times Leader)
  • Black Mountain southeast Fort Worth data center campus (Fort Worth, TX). $10.0B, approved. Fort Worth City Council approved Black Mountain’s revised site plan for 187 acres south of Lon Stephenson Road between Forest Hill and Anglin drives, with four buildings up to 70 feet, an electrical substation and more than 300 feet of buffer from residences. The plan cuts the project from 3 million sq ft in 18 buildings, tabled in May and June 2026 after resident opposition, to just over 1 million sq ft. The city formed a Data Center and Infrastructure Commission on 11 August 2026, and KERA reports the council’s subsequent moratorium does not affect existing projects such as Black Mountain (Bisnow)

Financing transactions added this period

  • CleanSpark, Inc., CSDC Finance I, LLC (issuer) and CSRE Properties Sandersville, LLC (guarantor). project bond, Proposed $2.227 billion aggregate principal amount of senior secured notes due 2031; final size and coupon subject to pricing. CleanSpark subsidiary CSDC Finance I, LLC proposed a Rule 144A / Regulation S private offering of $2.227 billion of senior secured notes due 2031. Net proceeds are intended to finance the remaining build-out cost of the Sandersville Facility, reimburse CleanSpark for prior equity contributions to the facility and fund debt service reserves. The notes are to be secured by first-priority liens on substantially all assets of the issuer and CSRE Properties Sandersville, LLC and on the issuer’s equity, and CleanSpark is to provide a customary completion guarantee. The facility is leased for 20 years to an unnamed high investment-grade global technology company (lease announced 14 July 2026). (CleanSpark Form 8-K Exhibit 99.2 (SEC))
  • CoreWeave, Inc.. convertible, Proposed $3.0 billion convertible senior notes due 1 April 2033, plus a 13-day option for initial purchasers to buy up to an additional $500 million (not included in amount). CoreWeave proposed a private offering of $3.0 billion of convertible senior notes maturing 1 April 2033, guaranteed by the wholly owned subsidiaries that guarantee its existing senior and convertible notes. A portion of proceeds is to fund capped call transactions, with the remainder for general corporate purposes; coupon and conversion terms are set at pricing. Coverage of the same announcement also reported an at-the-market program for up to 35 million Class A shares and contracted power of about 4.2 GW as of 11 August 2026. (Investing.com)
  • Vantage Data Centers, Evercore (lead arranger), Wells Fargo Securities (lead arranger) and About a dozen unnamed insurance and institutional investors. debt facility, $2 billion development facility. Vantage Data Centers closed a $2 billion development-stage financing facility to support early-stage development across its North American platform. It is structured as a five-year revolving credit platform including extension options, with an initial collateral pool of three undisclosed development assets and the ability to add assets over time. Evercore and Wells Fargo Securities were lead arrangers, with participation from insurance and institutional investors. Vantage said it has closed more than $40 billion of capital in 2026. (Vantage Data Centers press release)
  • Oracle. capex guidance, Low end of FY2027 capex guidance of $90 billion to $95 billion, with not more than $70 billion in net cash capex (reiterated). Fiscal Q1 capex was $28,499 million per the 10-Q. Oracle reiterated fiscal 2027 capital expenditure guidance of $90 billion to $95 billion, with not more than $70 billion of net cash capex after customer prepayments. Capital expenditures for the quarter ended 31 August 2026 were $28,499 million, versus $8,502 million a year earlier. Management said it delivered 850 MW of AI capacity since the end of fiscal Q4 and reported remaining performance obligations of $664 billion. The 10-Q shows about $19,909 million of net proceeds from common stock issued under an at-the-market program during the quarter. (Oracle Form 10-Q for quarter ended August 31, 2026 (SEC))
  • Microsoft. capex guidance, No dollar figure in the report; capacity target only. Reported: Bloomberg News reported that Microsoft plans to build data center capacity to about 38 GW by 2032, from about 12 GW today, of which about 2 GW is AI-specific. The capacity would combine self-built and leased capacity, including from neoclouds. Microsoft has not publicly confirmed the 38 GW figure. (CloudTech News (citing Bloomberg))
  • Blue Owl Capital. other, About $6.5 billion of existing Blue Owl data center assets expected to seed the REIT (assets contributed, not capital raised); IPO size not reported. Reported: Blue Owl Capital is planning a publicly traded data center REIT seeded with about $6.5 billion of its own data center assets, raising capital through an IPO and later share sales to acquire and build data centers. Deliberations were described as ongoing and details could change, and Blue Owl declined to comment. (WealthManagement.com (citing Bloomberg))
  • Amazon. senior notes, GBP 4.242 billion aggregate public offering price and about GBP 4.235 billion net proceeds, across GBP 1.25 billion 5.200% notes due 2029, GBP 1 billion 5.550% due 2032, GBP 1 billion 6.250% due 2038 and GBP 1 billion 6.650% due 2045. No US dollar figure is stated, so amount_usd_m is null. Amazon closed a four-tranche British pound notes offering under its February 2026 shelf registration. The filing does not mention data centers, and use of proceeds is not stated in the 8-K (SEC Form 8-K)
  • CleanSpark, Anviran, LLC (Meta subsidiary) and Meta Platforms (guarantor). lease, Approximately $6.6 billion contracted revenue over the 20-year initial term; up to $11.6 billion with two five-year extensions. CleanSpark signed a 20-year triple-net lease for 175 MW of critical IT load at Sandersville, Georgia, with deliveries expected to begin in Q4 2027. The tenant also executed a letter of intent and exclusivity arrangement covering CleanSpark’s Texas portfolio of 718 acres and up to 885 MW. CleanSpark estimated landlord project costs of $10 million to $12 million per MW On 17 September 2026 CleanSpark disclosed the tenant as Anviran, LLC, a wholly owned subsidiary of Meta, with Meta guaranteeing rent and operating expenses. The investor presentation shows development cost of about $11.9 million per IT MW, rent commencing 30 November 2027 and about $330 million of average annual NOI, and CleanSpark proposed a $2.227 billion senior secured notes offering to fund the remaining Sandersville build (CleanSpark)
  • CoreWeave, Deutsche Bank Securities, Goldman Sachs and J.P. Morgan Securities. equity raise, Up to 35,000,000 shares of common stock through at-the-market sales, with optional collared forward sale agreements; no dollar size disclosed. CoreWeave entered an equity distribution agreement with ten sales agents for up to 35 million shares, with commissions of up to 2.0%. It may also enter collared forward sales with Deutsche Bank AG, Goldman Sachs Bank USA, Morgan Stanley and Citibank. Proceeds are for general corporate purposes including debt repayment and migration toward an investment-grade credit profile (SEC EDGAR (CoreWeave 8-K))
  • Fluidstack and US Department of Defense Office of Strategic Capital. debt facility, Roughly $5 billion under discussion; size, terms and structure not final. The Pentagon’s Office of Strategic Capital was reported to be in talks to lend about $5 billion to Fluidstack to strengthen US manufacturing capacity and supply chains for data center components. Neither party commented on the report (Tech Startups)
  • Crux AI, Blackstone, Google, Goldman Sachs, Sumitomo Mitsui Banking Corp, Barclays, BNP Paribas and Bank of Nova Scotia. debt facility, Ten-bank loan secured by the chips and Crux AI customer contracts; may be syndicated and later refinanced with investment-grade bonds. Banks provided a $22 billion loan to Crux AI, the Blackstone and Google cloud venture, to buy Google TPUs. Blackstone provided $5 billion of initial equity, recorded as blackstone-google-tpu-jv-2026. The venture plans to bring its first 500 MW online in 2027 (Global Banking & Finance Review (Reuters))
  • Brookfield Asset Management, American Real Estate Partners (AREP) and Rothschild & Co (AREP adviser). acquisition, Price and stake size not disclosed. Brookfield affiliates agreed to buy a minority interest in AREP, a Washington DC-area investor with more than $30 billion deployed or committed. AREP has 32 million square feet of hyperscale data centers in development across the United States (Yahoo Finance)
  • Sabey Corporation and Indianapolis Metropolitan Development Commission. incentive, Tax abatement; Sabey community benefit commitment of $29.8 million to $39.8 million. The Indianapolis Metropolitan Development Commission approved $240 million in tax breaks for Sabey’s $4 billion data center in Decatur Township. Sabey is set to become the city’s second-largest taxpayer. One commissioner opposed (Indianapolis Business Journal)
  • Digital Realty, Allimac 2023 LLC, Hawthorne Race Course (seller) and Hilco Real Estate. acquisition, Purchase price for 119 acres out of Chapter 11. Digital Realty is the buyer, through Allimac 2023 LLC, of the 119-acre Hawthorne Race Course at 3501 South Laramie Avenue in Stickney, Illinois. The site is zoned heavy industrial, and a data center has not yet been formally proposed The $90 million sale closed on 2 September 2026. Digital Realty has not publicly confirmed it is behind Allimac (Yahoo Finance)
  • Digital Realty and Brennan Investment Group (seller). acquisition, Purchase price for 40-acre office campus. Digital Realty bought the 40-acre Rolling Meadows Atrium Campus at 3800 Golf Road, Rolling Meadows, Illinois, and plans to convert it to data center use. Planned MW was not disclosed (The Real Deal)
  • US Department of Energy (Office of Energy Dominance Financing), NextEra Energy and Google. doe loan, Loan of up to $1.9 billion. DOE closed a loan of up to $1.9 billion to NextEra Energy to restart the 615 MW Duane Arnold Energy Center in Linn County, Iowa, pending NRC licensing approvals. NextEra targets restart no later than the first quarter of 2029 and said the Iowa Utilities Commission issued a construction and operation certificate in June 2026. Neither DOE nor NextEra mentioned Google in the loan releases; mgrid.org reported that Google holds a 25-year agreement for the plant’s output for its cloud and AI infrastructure (US DOE)
  • Blue Energy and GE Vernova Hitachi Nuclear Energy. other, No value disclosed; final investment decision targeted for 2027. Blue Energy and GE Vernova Hitachi signed an agreement to advance a 2.5 GW gas-plus-nuclear project in Victoria, Texas, to engineering, licensing and safety analysis. Phase 1 would add about 1 GW from two 7HA.02 gas turbines in 2030 and Phase 2 about 1.5 GW from up to five BWRX-300 SMRs in 2032, serving a nearby unnamed data center under a gas bridge financing model. Blue Energy submitted the first part of its NRC construction permit application for the first nuclear unit at the Port of Victoria site late on 15 September 2026 and announced it on 16 September 2026, including a request for limited construction activities and approval to build the gas-fired portion and shared balance of plant first, plus a 300-page environmental report (POWER Magazine)
  • TAR (Transformative American Resources) and Spark Capital. other, $120 million Series A led by Spark Capital at a $1 billion post-money valuation; Spark’s $100 million share as reported by Latitude Media. Austin-based TAR raised a $120 million Series A at a $1 billion post-money valuation to build off-grid solar and battery power systems for data centers, with gas backup for emergencies, and is executing a utility-scale deployment with one of the largest neoclouds in West Texas (Latitude Media)
  • PowerTransitions, Partners Group and Castleton Commodities International. acquisition, Price not disclosed in the report. FERC approved PowerTransitions’ purchase of the 1,242 MW Roseton gas- and oil-fired plant in Newburgh, New York, from a Castleton Commodities subsidiary. PowerTransitions, owned by Partners Group, plans to develop an energy campus serving data centers and other energy-intensive industries at the site PowerTransitions announced on 8 September 2026 that it had completed the acquisition, lifting its operating fleet to about 1.8 GW across 8 plants (Utility Dive)
  • Generac Holdings and Amazon. supply agreement, Up to $8 billion of backup generator purchases, with initial deliveries of $2.4 billion expected across 2027 and 2028; Amazon received warrants for up to 1,693,745 Generac shares at $200.93, worth as much as $340 million per Quartz. Generac signed a long-term agreement to supply backup power generators for Amazon data centers worth up to $8 billion and issued warrants to an Amazon subsidiary that vest in stages as Amazon’s purchase payments accrue, with full vesting at $8 billion of payments. About 308,000 warrant shares became exercisable at signing and the warrants run through 16 September 2033 (Quartz via Yahoo Finance)
  • Blockfusion USA, Inc., North East Data, LLC and CoreWeave. lease, Contract value and MW not disclosed in the release. Blockfusion’s subsidiary North East Data, LLC entered a definitive 15-year anchor lease with two five-year renewal options, plus a companion expansion agreement, with CoreWeave at its Niagara Falls, New York campus. The agreements convert a non-binding letter of intent announced 30 June 2026. Blockfusion is pursuing a business combination with Blue Acquisition Corp. that would list the combined company on Nasdaq (Blockfusion (GlobeNewswire via Yahoo Finance))
  • Vulcan Infrastructure and Power (formerly Greenidge Generation Holdings), Machine Investment Group, Atlas Holdings and Conversant Capital. PIPE equity and senior secured convertible note, 17,146,190 Class A shares at $1.71 plus a $10.0 million senior secured convertible note to a Machine affiliate (10% PIK, conversion price $2.1375), aggregate gross proceeds approximately $39.4 million; warrant for 1,754,386 shares also issued. Greenidge Generation renamed itself Vulcan Infrastructure and Power and closed a strategic investment led by affiliates of Machine Investment Group and Atlas Holdings to reposition as a powered-site platform for AI and HPC data centers. Net proceeds are primarily for redeeming approximately $33.1 million of 8.50% senior notes due October 2026, with the remainder for predevelopment in Dresden, New York and Columbus, Mississippi. Vulcan cites up to 104 MW of near-term capacity and a 654 MW development pipeline across owned sites (SEC EDGAR (Vulcan press release, Ex. 99.1, 10 September 2026))
  • DigitalOcean, MUFG Bank, Ltd., Axos Bank, BMO Bank N.A., Wells Fargo Bank, N.A. and PNC Bank, N.A.. equipment finance facility, $725 million facility maturing 10 September 2030, with an accordion of up to $300 million that the company intends to exercise subject to commitments. DigitalOcean entered a $725 million equipment finance facility to acquire GPU, CPU and other equipment for its AI-native cloud platform, with capacity aimed at 2027 and 2028 demand. MUFG Bank served as sole administrative and collateral agent, with MUFG, Axos, BMO and Wells Fargo as joint lead arrangers (SEC EDGAR (DigitalOcean press release, Ex. 99.1))
  • Nscale, Nvidia, Third Point and Goldman Sachs. proposed convertible notes and strategic equity, About $3.5 billion sought: up to $1.5 billion of convertible notes led by Third Point and about $2 billion from Nvidia, per one source; size and investors could change. Reuters reported that Nscale was in talks to raise about $3.5 billion of pre-IPO funding, with the convertible notes offered at a double-digit discount to the IPO price adjusted up to a $30 billion valuation. Goldman Sachs is working on the fundraising. Nscale and Goldman declined to comment. Nscale was valued at $14.6 billion in March 2026 after a $2 billion Series C (Reuters via KSL.com)
  • Nscale and Goldman Sachs. proposed initial public offering, Seeking to raise as much as $3 billion in a US IPO, per people familiar; details could change or the listing could be delayed. Bloomberg reported that London-based Nscale was heading for a US IPO that could take place as soon as September 2026, working with Goldman Sachs. Nscale told prospective investors it had about $51 billion of total contracted revenue and is developing data centers including in West Virginia and Norway. A representative declined to comment (Bloomberg via Yahoo Finance)

Financing transactions added this period, newly verified from earlier periods

These entries were added in this cycle but their own dates fall before the current month. They are documentation catching up, not new activity.

  • Switch, Inc.. equity raise, No filed amount. Bloomberg reported a valuation approaching $50 billion including debt; Reuters sources in July cited a raise of up to $10 billion at close to an $80 billion valuation including debt. Reported: Switch has confidentially filed for a US IPO that could come as soon as November 2026, according to Bloomberg News citing people familiar with the matter, working with Bank of America, Citigroup, Goldman Sachs, JPMorgan Chase and Morgan Stanley. Bloomberg reported a valuation approaching $50 billion including debt, while Reuters had earlier reported, citing sources, a raise of up to $10 billion at close to an $80 billion valuation including debt. Switch has not confirmed the filing. (Reuters via WMBD (citing Bloomberg))
  • Alphabet. senior notes, Sum of the ten tranches listed in the opinion exhibit: $750 million floating rate notes due 2028, $1.25 billion 4.500% due 2028, $500 million floating rate due 2029, $2 billion 4.625% due 2029, $3.5 billion 4.875% due 2031, $2.5 billion 5.200% due 2033, $4.5 billion 5.450% due 2036, $3 billion 6.250% due 2046, $4.5 billion 6.375% due 2056 and $2.5 billion 6.500% due 2066. The exhibit does not state a total. Alphabet sold a ten-tranche US dollar bond with maturities from 2028 to 2066. Reuters, citing Bloomberg News, reported on 6 August 2026 that Alphabet was seeking up to $25 billion to fund AI infrastructure and capital expenditures. The issue followed Alphabet’s raise of its 2026 capex guidance to $195 billion to $205 billion on 22 July 2026 (SEC Form 8-K Exhibit 5.1)
  • Amazon. senior notes, Aggregate public offering price of $24.923 billion; estimated net proceeds of about $24.867 billion. Eight tranches: $750 million floating rate due 2029, $3.5 billion 4.600% due 2029, $4.25 billion 4.800% due 2031, $3 billion 5.100% due 2033, $4.5 billion 5.300% due 2036, $2.75 billion 6.000% due 2046, $4 billion 6.100% due 2056 and $2.25 billion 6.250% due 2066. Amazon closed an eight-tranche US dollar notes offering on 9 July 2026, maturing between 2029 and 2066. Amazon later raised its 2026 capital expenditure guidance to about $220 billion on 30 July 2026, mostly for AWS data centers (SEC Form 8-K)
  • Tesla. debt facility, Targeted borrowing capacity of up to $30 billion that Tesla said it is securing; not reported as a closed facility, and no lenders were named. Tesla told analysts it is securing debt facilities that could provide up to $30 billion of borrowing capacity to support robotaxis, Optimus, semiconductors, solar manufacturing and AI compute infrastructure. Q2 2026 capital expenditures were $5.789 billion, up 142% year over year, and 2026 capex guidance is more than $25 billion. The company reported negative free cash flow of $1.092 billion for the quarter (Implicator)
  • Google and Cypress Creek Energy. ppa, Google’s investment amount not disclosed; Google is anchor investor and offtaker, plus $5 million for community energy affordability initiatives. Google will invest in and buy energy and storage from the Steel River Energy Center in Mississippi County, Arkansas, developed with Cypress Creek Energy and described by Google as its largest solar and battery project. The full three-phase project is 2.5 GWdc of solar and 2.9 GWh of storage, with initial phases of 1.6 GWdc and 1.9 GWh and completion expected in 2029. Google tied the project to nearby AI data centers and a Greater West Memphis Energy Impact Fund (Google)
  • TeraWulf and Anthropic. lease, Approximately $19 billion of contracted revenue over the 20-year initial term; up to approximately $33 billion if Anthropic exercises both five-year extension options. TeraWulf signed a 20-year data center lease with Anthropic for approximately 401 MW of critical IT load at its Justified Data Campus in Hawesville, Kentucky. Initial capacity is expected in the second half of 2027 and full capacity by early 2028. TeraWulf said the lease is expected to be supported by an investment-grade credit (TeraWulf)
  • TeraWulf and Fluidstack. acquisition, Aggregate cash consideration of approximately $530 million for TeraWulf’s 50.1% interest, per the Q2 2026 release; the 6 July release described approximately $450 million of invested capital monetized at a premium. TeraWulf agreed to sell its 50.1% interest in the Abernathy joint venture to an investor group led by Fluidstack. The Abernathy campus in Abernathy, Texas, has 168 MW of critical IT load (TeraWulf)
  • Core Scientific and AMD. lease, More than $14 billion of potential base contracted revenue under 15-year agreements for approximately 530 MW; partnership could support up to 2.5 GW of leasable capacity. Core Scientific and AMD announced an infrastructure partnership anchored by 15-year agreements for approximately 530 MW across five sites, with deployments beginning in 2027. AMD received market-priced warrants to purchase Core Scientific common stock, subject to commercial conditions. Individual site allocations were not given in the company releases Core Scientific’s 8-K states that on 27 July 2026 it signed leases with AMD for 377 MW of critical IT at Pecos TX, Muskogee OK and Hunt County TX, and leases with an undisclosed neocloud for 152 MW at Auburn AL and Dalton Phase 3 GA, each for 15 years with three five-year options. AMD holds a reservation right to lease up to an additional 1,925 MW through 28 December 2028. AMD received a warrant for up to 30 million shares at $23.47 vesting at 12,222 shares per MW leased, with about 6.5 million shares vested at signing, and entered credit support agreements for the neocloud leases (Core Scientific)
  • Riot Platforms and Undisclosed frontier AI lab. lease, Approximately $9.1 billion base-term contract revenue; $16.1 billion including two optional five-year extensions. Riot signed a 20-year data center lease (through June 2048) with a leading frontier AI lab for 191 MW of critical IT capacity at its Rockdale campus. Delivery of 96 MW is expected by December 2027 and the full 191 MW by June 2028. Riot also disclosed a non-binding letter of intent for a proposed lease at its Corsicana facility (Riot Platforms)
  • Riot Platforms, Riot DC Logistics, LLC and Morgan Stanley Senior Funding, Inc.. debt facility, $573.0 million senior secured delayed-draw term loan; Term SOFR plus 2.75%; matures 31 December 2026. Riot subsidiary Riot DC Logistics, LLC entered a $573.0 million senior secured delayed-draw term loan with Morgan Stanley Senior Funding as administrative agent to fund long-lead equipment for the 191 MW Rockdale data center. The loan is secured by substantially all assets of the credit parties with no recourse to Riot Platforms. Riot described it as interim financing while an investment-grade credit backstop is finalized (SEC EDGAR (Riot Platforms 8-K))
  • MARA Holdings, Volt Texas, LLC and HIF USA LLC. acquisition, Maximum potential consideration of $600.0 million, payable as post-closing milestone payments tied to regulatory approvals, power authorization and a data center lease; no upfront amount disclosed. MARA subsidiary Volt Texas acquired MAT 1177 LLC from HIF USA, which holds land rights of more than 1,200 acres in Matagorda County, Texas and a utility power agreement for 2,000 MW. HIF retains a minority interest upon execution of a lease with an HPC tenant. MARA plans to develop the site with Starwood Digital Ventures (SEC EDGAR (MARA 8-K))
  • MARA Holdings, Coinbase and Two Prime. debt facility, $600 million incremental bitcoin-backed borrowing at a 7.56% weighted average cost of debt, two-year maturity; also refinanced an existing $150 million Coinbase facility. MARA added $600 million of bitcoin-backed borrowing from Coinbase and Two Prime. Proceeds are intended to fund part of the cash consideration for the pending Long Ridge acquisition and assumption of existing indebtedness The facilities were initially collateralized by 18,750 bitcoin (MARA (Q2 2026 shareholder letter))
  • Hut 8 and Undisclosed high-investment-grade tenant. lease, Approximately $9.8 billion expected base-term contract value for the second lease; campus-level base-term value $19.6 billion, up to $50.2 billion with renewal options. Hut 8 signed a second 15-year lease for 352 MW of IT capacity at Beacon Point, doubling the tenant’s contracted capacity to 704 MW and fully commercializing the 1,000 MW campus. The initial Phase 2 data hall is expected in Q2 2028. Hut 8 reported expected average annual NOI of $655 million for the second lease (SEC EDGAR (Hut 8 8-K))
  • IREN and Undisclosed AI developers. other, $2.8 billion in new multi-year AI cloud contracts in aggregate; weighted average term of four years. IREN reported $2.8 billion of new multi-year contracts with AI developers and raised its year-end 2026 AI Cloud annualized run-rate revenue target from $3.7 billion to over $4 billion. Customer prepayments cover approximately 45% of GPU capex on recent contracts. This is a customer contract total, distinct from the $2.8 billion GPU financing already recorded (SEC EDGAR (IREN 8-K))
  • IREN and Mirantis. acquisition, Announced 5 May 2026 as a transaction worth about $625 million; at completion consideration was approximately 12.6 million IREN ordinary shares (fixed at signing) plus approximately $40 million in cash, restricted stock units and other consideration. IREN completed its acquisition of Mirantis, a cloud software company serving more than 1,500 enterprise customers, to add orchestration, monitoring and support software to its AI Cloud platform (SEC EDGAR (IREN 8-K))
  • Crusoe and Aalo Atomics. other, No investment amount disclosed. Crusoe and Aalo Atomics formed a partnership to deploy a Crusoe Spark modular data center powered by an Aalo reactor at Idaho National Laboratory in 2027, with Aalo Pods and a 50 MWe XMR power plant planned by the end of 2029 (Crusoe)
  • CoreWeave, JPMorgan and MUFG. debt facility, $2.6 billion delayed draw term loan; SOFR plus 5.50%; approximately five-year maturity; rated Ba2 by Moody’s and BB+ by Fitch. CoreWeave closed its DDTL 5.5 facility with JPMorgan and MUFG as joint lead arrangers and bookrunners. Proceeds support purchase and deployment of GPU infrastructure dedicated to customer contracts averaging about three years, secured by those contracts (SEC EDGAR (CoreWeave 8-K))
  • CoreWeave. other, More than $25 billion of net new customer commitments, excluded from the $104.2 billion backlog at 30 June 2026; customers not named. CoreWeave reported more than $25 billion of net new customer commitments in the early weeks of Q3 2026 and total contracted power of approximately 4.2 GW as of 11 August 2026. Individual customers and contract values were not disclosed (SEC EDGAR (CoreWeave investor presentation))
  • Nebius Group, MUFG, ABN AMRO, Bank of America, Deutsche Bank and HSBC. debt facility, $775 million senior secured facility; SOFR plus 2.50%; matures 31 October 2030. Nebius raised its first secured debt, backed by deployed GPU infrastructure and contracted cash flows from an agreement with an investment-grade customer. MUFG was structuring agent and sole bookrunner; Citi, Credit Agricole CIB, ING and Morgan Stanley were senior lead arrangers, with Goldman Sachs also participating (Nebius)
  • Nscale, J.P. Morgan and Goldman Sachs. debt facility, Up to $1.85 billion senior secured delayed draw term loan; investment-grade rating with stable outlook; pricing and tenor not disclosed. Nscale closed a delayed draw term loan supporting approximately 200 MW of IT load at its Ward County, Texas deployment of NVIDIA GB300 and VR200 systems. J.P. Morgan was lead left arranger. The release did not name the offtaker (Nscale)
  • Nscale, Goldman Sachs and J.P. Morgan. debt facility, Up to $1.2 billion senior secured delayed draw term loan; investment-grade rating with stable outlook; pricing and tenor not disclosed. Nscale closed a delayed draw term loan for its deployment at a 96-acre colocation site in Madison, North Carolina with up to 40 MW of IT load. Goldman Sachs was lead left arranger (Nscale)
  • HIVE Digital Technologies, BUZZ HPC, Undisclosed investment-grade enterprise customer and Bell AI Fabric. other, $350 million total contract value over five years; approximately $185 million capex; approximately $35 million customer deposit. HIVE’s BUZZ HPC signed a five-year AI cloud services agreement to deploy 2,016 NVIDIA GB300 NVL72 GPUs at the Bell AI Fabric facility in Merritt, British Columbia. The contract adds $70 million of annualized revenue (SEC EDGAR (HIVE 8-K))
  • Flexential, GI Partners, Morgan Stanley Infrastructure Partners, TD Securities, RBC Capital Markets, J.P. Morgan, Goldman Sachs, ING, SMBC, Bank of America, KeyBanc, Flagstar, Citibank and Investec. debt facility, Credit facility upsized 60% from an initial $500 million target; 11-bank syndicate with TD Securities as administrative agent. Flexential closed an $800 million credit facility to fund more than 130 MW of new capacity. Named projects are a 36 MW facility in Atlanta-Douglasville, Georgia, 36 MW in Portland-Hillsboro, Oregon, 22.5 MW in Denver-Parker, Colorado, and a 4.5 MW expansion in Atlanta-Norcross, Georgia. GI Partners and MSIP remain the equity sponsors (PR Newswire)
  • STACK Infrastructure, Blue Owl Capital, RACM (seller) and Greysteel (broker). acquisition, Purchase price for 71 acres, about $935,000 per acre. Blue Owl’s STACK Infrastructure bought the 71-acre Culpeper Technology Park at 15140 Keyser Road, Culpeper, Virginia, from RACM. The site sits in the county-designated Culpeper Tech Zone with by-right data center zoning. Planned MW was not disclosed (Commercial Observer)
  • Aligned Data Centers. abs, Class A-2-I and Class B term notes with five-year anticipated repayment dates; upsized about 30% from a $905 million target. Aligned completed a $1.183 billion securitization, its first issuance since 2023, one week after the AIP, MGX and GIP acquisition closed. Collateral is four Aligned campuses with 14 customers, and more than 90% of annualized adjusted base rent comes from investment-grade counterparties. Proceeds fund the development pipeline, refinance upcoming maturities and fund reserve accounts (GlobeNewswire)

Status changes

  • King George campus. delayed, now delayed. Delayed In late August 2026 AWS changed course on water supply for its planned King George data center campus at the 869-acre Birchwood Drive tech campus after its application to renew a groundwater permit for up to 6.4 million gallons a year from the Potomac aquifer drew opposition from state Sen. Richard Stuart and followed a DEQ report warning of declining groundwater east of Interstate 95. Part of the project remains tied up in court proceedings
  • Project Delta. court halt, now approved after delay. Jan rezoning voided by court; six-month moratorium proposal rejected Stokes County commissioners voted 3-2 on 14 September 2026 to approve the Project Delta rezoning of about 1,800 acres of farmland near Walnut Cove for developer Engineered Land Solutions. It was the board’s second vote, after the January 2026 approval was voided following a legal challenge Stokes County commissioners rejected a proposed six-month data center moratorium on 13 July 2026, and the Project Delta rezoning was refiled in July 2026. The Stokes County Planning Board voted 5-2 on 13 August 2026 to recommend denying the refiled Project Delta rezoning. On 14 September 2026 the Board of Commissioners voted 3-2 to rezone roughly 1,800 acres in Walnut Cove for developer Engineered Land Solutions, the same margin as its January 2026 approval, which had been voided over a procedural issue. Chairman Wayne Barneycastle and Commissioner Brad Chandler voted no. A Southern Coalition for Social Justice attorney would not say whether another lawsuit is planned.
  • Ellenwood facility. moratorium, now moratorium. Moratorium extended Jul 7 2026 through early 2027 DeKalb County commissioners voted 5-2 to extend the county’s data center moratorium by 100 days, to 26 September 2026. WSB Radio reported on 10 September 2026 that DeKalb County’s data center moratorium, extended multiple times, currently runs through the end of March 2027.
  • Coachella Valley Technology Campus (400+ acres, six data centers). moratorium, now moratorium. Campus shelved; moratorium extended to ~one year; permanent-ban draft approved by Planning Commission On 26 August 2026 the Coachella City Council unanimously adopted Ordinance No. 1231, a permanent ban on data centers within city limits, after approving a first reading on 12 August. Accessory server rooms are exempt. The ordinance takes effect 30 days after adoption. KESQ described the campus site as 240-plus acres near Fillmore Street and Avenue 52.
  • Riverview Innovation & Technology Campus. paused, now paused. Application “on hold” due to NYISO backlog The Town of Tonawanda approved a one-year moratorium on 4 August 2026 blocking permits for data centers with 20 MW or more of peak demand.
  • Kenilworth project. other, now other. Permanent-ban proposal; first reading passed CoreWeave is building a $1.8 billion, nearly 400,000 square foot AI data center at the former Merck campus in Kenilworth, expected to use up to 250 megawatts and begin operating in early 2027, according to NJ Advance Media. Residents of the borough and neighboring towns have packed public meetings and held weekly rallies in opposition. Gov. Mikie Sherrill signed the End Data Center Tax Credits Act, reported 2 September 2026, blocking the state from awarding the remaining $250 million under the Next New Jersey Program AI; CoreWeave’s approved award of up to $250 million remains in place
  • Landover project. moratorium, now moratorium. 180-day moratorium led to regulations; two-year countywide hyperscale moratorium approved Jul 7, 2026 On 8 July 2026 the Prince George’s County Council adopted a two-year moratorium on hyperscale data centers, sponsored by Council Chair Krystal Oriadha, with the proposed Landover Mall server farm conversion cited as the trigger.
  • Google-led port project. moratorium, now other. Moratorium proposed to Jan 1 2027; measure deferred Jul 7 2026 On 4 August 2026 the proposed 18-month Little Rock moratorium on large-scale data centers failed on a 4-4 vote with two members absent; six votes were needed. The Google facility at the Port of Little Rock is expected to need 100 MW and about 1 million gallons of water per day.
  • Deltona 800-acre AI campus. paused, now withdrawn. Commissioners voted 5-0 to freeze all AI data centers; on hold ≥1 year Citrus County’s Planning and Development Commission voted down Deltona Corporation’s request to convert almost 800 acres to heavy industrial use and expand Holder Industrial Park from about 557 acres to about 1,300 acres (reported 18 June 2026). Deltona then withdrew its comprehensive plan amendment and zoning applications, and the county canceled the public hearings set for the 14 July 2026 commission meeting (announced on a Tuesday, reported 23 and 24 June 2026). The county’s one-year moratorium on data centers, adopted in May 2026, remains in effect
  • Lighthouse campus (Port Washington). litigation, now litigation. Nearly 1GW Stargate-partnership campus. Wisconsin PSC’s April 2026 order required hyperscale operators (incl. On 6 August 2026 the Wisconsin PSC told American Transmission Co. to resubmit its application for the roughly 100-mile power line project serving the $15 billion Port Washington campus, citing about 564 changes made after the application was deemed complete. ATC refiled on 14 September 2026 at an estimated $2.5 billion to $2.7 billion, up from $1.6 billion, with Oracle paying most of the cost; Vantage says the campus remains on track for 2028.
  • STAMP campus (Stream). litigation, now litigation. 2.2M sq ft facility; $1.46B in requested state/local sales tax breaks ($716M state + $716M local); Hochul had previously called it a ‘local decision’ she wouldn’t override (March 2026) before reversing via executive order. The Batavian described Stream’s STAMP data center, Project Double Reed, as a $19.46 billion project with North and South campuses. The town of Alabama was awaiting revised plans as of 14 September 2026 after the state DEC took the position that STAMP development is no longer grandfathered from new wetland rules, which the Genesee County EDC contested in a 24 August 2026 letter. Separately, Plug Power and Stream amended their Gateway land sale on 9 July 2026, fixing the price at $142 million, allowing an interim land closing and extending the outside closing date to 31 March 2027 The Genesee County Economic Development Center board voted on 2 July 2026 to prepare resolutions approving the State Environmental Quality Review for the Stream data center, with a vote planned for a July special meeting ahead of a 3 August Alabama Planning Board meeting. GCEDC never called that meeting, the planning board meeting was canceled, and no approval vote appeared on the agendas for its late July meetings. Gov. Kathy Hochul signed an executive order on 14 July imposing a yearlong moratorium on new hyperscale data centers and has criticized GCEDC’s plan to provide Stream with $1.44 billion in subsidies The $6.3B and 250 MW figures are superseded. Stream’s revised application to the Genesee County EDC in March 2026 raised the Project Double Reed investment from $11.1 billion to $19.461 billion for a 500 MW, 2.2 million square foot, three-building facility and raised the requested tax abatements from $774 million to about $1.4 billion (The Daily News, 5 and 12 March 2026). The July 2025 lawsuit coverage described the earlier plan at 250 MW and 900,000 square feet. The Batavian still cited $19.46 billion with North and South campuses on 14 September 2026
  • Sabey Decatur Township campus. moratorium, now moratorium. Metropolitan Development Commission approved the $4B Sabey project in March 2026; one of the three flashpoint projects behind Indianapolis’s moratorium debate. Indianapolis Metropolitan Development Commission approved about $240 million in tax breaks for Sabey’s $4 billion Decatur Township data center on 16 September 2026, with Commissioner Schumacher voting against. Community commitments reported include $29.8 million to $39.8 million of investment, aquatic center financing, $5 million for nearby roads, and $50,000 for The Arts Council of Indianapolis. The Metropolitan Development Commission had approved the 250 MW, 130-acre project’s variance 6-2 on 18 March 2026, and it is one of three previously approved projects exempt from the Marion County moratorium adopted 10 August 2026
  • NorthMark / Valara computing center. other, now other. $2.8B conversion of a former Kohler kitchen/bath plant (also a longtime bitcoin-mining site) into a computing center. State regulators initially approved ~50MW; company sought to expand to 450MW (five 17MW plus six 54MW natural gas turbines, atop 24 existing 2MW generators). On 27 August 2026 the South Carolina Public Service Commission ruled unanimously, with Commissioner David Britt recused, that the Utility Facility Siting and Environmental Protection Act does not apply to NorthMark’s 457 MW on-site power station on Pine Street in Spartanburg because it generates power for internal use rather than export to the grid, and that only the Office of Regulatory Staff can enforce the Act. The Southern Environmental Law Center opposed the ruling On 27 August 2026 the South Carolina Public Service Commission ruled unanimously, with one commissioner recused, that the Utility Facility Siting and Environmental Protection Act does not apply to Valara’s on-site generation for the 457 MW Spartanburg facility because it will not export power to the grid, and that only the Office of Regulatory Staff can bring enforcement under the act. The Southern Environmental Law Center may seek reconsideration or appeal.
  • Lex Pocatello data center. litigation, now litigation. Proposed at a former polysilicon plant site; Idaho Conservation League highlighted unprecedented cumulative energy use concerns, comparing water use to an 18-hole golf course or large alfalfa field. On Thursday 16 July 2026 the Pocatello City Council, acting in a quasi-judicial role, voted to affirm hearing examiner Kathleen Lewis’s June 2026 denial of a conditional use permit for Lex Developments’ AI data center at the former Hoku site. Councilman Dakota Bates cast the lone no vote, and Councilwoman Ann Swanson was absent.
  • Google Botetourt County campus. litigation, now litigation. Western Virginia Water Authority stated it will not supply the 10-million-gallons/day Google sought; a FOIA lawsuit forced disclosure of secret water-use contracts (judge ordered release Nov 5, 2025), and the Water Authority is appealing to the Virginia Court of Appeals while a related water pipeline permit split the Planning Commission in August 2026. Botetourt County issued a land disturbance permit for the 312-acre Google site in the Botetourt Center at Greenfield, reported 30 August 2026, with night construction noise limits; DEQ environmental permits remain under review. In July 2026 Google announced air cooling for the first building
  • Revity Energy business park and data center, Hanton City. blocked, now blocked. Revity Energy proposed a business park including a data center at Hanton City in March 2026. After public opposition, Smithfield’s planning board and town council voted to ban such development in early May 2026, the first municipal data center ban in Rhode Island. Single-sourced from a secondary account in the Charlestown reporting; the Smithfield record has not been confirmed from a Smithfield source. Developers Hanton City Investments LLC and ROK LLC are appealing the town administrative officer’s 11 June 2026 decision that their major land development application for the Smithfield Corporate Complex at 364 George Washington Highway was incomplete. The application was filed a day before the Town Council adopted a data center ban. The Zoning Board of Review hearing on the appeal, postponed from 2 September 2026, was rescheduled for 7 October 2026, according to a Town Council member
  • Project Jupiter permitting stay (Oracle campus). court halt, now court halt. The New Mexico Supreme Court unanimously granted two stays reported 24 August 2026. It halted the New Mexico Environment Department air quality permit hearing set to open 14 September 2026 in Sunland Park on the campus’s on-site methane fuel-cell microgrid, and it ordered the Office of the State Engineer to pause emergency authorization of water from a newly constructed well used for construction. New Energy Economy petitioned on the air permit, arguing the department cannot hold a hearing before the project’s fuel source is established; the Center for Biological Diversity petitioned on the water authorization. The designated hearing officer withdrew from the case, and a replacement will be appointed after the stay is lifted. Site work continued after the New Mexico Supreme Court order pausing the air quality permit process and the State Engineer water permit, with 2,105 construction workers on site as of 30 June 2026 per Oracle records reported by Searchlight New Mexico. On 8 September 2026 Oracle issued an RFP for 2 GW of new New Mexico renewable generation deliverable between 2027 and 2031, tied to 100% carbon-free matching for Project Jupiter by 2031, and offered up to $1 million for carbon capture research on the Bloom fuel cells
  • Eastport data center moratorium (DeepGreen Western Passage). moratorium, now moratorium. City councilors unanimously adopted a 180-day moratorium on 12 August 2026 barring approval of any permit, license or application for industrial data centers or computing facilities and associated infrastructure, on land or underwater. On 27 August 2026 the Planning Board unanimously recommended that the city adopt a permanent ban. The measures respond to DeepGreen Western Passage’s February 2026 application to the Federal Energy Regulatory Commission for a preliminary permit to study a tidal-powered subsea data center in Passamaquoddy Bay; federal regulators accepted that application in the week after the moratorium took effect. A separate citizen petition from the Eastport Coalition for Healthy Oceans seeks an ordinance prohibiting data centers larger than 25,000 sq ft in the city and its coastal waters. The city held a public hearing on citizen-initiated ordinances in September 2026 while residents sought intervenor status in the FERC preliminary permit proceeding for the DeepGreen project.
  • Bow data center (former Merrimack Station site). other, now other. Governor Kelly Ayotte said on 2 September 2026 that she opposes the proposed Bow hyperscale data center and any data center in New Hampshire, and that she will include a multi-year moratorium in her next state budget proposal, which would not take effect before July 2027. She said an executive order could impose a ban sooner. State House Democrats separately announced plans to file 24-month moratorium legislation for the 2027 session. The project is at feasibility-study stage: Eversource Energy is conducting a study at Granite Shore Power’s request for a hyperscale data center tied to the Bow coal plant that ceased operating in 2025. No moratorium has been enacted and no formal application has been filed. FERC filings describe a preliminary Eversource study, requested by Merrimack Station owner Granite Shore Power, on the viability of connecting a 350 MW project to the grid, while an Eversource executive mentioned a developer considering a data center of up to 200 MW in Bow. On 2 September 2026 Gov. Kelly Ayotte said she opposes the potential Bow data center and plans to propose a statewide moratorium on data centers.
  • CRG Festus campus litigation. litigation, now litigation. Wake Up Jeffco LLC, Sherman Doyle, Vernon Valish, Sharon Valish and Rozilyn Daniels filed suit on 8 April 2026 in St. Louis County Circuit Court against the City of Festus and CRG Acquisition LLC, seeking to stop the project by invalidating the city’s rezoning decisions and its development agreement. The suit followed the council’s 6-2 approval of the development agreement on 30 March 2026. Motions to dismiss had been filed and answered as of mid-June 2026, and as of 12 June 2026 no construction plans or permit requests had been submitted. The council separately voted 5-2 on 24 August 2026 to annex three additional parcels for the project. On 24 August 2026 the Festus City Council voted 5-2 to annex three more parcels totaling 6.55 acres along Hwy. 67 for the CRG data center project, which the Leader describes as a hyperscale data center on 361 acres that CRG, the data center development arm of Clayco, estimates will cost US$6 billion. The council approved a development agreement with CRG Acquisition on 30 March 2026, and CRG’s president hopes construction starts in November 2026. The St. Louis Post-Dispatch reports data center opponents were in Jefferson County court over whether a recall of four Festus officials should go before voters.
  • Mona area data center approval process challenge. other, now under appeal. Residents of the Mona area are challenging how a proposed data center of roughly 3 million square feet, described in reporting as a $10 billion project and the largest in Juab County’s history, was approved with little public input. County commissioners did not approve the project themselves: planning officials cleared it through a zone change and a conditional use permit, and the public hearing on 15 April 2026 lasted about four minutes with only the county, the selling landowners and the developers present. Residents say they learned of the project only recently and are asking how the zone change was presented to the public and how the conditional use permit was approved, and are demanding a public hearing before any further decision rather than after it is final. No approval has been rescinded and no litigation is recorded here; this is a live challenge to the process. The capital figure is left blank because the $10 billion is a press characterization, not a disclosed commitment. On Tuesday 15 September 2026 the community group Mona Cares filed an appeal asking the Juab County Commission to overturn the conditional use permit, arguing the county did not give residents adequate and actual notice. Commission Chair Clint Painter said the county followed state notice requirements and warned that reversing the approval could expose the county to costly developer lawsuits. Appeals are normally due within 30 days; the group argues the August posting of the meeting minutes supports accepting it. Whether the commission will accept the appeal had not been decided.
  • Springhill Township application bar and data center ordinances. moratorium, now moratorium. Springhill Township supervisors approved a resolution on 4 September 2026 prohibiting anyone from applying for a data center or power plant in the township until the next meeting, and tabled two ordinances regulating data centers and fossil fuel power plants to satisfy state notice requirements. The final vote was scheduled for 17 September 2026. As drafted, the ordinances would treat data centers and accompanying power plants as conditional uses in the heavy and light industrial districts, require data centers to sit 200 feet from property lines and 400 feet from occupied homes and power plants 500 feet and 1,500 feet respectively, and cap noise at 55 decibels by day and 45 at night measured at the nearest property line. The township began drafting the ordinances after being approached by Nadara.
  • Burgin hyperscale campus annexation. restarted, now delayed. Burgin’s earlier attempt to annex more than 1,000 acres for a Panattoni Data Centers hyperscale campus was declared null and void. The city restarted the process in September 2026 with adjusted boundary lines, and the city council was scheduled to vote at a special meeting on 8 September 2026 to begin drafting a new annexation ordinance for the revised land. Residents opposing the project called for basic protections and third-party expertise during the drafting. At the 8 September 2026 special meeting, the council passed the first reading of an ordinance to rejoin the joint planning and zoning commission on Mayor Joseph Monroe’s tie-breaking vote. Council member Melinda Wofford then left the meeting, leaving the council without a quorum, so no vote was taken on the annexation measure. The zoning ordinance still needs a second reading, state review and a final council vote; the mayor said rejoining makes development harder but does not end the project. The Harrodsburg Herald reported on 17 September 2026 that the council had approved the data center annexation of 10 properties at a July special meeting but a later special meeting for second reading was canceled, and that the 8 September vote was only to have the city attorney draft a new annexation ordinance. The interlocal agreement to rejoin the Harrodsburg-Burgin-Mercer County Joint Planning and Zoning Commission still needs second readings by all three bodies and Kentucky Department of Local Government approval

Site status changes

  • Eagle Mountain campus. expansion, now expansion.
  • Nscale West Virginia campus. announced, now approved.
  • CyrusOne Freestone County campus (Freestone Energy Center). announced, now under_construction.
  • Corscale Swatara Township data center. announced, now announced.
  • Cameron County AI data center campus. construction, now under construction.

How to read this

Every figure in the atlas links to the page that states it. Where a value could not be confirmed from a fetched source, the entry reads n.a. rather than an estimate, and roughly two-thirds of the capital-at-risk rows carry either a dollar figure or a megawatt figure but not both, because local rezoning dockets disclose acreage and square footage while investment figures come from economic-development announcements that a withdrawn project never makes. The dollar total of the rows that do disclose a figure is therefore a floor, not a census.

The atlas sits alongside two companion references: the Nationwide Data Center Delay Watchlist, which tracks project-level slippage, queues, and securities filings, and the U.S. Data Center Moratorium Tracker, which maps state and local policy measures. All citations behind this atlas are listed on one page.

Would you like the atlas update?

The atlas is re-verified and republished on Tuesday, Thursday and Saturday. You get one email when it goes out, with what changed. Nothing else.

Also send me