ERCOT
Electric Reliability Council of Texas, Inc. (ERCOT) RTO / ISOInterconnection of new data centers is paused statewide while ERCOT audits its entire large-load queue under Gov. Abbott's August 3, 2026 directive. The audit report is due to the PUCT by December 10, 2026, and ERCOT has told regulators the Batch Zero study will miss its April 9, 2027 deadline with no replacement date set. Texas law already lets ERCOT remotely disconnect non-critical loads of 75 MW or more during firm load shed.
| Measure | Status | What it does | Source |
|---|---|---|---|
| Texas Senate Bill 6 — large-load interconnection, curtailment, and remote-disconnect standardsSB 6, 89th Texas Legislature (2025) |
Effective · Jun 20, 2025
effective; PUCT implementation rulemakings ongoing through 2026
|
Applies to non-critical loads of 75 MW or greater in ERCOT. Requires remote-disconnect capability as a condition of interconnection for loads interconnecting after December 31, 2025, and authorizes utilities/ERCOT to disconnect eligible large loads during firm load shed events; creates a competitively procured voluntary curtailment/reliability service with a minimum 24-hour notice period. Also sets a $100,000 minimum interconnection study fee, mandatory disclosure of duplicative interconnection requests in Texas,… | |
| Batch Zero large-load interconnection framework (PGRR145 + NPRR1325)ERCOT Planning Guide Revision Request 145; Nodal Protocol Revision… |
Effective · Jun 18, 2026
approved/effective; classification and study timelines now partially suspended by the August 2026 audit pause
|
Groups qualified large loads of 75 MW+ into a single batch study to allocate available grid capacity year-by-year (2028–2032) via Load Commissioning Plans, set financial commitments ($50,000/MW financial security), and produce an actionable transmission plan. Key milestones: developer submissions due July 10, 2026; TSP/DSP packages due July 24, 2026; ERCOT classification notices (Base Load / Studied Load) by August 7, 2026; study results April 9, 2027; interconnection agreements executed by June 8, 2027. ERCOT… | |
| PUCT proposed rule 16 TAC §25.194 — large load interconnection standards (SB 6 implementation)PUCT Project No. 58481 |
Filed · Mar 12, 2026
proposed / pending adoption (adoption expected later in 2026)
|
Would establish interconnection standards for new or expanded loads of 75 MW+ in ERCOT: minimum study fees of $100,000 (75–249 MW) and $300,000 (250 MW+), CPI-adjusted every five years from 2027; financial security of $50,000 per MW of requested peak demand at intermediate-agreement execution plus additional security for long-lead equipment; a non-refundable interconnection fee of $50,000 per MW of contracted peak demand after study completion; site-control and development-readiness showings before studies begin;… | |
| PUCT order in Docket 59220 — first SB 6 net-metering/co-location ruling, affirming curtailment authority over co-located data…PUCT Docket No. 59220 |
Effective · Jul 23, 2026
approved with conditions (binding on the applicants; first precedent for SB 6 co-location cases)
|
PUCT approved a net-metering arrangement for a Crusoe-developed AI data center co-located behind the ~265.5 MW Goodnight 1 wind farm (a 260 MW second facility at the campus), with conditions: the full campus load must curtail within 30 minutes during ERCOT grid emergencies, physical breaker disconnection authorized, ERCOT to give 60 minutes advance notice when practicable, and the project is barred from compensation for load reductions during grid emergencies. Establishes that emergency curtailment of co-located… | |
| Gov. Abbott directive — comprehensive verification and audit of data centers in the ERCOT queue; pause on new data center…Gubernatorial directive to PUCT Chairman Thomas Gleeson and ERCOT… |
Effective · Aug 3, 2026
effective; audit in progress, pause remains pending audit completion
|
Directs PUCT and ERCOT to verify every data center project advancing through the interconnection process — power demand and sourcing, on-site generation progress, water use and cooling, state/local financial assistance, community protections, and ownership — before any additional data center is approved to advance. States that projects failing the verification and audit process 'must be denied' grid access. Binds ERCOT and the PUCT. | |
| ERCOT Market Notice M-A080326-01 — suspension of Batch Zero classification deadlineERCOT Market Notice M-A080326-01 | Effective · Aug 3, 2026 | ERCOT announced it would not meet the August 7, 2026 deadline to notify service providers of Large Load classifications in the Batch Zero Interconnection Study, citing the Governor's directive to conduct a verification process before advancing any data center large loads. ERCOT committed to file a good cause exception request with the PUCT before the PUCT's August 20, 2026 open meeting, seeking modification of timelines in Planning Guide Sections 5 and 9. | |
| ERCOT good-cause-exception filing and PUCT approval; audit timeline set (RFIs now, reports due December 10, 2026)PUCT Control No. 59142 (Item 42) |
Effective · Aug 10, 2026
approved
|
ERCOT requested relief from the August 7 classification deadline, authority for large loads to participate in the August and November Quarterly Stability Assessments (6 projects for August, up to 17 for November), and an extension for dynamic-data deficiency notifications; the PUCT granted the exceptions on August 20. ERCOT's timeline: RFIs to developers via TSPs/DSPs from late August through September, information gathering October–November, and filing of the Batch Zero Eligibility Verification Report and… | |
| PUCT Project 58484 — evaluation of transmission cost recovery (4CP methodology) for large loadsPUCT Project No. 58484 |
Filed · Aug 1, 2025
pending rulemaking (SB 6 requires amended rules no later than December 31, 2026)
|
Evaluates whether the four-coincident-peak (4CP) wholesale transmission cost allocation method appropriately assigns costs given large-load growth. Draft recommendations under comment include moving to more coincident peaks over longer intervals, eliminating interconnection cost allowances for large loads, requiring large loads to pay a share of system upgrade costs, and minimum demand charges based on contracted peak demand for 10–15 years. | |
| SB 6 companion rulemakings: Project 58479 (co-location net metering), Project 58480 (large-load forecasting, ≥10 MW definition),…PUCT Project Nos. 58479, 58480, 58482 |
Filed · Jan 2026
pending as of the December 23, 2025 source; mid-2026 adoption status not independently confirmed (see flags)
|
58479 requires PUCT approval of net-metering arrangements between new 75 MW+ customers and stand-alone generators, allowing conditional approvals (callable capacity, behind-the-meter curtailment) — the framework applied in Docket 59220. 58480 defines a large load customer as 10 MW+ at a single site for forecasting and sets documentation/milestones for inclusion in ERCOT forecasts. 58482 creates the SB 6 voluntary demand-reduction/reliability program for large loads. | |
| ERCOT market notice M-A013126-02: Results of Final Ad Hoc Interim VRT Assessment for Large LoadsERCOT Market Notice M-A013126-02 |
Issued · Jun 26, 2026
Market notice
|
ERCOT issued market notice M-A013126-02, Results of Final Ad Hoc Interim VRT Assessment for Large Loads, on Jun 26, 2026. | |
| ERCOT market notice M-A052026-02: Impact Analysis - Incorrect consideration of ECRS Ramp Rate Telemetry for Non-Controllable Load ResourcesERCOT Market Notice M-A052026-02 |
Issued · Jul 31, 2026
Market notice
|
ERCOT issued market notice M-A052026-02, Impact Analysis - Incorrect consideration of ECRS Ramp Rate Telemetry for Non-Controllable Load Resources, on Jul 31, 2026. | |
| ERCOT market notice M-A080326-02: PUC Approval of Good Cause Exceptions Relating To Batch Zero ProcessERCOT Market Notice M-A080326-02 |
Issued · Aug 21, 2026
Market notice
|
ERCOT issued market notice M-A080326-02, PUC Approval of Good Cause Exceptions Relating To Batch Zero Process, on Aug 21, 2026. | |
| ERCOT market notice M-A080326-03: Delayed Issuance of Batch Zero Conditional ClassificationsERCOT Market Notice M-A080326-03 |
Issued · Aug 31, 2026
Market notice
|
ERCOT issued market notice M-A080326-03, Delayed Issuance of Batch Zero Conditional Classifications, on Aug 31, 2026. | |
| ERCOT market notice M-A080326-04: Batch Zero Conditional Classification issued to Transmission and/or Distribution Service ProvidersERCOT Market Notice M-A080326-04 |
Issued · Sep 3, 2026
Market notice
|
ERCOT issued market notice M-A080326-04, Batch Zero Conditional Classification issued to Transmission and/or Distribution Service Providers, on Sep 3, 2026. | |
| ERCOT market notice M-A090226-01: Workshop to share proposed operational framework for implementing SB6-related Large Load curtailments, including registration requirementsERCOT Market Notice M-A090226-01 |
Issued · Sep 2, 2026
Market notice
|
ERCOT issued market notice M-A090226-01, Workshop to share proposed operational framework for implementing SB6-related Large Load curtailments, including registration requirements, on Sep 2, 2026. | |
| ERCOT market notice M-A090926-01: Issuance of Batch Zero Verification Requests for InformationERCOT Market Notice M-A090926-01 |
Issued · Sep 9, 2026
Market notice
|
ERCOT issued market notice M-A090926-01, Issuance of Batch Zero Verification Requests for Information, on Sep 9, 2026. | |
| ERCOT market notice M-B062326-01: Implementation of the Batch Zero Process (PGRR145/NPRR1325)ERCOT Market Notice M-B062326-01 |
Issued · Jun 23, 2026
Market notice
|
ERCOT issued market notice M-B062326-01, Implementation of the Batch Zero Process (PGRR145/NPRR1325), on Jun 23, 2026. | |
| ERCOT market notice M-B062326-02: Batch Zero follow-up for WLPUN/BYOGERCOT Market Notice M-B062326-02 |
Issued · Jun 26, 2026
Market notice
|
ERCOT issued market notice M-B062326-02, Batch Zero follow-up for WLPUN/BYOG, on Jun 26, 2026. | |
| ERCOT market notice M-B062326-03: Large Load Prerequisites for the Quarterly Stability Assessment with a Prerequisite Deadline of August 1, 2026ERCOT Market Notice M-B062326-03 |
Issued · Jul 8, 2026
Market notice
|
ERCOT issued market notice M-B062326-03, Large Load Prerequisites for the Quarterly Stability Assessment with a Prerequisite Deadline of August 1, 2026, on Jul 8, 2026. | |
| ERCOT market notice M-B062326-04: Details for ending the Large Load Interconnection Study process under PGRR115 and submission deadlines for PGRR145 (Batch Zero) on July 10, 2026ERCOT Market Notice M-B062326-04 |
Issued · Jul 8, 2026
Market notice
|
ERCOT issued market notice M-B062326-04, Details for ending the Large Load Interconnection Study process under PGRR115 and submission deadlines for PGRR145 (Batch Zero) on July 10, 2026, on Jul 8, 2026. | |
| ERCOT market notice M-B062326-05: Batch Zero submissions of Dynamic Model files to ERCOT for July 10, 2026 deadlineERCOT Market Notice M-B062326-05 |
Issued · Jul 10, 2026
Market notice
|
ERCOT issued market notice M-B062326-05, Batch Zero submissions of Dynamic Model files to ERCOT for July 10, 2026 deadline, on Jul 10, 2026. | |
| ERCOT market notice M-B062326-06: Batch Zero Eligibility Submissions and Good Cause Exception Process for PGRR145ERCOT Market Notice M-B062326-06 |
Issued · Jul 23, 2026
Market notice
|
ERCOT issued market notice M-B062326-06, Batch Zero Eligibility Submissions and Good Cause Exception Process for PGRR145, on Jul 23, 2026. | |
| ERCOT market notice M-B063026-01: Partial Implementation Details of PGRR145/NPRR1325, Batch Zero Process for Large Load InterconnectionsERCOT Market Notice M-B063026-01 |
Issued · Jun 30, 2026
Market notice
|
ERCOT issued market notice M-B063026-01, Partial Implementation Details of PGRR145/NPRR1325, Batch Zero Process for Large Load Interconnections, on Jun 30, 2026. | |
| ERCOT market notice M-F073126-01: Revised Notice of Proposed Net Metering Arrangement Form relating to Net Metering Arrangements Involving a Large Load Customer Co-Located with an Existing Generation ResourceERCOT Market Notice M-F073126-01 |
Issued · Jul 31, 2026
Market notice
|
ERCOT issued market notice M-F073126-01, Revised Notice of Proposed Net Metering Arrangement Form relating to Net Metering Arrangements Involving a Large Load Customer Co-Located with an Existing Generation Resource, on Jul 31, 2026. | |
| ERCOT news release: PUCT Approves ERCOT's Batch Zero Process for Connecting Large Electricity Users While Protecting System Reliability for TexansERCOT News Release 2026-06-18 06182026-puct-approves-ercots |
Published · Jun 18, 2026
News release
|
ERCOT published the news release PUCT Approves ERCOT's Batch Zero Process for Connecting Large Electricity Users While Protecting System Reliability for Texans on Jun 18, 2026. | |
| PUCT Project 58481: Request for Control NumberPUCT Project 58481, Item 1 |
Filed · Jul 31, 2025
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Request for Control Number in PUCT Project 58481 on Jul 31, 2025. | |
| PUCT Project 58481: Staff Memo and Questions for Comment w/Oct. 10 Comment DeadlinePUCT Project 58481, Item 2 |
Filed · Sep 12, 2025
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Staff Memo and Questions for Comment w/Oct. 10 Comment Deadline in PUCT Project 58481 on Sep 12, 2025. | |
| PUCT Project 58481: OPUC NOTICE OF PARTICIPATION LETTERPUCT Project 58481, Item 3 |
Filed · Sep 24, 2025
OPUC
|
OPUC filed OPUC NOTICE OF PARTICIPATION LETTER in PUCT Project 58481 on Sep 24, 2025. | |
| PUCT Project 59142: ERCOT LARGE LOAD BATCH STUDY PROCESS UPDATEPUCT Project 59142, Item 11 |
Filed · Feb 5, 2026
ERCOT
|
ERCOT filed ERCOT LARGE LOAD BATCH STUDY PROCESS UPDATE in PUCT Project 59142 on Feb 5, 2026. | |
| PUCT Project 59142: TBC ERCOT Large Load Interconnection Batch Study CommentsPUCT Project 59142, Item 12 |
Filed · Feb 6, 2026
TEXAS BLOCKCHAIN COUNCIL
|
TEXAS BLOCKCHAIN COUNCIL filed TBC ERCOT Large Load Interconnection Batch Study Comments in PUCT Project 59142 on Feb 6, 2026. | |
| PUCT Project 59142: ERCOT LARGE LOAD BATCH STUDY UPDATEPUCT Project 59142, Item 13 |
Filed · Feb 13, 2026
ERCOT
|
ERCOT filed ERCOT LARGE LOAD BATCH STUDY UPDATE in PUCT Project 59142 on Feb 13, 2026. | |
| PUCT Project 59142: ERCOT LARGE LOAD BATCH STUDY UPDATEPUCT Project 59142, Item 14 |
Filed · Mar 5, 2026
ERCOT
|
ERCOT filed ERCOT LARGE LOAD BATCH STUDY UPDATE in PUCT Project 59142 on Mar 5, 2026. | |
| PUCT Project 59142: PUC PROJECT NO. 59142 - BATCH STUDY CONSIDERATIONS AND PGRR145PUCT Project 59142, Item 15 |
Filed · Mar 9, 2026
SCHAPER ENERGY CONSULTING LLC
|
SCHAPER ENERGY CONSULTING LLC filed PUC PROJECT NO. 59142 - BATCH STUDY CONSIDERATIONS AND PGRR145 in PUCT Project 59142 on Mar 9, 2026. | |
| PUCT Project 59142: Vistra Corp.'s Comments on Planning Guide Revision Request 145 for Project 59142PUCT Project 59142, Item 16 |
Filed · Mar 20, 2026
VISTRA CORP.
|
VISTRA CORP. filed Vistra Corp.'s Comments on Planning Guide Revision Request 145 for Project 59142 in PUCT Project 59142 on Mar 20, 2026. | |
| PUCT Project 59142: ERCOT LARGE LOAD BATCH STUDY UPDATEPUCT Project 59142, Item 17 |
Filed · Mar 30, 2026
ERCOT
|
ERCOT filed ERCOT LARGE LOAD BATCH STUDY UPDATE in PUCT Project 59142 on Mar 30, 2026. | |
| PUCT Project 59142: Vistra Corp.'s Comments on Planning Guide Revision Request 145 for Project 59142PUCT Project 59142, Item 18 |
Filed · Apr 9, 2026
VISTRA CORP.
|
VISTRA CORP. filed Vistra Corp.'s Comments on Planning Guide Revision Request 145 for Project 59142 in PUCT Project 59142 on Apr 9, 2026. | |
| PUCT Project 59142: ONCOR ELECTRIC DELIVERY COMPANY LLC’S COMMENTS ON ERCOT’S PGRR 145PUCT Project 59142, Item 19 |
Filed · Apr 10, 2026
ONCOR ELECTRIC DELIVERY COMPANY LLC
|
ONCOR ELECTRIC DELIVERY COMPANY LLC filed ONCOR ELECTRIC DELIVERY COMPANY LLC’S COMMENTS ON ERCOT’S PGRR 145 in PUCT Project 59142 on Apr 10, 2026. | |
| PUCT Project 59142: CONTROL NUMBER REQUESTPUCT Project 59142, Item 1 |
Filed · Dec 17, 2025
PUC EXECUTIVE DIRECTOR
|
PUC EXECUTIVE DIRECTOR filed CONTROL NUMBER REQUEST in PUCT Project 59142 on Dec 17, 2025. | |
| PUCT Project 59142: ERCOT LARGE LOAD BATCH STUDY UPDATEPUCT Project 59142, Item 20 |
Filed · Apr 10, 2026
ERCOT
|
ERCOT filed ERCOT LARGE LOAD BATCH STUDY UPDATE in PUCT Project 59142 on Apr 10, 2026. | |
| PUCT Project 59142: PGRR145 & ERCOT BATCH ZERO CRITERIA CONSIDERATIONPUCT Project 59142, Item 21 |
Filed · Apr 11, 2026
SCHAPER ENERGY CONSULTING LLC
|
SCHAPER ENERGY CONSULTING LLC filed PGRR145 & ERCOT BATCH ZERO CRITERIA CONSIDERATION in PUCT Project 59142 on Apr 11, 2026. | |
| PUCT Project 59142: Staff MemoPUCT Project 59142, Item 22 |
Filed · Apr 13, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Staff Memo in PUCT Project 59142 on Apr 13, 2026. | |
| PUCT Project 59142: Joint Comments of Google LLC, Lancium LLC, and Eolic Development LLCPUCT Project 59142, Item 24 |
Filed · Apr 16, 2026
Google LLC, Lancium LLC, Eolic Development LLC
|
Google LLC, Lancium LLC, Eolic Development LLC filed Joint Comments of Google LLC, Lancium LLC, and Eolic Development LLC in PUCT Project 59142 on Apr 16, 2026. | |
| PUCT Project 59142: TRACT HOLDING COMPANY I, LLC’S COMMENTS ON THE COMMISSION’S STAFF MEMO DATED APRIL 12, 2026PUCT Project 59142, Item 25 |
Filed · Apr 16, 2026
Tract Holding Company I, LLC
|
Tract Holding Company I, LLC filed TRACT HOLDING COMPANY I, LLC’S COMMENTS ON THE COMMISSION’S STAFF MEMO DATED APRIL 12, 2026 in PUCT Project 59142 on Apr 16, 2026. | |
| PUCT Project 59142: Comments in Response to Staff MemoPUCT Project 59142, Item 27 |
Filed · Apr 16, 2026
Engine No. 1
|
Engine No. 1 filed Comments in Response to Staff Memo in PUCT Project 59142 on Apr 16, 2026. | |
| PUCT Project 59142: CyrusOne Project No. 59142 Batch Study Considerations and PGRR145PUCT Project 59142, Item 29 |
Filed · Apr 17, 2026
CyrusOne, LP
|
CyrusOne, LP filed CyrusOne Project No. 59142 Batch Study Considerations and PGRR145 in PUCT Project 59142 on Apr 17, 2026. | |
| PUCT Project 59142: Joint Comments of Google LLC and Lancium LLC as it pertains to ERCOT's Large Load Process ReformsPUCT Project 59142, Item 2 |
Filed · Dec 18, 2025
GOOGLE LLC, LANCIUM LLC
|
GOOGLE LLC, LANCIUM LLC filed Joint Comments of Google LLC and Lancium LLC as it pertains to ERCOT's Large Load Process Reforms in PUCT Project 59142 on Dec 18, 2025. | |
| PUCT Project 59142: Staff's April 29, 2026 comments on PGRR 145PUCT Project 59142, Item 30 |
Filed · Apr 29, 2026
PUC DEPUTY EXECUTIVE DIRECTOR
|
PUC DEPUTY EXECUTIVE DIRECTOR filed Staff's April 29, 2026 comments on PGRR 145 in PUCT Project 59142 on Apr 29, 2026. | |
| PUCT Project 59142: TRACT HOLDING COMPANY I, LLC’S COMMENTS ON THE COMMISSION’S STAFF MEMO DATED APRIL 12, 2026PUCT Project 59142, Item 31 |
Filed · May 4, 2026
Tract Holding Company I, LLC
|
Tract Holding Company I, LLC filed TRACT HOLDING COMPANY I, LLC’S COMMENTS ON THE COMMISSION’S STAFF MEMO DATED APRIL 12, 2026 in PUCT Project 59142 on May 4, 2026. | |
| PUCT Project 59142: ERCOT LARGE LOAD BATCH STUDY UPDATEPUCT Project 59142, Item 32 |
Filed · May 5, 2026
ERCOT
|
ERCOT filed ERCOT LARGE LOAD BATCH STUDY UPDATE in PUCT Project 59142 on May 5, 2026. | |
| PUCT Project 59142: Staff memo on Batch 0 entry criteriaPUCT Project 59142, Item 33 |
Filed · May 6, 2026
PUC DEPUTY EXECUTIVE DIRECTOR
|
PUC DEPUTY EXECUTIVE DIRECTOR filed Staff memo on Batch 0 entry criteria in PUCT Project 59142 on May 6, 2026. | |
| PUCT Project 59142: DCC Comments on Net Metering Arrangements in Batch ZeroPUCT Project 59142, Item 34 |
Filed · May 14, 2026
Data Center Coalition (DCC)
|
Data Center Coalition (DCC) filed DCC Comments on Net Metering Arrangements in Batch Zero in PUCT Project 59142 on May 14, 2026. | |
| PUCT Project 59142: Comments on May 6th Staff MemorandumPUCT Project 59142, Item 36 |
Filed · May 26, 2026
Nightpeak Energy LLC
|
Nightpeak Energy LLC filed Comments on May 6th Staff Memorandum in PUCT Project 59142 on May 26, 2026. | |
| PUCT Project 59142: Crusoe Technologies, LLC Comments on Recommended Approval of PGRR 145 by the ERCOT Board of DirectorsPUCT Project 59142, Item 37 |
Filed · Jun 12, 2026
Crusoe Technologies, LLC
|
Crusoe Technologies, LLC filed Crusoe Technologies, LLC Comments on Recommended Approval of PGRR 145 by the ERCOT Board of Directors in PUCT Project 59142 on Jun 12, 2026. | |
| PUCT Project 59142: First Ammonia LLC's Comments on Commission Consideration of PGRR 145, Batch Zero Process for Large Load InterconnectionsPUCT Project 59142, Item 39 |
Filed · Jun 17, 2026
First Ammonia LLC
|
First Ammonia LLC filed First Ammonia LLC's Comments on Commission Consideration of PGRR 145, Batch Zero Process for Large Load Interconnections in PUCT Project 59142 on Jun 17, 2026. | |
| PUCT Project 59142: Project Trailblazer - Request for Legacy and/or batch zero Interconnection Process ConsiderationPUCT Project 59142, Item 40 |
Filed · Jul 10, 2026
Trailblazer Infrastructure LLC
|
Trailblazer Infrastructure LLC filed Project Trailblazer - Request for Legacy and/or batch zero Interconnection Process Consideration in PUCT Project 59142 on Jul 10, 2026. | |
| PUCT Project 59142: Notice of Withdrawal - This filing formally withdraws Trailblazer Infrastructure LLC's previously submitted Informational Memorandum in PUCT Project No. 59142. The notice advises the Commission that, due to ongoing discussions among the relevant parties.PUCT Project 59142, Item 41 |
Filed · Jul 13, 2026
Trailblazer Infrastrructure LLC.
|
Trailblazer Infrastrructure LLC. filed Notice of Withdrawal - This filing formally withdraws Trailblazer Infrastructure LLC's previously submitted Informational Memorandum in PUCT Project No. 59142. The notice advises the Commission that, due to ongoing discussions among the relevant parties. in PUCT Project 59142 on Jul 13, 2026. | |
| PUCT Project 59142: ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S REQUESTS FOR GOOD CAUSE EXCEPTIONS RELATING TO BATCH ZERO DEADLINES AND STATUS UPDATE ON ADDITIONAL MATTERS INCLUDING THE LONG-TERM LOAD FORECASTPUCT Project 59142, Item 42 |
Filed · Aug 10, 2026
ERCOT
|
ERCOT filed ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S REQUESTS FOR GOOD CAUSE EXCEPTIONS RELATING TO BATCH ZERO DEADLINES AND STATUS UPDATE ON ADDITIONAL MATTERS INCLUDING THE LONG-TERM LOAD FORECAST in PUCT Project 59142 on Aug 10, 2026. | |
| PUCT Project 59142: Letter regarding ERCOT's Requests for Exceptions Relating to Batch Zero DeadlinesPUCT Project 59142, Item 44 |
Filed · Aug 13, 2026
First Ammonia LLC
|
First Ammonia LLC filed Letter regarding ERCOT's Requests for Exceptions Relating to Batch Zero Deadlines in PUCT Project 59142 on Aug 13, 2026. | |
| PUCT Project 59142: Octa's Comments on ERCOT's August 10, 2026 Status UpdatePUCT Project 59142, Item 45 |
Filed · Aug 13, 2026
Octa Data Center Development Company LLC
|
Octa Data Center Development Company LLC filed Octa's Comments on ERCOT's August 10, 2026 Status Update in PUCT Project 59142 on Aug 13, 2026. | |
| PUCT Project 59142: Public Comment - Audit Standards Required Under Governor’s DirectivePUCT Project 59142, Item 46 |
Filed · Aug 16, 2026
Sandra Gail Gilbreath Wright
|
Sandra Gail Gilbreath Wright filed Public Comment - Audit Standards Required Under Governor’s Directive in PUCT Project 59142 on Aug 16, 2026. | |
| PUCT Project 59142: Ionic Digital Inc.'s Comments Regarding ERCOT's Requests for Good Cause Exceptions Relating to Batch Zero DeadlinesPUCT Project 59142, Item 48 |
Filed · Aug 19, 2026
Ionic Digital Inc.
|
Ionic Digital Inc. filed Ionic Digital Inc.'s Comments Regarding ERCOT's Requests for Good Cause Exceptions Relating to Batch Zero Deadlines in PUCT Project 59142 on Aug 19, 2026. | |
| PUCT Project 59142: Request for Commission Action on Batch Zero Eligibility (CloudPeak BZ-259 & BZ-180)PUCT Project 59142, Item 49 |
Filed · Aug 19, 2026
PowerHouse CloudPeak Venture Alpha LLC and PowerHouse CloudPeak Venture C LLC
|
PowerHouse CloudPeak Venture Alpha LLC and PowerHouse CloudPeak Venture C LLC filed Request for Commission Action on Batch Zero Eligibility (CloudPeak BZ-259 & BZ-180) in PUCT Project 59142 on Aug 19, 2026. | |
| PUCT Project 59142: LETTER RE ERCOT LARGE LOAD BATCH STUDY PROCESS UPDATEPUCT Project 59142, Item 4 |
Filed · Jan 12, 2026
ERCOT
|
ERCOT filed LETTER RE ERCOT LARGE LOAD BATCH STUDY PROCESS UPDATE in PUCT Project 59142 on Jan 12, 2026. | |
| PUCT Project 59142: ERCOT UPDATES - GOOD CAUSE EXCEPTIONS FOR PGRR 145, BATCH ZERO VERIFICATION AND AUDIT PROCESS, AND COMMUNITY IMPACT REVIEW PROCESSPUCT Project 59142, Item 52 |
Filed · Aug 20, 2026
ERCOT
|
ERCOT filed ERCOT UPDATES - GOOD CAUSE EXCEPTIONS FOR PGRR 145, BATCH ZERO VERIFICATION AND AUDIT PROCESS, AND COMMUNITY IMPACT REVIEW PROCESS in PUCT Project 59142 on Aug 20, 2026. | |
| PUCT Project 59142: ORDER GRANTING GOOD CAUSE EXCEPTIONSPUCT Project 59142, Item 53 |
Filed · Aug 20, 2026
PUC OPDM
|
PUC OPDM filed ORDER GRANTING GOOD CAUSE EXCEPTIONS in PUCT Project 59142 on Aug 20, 2026. | |
| PUCT Project 59142: SCHAPER ENERGY CONSULTING PROPOSED APPROACH TO PUBLIC BENEFIT DISCLOSURE IN THE COMMUNITY IMPACT COMPONENT OF THE LARGE LOAD AUDITPUCT Project 59142, Item 54 |
Filed · Aug 20, 2026
SCHAPER ENERGY CONSULTING LLC
|
SCHAPER ENERGY CONSULTING LLC filed SCHAPER ENERGY CONSULTING PROPOSED APPROACH TO PUBLIC BENEFIT DISCLOSURE IN THE COMMUNITY IMPACT COMPONENT OF THE LARGE LOAD AUDIT in PUCT Project 59142 on Aug 20, 2026. | |
| PUCT Project 59142: ERCOT UPDATE FOR SEPTEMBER 11, 2026 OPEN MEETING - BATCH ZERO AND STATE AND COMMUNITY IMPACT RFI PROCESSPUCT Project 59142, Item 55 |
Filed · Sep 11, 2026
ERCOT
|
ERCOT filed ERCOT UPDATE FOR SEPTEMBER 11, 2026 OPEN MEETING - BATCH ZERO AND STATE AND COMMUNITY IMPACT RFI PROCESS in PUCT Project 59142 on Sep 11, 2026. | |
| PUCT Project 59142: Request for Audit for Project RaptorPUCT Project 59142, Item 56 |
Filed · Sep 11, 2026
Laura Lindemann
|
Laura Lindemann filed Request for Audit for Project Raptor in PUCT Project 59142 on Sep 11, 2026. | |
| PUCT Project 59142: Synergen's Request for Good Cause Exception Relating To Batch Zero Eligibility DeadlinesPUCT Project 59142, Item 57 |
Filed · Sep 11, 2026
Synergen Green Energy, Inc.
|
Synergen Green Energy, Inc. filed Synergen's Request for Good Cause Exception Relating To Batch Zero Eligibility Deadlines in PUCT Project 59142 on Sep 11, 2026. | |
| PUCT Project 59142: LETTER RE FEBRUARY 3 2026 BATCH STUDY WORKSHOPPUCT Project 59142, Item 5 |
Filed · Jan 16, 2026
ERCOT
|
ERCOT filed LETTER RE FEBRUARY 3 2026 BATCH STUDY WORKSHOP in PUCT Project 59142 on Jan 16, 2026. | |
| PUCT Project 59142: LETTER RE ERCOT LARGE LOAD BATCH STUDY PROCESS UPDATEPUCT Project 59142, Item 6 |
Filed · Jan 26, 2026
ERCOT
|
ERCOT filed LETTER RE ERCOT LARGE LOAD BATCH STUDY PROCESS UPDATE in PUCT Project 59142 on Jan 26, 2026. | |
| PUCT Project 59142: OPEN LETTER TO THE COMMISSION REGARDING ERCOT'S INTERCONNECTION PROCESS FOR LARGE LOADSPUCT Project 59142, Item 7 |
Filed · Jan 29, 2026
Rose City Partners, Schaper Energy Consulting, Crusoe Energy Systems, Outlaw Ventures, Solomon Data Systems, Eolic Development Partners, Zero Emission Grid, Juvo Energy, Belisari, and V-Wire
|
Rose City Partners, Schaper Energy Consulting, Crusoe Energy Systems, Outlaw Ventures, Solomon Data Systems, Eolic Development Partners, Zero Emission Grid, Juvo Energy, Belisari, and V-Wire filed OPEN LETTER TO THE COMMISSION REGARDING ERCOT'S INTERCONNECTION PROCESS FOR LARGE LOADS in PUCT Project 59142 on Jan 29, 2026. | |
| PUCT Project 59142: ERCOT LARGE LOAD BATCH STUDY PROCESS DRAFT FRAMEWORK PRESENTATIONSPUCT Project 59142, Item 8 |
Filed · Jan 30, 2026
ERCOT
|
ERCOT filed ERCOT LARGE LOAD BATCH STUDY PROCESS DRAFT FRAMEWORK PRESENTATIONS in PUCT Project 59142 on Jan 30, 2026. | |
| PUCT Project 59142: OPUC NOTICE OF PARTICIPATION LETTERPUCT Project 59142, Item 9 |
Filed · Feb 2, 2026
OPUC
|
OPUC filed OPUC NOTICE OF PARTICIPATION LETTER in PUCT Project 59142 on Feb 2, 2026. | |
| PUCT Project 58481: VOID SEE ITEM 205PUCT Project 58481, Item 204 |
Filed · Aug 24, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed VOID SEE ITEM 205 in PUCT Project 58481 on Aug 24, 2026. | |
| PUCT Project 58481: Memo Requesting CR Void Item No. 204PUCT Project 58481, Item 205 |
Filed · Aug 24, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Memo Requesting CR Void Item No. 204 in PUCT Project 58481 on Aug 24, 2026. | |
| PUCT Project 58481: Staff Memo w/Draft Recommended Changes to Proposed RulePUCT Project 58481, Item 206 |
Filed · Aug 24, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Staff Memo w/Draft Recommended Changes to Proposed Rule in PUCT Project 58481 on Aug 24, 2026. | |
| PUCT Project 58796: SOAH ORDER NO. 10 - EXTENDING BRIEFING DEADLINESPUCT Project 58796, Item 99 |
Filed · Aug 27, 2026
SOAH
|
SOAH filed SOAH ORDER NO. 10 - EXTENDING BRIEFING DEADLINES in PUCT Project 58796 on Aug 27, 2026. | |
| PUCT Project 59948: EPE's Proof of NoticePUCT Project 59948, Item 11 |
Filed · Aug 27, 2026
EL PASO ELECTRIC COMPANY
|
EL PASO ELECTRIC COMPANY filed EPE's Proof of Notice in PUCT Project 59948 on Aug 27, 2026. | |
| PUCT Project 58481: Comments of CenterPoint Energy Houston Electric, LLCPUCT Project 58481, Item 10 |
Filed · Oct 10, 2025
CENTERPOINT ENERGY HOUSTON ELECTRIC
|
CENTERPOINT ENERGY HOUSTON ELECTRIC filed Comments of CenterPoint Energy Houston Electric, LLC in PUCT Project 58481 on Oct 10, 2025. | |
| PUCT Project 58481: ONCOR'S RESPONSE TO COMMISSION STAFF’S FIRST SET OF QUESTIONS FOR COMMENTSPUCT Project 58481, Item 11 |
Filed · Oct 10, 2025
ONCOR ELECTRIC DELIVERY COMPANY LLC
|
ONCOR ELECTRIC DELIVERY COMPANY LLC filed ONCOR'S RESPONSE TO COMMISSION STAFF’S FIRST SET OF QUESTIONS FOR COMMENTS in PUCT Project 58481 on Oct 10, 2025. | |
| PUCT Project 58481: RESPONSE TO QUESTIONS FOR COMMENTPUCT Project 58481, Item 12 |
Filed · Oct 10, 2025
LCRA TRANSMISSION SERVICE CORPORATION
|
LCRA TRANSMISSION SERVICE CORPORATION filed RESPONSE TO QUESTIONS FOR COMMENT in PUCT Project 58481 on Oct 10, 2025. | |
| PUCT Project 58481: DCC Comments on Project 58481, Rulemaking to Implement Large Load Interconnection StandardsPUCT Project 58481, Item 13 |
Filed · Oct 10, 2025
Data Center Coalition
|
Data Center Coalition filed DCC Comments on Project 58481, Rulemaking to Implement Large Load Interconnection Standards in PUCT Project 58481 on Oct 10, 2025. | |
| PUCT Project 58481: Responses of Texas Electric Cooperatives, Inc.PUCT Project 58481, Item 15 |
Filed · Oct 10, 2025
Texas Electric Cooperatives, Inc.
|
Texas Electric Cooperatives, Inc. filed Responses of Texas Electric Cooperatives, Inc. in PUCT Project 58481 on Oct 10, 2025. | |
| PUCT Project 58481: Sharyland Utilities, L.L.C's Comments to Commission Staff's Questions for CommentsPUCT Project 58481, Item 16 |
Filed · Oct 10, 2025
SHARYLAND UTILITIES, L.L.C.
|
SHARYLAND UTILITIES, L.L.C. filed Sharyland Utilities, L.L.C's Comments to Commission Staff's Questions for Comments in PUCT Project 58481 on Oct 10, 2025. | |
| PUCT Project 58481: Eneus Response to Staff Questions on Project No. 58481PUCT Project 58481, Item 19 |
Filed · Oct 10, 2025
Eneus Energy
|
Eneus Energy filed Eneus Response to Staff Questions on Project No. 58481 in PUCT Project 58481 on Oct 10, 2025. | |
| PUCT Project 58481: OPUC’S RESPONSES TO QUESTIONS FOR PUBLIC COMMENT RELATED TO THE IMPLEMENTATION OF PURA § 37.0561PUCT Project 58481, Item 20 |
Filed · Oct 10, 2025
OPUC
|
OPUC filed OPUC’S RESPONSES TO QUESTIONS FOR PUBLIC COMMENT RELATED TO THE IMPLEMENTATION OF PURA § 37.0561 in PUCT Project 58481 on Oct 10, 2025. | |
| PUCT Project 58481: ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S RESPONSES TO STAFF QUESTIONSPUCT Project 58481, Item 21 |
Filed · Oct 10, 2025
ERCOT
|
ERCOT filed ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S RESPONSES TO STAFF QUESTIONS in PUCT Project 58481 on Oct 10, 2025. | |
| PUCT Project 58481: AEP Texas Responses to Questions for Public CommentPUCT Project 58481, Item 22 |
Filed · Oct 10, 2025
AEP TEXAS INC.
|
AEP TEXAS INC. filed AEP Texas Responses to Questions for Public Comment in PUCT Project 58481 on Oct 10, 2025. | |
| PUCT Project 58481: TEBA Responses to Staff Questions on Project 58481PUCT Project 58481, Item 24 |
Filed · Oct 10, 2025
TEXAS ENERGY BUYERS ALLIANCE
|
TEXAS ENERGY BUYERS ALLIANCE filed TEBA Responses to Staff Questions on Project 58481 in PUCT Project 58481 on Oct 10, 2025. | |
| PUCT Project 58481: Texas-New Mexico Power Company's Comments to Commission Staff's Questions for CommentPUCT Project 58481, Item 27 |
Filed · Oct 10, 2025
TEXAS-NEW MEXICO POWER COMPANY
|
TEXAS-NEW MEXICO POWER COMPANY filed Texas-New Mexico Power Company's Comments to Commission Staff's Questions for Comment in PUCT Project 58481 on Oct 10, 2025. | |
| PUCT Project 58481: Lancium Comments on Project No. 58481PUCT Project 58481, Item 28 |
Filed · Oct 10, 2025
LANCIUM, LLC
|
LANCIUM, LLC filed Lancium Comments on Project No. 58481 in PUCT Project 58481 on Oct 10, 2025. | |
| PUCT Project 58481: Enchanted Rock, LLC's Responses to Commission Staff's Questions for CommentPUCT Project 58481, Item 30 |
Filed · Oct 14, 2025
ENCHANTED ROCK, LLC
|
ENCHANTED ROCK, LLC filed Enchanted Rock, LLC's Responses to Commission Staff's Questions for Comment in PUCT Project 58481 on Oct 14, 2025. | |
| PUCT Project 58481: Discussion Draft w/12.19 Comment DeadlinePUCT Project 58481, Item 31 |
Filed · Dec 1, 2025
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Discussion Draft w/12.19 Comment Deadline in PUCT Project 58481 on Dec 1, 2025. | |
| PUCT Project 58481: SCHAPER ENERGY CONSULTING LLC RESPONSE TO PROJECT NO. 58481, COMMENTS TO STAFF’s QUESTIONS AND DRAFT 16 TAC §25.194PUCT Project 58481, Item 32 |
Filed · Dec 8, 2025
Schaper Energy Consulting LLC
|
Schaper Energy Consulting LLC filed SCHAPER ENERGY CONSULTING LLC RESPONSE TO PROJECT NO. 58481, COMMENTS TO STAFF’s QUESTIONS AND DRAFT 16 TAC §25.194 in PUCT Project 58481 on Dec 8, 2025. | |
| PUCT Project 58481: Notice of January 9 WorkshopPUCT Project 58481, Item 33 |
Filed · Dec 16, 2025
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Notice of January 9 Workshop in PUCT Project 58481 on Dec 16, 2025. | |
| PUCT Project 58481: Cholla Comments on Draft RulePUCT Project 58481, Item 34 |
Filed · Dec 16, 2025
Cholla Petroleum, Inc.
|
Cholla Petroleum, Inc. filed Cholla Comments on Draft Rule in PUCT Project 58481 on Dec 16, 2025. | |
| PUCT Project 58481: Cholla Comments on Draft Rule AmendedPUCT Project 58481, Item 35 |
Filed · Dec 17, 2025
Cholla Petroleum, Inc.
|
Cholla Petroleum, Inc. filed Cholla Comments on Draft Rule Amended in PUCT Project 58481 on Dec 17, 2025. | |
| PUCT Project 58481: Comments on proposed staff draft on large load interconnection standards.PUCT Project 58481, Item 36 |
Filed · Dec 18, 2025
SIERRA CLUB
|
SIERRA CLUB filed Comments on proposed staff draft on large load interconnection standards. in PUCT Project 58481 on Dec 18, 2025. | |
| PUCT Project 58481: Joint Comments of Google LLC and Lancium LLC to 58481 Large Load Interconnection StandardsPUCT Project 58481, Item 40 |
Filed · Dec 18, 2025
GOOGLE LLC, LANCIUM LLC
|
GOOGLE LLC, LANCIUM LLC filed Joint Comments of Google LLC and Lancium LLC to 58481 Large Load Interconnection Standards in PUCT Project 58481 on Dec 18, 2025. | |
| PUCT Project 58481: TCPA Comments on Staff Questions & Discussion DraftPUCT Project 58481, Item 42 |
Filed · Dec 19, 2025
TCPA
|
TCPA filed TCPA Comments on Staff Questions & Discussion Draft in PUCT Project 58481 on Dec 19, 2025. | |
| PUCT Project 58481: Comments of Texas Electric Cooperatives, Inc.PUCT Project 58481, Item 48 |
Filed · Dec 19, 2025
Texas Electric Cooperatives, Inc.
|
Texas Electric Cooperatives, Inc. filed Comments of Texas Electric Cooperatives, Inc. in PUCT Project 58481 on Dec 19, 2025. | |
| PUCT Project 58481: Comments of CenterPoint Energy Houston Electric, LLCPUCT Project 58481, Item 49 |
Filed · Dec 19, 2025
CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC
|
CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC filed Comments of CenterPoint Energy Houston Electric, LLC in PUCT Project 58481 on Dec 19, 2025. | |
| PUCT Project 58481: SCHAPER ENERGY CONSULTING LLC RESPONSE TO STAFF’s QUESTIONS ON PROJECT NO. 58481; RULEMAKING TO IMPLEMENT LARGE LOAD INTERCONNECTION STANDARDS UNDER PURA §37.0561PUCT Project 58481, Item 4 |
Filed · Sep 30, 2025
Schaper Energy Consulting LLC
|
Schaper Energy Consulting LLC filed SCHAPER ENERGY CONSULTING LLC RESPONSE TO STAFF’s QUESTIONS ON PROJECT NO. 58481; RULEMAKING TO IMPLEMENT LARGE LOAD INTERCONNECTION STANDARDS UNDER PURA §37.0561 in PUCT Project 58481 on Sep 30, 2025. | |
| PUCT Project 58481: NRG Energy, Inc.'s Comments on Staff's Discussion DraftPUCT Project 58481, Item 50 |
Filed · Dec 19, 2025
NRG ENERGY, INC.
|
NRG ENERGY, INC. filed NRG Energy, Inc.'s Comments on Staff's Discussion Draft in PUCT Project 58481 on Dec 19, 2025. | |
| PUCT Project 58481: BASF Comments on Rule Project 58481PUCT Project 58481, Item 52 |
Filed · Dec 19, 2025
BASF
|
BASF filed BASF Comments on Rule Project 58481 in PUCT Project 58481 on Dec 19, 2025. | |
| PUCT Project 58481: RESPONSE TO QUESTIONS FOR COMMENT AND DRAFT NEW 16 TAC § 25.194PUCT Project 58481, Item 53 |
Filed · Dec 19, 2025
LCRA TRANSMISSION SERVICES CORPORATION
|
LCRA TRANSMISSION SERVICES CORPORATION filed RESPONSE TO QUESTIONS FOR COMMENT AND DRAFT NEW 16 TAC § 25.194 in PUCT Project 58481 on Dec 19, 2025. | |
| PUCT Project 58481: Comments on Staff new Draft 16 TAC §25.194PUCT Project 58481, Item 55 |
Filed · Dec 19, 2025
Aperture
|
Aperture filed Comments on Staff new Draft 16 TAC §25.194 in PUCT Project 58481 on Dec 19, 2025. | |
| PUCT Project 58481: ERCOT Steel Mills' Comments on Staff's Discussion Draft for Project No. 58481PUCT Project 58481, Item 57 |
Filed · Dec 19, 2025
ERCOT STEEL MILLS
|
ERCOT STEEL MILLS filed ERCOT Steel Mills' Comments on Staff's Discussion Draft for Project No. 58481 in PUCT Project 58481 on Dec 19, 2025. | |
| PUCT Project 58481: Cholla, Inc. Response to Staff Questions on Project No. 58481; Large Load Interconnection Framework RecommendationsPUCT Project 58481, Item 5 |
Filed · Oct 9, 2025
Cholla, Inc.
|
Cholla, Inc. filed Cholla, Inc. Response to Staff Questions on Project No. 58481; Large Load Interconnection Framework Recommendations in PUCT Project 58481 on Oct 9, 2025. | |
| PUCT Project 58481: ONCOR ELECTRIC DELIVERY'S COMMENTS ON COMMISSION STAFF'S RULE 25.194 DISCUSSION DRAFTPUCT Project 58481, Item 61 |
Filed · Dec 19, 2025
ONCOR ELECTRIC DELIVERY COMPANY LLC
|
ONCOR ELECTRIC DELIVERY COMPANY LLC filed ONCOR ELECTRIC DELIVERY'S COMMENTS ON COMMISSION STAFF'S RULE 25.194 DISCUSSION DRAFT in PUCT Project 58481 on Dec 19, 2025. | |
| PUCT Project 58481: Provident Inc. comments on staff discussion draftPUCT Project 58481, Item 62 |
Filed · Dec 19, 2025
Provident Inc.
|
Provident Inc. filed Provident Inc. comments on staff discussion draft in PUCT Project 58481 on Dec 19, 2025. | |
| PUCT Project 58481: OFFICE OF PUBLIC UTILITY COUNSEL’S COMMENTS ON DISCUSSION DRAFT AND QUESTIONS FOR PUBLIC COMMENTS RELATED TO NEW 16 TAC § 25.194PUCT Project 58481, Item 64 |
Filed · Dec 19, 2025
OPUC
|
OPUC filed OFFICE OF PUBLIC UTILITY COUNSEL’S COMMENTS ON DISCUSSION DRAFT AND QUESTIONS FOR PUBLIC COMMENTS RELATED TO NEW 16 TAC § 25.194 in PUCT Project 58481 on Dec 19, 2025. | |
| PUCT Project 58481: DCC's Comments on the Discussion Draft (Project 58481)PUCT Project 58481, Item 66 |
Filed · Dec 19, 2025
Data Center Coalition
|
Data Center Coalition filed DCC's Comments on the Discussion Draft (Project 58481) in PUCT Project 58481 on Dec 19, 2025. | |
| PUCT Project 58481: SPLIGHT COMMENTS ON STAFF'S DRAFT DISCUSSION RULE § 25.194PUCT Project 58481, Item 69 |
Filed · Dec 19, 2025
Splight Inc.
|
Splight Inc. filed SPLIGHT COMMENTS ON STAFF'S DRAFT DISCUSSION RULE § 25.194 in PUCT Project 58481 on Dec 19, 2025. | |
| PUCT Project 58481: TCPA Response to Staff QuestionsPUCT Project 58481, Item 6 |
Filed · Oct 10, 2025
TCPA
|
TCPA filed TCPA Response to Staff Questions in PUCT Project 58481 on Oct 10, 2025. | |
| PUCT Project 58481: AEP TEXAS INC.’S COMMENTS ON STAFF DISCUSSION DRAFTPUCT Project 58481, Item 71 |
Filed · Dec 19, 2025
AEP TEXAS INC.
|
AEP TEXAS INC. filed AEP TEXAS INC.’S COMMENTS ON STAFF DISCUSSION DRAFT in PUCT Project 58481 on Dec 19, 2025. | |
| PUCT Project 58481: Targa Resources LLC's Comments in Response to Commission Staff's Discussion DraftPUCT Project 58481, Item 72 |
Filed · Dec 19, 2025
Targa Resources LLC
|
Targa Resources LLC filed Targa Resources LLC's Comments in Response to Commission Staff's Discussion Draft in PUCT Project 58481 on Dec 19, 2025. | |
| PUCT Project 58481: Texas-New Mexico Power Company’s Comments To Commission Staff’s Questions For Comment On Draft New 16 Tac § 25.194PUCT Project 58481, Item 73 |
Filed · Dec 19, 2025
TEXAS-NEW MEXICO POWER COMPANY
|
TEXAS-NEW MEXICO POWER COMPANY filed Texas-New Mexico Power Company’s Comments To Commission Staff’s Questions For Comment On Draft New 16 Tac § 25.194 in PUCT Project 58481 on Dec 19, 2025. | |
| PUCT Project 58481: CRUSOE ENERGY SYSTEMS LLC’S COMMENTS ON STAFF’S DRAFT DISCUSSION RULE 16 TAC § 25.194PUCT Project 58481, Item 75 |
Filed · Dec 19, 2025
CRUSOE ENERGY SYSTEMS LLC
|
CRUSOE ENERGY SYSTEMS LLC filed CRUSOE ENERGY SYSTEMS LLC’S COMMENTS ON STAFF’S DRAFT DISCUSSION RULE 16 TAC § 25.194 in PUCT Project 58481 on Dec 19, 2025. | |
| PUCT Project 58481: ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S COMMENTS ON DISCUSSION DRAFTPUCT Project 58481, Item 76 |
Filed · Dec 19, 2025
ERCOT
|
ERCOT filed ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S COMMENTS ON DISCUSSION DRAFT in PUCT Project 58481 on Dec 19, 2025. | |
| PUCT Project 58481: TEBA's Comments on Commission Staff's Questions and Discussion DraftPUCT Project 58481, Item 78 |
Filed · Dec 19, 2025
TEXAS ENERGY BUYERS ALLIANCE
|
TEXAS ENERGY BUYERS ALLIANCE filed TEBA's Comments on Commission Staff's Questions and Discussion Draft in PUCT Project 58481 on Dec 19, 2025. | |
| PUCT Project 58481: EDGECONNEX RESPONSE TO STAFF’S QUESTIONS ON PROJECT NO. 58481; RULEMAKING TO IMPLEMENT LARGE LOAD INTERCONNECTION STANDARDS UNDER PURA §37.0561PUCT Project 58481, Item 7 |
Filed · Oct 10, 2025
EdgeConneX
|
EdgeConneX filed EDGECONNEX RESPONSE TO STAFF’S QUESTIONS ON PROJECT NO. 58481; RULEMAKING TO IMPLEMENT LARGE LOAD INTERCONNECTION STANDARDS UNDER PURA §37.0561 in PUCT Project 58481 on Oct 10, 2025. | |
| PUCT Project 58481: SOLUNA DIGITAL’S SUPPORTIVE COMMENTS FOR COMMENTS SUBMITTED BY SATOSHI ENERGY ON STAFF'S DISCUSSION DRAFT NEW 16 TAC §25.194PUCT Project 58481, Item 81 |
Filed · Dec 19, 2025
Soluna Digital
|
Soluna Digital filed SOLUNA DIGITAL’S SUPPORTIVE COMMENTS FOR COMMENTS SUBMITTED BY SATOSHI ENERGY ON STAFF'S DISCUSSION DRAFT NEW 16 TAC §25.194 in PUCT Project 58481 on Dec 19, 2025. | |
| PUCT Project 58481: Staff Memo and January 9 Workshop Agenda w/AttachmentsPUCT Project 58481, Item 82 |
Filed · Jan 2, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Staff Memo and January 9 Workshop Agenda w/Attachments in PUCT Project 58481 on Jan 2, 2026. | |
| PUCT Project 58481: SATOSHI ENERGY COMMENTS ON STAFF'S SECOND DISCUSSION DRAFT ON PROJECT NO. 58481, RULEMAKING TO IMPLEMENT LARGE LOAD INTERCONNECTION STANDARDS UNDER PURA §37.0561PUCT Project 58481, Item 83 |
Filed · Jan 16, 2026
SATOSHI ENERGY CORP.
|
SATOSHI ENERGY CORP. filed SATOSHI ENERGY COMMENTS ON STAFF'S SECOND DISCUSSION DRAFT ON PROJECT NO. 58481, RULEMAKING TO IMPLEMENT LARGE LOAD INTERCONNECTION STANDARDS UNDER PURA §37.0561 in PUCT Project 58481 on Jan 16, 2026. | |
| PUCT Project 58481: CRUSOE ENERGY SYSTEMS LLC’S COMMENTS ON STAFF’S SECOND DRAFT DISCUSSION RULE 16 TAC § 25.194PUCT Project 58481, Item 84 |
Filed · Jan 16, 2026
CRUSOE ENERGY SYSTEMS LLC
|
CRUSOE ENERGY SYSTEMS LLC filed CRUSOE ENERGY SYSTEMS LLC’S COMMENTS ON STAFF’S SECOND DRAFT DISCUSSION RULE 16 TAC § 25.194 in PUCT Project 58481 on Jan 16, 2026. | |
| PUCT Project 58481: Google and Lancium Joint Comments to STaff Questions and 2nd Discussion DraftPUCT Project 58481, Item 87 |
Filed · Jan 16, 2026
GOOGLE LLC, LANCIUM LLC
|
GOOGLE LLC, LANCIUM LLC filed Google and Lancium Joint Comments to STaff Questions and 2nd Discussion Draft in PUCT Project 58481 on Jan 16, 2026. | |
| PUCT Project 58481: NRG Energy, Inc.'s Comments on PUCT Staff's QuestionsPUCT Project 58481, Item 8 |
Filed · Oct 10, 2025
NRG ENERGY, INC.
|
NRG ENERGY, INC. filed NRG Energy, Inc.'s Comments on PUCT Staff's Questions in PUCT Project 58481 on Oct 10, 2025. | |
| PUCT Project 58481: Texas Public Power Association (TPPA) Response to Questions for CommentPUCT Project 58481, Item 9 |
Filed · Oct 10, 2025
TPPA
|
TPPA filed Texas Public Power Association (TPPA) Response to Questions for Comment in PUCT Project 58481 on Oct 10, 2025. | |
| PUCT Project 59142: Request of audit for Project RaptorPUCT Project 59142, Item 58 |
Filed · Sep 13, 2026
Ray Baggett
|
Ray Baggett filed Request of audit for Project Raptor in PUCT Project 59142 on Sep 13, 2026. | |
| PUCT Project 59142: Audit Request- Project RaptorPUCT Project 59142, Item 59 |
Filed · Sep 13, 2026
Megan Atchison
|
Megan Atchison filed Audit Request- Project Raptor in PUCT Project 59142 on Sep 13, 2026. | |
| PUCT Project 59142: Audit Request- Project RaptorPUCT Project 59142, Item 60 |
Filed · Sep 13, 2026
Andrew Atchison
|
Andrew Atchison filed Audit Request- Project Raptor in PUCT Project 59142 on Sep 13, 2026. | |
| PUCT Project 59142: Audit Request- Project RaptorPUCT Project 59142, Item 61 |
Filed · Sep 13, 2026
Merri Dawn Bolton
|
Merri Dawn Bolton filed Audit Request- Project Raptor in PUCT Project 59142 on Sep 13, 2026. | |
| PUCT Project 59142: Audit Request- Project RaptorPUCT Project 59142, Item 62 |
Filed · Sep 13, 2026
Brad Bolton
|
Brad Bolton filed Audit Request- Project Raptor in PUCT Project 59142 on Sep 13, 2026. | |
| PUCT Project 59142: Audit Request- Project RaptorPUCT Project 59142, Item 63 |
Filed · Sep 13, 2026
Mark Steel
|
Mark Steel filed Audit Request- Project Raptor in PUCT Project 59142 on Sep 13, 2026. | |
| PUCT Project 59142: Audit Request- Project RaptorPUCT Project 59142, Item 64 |
Filed · Sep 13, 2026
Holly Steel
|
Holly Steel filed Audit Request- Project Raptor in PUCT Project 59142 on Sep 13, 2026. | |
| PUCT Project 59142: Request for audit -Project RaptorPUCT Project 59142, Item 65 |
Filed · Sep 14, 2026
Adam Lindemann
|
Adam Lindemann filed Request for audit -Project Raptor in PUCT Project 59142 on Sep 14, 2026. | |
| PUCT Project 59142: Request for audit - Project RaptorPUCT Project 59142, Item 66 |
Filed · Sep 14, 2026
Katrina Farmer
|
Katrina Farmer filed Request for audit - Project Raptor in PUCT Project 59142 on Sep 14, 2026. | |
| PUCT Project 58481: OM Item No. 24 - (Staff Recommendation) Order Adopting New §25.194PUCT Project 58481, Item 208 |
Filed · Sep 3, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed OM Item No. 24 - (Staff Recommendation) Order Adopting New §25.194 in PUCT Project 58481 on Sep 3, 2026. | |
| PUCT Project 58481: Vistra's Comments on Project 58481 Recommended Adoption OrderPUCT Project 58481, Item 211 |
Filed · Sep 8, 2026
VISTRA CORPORATE SERVICES COMPANY
|
VISTRA CORPORATE SERVICES COMPANY filed Vistra's Comments on Project 58481 Recommended Adoption Order in PUCT Project 58481 on Sep 8, 2026. | |
| PUCT Project 58482: OFFICE OF PUBLIC UTILITY COUNSEL’S COMMENTS REGARDING THE PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.521PUCT Project 58482, Item 36 |
Filed · Sep 3, 2026
OPUC
|
OPUC filed OFFICE OF PUBLIC UTILITY COUNSEL’S COMMENTS REGARDING THE PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.521 in PUCT Project 58482 on Sep 3, 2026. | |
| PUCT Project 58482: TAEBA'S COMMENTS ON PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.521PUCT Project 58482, Item 38 |
Filed · Sep 4, 2026
TEXAS ADVANCED ENERGY BUSINESS ALLIANCE
|
TEXAS ADVANCED ENERGY BUSINESS ALLIANCE filed TAEBA'S COMMENTS ON PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.521 in PUCT Project 58482 on Sep 4, 2026. | |
| PUCT Project 58482: ERCOT Steel Mills Comments Project 58482_Proposal for PublicationPUCT Project 58482, Item 39 |
Filed · Sep 4, 2026
ERCOT STEEL MILLS
|
ERCOT STEEL MILLS filed ERCOT Steel Mills Comments Project 58482_Proposal for Publication in PUCT Project 58482 on Sep 4, 2026. | |
| PUCT Project 58482: GOOGLE COMMENTS FOR THE 58482 PROPOSAL FOR PUBLICATIONPUCT Project 58482, Item 40 |
Filed · Sep 4, 2026
GOOGLE LLC
|
GOOGLE LLC filed GOOGLE COMMENTS FOR THE 58482 PROPOSAL FOR PUBLICATION in PUCT Project 58482 on Sep 4, 2026. | |
| PUCT Project 58482: Comments of Texas Electric Cooperatives, Inc.PUCT Project 58482, Item 41 |
Filed · Sep 4, 2026
TEXAS ELECTRIC COOPERATIVES, INC.
|
TEXAS ELECTRIC COOPERATIVES, INC. filed Comments of Texas Electric Cooperatives, Inc. in PUCT Project 58482 on Sep 4, 2026. | |
| PUCT Project 58482: Data Center Coalition's Comment on Proposal for Publication (Project 58482)PUCT Project 58482, Item 45 |
Filed · Sep 4, 2026
DATA CENTER COALITION
|
DATA CENTER COALITION filed Data Center Coalition's Comment on Proposal for Publication (Project 58482) in PUCT Project 58482 on Sep 4, 2026. | |
| PUCT Project 58482: ENGIE North America Inc. Comments on Proposal for PublicationPUCT Project 58482, Item 46 |
Filed · Sep 4, 2026
ENGIE NORTH AMERICA INC.
|
ENGIE NORTH AMERICA INC. filed ENGIE North America Inc. Comments on Proposal for Publication in PUCT Project 58482 on Sep 4, 2026. | |
| PUCT Project 58482: COMMENTS OF AEP TEXAS INC. ON COMMISSION STAFF’S PROPOSAL FOR PUBLICATIONPUCT Project 58482, Item 47 |
Filed · Sep 4, 2026
AEP TEXAS INC.
|
AEP TEXAS INC. filed COMMENTS OF AEP TEXAS INC. ON COMMISSION STAFF’S PROPOSAL FOR PUBLICATION in PUCT Project 58482 on Sep 4, 2026. | |
| PUCT Project 58482: COMMENTS OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLCPUCT Project 58482, Item 48 |
Filed · Sep 4, 2026
CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC
|
CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC filed COMMENTS OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC in PUCT Project 58482 on Sep 4, 2026. | |
| PUCT Project 58482: TCPA'S COMMENTS ON PROPOSAL FOR PUBLICATION OF NEW §25.521PUCT Project 58482, Item 49 |
Filed · Sep 4, 2026
TCPA
|
TCPA filed TCPA'S COMMENTS ON PROPOSAL FOR PUBLICATION OF NEW §25.521 in PUCT Project 58482 on Sep 4, 2026. | |
| PUCT Project 58482: COMMENTS ON THE PROPOSAL FOR PUBLICATION OF NEW §25.521PUCT Project 58482, Item 52 |
Filed · Sep 4, 2026
LOWER COLORADO RIVER AUTHORITY
|
LOWER COLORADO RIVER AUTHORITY filed COMMENTS ON THE PROPOSAL FOR PUBLICATION OF NEW §25.521 in PUCT Project 58482 on Sep 4, 2026. | |
| PUCT Project 58482: ONCOR ELECTRIC DELIVERY COMPANY'S COMMENTS ON THE PROPOSAL FOR PUBLICATION OF NEW 16 TAC § 25.521PUCT Project 58482, Item 53 |
Filed · Sep 4, 2026
ONCOR ELECTRIC DELIVERY COMPANY LLC
|
ONCOR ELECTRIC DELIVERY COMPANY LLC filed ONCOR ELECTRIC DELIVERY COMPANY'S COMMENTS ON THE PROPOSAL FOR PUBLICATION OF NEW 16 TAC § 25.521 in PUCT Project 58482 on Sep 4, 2026. | |
| PUCT Project 58482: NRG Comments on Proposed RulePUCT Project 58482, Item 54 |
Filed · Sep 4, 2026
NRG ENERGY, INC.
|
NRG ENERGY, INC. filed NRG Comments on Proposed Rule in PUCT Project 58482 on Sep 4, 2026. | |
| PUCT Project 58482: Vistra Corporate Services Company's Comments on the Proposal for Publication of new 16 TAC § 25.521PUCT Project 58482, Item 55 |
Filed · Sep 4, 2026
VISTRA CORPORATE SERVICES COMPANY
|
VISTRA CORPORATE SERVICES COMPANY filed Vistra Corporate Services Company's Comments on the Proposal for Publication of new 16 TAC § 25.521 in PUCT Project 58482 on Sep 4, 2026. | |
| PUCT Project 58482: The Steering Committee of Cities Served by Oncor and Texas Coalition for Affordable Power's Comments on Proposal for Publication of New 16 TAC § 25.521PUCT Project 58482, Item 58 |
Filed · Sep 4, 2026
STEERING COMMITTEE OF CITIES SERVED BY ONCOR AND TEXAS COALITION FOR AFFORDABLE POWER
|
STEERING COMMITTEE OF CITIES SERVED BY ONCOR AND TEXAS COALITION FOR AFFORDABLE POWER filed The Steering Committee of Cities Served by Oncor and Texas Coalition for Affordable Power's Comments on Proposal for Publication of New 16 TAC § 25.521 in PUCT Project 58482 on Sep 4, 2026. | |
| PUCT Project 58482: TNMP'S COMMENTS ON PROPOSAL FOR PUBLICATION OF NEW §25.521PUCT Project 58482, Item 59 |
Filed · Sep 4, 2026
TEXAS NEW MEXICO POWER COMPANY
|
TEXAS NEW MEXICO POWER COMPANY filed TNMP'S COMMENTS ON PROPOSAL FOR PUBLICATION OF NEW §25.521 in PUCT Project 58482 on Sep 4, 2026. | |
| PUCT Project 58482: TEBA Comments on Proposal for Publication for Project No. 58482PUCT Project 58482, Item 60 |
Filed · Sep 4, 2026
TEXAS ENERGY BUYERS ALLIANCE
|
TEXAS ENERGY BUYERS ALLIANCE filed TEBA Comments on Proposal for Publication for Project No. 58482 in PUCT Project 58482 on Sep 4, 2026. | |
| PUCT Project 58482: ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S COMMENTS ON THE PROPOSAL FOR PUBLICATIONPUCT Project 58482, Item 62 |
Filed · Sep 4, 2026
ERCOT
|
ERCOT filed ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S COMMENTS ON THE PROPOSAL FOR PUBLICATION in PUCT Project 58482 on Sep 4, 2026. | |
| PUCT Project 58796: SOAH ORDER NO. 11- GRANTING MOTION TO ABATEPUCT Project 58796, Item 101 |
Filed · Sep 3, 2026
SOAH
|
SOAH filed SOAH ORDER NO. 11- GRANTING MOTION TO ABATE in PUCT Project 58796 on Sep 3, 2026. | |
| PUCT Project 58481: OPUC’S COMMENTS ON STAFF’S SECOND SET OF QUESTIONS FOR PUBLIC COMMENT AND SECOND DISCUSSION DRAFT RELATED TO NEW 16 TAC § 25.194PUCT Project 58481, Item 100 |
Filed · Jan 16, 2026
OPUC
|
OPUC filed OPUC’S COMMENTS ON STAFF’S SECOND SET OF QUESTIONS FOR PUBLIC COMMENT AND SECOND DISCUSSION DRAFT RELATED TO NEW 16 TAC § 25.194 in PUCT Project 58481 on Jan 16, 2026. | |
| PUCT Project 58481: Tract Post-Workshop Comments on Staff's Second Discussion DraftPUCT Project 58481, Item 104 |
Filed · Jan 17, 2026
Tract
|
Tract filed Tract Post-Workshop Comments on Staff's Second Discussion Draft in PUCT Project 58481 on Jan 17, 2026. | |
| PUCT Project 58481: Comments of Texas-New Mexico Power CompanyPUCT Project 58481, Item 105 |
Filed · Jan 20, 2026
TEXAS-NEW MEXICO POWER COMPANY
|
TEXAS-NEW MEXICO POWER COMPANY filed Comments of Texas-New Mexico Power Company in PUCT Project 58481 on Jan 20, 2026. | |
| PUCT Project 58481: OM Item No. 27 - Staff Memo & PFP w/March 27 Comment DeadlinePUCT Project 58481, Item 107 |
Filed · Feb 13, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed OM Item No. 27 - Staff Memo & PFP w/March 27 Comment Deadline in PUCT Project 58481 on Feb 13, 2026. | |
| PUCT Project 58481: Comments regarding Fee recommendation by StaffPUCT Project 58481, Item 108 |
Filed · Feb 17, 2026
Cholla, Inc.
|
Cholla, Inc. filed Comments regarding Fee recommendation by Staff in PUCT Project 58481 on Feb 17, 2026. | |
| PUCT Project 58481: SCHAPER ENERGY ENERGY CONSULTING COMMENTS TO STAFF DISCUSSION DRAFT 16 (TAC) §25.194 DATED FEBRUARY 13, 2026PUCT Project 58481, Item 109 |
Filed · Feb 18, 2026
SCHAPER ENERGY CONSULTING LLC
|
SCHAPER ENERGY CONSULTING LLC filed SCHAPER ENERGY ENERGY CONSULTING COMMENTS TO STAFF DISCUSSION DRAFT 16 (TAC) §25.194 DATED FEBRUARY 13, 2026 in PUCT Project 58481 on Feb 18, 2026. | |
| PUCT Project 58481: Google and Lancium Joint Comments to Proposed PFPPUCT Project 58481, Item 110 |
Filed · Feb 19, 2026
Google LLC, Lancium LLC
|
Google LLC, Lancium LLC filed Google and Lancium Joint Comments to Proposed PFP in PUCT Project 58481 on Feb 19, 2026. | |
| PUCT Project 58481: Speed to Power Concept Paper for ERCOT Large Load Batch Study ProceedingsPUCT Project 58481, Item 111 |
Filed · Feb 26, 2026
Luminary Strategies,LLC
|
Luminary Strategies,LLC filed Speed to Power Concept Paper for ERCOT Large Load Batch Study Proceedings in PUCT Project 58481 on Feb 26, 2026. | |
| PUCT Project 58481: Monarch Energy Comments on Proposal for PublicationPUCT Project 58481, Item 113 |
Filed · Mar 4, 2026
Monarch Energy Development LLC
|
Monarch Energy Development LLC filed Monarch Energy Comments on Proposal for Publication in PUCT Project 58481 on Mar 4, 2026. | |
| PUCT Project 58481: Provident, Inc. Comments on Proposed Proposal for PublicationPUCT Project 58481, Item 114 |
Filed · Mar 4, 2026
Provident, Inc.
|
Provident, Inc. filed Provident, Inc. Comments on Proposed Proposal for Publication in PUCT Project 58481 on Mar 4, 2026. | |
| PUCT Project 58481: JOINT REDLINES FOR THE PROPOSED PROPOSAL FOR PUBLICATIONPUCT Project 58481, Item 115 |
Filed · Mar 10, 2026
GOOGLE LLC, LANCIUM LLC
|
GOOGLE LLC, LANCIUM LLC filed JOINT REDLINES FOR THE PROPOSED PROPOSAL FOR PUBLICATION in PUCT Project 58481 on Mar 10, 2026. | |
| PUCT Project 58481: CIPHER DIGITAL INC. COMMENTS TO STAFF PROPOSED PROPOSAL FOR PUBLICATIONPUCT Project 58481, Item 116 |
Filed · Mar 11, 2026
Cipher Digital
|
Cipher Digital filed CIPHER DIGITAL INC. COMMENTS TO STAFF PROPOSED PROPOSAL FOR PUBLICATION in PUCT Project 58481 on Mar 11, 2026. | |
| PUCT Project 58481: EDGECONNEX COMMENTS TO STAFF'S PROPOSED PROPOSAL FOR PUBLICATIONPUCT Project 58481, Item 117 |
Filed · Mar 11, 2026
EdgeConnex
|
EdgeConnex filed EDGECONNEX COMMENTS TO STAFF'S PROPOSED PROPOSAL FOR PUBLICATION in PUCT Project 58481 on Mar 11, 2026. | |
| PUCT Project 58481: CHAIRMAN GLEESON MEMORANDUMPUCT Project 58481, Item 118 |
Filed · Mar 11, 2026
PUC OPDM
|
PUC OPDM filed CHAIRMAN GLEESON MEMORANDUM in PUCT Project 58481 on Mar 11, 2026. | |
| PUCT Project 58481: Engine 1's Comments on PUCT Staff's Proposal for PublicationPUCT Project 58481, Item 119 |
Filed · Mar 11, 2026
Engine 1
|
Engine 1 filed Engine 1's Comments on PUCT Staff's Proposal for Publication in PUCT Project 58481 on Mar 11, 2026. | |
| PUCT Project 58481: Hut 8 Comments on Staff's Proposal for PublicationPUCT Project 58481, Item 120 |
Filed · Mar 11, 2026
Hut 8 Corp
|
Hut 8 Corp filed Hut 8 Comments on Staff's Proposal for Publication in PUCT Project 58481 on Mar 11, 2026. | |
| PUCT Project 58481: Nightpeak Energy Comments on Staff's Proposal for PublicationPUCT Project 58481, Item 121 |
Filed · Mar 11, 2026
Nightpeak Energy
|
Nightpeak Energy filed Nightpeak Energy Comments on Staff's Proposal for Publication in PUCT Project 58481 on Mar 11, 2026. | |
| PUCT Project 58481: PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.194PUCT Project 58481, Item 122 |
Filed · Mar 12, 2026
PUC OPDM
|
PUC OPDM filed PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.194 in PUCT Project 58481 on Mar 12, 2026. | |
| PUCT Project 58481: Texas Register Acknowledgement of Receipt - Comments Due 04/17/2026PUCT Project 58481, Item 123 |
Filed · Mar 12, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Texas Register Acknowledgement of Receipt - Comments Due 04/17/2026 in PUCT Project 58481 on Mar 12, 2026. | |
| PUCT Project 58481: Staff Memo w/MS Word Version of PFPPUCT Project 58481, Item 124 |
Filed · Mar 16, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Staff Memo w/MS Word Version of PFP in PUCT Project 58481 on Mar 16, 2026. | |
| PUCT Project 58481: Monarch Energy Additional Comments on Proposal for PublicationPUCT Project 58481, Item 125 |
Filed · Mar 19, 2026
MONARCH ENERGY
|
MONARCH ENERGY filed Monarch Energy Additional Comments on Proposal for Publication in PUCT Project 58481 on Mar 19, 2026. | |
| PUCT Project 58481: Vistra Corp.'s Comments on Planning Guide Revision Request 145 for Project 58481PUCT Project 58481, Item 127 |
Filed · Mar 20, 2026
VISTRA CORP.
|
VISTRA CORP. filed Vistra Corp.'s Comments on Planning Guide Revision Request 145 for Project 58481 in PUCT Project 58481 on Mar 20, 2026. | |
| PUCT Project 58481: PUC Project No. 58481 - Interconnection Agreement Standards Applicability to Batch ZeroPUCT Project 58481, Item 129 |
Filed · Mar 29, 2026
SCHAPER ENERGY CONSULTING LLC
|
SCHAPER ENERGY CONSULTING LLC filed PUC Project No. 58481 - Interconnection Agreement Standards Applicability to Batch Zero in PUCT Project 58481 on Mar 29, 2026. | |
| PUCT Project 58481: Comments on Proposal for Publication of 16 TAC §25.194 - Project No. 58481PUCT Project 58481, Item 130 |
Filed · Mar 30, 2026
Jason Buster
|
Jason Buster filed Comments on Proposal for Publication of 16 TAC §25.194 - Project No. 58481 in PUCT Project 58481 on Mar 30, 2026. | |
| PUCT Project 58481: CPV Comments on Proposal for Publication of 16 TAC §25.194PUCT Project 58481, Item 132 |
Filed · Apr 6, 2026
Competitive Power Ventures
|
Competitive Power Ventures filed CPV Comments on Proposal for Publication of 16 TAC §25.194 in PUCT Project 58481 on Apr 6, 2026. | |
| PUCT Project 58481: Cholla comments on Proposal for PublicationPUCT Project 58481, Item 133 |
Filed · Apr 7, 2026
Cholla, Inc.
|
Cholla, Inc. filed Cholla comments on Proposal for Publication in PUCT Project 58481 on Apr 7, 2026. | |
| PUCT Project 58481: Vistra Corp.'s Additional Comments on Planning Guide Revision Request 145 for Project 58481PUCT Project 58481, Item 134 |
Filed · Apr 9, 2026
VISTRA CORP.
|
VISTRA CORP. filed Vistra Corp.'s Additional Comments on Planning Guide Revision Request 145 for Project 58481 in PUCT Project 58481 on Apr 9, 2026. | |
| PUCT Project 58481: AEP COMPANIES’ COMMENTS ON COMMISSION’S PROPOSAL FOR PUBLICATIONPUCT Project 58481, Item 139 |
Filed · Apr 13, 2026
AEP COMPANIES
|
AEP COMPANIES filed AEP COMPANIES’ COMMENTS ON COMMISSION’S PROPOSAL FOR PUBLICATION in PUCT Project 58481 on Apr 13, 2026. | |
| PUCT Project 58481: CCNG Comments and Redlines for the Proposal for Publication in Project 58481PUCT Project 58481, Item 140 |
Filed · Apr 13, 2026
CCNG, Inc.
|
CCNG, Inc. filed CCNG Comments and Redlines for the Proposal for Publication in Project 58481 in PUCT Project 58481 on Apr 13, 2026. | |
| PUCT Project 58481: TRACT HOLDING COMPANY I, LLC’S COMMENTS ON THE COMMISSION’S PROPOSAL FOR PUBLICATION TO IMPLEMENT LARGE LOAD INTERCONNECTION STANDARDS (“STANDARDS”)PUCT Project 58481, Item 141 |
Filed · Apr 13, 2026
Tract Holding Company I, LLC
|
Tract Holding Company I, LLC filed TRACT HOLDING COMPANY I, LLC’S COMMENTS ON THE COMMISSION’S PROPOSAL FOR PUBLICATION TO IMPLEMENT LARGE LOAD INTERCONNECTION STANDARDS (“STANDARDS”) in PUCT Project 58481 on Apr 13, 2026. | |
| PUCT Project 58481: Project# Rule 25.194 The people demand full and extensive transparency on all water and gas studies, usage records and future plans pertaining to industrial use especially for large scale data centers in bell countyPUCT Project 58481, Item 142 |
Filed · Apr 14, 2026
SARAH DUNHAM
|
SARAH DUNHAM filed Project# Rule 25.194 The people demand full and extensive transparency on all water and gas studies, usage records and future plans pertaining to industrial use especially for large scale data centers in bell county in PUCT Project 58481 on Apr 14, 2026. | |
| PUCT Project 58481: HUT 8 COMMENTS ON PUC PROPOSAL FOR PUBLICATIONPUCT Project 58481, Item 144 |
Filed · Apr 14, 2026
HUT 8 CORP
|
HUT 8 CORP filed HUT 8 COMMENTS ON PUC PROPOSAL FOR PUBLICATION in PUCT Project 58481 on Apr 14, 2026. | |
| PUCT Project 58481: Suplement filing to comment XYAWFICE - Updated analytic methodology attribution of SVI/TRI addition to researchPUCT Project 58481, Item 146 |
Filed · Apr 15, 2026
Zack Butler | EnerShield AI
|
Zack Butler | EnerShield AI filed Suplement filing to comment XYAWFICE - Updated analytic methodology attribution of SVI/TRI addition to research in PUCT Project 58481 on Apr 15, 2026. | |
| PUCT Project 58481: COMMENTS ON THE PROPOSAL FOR PUBLICATIONPUCT Project 58481, Item 147 |
Filed · Apr 15, 2026
LOWER COLORADO RIVER AUTHORITY AND LCRA TRANSMISSION SERVICES CORPORATION
|
LOWER COLORADO RIVER AUTHORITY AND LCRA TRANSMISSION SERVICES CORPORATION filed COMMENTS ON THE PROPOSAL FOR PUBLICATION in PUCT Project 58481 on Apr 15, 2026. | |
| PUCT Project 58481: COMMENTS OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLCPUCT Project 58481, Item 148 |
Filed · Apr 15, 2026
CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC
|
CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC filed COMMENTS OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC in PUCT Project 58481 on Apr 15, 2026. | |
| PUCT Project 58481: STACK INFRASTRUCTURE COMMENTS TO PROPOSAL FOR PUBLICATION IN PROJECT NO. 58481PUCT Project 58481, Item 151 |
Filed · Apr 15, 2026
STACK Infrastructure
|
STACK Infrastructure filed STACK INFRASTRUCTURE COMMENTS TO PROPOSAL FOR PUBLICATION IN PROJECT NO. 58481 in PUCT Project 58481 on Apr 15, 2026. | |
| PUCT Project 58481: SATOSHI ENERGY COMMENTS ON STAFF'S PROPOSAL FOR PUBLICATION ON PROJECT NO. 58481, RULEMAKING TO IMPLEMENT LARGE LOAD INTERCONNECTION STANDARDS UNDER PURA §37.0561PUCT Project 58481, Item 156 |
Filed · Apr 16, 2026
SATOSHI ENERGY CORP.
|
SATOSHI ENERGY CORP. filed SATOSHI ENERGY COMMENTS ON STAFF'S PROPOSAL FOR PUBLICATION ON PROJECT NO. 58481, RULEMAKING TO IMPLEMENT LARGE LOAD INTERCONNECTION STANDARDS UNDER PURA §37.0561 in PUCT Project 58481 on Apr 16, 2026. | |
| PUCT Project 58481: INFINIUM'S COMMENTS ON LARGE LOAD INTERCONNECTION STANDARDS PROPOSAL FOR PUBLICATIONPUCT Project 58481, Item 159 |
Filed · Apr 16, 2026
INFINIUM OPERATIONS, LLC
|
INFINIUM OPERATIONS, LLC filed INFINIUM'S COMMENTS ON LARGE LOAD INTERCONNECTION STANDARDS PROPOSAL FOR PUBLICATION in PUCT Project 58481 on Apr 16, 2026. | |
| PUCT Project 58481: TCPA Comments on Large Load Interconnection PfP & IssuesPUCT Project 58481, Item 162 |
Filed · Apr 16, 2026
TCPA
|
TCPA filed TCPA Comments on Large Load Interconnection PfP & Issues in PUCT Project 58481 on Apr 16, 2026. | |
| PUCT Project 58481: HUNT ENERGY NETWORK'S COMMENTS ON COMMISSION’S PROPOSAL FOR PUBLICATIONPUCT Project 58481, Item 164 |
Filed · Apr 16, 2026
HUNT ENERGY NETWORK L.L.C.
|
HUNT ENERGY NETWORK L.L.C. filed HUNT ENERGY NETWORK'S COMMENTS ON COMMISSION’S PROPOSAL FOR PUBLICATION in PUCT Project 58481 on Apr 16, 2026. | |
| PUCT Project 58481: Joint Comments of Google LLC, Lancium LLC, and TotalEnergies Renewables USAPUCT Project 58481, Item 165 |
Filed · Apr 16, 2026
GOOGLE LLC, LANCIUM LLC, TOTALENERGIES RENEWABLES USA
|
GOOGLE LLC, LANCIUM LLC, TOTALENERGIES RENEWABLES USA filed Joint Comments of Google LLC, Lancium LLC, and TotalEnergies Renewables USA in PUCT Project 58481 on Apr 16, 2026. | |
| PUCT Project 58481: TEBA's Comments on Commission Staff's Proposal for PublicationPUCT Project 58481, Item 166 |
Filed · Apr 16, 2026
TEXAS ENERGY BUYERS ALLIANCE
|
TEXAS ENERGY BUYERS ALLIANCE filed TEBA's Comments on Commission Staff's Proposal for Publication in PUCT Project 58481 on Apr 16, 2026. | |
| PUCT Project 58481: Trammell Crow Company's Comments on Proposal for Publication of 16 TAC§ 25.194PUCT Project 58481, Item 169 |
Filed · Apr 17, 2026
Trammell Crow Company
|
Trammell Crow Company filed Trammell Crow Company's Comments on Proposal for Publication of 16 TAC§ 25.194 in PUCT Project 58481 on Apr 17, 2026. | |
| PUCT Project 58481: PUCT 58481 Large Load Interconnection Standards PfP - NRG Comments - FINALPUCT Project 58481, Item 173 |
Filed · Apr 17, 2026
NRG ENERGY INC
|
NRG ENERGY INC filed PUCT 58481 Large Load Interconnection Standards PfP - NRG Comments - FINAL in PUCT Project 58481 on Apr 17, 2026. | |
| PUCT Project 58481: Targa Resources LLC's Comments and Proposed Redlines in Response to Proposal for Publication of 16 TAC § 25.194PUCT Project 58481, Item 175 |
Filed · Apr 17, 2026
Targa Resources LLC
|
Targa Resources LLC filed Targa Resources LLC's Comments and Proposed Redlines in Response to Proposal for Publication of 16 TAC § 25.194 in PUCT Project 58481 on Apr 17, 2026. | |
| PUCT Project 58481: Permian Basin Petroleum Association's Comments in Response to Proposal for Publication of 16 TAC § 25.194PUCT Project 58481, Item 176 |
Filed · Apr 17, 2026
Permian Basin Petroleum Association
|
Permian Basin Petroleum Association filed Permian Basin Petroleum Association's Comments in Response to Proposal for Publication of 16 TAC § 25.194 in PUCT Project 58481 on Apr 17, 2026. | |
| PUCT Project 58481: BLACK MOUNTAIN POWER COMMENTS ON PROJECT NO. 58481 PROPOSAL FOR PUBLICATIONPUCT Project 58481, Item 177 |
Filed · Apr 17, 2026
BLACK MOUNTAIN POWER
|
BLACK MOUNTAIN POWER filed BLACK MOUNTAIN POWER COMMENTS ON PROJECT NO. 58481 PROPOSAL FOR PUBLICATION in PUCT Project 58481 on Apr 17, 2026. | |
| PUCT Project 58481: CONSTELLATION ENERGY GENERATION, LLC’S COMMENTS ON COMMISSION STAFF’S PROPOSAL FOR PUBLICATION OF NEW 16 TAC § 25.194PUCT Project 58481, Item 178 |
Filed · Apr 17, 2026
CONSTELLATION ENERGY GENERATION, LLC
|
CONSTELLATION ENERGY GENERATION, LLC filed CONSTELLATION ENERGY GENERATION, LLC’S COMMENTS ON COMMISSION STAFF’S PROPOSAL FOR PUBLICATION OF NEW 16 TAC § 25.194 in PUCT Project 58481 on Apr 17, 2026. | |
| PUCT Project 58481: POST-WORKSHOP COMMENTS OF TEXAS ELECTRIC COOPERATIVES, INC.PUCT Project 58481, Item 88 |
Filed · Jan 16, 2026
TEXAS ELECTRIC COOPERATIVES, INC.
|
TEXAS ELECTRIC COOPERATIVES, INC. filed POST-WORKSHOP COMMENTS OF TEXAS ELECTRIC COOPERATIVES, INC. in PUCT Project 58481 on Jan 16, 2026. | |
| PUCT Project 58481: Comments of CenterPoint Energy Houston Electric, LLCPUCT Project 58481, Item 90 |
Filed · Jan 16, 2026
CENTERPOINT ENERGY HOUSTON ELECTRIC
|
CENTERPOINT ENERGY HOUSTON ELECTRIC filed Comments of CenterPoint Energy Houston Electric, LLC in PUCT Project 58481 on Jan 16, 2026. | |
| PUCT Project 58481: ETT’S COMMENTS ON STAFF’S 2ND DISCUSSION DRAFTPUCT Project 58481, Item 92 |
Filed · Jan 16, 2026
ELECTRIC TRANSMISSION TEXAS, LLC
|
ELECTRIC TRANSMISSION TEXAS, LLC filed ETT’S COMMENTS ON STAFF’S 2ND DISCUSSION DRAFT in PUCT Project 58481 on Jan 16, 2026. | |
| PUCT Project 58481: CPS Energy's Response to Questions for CommentPUCT Project 58481, Item 93 |
Filed · Jan 16, 2026
CPS ENERGY
|
CPS ENERGY filed CPS Energy's Response to Questions for Comment in PUCT Project 58481 on Jan 16, 2026. | |
| PUCT Project 58481: Comments on Staff's Second Draft Discussion Rule in 16 TAC 25.194PUCT Project 58481, Item 94 |
Filed · Jan 16, 2026
ROWAN DIGITAL INFRASTRUCTURE LLC
|
ROWAN DIGITAL INFRASTRUCTURE LLC filed Comments on Staff's Second Draft Discussion Rule in 16 TAC 25.194 in PUCT Project 58481 on Jan 16, 2026. | |
| PUCT Project 58481: ONCOR ELECTRIC DELIVERY’S COMMENTS ON COMMISSION STAFF’S SECOND RULE 25.194 DISCUSSION DRAFTPUCT Project 58481, Item 95 |
Filed · Jan 16, 2026
ONCOR ELECTRIC DELIVERY COMPANY LLC
|
ONCOR ELECTRIC DELIVERY COMPANY LLC filed ONCOR ELECTRIC DELIVERY’S COMMENTS ON COMMISSION STAFF’S SECOND RULE 25.194 DISCUSSION DRAFT in PUCT Project 58481 on Jan 16, 2026. | |
| PUCT Project 58481: AEP TEXAS' COMMENTS ON STAFF’S SECOND DISCUSSION DRAFTPUCT Project 58481, Item 97 |
Filed · Jan 16, 2026
AEP TEXAS INC.
|
AEP TEXAS INC. filed AEP TEXAS' COMMENTS ON STAFF’S SECOND DISCUSSION DRAFT in PUCT Project 58481 on Jan 16, 2026. | |
| PUCT Project 58481: Additional Comment's on Second Discussion DraftPUCT Project 58481, Item 98 |
Filed · Jan 16, 2026
Data Center Coalition
|
Data Center Coalition filed Additional Comment's on Second Discussion Draft in PUCT Project 58481 on Jan 16, 2026. | |
| PUCT Project 59142: My name is Chad Peysen and I live at 1116 Three Way Rd, Wichita Falls, TX 76310. The 1000 MW request sits 1200 ft from my home. I would like the audit applied to Project Raptor specifically.PUCT Project 59142, Item 69 |
Filed · Sep 14, 2026
Chad Peysen
|
Chad Peysen filed My name is Chad Peysen and I live at 1116 Three Way Rd, Wichita Falls, TX 76310. The 1000 MW request sits 1200 ft from my home. I would like the audit applied to Project Raptor specifically. in PUCT Project 59142 on Sep 14, 2026. | |
| PUCT Project 59142: My name is Heather Peysen and I live at 1116 Three Way Rd, Wichita Falls, TX 76310. The 1000 MW request sits 1200 ft from my home. I would like the audit applied to Project Raptor specifically.PUCT Project 59142, Item 70 |
Filed · Sep 14, 2026
Heather Peysen
|
Heather Peysen filed My name is Heather Peysen and I live at 1116 Three Way Rd, Wichita Falls, TX 76310. The 1000 MW request sits 1200 ft from my home. I would like the audit applied to Project Raptor specifically. in PUCT Project 59142 on Sep 14, 2026. | |
| PUCT Project 59142: My name is John Peysen and I live at 433 Mahler Rd, Wichita Falls, TX 76310. The 1000 MW request sits 1 road over from my home. I would like the audit applied to Project Raptor specifically.PUCT Project 59142, Item 71 |
Filed · Sep 14, 2026
John Peysen
|
John Peysen filed My name is John Peysen and I live at 433 Mahler Rd, Wichita Falls, TX 76310. The 1000 MW request sits 1 road over from my home. I would like the audit applied to Project Raptor specifically. in PUCT Project 59142 on Sep 14, 2026. | |
| PUCT Project 59142: My name is Rhonda Peysen and I live at 433 Mahler Rd, Wichita Falls, TX 76310. The 1000 MW request sits 1 road over from my home. I would like the audit applied to Project Raptor specifically.PUCT Project 59142, Item 72 |
Filed · Sep 14, 2026
Rhonda Peysen
|
Rhonda Peysen filed My name is Rhonda Peysen and I live at 433 Mahler Rd, Wichita Falls, TX 76310. The 1000 MW request sits 1 road over from my home. I would like the audit applied to Project Raptor specifically. in PUCT Project 59142 on Sep 14, 2026. | |
| PUCT Project 58481: SOLUNA HOLDINGS, INC. COMMENTS TO PROPOSAL FOR ADOPTION OF NEW 16 TAC § 25.194PUCT Project 58481, Item 212 |
Filed · Sep 9, 2026
Soluna Holdings
|
Soluna Holdings filed SOLUNA HOLDINGS, INC. COMMENTS TO PROPOSAL FOR ADOPTION OF NEW 16 TAC § 25.194 in PUCT Project 58481 on Sep 9, 2026. | |
| PUCT Project 58481: GOOD COMPANY ASSOOCIATES COMMENTS ON THE COMMISSION’S PROPOSAL FOR ADOPTION (PFA)PUCT Project 58481, Item 213 |
Filed · Sep 9, 2026
Good Company Associates
|
Good Company Associates filed GOOD COMPANY ASSOOCIATES COMMENTS ON THE COMMISSION’S PROPOSAL FOR ADOPTION (PFA) in PUCT Project 58481 on Sep 9, 2026. | |
| PUCT Project 58481: SATOSHI ENERGY COMMENTS ON STAFF'S RECOMMENDED ADOPTION ORDER ON PROJECT NO. 58481, RULEMAKING TO IMPLEMENT LARGE LOAD INTERCONNECTION STANDARDS UNDER PURA §37.0561PUCT Project 58481, Item 214 |
Filed · Sep 9, 2026
SATOSHI ENERGY CORP.
|
SATOSHI ENERGY CORP. filed SATOSHI ENERGY COMMENTS ON STAFF'S RECOMMENDED ADOPTION ORDER ON PROJECT NO. 58481, RULEMAKING TO IMPLEMENT LARGE LOAD INTERCONNECTION STANDARDS UNDER PURA §37.0561 in PUCT Project 58481 on Sep 9, 2026. | |
| PUCT Project 58481: Comments of Lancium LLC on Project 58481 Recommended Adoption OrderPUCT Project 58481, Item 215 |
Filed · Sep 9, 2026
Lancium LLC
|
Lancium LLC filed Comments of Lancium LLC on Project 58481 Recommended Adoption Order in PUCT Project 58481 on Sep 9, 2026. | |
| PUCT Project 58796: Joint Status ReportPUCT Project 58796, Item 102 |
Filed · Sep 9, 2026
SOUTHWESTERN ELECTRIC POWER COMPANY
|
SOUTHWESTERN ELECTRIC POWER COMPANY filed Joint Status Report in PUCT Project 58796 on Sep 9, 2026. | |
| PUCT Project 59948: PROTECTIVE ORDER CERTIFICATIONSPUCT Project 59948, Item 12 |
Filed · Sep 14, 2026
PUC LEGAL
|
PUC LEGAL filed PROTECTIVE ORDER CERTIFICATIONS in PUCT Project 59948 on Sep 14, 2026. | |
| PUCT Project 59948: COMMISSION STAFF’S RECOMMENDATION ON FINAL DISPOSITIONPUCT Project 59948, Item 13 |
Filed · Sep 15, 2026
PUC LEGAL
|
PUC LEGAL filed COMMISSION STAFF’S RECOMMENDATION ON FINAL DISPOSITION in PUCT Project 59948 on Sep 15, 2026. | |
| PUCT Project 54445: NOTICE OF RECOMMENDED APPROVAL OF REVISION REQUESTS BY ERCOT BOARD OF DIRECTORSPUCT Project 54445, Item 112 |
Filed · Jun 26, 2025
ERCOT
|
ERCOT filed NOTICE OF RECOMMENDED APPROVAL OF REVISION REQUESTS BY ERCOT BOARD OF DIRECTORS in PUCT Project 54445 on Jun 26, 2025. | |
| PUCT Project 54445: Staff Memo and Proposed OrderPUCT Project 54445, Item 113 |
Filed · Jul 24, 2025
PUC MARKET ANALYSIS
|
PUC MARKET ANALYSIS filed Staff Memo and Proposed Order in PUCT Project 54445 on Jul 24, 2025. | |
| PUCT Project 54445: ORDER APPROVING ERCOT REVISION REQUESTSPUCT Project 54445, Item 114 |
Filed · Jul 31, 2025
PUC OPDM
|
PUC OPDM filed ORDER APPROVING ERCOT REVISION REQUESTS in PUCT Project 54445 on Jul 31, 2025. | |
| PUCT Project 54445: NOTICE OF RECOMMENDED APPROVAL OF REVISION REQUESTS BY ERCOT BOARD OF DIRECTORSPUCT Project 54445, Item 115 |
Filed · Sep 29, 2025
ERCOT
|
ERCOT filed NOTICE OF RECOMMENDED APPROVAL OF REVISION REQUESTS BY ERCOT BOARD OF DIRECTORS in PUCT Project 54445 on Sep 29, 2025. | |
| PUCT Project 54445: ERCOT Request for Approval of 2026 Ancillary Service MethodologyPUCT Project 54445, Item 116 |
Filed · Oct 6, 2025
ERCOT
|
ERCOT filed ERCOT Request for Approval of 2026 Ancillary Service Methodology in PUCT Project 54445 on Oct 6, 2025. | |
| PUCT Project 54445: Staff Memo and Proposed Order_1 (revision requests only)PUCT Project 54445, Item 117 |
Filed · Oct 30, 2025
PUC MARKET ANALYSIS
|
PUC MARKET ANALYSIS filed Staff Memo and Proposed Order_1 (revision requests only) in PUCT Project 54445 on Oct 30, 2025. | |
| PUCT Project 54445: Staff Memo and Proposed Order_2 (2026 AS Methodology)PUCT Project 54445, Item 118 |
Filed · Oct 30, 2025
PUC MARKET ANALYSIS
|
PUC MARKET ANALYSIS filed Staff Memo and Proposed Order_2 (2026 AS Methodology) in PUCT Project 54445 on Oct 30, 2025. | |
| PUCT Project 54445: ORDER APPROVING ERCOT REVISION REQUESTSPUCT Project 54445, Item 119 |
Filed · Nov 6, 2025
PUC OPDM
|
PUC OPDM filed ORDER APPROVING ERCOT REVISION REQUESTS in PUCT Project 54445 on Nov 6, 2025. | |
| PUCT Project 54445: ORDER APPROVING 2026 ERCOT METHODOLOGIES FOR DETERMINING MINIMUM ANCILLARY SERVICE REQUIREMENTSPUCT Project 54445, Item 120 |
Filed · Nov 6, 2025
PUC OPDM
|
PUC OPDM filed ORDER APPROVING 2026 ERCOT METHODOLOGIES FOR DETERMINING MINIMUM ANCILLARY SERVICE REQUIREMENTS in PUCT Project 54445 on Nov 6, 2025. | |
| PUCT Project 54445: Staff memo regarding ERCOT revision requests approval timelinesPUCT Project 54445, Item 121 |
Filed · Nov 19, 2025
PUC MARKET ANALYSIS
|
PUC MARKET ANALYSIS filed Staff memo regarding ERCOT revision requests approval timelines in PUCT Project 54445 on Nov 19, 2025. | |
| PUCT Project 54445: NOTICE OF RECOMMENDED APPROVAL OF REVISION REQUESTS BY ERCOT BOARD OF DIRECTORSPUCT Project 54445, Item 122 |
Filed · Dec 15, 2025
ERCOT
|
ERCOT filed NOTICE OF RECOMMENDED APPROVAL OF REVISION REQUESTS BY ERCOT BOARD OF DIRECTORS in PUCT Project 54445 on Dec 15, 2025. | |
| PUCT Project 54445: Staff Memo and Proposed OrderPUCT Project 54445, Item 123 |
Filed · Jan 8, 2026
PUC MARKET ANALYSIS
|
PUC MARKET ANALYSIS filed Staff Memo and Proposed Order in PUCT Project 54445 on Jan 8, 2026. | |
| PUCT Project 54445: ORDER APPROVING ERCOT REVISION REQUESTSPUCT Project 54445, Item 124 |
Filed · Jan 15, 2026
PUC OPDM
|
PUC OPDM filed ORDER APPROVING ERCOT REVISION REQUESTS in PUCT Project 54445 on Jan 15, 2026. | |
| PUCT Project 54445: NOTICE OF RECOMMENDED APPROVAL OF REVISION REQUESTS BY ERCOT BOARD OF DIRECTORSPUCT Project 54445, Item 125 |
Filed · Feb 13, 2026
ERCOT
|
ERCOT filed NOTICE OF RECOMMENDED APPROVAL OF REVISION REQUESTS BY ERCOT BOARD OF DIRECTORS in PUCT Project 54445 on Feb 13, 2026. | |
| PUCT Project 54445: Staff Memo and Proposed OrderPUCT Project 54445, Item 126 |
Filed · Mar 19, 2026
PUC MARKET ANALYSIS
|
PUC MARKET ANALYSIS filed Staff Memo and Proposed Order in PUCT Project 54445 on Mar 19, 2026. | |
| PUCT Project 54445: ORDER APPROVING ERCOT REVISION REQUESTSPUCT Project 54445, Item 127 |
Filed · Mar 26, 2026
PUC OPDM
|
PUC OPDM filed ORDER APPROVING ERCOT REVISION REQUESTS in PUCT Project 54445 on Mar 26, 2026. | |
| PUCT Project 54445: NOTICE OF RECOMMENDED APPROVAL OF REVISION REQUESTS BY ERCOT BOARD OF DIRECTORSPUCT Project 54445, Item 128 |
Filed · Apr 28, 2026
ERCOT
|
ERCOT filed NOTICE OF RECOMMENDED APPROVAL OF REVISION REQUESTS BY ERCOT BOARD OF DIRECTORS in PUCT Project 54445 on Apr 28, 2026. | |
| PUCT Project 54445: Staff Memo and Proposed OrderPUCT Project 54445, Item 129 |
Filed · May 21, 2026
PUC MARKET ANALYSIS
|
PUC MARKET ANALYSIS filed Staff Memo and Proposed Order in PUCT Project 54445 on May 21, 2026. | |
| PUCT Project 54445: PROPOSED ORDER APPROVING ERCOT REVISION REQUESTSPUCT Project 54445, Item 130 |
Filed · May 29, 2026
PUC OPDM
|
PUC OPDM filed PROPOSED ORDER APPROVING ERCOT REVISION REQUESTS in PUCT Project 54445 on May 29, 2026. | |
| PUCT Project 54445: NOTICE OF RECOMMENDED APPROVAL OF REVISION REQUESTS BY ERCOT BOARD OF DIRECTORSPUCT Project 54445, Item 131 |
Filed · Jun 2, 2026
ERCOT
|
ERCOT filed NOTICE OF RECOMMENDED APPROVAL OF REVISION REQUESTS BY ERCOT BOARD OF DIRECTORS in PUCT Project 54445 on Jun 2, 2026. | |
| PUCT Project 54445: Commission Staff's Memo Regarding NOGRR282PUCT Project 54445, Item 132 |
Filed · Jun 3, 2026
PUC MARKET ANALYSIS
|
PUC MARKET ANALYSIS filed Commission Staff's Memo Regarding NOGRR282 in PUCT Project 54445 on Jun 3, 2026. | |
| PUCT Project 54445: NOTICE OF RECOMMENDED APPROVAL OF REVISION REQUESTS BY ERCOT BOARD OF DIRECTORSPUCT Project 54445, Item 133 |
Filed · Jun 8, 2026
ERCOT
|
ERCOT filed NOTICE OF RECOMMENDED APPROVAL OF REVISION REQUESTS BY ERCOT BOARD OF DIRECTORS in PUCT Project 54445 on Jun 8, 2026. | |
| PUCT Project 54445: Skybox Datacenters, LLC's Comments regarding Planning Guide Revision Request ("PGRR") 145 and Site Control Requirements for Batch Zero Large Load InterconnectionsPUCT Project 54445, Item 134 |
Filed · Jun 10, 2026
SKYBOX DATACENTERS, LLC
|
SKYBOX DATACENTERS, LLC filed Skybox Datacenters, LLC's Comments regarding Planning Guide Revision Request ("PGRR") 145 and Site Control Requirements for Batch Zero Large Load Interconnections in PUCT Project 54445 on Jun 10, 2026. | |
| PUCT Project 54445: Staff Memo and Proposed Order for PGRR 145 and NPRR 1325PUCT Project 54445, Item 138 |
Filed · Jun 11, 2026
PUC MARKET ANALYSIS
|
PUC MARKET ANALYSIS filed Staff Memo and Proposed Order for PGRR 145 and NPRR 1325 in PUCT Project 54445 on Jun 11, 2026. | |
| PUCT Project 54445: COMMENTS OF TEXAS ELECTRIC COOPERATIVES, INC. REGARDING NOGRR 282PUCT Project 54445, Item 142 |
Filed · Jun 12, 2026
TEXAS ELECTRIC COOPERATIVES, INC.
|
TEXAS ELECTRIC COOPERATIVES, INC. filed COMMENTS OF TEXAS ELECTRIC COOPERATIVES, INC. REGARDING NOGRR 282 in PUCT Project 54445 on Jun 12, 2026. | |
| PUCT Project 54445: DCC Comments on NOGRR282 Large Computational Load Ride-Through RequirementsPUCT Project 54445, Item 148 |
Filed · Jun 12, 2026
DATA CENTER COALITION
|
DATA CENTER COALITION filed DCC Comments on NOGRR282 Large Computational Load Ride-Through Requirements in PUCT Project 54445 on Jun 12, 2026. | |
| PUCT Project 54445: Crusoe Technologies, LLC Comments on Recommended Approval of PGRR 145 by the ERCOT Board of DirectorsPUCT Project 54445, Item 149 |
Filed · Jun 12, 2026
Crusoe Technologies, LLC
|
Crusoe Technologies, LLC filed Crusoe Technologies, LLC Comments on Recommended Approval of PGRR 145 by the ERCOT Board of Directors in PUCT Project 54445 on Jun 12, 2026. | |
| PUCT Project 54445: ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S COMMENTS REGARDING NODAL OPERATING GUIDE REVISION REQUEST 282PUCT Project 54445, Item 150 |
Filed · Jun 12, 2026
ERCOT
|
ERCOT filed ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S COMMENTS REGARDING NODAL OPERATING GUIDE REVISION REQUEST 282 in PUCT Project 54445 on Jun 12, 2026. | |
| PUCT Project 54445: Data Center Coalition's Comments Regarding PGRR 145PUCT Project 54445, Item 154 |
Filed · Jun 16, 2026
Data Center Coalition (DCC)
|
Data Center Coalition (DCC) filed Data Center Coalition's Comments Regarding PGRR 145 in PUCT Project 54445 on Jun 16, 2026. | |
| PUCT Project 54445: ERCOT LETTER REGARDING PGRR145PUCT Project 54445, Item 155 |
Filed · Jun 16, 2026
ERCOT
|
ERCOT filed ERCOT LETTER REGARDING PGRR145 in PUCT Project 54445 on Jun 16, 2026. | |
| PUCT Project 54445: First Ammonia LLC's Comments on Commission Consideration of PGRR 145, Batch Zero Process for Large Load InterconnectionsPUCT Project 54445, Item 157 |
Filed · Jun 17, 2026
First Ammonia LLC
|
First Ammonia LLC filed First Ammonia LLC's Comments on Commission Consideration of PGRR 145, Batch Zero Process for Large Load Interconnections in PUCT Project 54445 on Jun 17, 2026. | |
| PUCT Project 54445: ORDER APPROVING ERCOT REVISION REQUESTSPUCT Project 54445, Item 158 |
Filed · Jun 18, 2026
PUC OPDM
|
PUC OPDM filed ORDER APPROVING ERCOT REVISION REQUESTS in PUCT Project 54445 on Jun 18, 2026. | |
| PUCT Project 54445: Staff Memos and Proposed OrderPUCT Project 54445, Item 160 |
Filed · Jul 2, 2026
PUC MARKET ANALYSIS
|
PUC MARKET ANALYSIS filed Staff Memos and Proposed Order in PUCT Project 54445 on Jul 2, 2026. | |
| PUCT Project 54445: PROPOSED ORDER APPROVING ERCOT REVISION REQUESTSPUCT Project 54445, Item 162 |
Filed · Jul 9, 2026
PUC OPDM
|
PUC OPDM filed PROPOSED ORDER APPROVING ERCOT REVISION REQUESTS in PUCT Project 54445 on Jul 9, 2026. | |
| PUCT Project 58481: ROWAN DIGITAL INFRASTRUCTURE LLC COMMENTS ON PROPOSAL FOR PUBLICATION OF NEW 16 TAC § 25.194PUCT Project 58481, Item 179 |
Filed · Apr 17, 2026
ROWAN DIGITAL INFRASTRUCTURE LLC
|
ROWAN DIGITAL INFRASTRUCTURE LLC filed ROWAN DIGITAL INFRASTRUCTURE LLC COMMENTS ON PROPOSAL FOR PUBLICATION OF NEW 16 TAC § 25.194 in PUCT Project 58481 on Apr 17, 2026. | |
| PUCT Project 58481: Comments on Proposal for Publication on Proposed New 16 TAC §25.194PUCT Project 58481, Item 180 |
Filed · Apr 17, 2026
Data Center Coalition (DCC)
|
Data Center Coalition (DCC) filed Comments on Proposal for Publication on Proposed New 16 TAC §25.194 in PUCT Project 58481 on Apr 17, 2026. | |
| PUCT Project 58481: Comments of Texas Electric Cooperatives, Inc.PUCT Project 58481, Item 182 |
Filed · Apr 17, 2026
TEXAS ELECTRIC COOPERATIVES, INC.
|
TEXAS ELECTRIC COOPERATIVES, INC. filed Comments of Texas Electric Cooperatives, Inc. in PUCT Project 58481 on Apr 17, 2026. | |
| PUCT Project 58481: The Steering Committee of Cities Served by Oncor and Texas Coalition for Affordable Power's Comments on Proposal for Publication of New 16 TAC § 25.194PUCT Project 58481, Item 183 |
Filed · Apr 17, 2026
STEERING COMMITTEE OF CITIES SERVED BY ONCOR AND TEXAS COALITION FOR AFFORDABLE POWER
|
STEERING COMMITTEE OF CITIES SERVED BY ONCOR AND TEXAS COALITION FOR AFFORDABLE POWER filed The Steering Committee of Cities Served by Oncor and Texas Coalition for Affordable Power's Comments on Proposal for Publication of New 16 TAC § 25.194 in PUCT Project 58481 on Apr 17, 2026. | |
| PUCT Project 58481: ONCOR ELECTRIC DELIVERY'S COMMENTS ON THE PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.194PUCT Project 58481, Item 184 |
Filed · Apr 17, 2026
ONCOR ELECTRIC DELIVERY COMPANY LLC
|
ONCOR ELECTRIC DELIVERY COMPANY LLC filed ONCOR ELECTRIC DELIVERY'S COMMENTS ON THE PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.194 in PUCT Project 58481 on Apr 17, 2026. | |
| PUCT Project 58481: ERCOT Steel Mills Comments on Proposal for Publication of New Rule 16 TAC §25.194PUCT Project 58481, Item 185 |
Filed · Apr 17, 2026
ERCOT STEEL MILLS
|
ERCOT STEEL MILLS filed ERCOT Steel Mills Comments on Proposal for Publication of New Rule 16 TAC §25.194 in PUCT Project 58481 on Apr 17, 2026. | |
| PUCT Project 58481: TXOGA Comments on Proposal for Publication on Proposed New 16 TAC §25.194PUCT Project 58481, Item 188 |
Filed · Apr 17, 2026
TEXAS OIL & GAS ASSOCIATION
|
TEXAS OIL & GAS ASSOCIATION filed TXOGA Comments on Proposal for Publication on Proposed New 16 TAC §25.194 in PUCT Project 58481 on Apr 17, 2026. | |
| PUCT Project 58481: GVEC's Comments on Proposal for PublicationPUCT Project 58481, Item 189 |
Filed · Apr 17, 2026
GUADALUPE VALLEY ELECTRIC COOPERATIVE, INC
|
GUADALUPE VALLEY ELECTRIC COOPERATIVE, INC filed GVEC's Comments on Proposal for Publication in PUCT Project 58481 on Apr 17, 2026. | |
| PUCT Project 58481: Thor Equities’ Comments on PUCT Staff’s Proposal for PublicationPUCT Project 58481, Item 191 |
Filed · Apr 17, 2026
Thor Equities LLC
|
Thor Equities LLC filed Thor Equities’ Comments on PUCT Staff’s Proposal for Publication in PUCT Project 58481 on Apr 17, 2026. | |
| PUCT Project 58481: Tesla, Inc. Comments on Proposal for Publication on Proposed New 16 TAC §25.194PUCT Project 58481, Item 192 |
Filed · Apr 17, 2026
TESLA
|
TESLA filed Tesla, Inc. Comments on Proposal for Publication on Proposed New 16 TAC §25.194 in PUCT Project 58481 on Apr 17, 2026. | |
| PUCT Project 58481: TEXAS INDUSTRIAL ENERGY CONSUMERS’ PROPOSED COMMENTS TO PROPOSAL FOR PUBLICATION OF NEW 16 TAC § 25.194PUCT Project 58481, Item 193 |
Filed · Apr 17, 2026
TIEC
|
TIEC filed TEXAS INDUSTRIAL ENERGY CONSUMERS’ PROPOSED COMMENTS TO PROPOSAL FOR PUBLICATION OF NEW 16 TAC § 25.194 in PUCT Project 58481 on Apr 17, 2026. | |
| PUCT Project 58481: Joint TSPs’ Comments on Proposal for PublicationPUCT Project 58481, Item 194 |
Filed · Apr 17, 2026
WIND ENERGY TRANSMISSION TEXAS, LLC
|
WIND ENERGY TRANSMISSION TEXAS, LLC filed Joint TSPs’ Comments on Proposal for Publication in PUCT Project 58481 on Apr 17, 2026. | |
| PUCT Project 58481: OPUC’S COMMENTS REGARDING THE PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.194PUCT Project 58481, Item 195 |
Filed · Apr 17, 2026
OPUC
|
OPUC filed OPUC’S COMMENTS REGARDING THE PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.194 in PUCT Project 58481 on Apr 17, 2026. | |
| PUCT Project 58481: TNMP’s Comments To Proposal For Publication Of New 16 TAC § 25.194PUCT Project 58481, Item 197 |
Filed · Apr 17, 2026
TEXAS-NEW MEXICO POWER COMPANY
|
TEXAS-NEW MEXICO POWER COMPANY filed TNMP’s Comments To Proposal For Publication Of New 16 TAC § 25.194 in PUCT Project 58481 on Apr 17, 2026. | |
| PUCT Project 58481: CRUSOE TECHNOLOGIES LLC’S COMMENTS ON STAFF’S PROPOSAL FOR PUBLICATION OF NEW 16 TAC § 25.194PUCT Project 58481, Item 199 |
Filed · Apr 17, 2026
Crusoe Technologies LLC
|
Crusoe Technologies LLC filed CRUSOE TECHNOLOGIES LLC’S COMMENTS ON STAFF’S PROPOSAL FOR PUBLICATION OF NEW 16 TAC § 25.194 in PUCT Project 58481 on Apr 17, 2026. | |
| PUCT Project 58481: Vistra's Comments - Project 58481PUCT Project 58481, Item 200 |
Filed · Apr 17, 2026
VISTRA CORPORATE SERVICES COMPANY
|
VISTRA CORPORATE SERVICES COMPANY filed Vistra's Comments - Project 58481 in PUCT Project 58481 on Apr 17, 2026. | |
| PUCT Project 58481: Cormint Data Systems Comments on Staff PforP in 58481PUCT Project 58481, Item 203 |
Filed · Apr 20, 2026
Cormint Data Systems
|
Cormint Data Systems filed Cormint Data Systems Comments on Staff PforP in 58481 in PUCT Project 58481 on Apr 20, 2026. | |
| PUCT Project 54445: Staff memo regarding ERCOT revision requests approval timelinesPUCT Project 54445, Item 163 |
Filed · Aug 11, 2026
PUC MARKET ANALYSIS
|
PUC MARKET ANALYSIS filed Staff memo regarding ERCOT revision requests approval timelines in PUCT Project 54445 on Aug 11, 2026. | |
| PUCT Project 58317: Request for control numberPUCT Project 58317, Item 1 |
Filed · Jun 30, 2025
PUC RULES AND PROJECTS
|
PUC RULES AND PROJECTS filed Request for control number in PUCT Project 58317 on Jun 30, 2025. | |
| PUCT Project 58317: Notice of July 21 WorkshopPUCT Project 58317, Item 2 |
Filed · Jul 8, 2025
PUC RULES AND PROJECTS
|
PUC RULES AND PROJECTS filed Notice of July 21 Workshop in PUCT Project 58317 on Jul 8, 2025. | |
| PUCT Project 58317: July 21 Workshop AgendaPUCT Project 58317, Item 3 |
Filed · Jul 14, 2025
PUC RULES AND PROJECTS
|
PUC RULES AND PROJECTS filed July 21 Workshop Agenda in PUCT Project 58317 on Jul 14, 2025. | |
| PUCT Project 58317: Response to Commission Request for Information Regarding Net Metering Arrangements Under PURA § 39.169PUCT Project 58317, Item 4 |
Filed · Jul 24, 2025
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Response to Commission Request for Information Regarding Net Metering Arrangements Under PURA § 39.169 in PUCT Project 58317 on Jul 24, 2025. | |
| PUCT Project 58317: Staff Memo and RoadmapPUCT Project 58317, Item 5 |
Filed · Aug 1, 2025
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Staff Memo and Roadmap in PUCT Project 58317 on Aug 1, 2025. | |
| PUCT Project 59220: ORDER NO. 3- GRANTING MOTIONS TO INTERVENEPUCT Project 59220, Item 10 |
Filed · Feb 9, 2026
PUC OPDM
|
PUC OPDM filed ORDER NO. 3- GRANTING MOTIONS TO INTERVENE in PUCT Project 59220 on Feb 9, 2026. | |
| PUCT Project 59220: AMENDED APPLICATION FOR NET METERING APPROVAL BY FGE GOODNIGHT I, LLC (GOODNIGHT WIND) AND CRUSOE ENERGY SYSTEMS LLC, AND ENSIGN INFRASTRUCTURE LLCPUCT Project 59220, Item 11 |
Filed · Mar 26, 2026
CRUSOE ENERGY SYSTEMS LLC
|
CRUSOE ENERGY SYSTEMS LLC filed AMENDED APPLICATION FOR NET METERING APPROVAL BY FGE GOODNIGHT I, LLC (GOODNIGHT WIND) AND CRUSOE ENERGY SYSTEMS LLC, AND ENSIGN INFRASTRUCTURE LLC in PUCT Project 59220 on Mar 26, 2026. | |
| PUCT Project 59220: SUPPLEMENT TO AMENDED APPLICATION FOR NET METERING APPROVAL BY FGE GOODNIGHT I, LLC (GOODNIGHT WIND) AND CRUSOE ENERGY SYSTEMS LLC, AND ENSIGN INFRASTRUCTURE LLCPUCT Project 59220, Item 12 |
Filed · Mar 26, 2026
CRUSOE ENERGY SYSTEMS LLC
|
CRUSOE ENERGY SYSTEMS LLC filed SUPPLEMENT TO AMENDED APPLICATION FOR NET METERING APPROVAL BY FGE GOODNIGHT I, LLC (GOODNIGHT WIND) AND CRUSOE ENERGY SYSTEMS LLC, AND ENSIGN INFRASTRUCTURE LLC in PUCT Project 59220 on Mar 26, 2026. | |
| PUCT Project 59220: ORDER NO. 4 - RESTYLING DOCKETPUCT Project 59220, Item 13 |
Filed · Apr 8, 2026
PUC OPDM
|
PUC OPDM filed ORDER NO. 4 - RESTYLING DOCKET in PUCT Project 59220 on Apr 8, 2026. | |
| PUCT Project 59220: PROTECTIVE ORDER CERTIFICATIONSPUCT Project 59220, Item 14 |
Filed · May 12, 2026
PUC LEGAL
|
PUC LEGAL filed PROTECTIVE ORDER CERTIFICATIONS in PUCT Project 59220 on May 12, 2026. | |
| PUCT Project 59220: ERCOT NOTICE OF INTENT TO FILE STUDY RESULTS AND RECOMMENDATIONSPUCT Project 59220, Item 15 |
Filed · May 19, 2026
ERCOT
|
ERCOT filed ERCOT NOTICE OF INTENT TO FILE STUDY RESULTS AND RECOMMENDATIONS in PUCT Project 59220 on May 19, 2026. | |
| PUCT Project 59220: ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S FILING OF STUDY RESULTS AND RECOMMENDATIONSPUCT Project 59220, Item 16 |
Filed · May 29, 2026
ERCOT
|
ERCOT filed ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S FILING OF STUDY RESULTS AND RECOMMENDATIONS in PUCT Project 59220 on May 29, 2026. | |
| PUCT Project 59220: CONFIDENTIAL - ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S FILING OF STUDY RESULTS AND RECOMMENDATIONSPUCT Project 59220, Item 17 |
Filed · May 29, 2026
ERCOT
|
ERCOT filed CONFIDENTIAL - ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S FILING OF STUDY RESULTS AND RECOMMENDATIONS in PUCT Project 59220 on May 29, 2026. | |
| PUCT Project 59220: ORDER NO. 5 - ESTABLISHING PROCEDURAL SCHEDULEPUCT Project 59220, Item 18 |
Filed · May 29, 2026
PUC OPDM
|
PUC OPDM filed ORDER NO. 5 - ESTABLISHING PROCEDURAL SCHEDULE in PUCT Project 59220 on May 29, 2026. | |
| PUCT Project 59220: ENSIGN INFRASTRUCTURE LLC’S NOTICE OF FILING PROTECTIVE ORDER CERTIFICATIONSPUCT Project 59220, Item 19 |
Filed · May 30, 2026
ENSIGN INFRASTRUCTURE LLC
|
ENSIGN INFRASTRUCTURE LLC filed ENSIGN INFRASTRUCTURE LLC’S NOTICE OF FILING PROTECTIVE ORDER CERTIFICATIONS in PUCT Project 59220 on May 30, 2026. | |
| PUCT Project 59220: JOINT APPLICATION FOR NET METERING APPROVAL BY FGE GOODNIGHT I, LLC AND CRUSOE ENERGY SYSTEMS LLCPUCT Project 59220, Item 1 |
Filed · Jan 9, 2026
FGE Goodnight I, LLC and Crusoe Energy Systems LLC
|
FGE Goodnight I, LLC and Crusoe Energy Systems LLC filed JOINT APPLICATION FOR NET METERING APPROVAL BY FGE GOODNIGHT I, LLC AND CRUSOE ENERGY SYSTEMS LLC in PUCT Project 59220 on Jan 9, 2026. | |
| PUCT Project 59220: Direct Testimony of Bharath Kumar RavulapatiPUCT Project 59220, Item 22 |
Filed · Jun 3, 2026
CRUSOE ENERGY SYSTEMS
|
CRUSOE ENERGY SYSTEMS filed Direct Testimony of Bharath Kumar Ravulapati in PUCT Project 59220 on Jun 3, 2026. | |
| PUCT Project 59220: ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S STATEMENT OF POSITION IN RESPONSE TO ORDER NO. 5PUCT Project 59220, Item 23 |
Filed · Jun 8, 2026
ERCOT
|
ERCOT filed ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S STATEMENT OF POSITION IN RESPONSE TO ORDER NO. 5 in PUCT Project 59220 on Jun 8, 2026. | |
| PUCT Project 59220: Staff's Recommendation on Administrative Completeness and Sufficiency of NoticePUCT Project 59220, Item 24 |
Filed · Jun 8, 2026
PUC MARKET ANALYSIS
|
PUC MARKET ANALYSIS filed Staff's Recommendation on Administrative Completeness and Sufficiency of Notice in PUCT Project 59220 on Jun 8, 2026. | |
| PUCT Project 59220: ENSIGN INFRASTRUCTURE, LLC’S AND CRUSOE ENERGY SYSTEMS LLC’S NOTICE OF HEARING AND NOTICE OF INTENT TO REQUEST COURT REPORTERPUCT Project 59220, Item 25 |
Filed · Jun 8, 2026
ENSIGN INFRASTRUCTURE LLC
|
ENSIGN INFRASTRUCTURE LLC filed ENSIGN INFRASTRUCTURE, LLC’S AND CRUSOE ENERGY SYSTEMS LLC’S NOTICE OF HEARING AND NOTICE OF INTENT TO REQUEST COURT REPORTER in PUCT Project 59220 on Jun 8, 2026. | |
| PUCT Project 59220: ORDER NO. 6 - FINDING APPLICATION ADMINISTRATIVELY COMPLETE AND NOTICE SUFFICIENT, REQUIRING CORRECTED NOTICE OF HEARING, PROVIDING NOTICE OF PREHEARING CONFERENCE, AND REVISING PROCEDURAL SCHEDULEPUCT Project 59220, Item 28 |
Filed · Jun 9, 2026
PUC OPDM
|
PUC OPDM filed ORDER NO. 6 - FINDING APPLICATION ADMINISTRATIVELY COMPLETE AND NOTICE SUFFICIENT, REQUIRING CORRECTED NOTICE OF HEARING, PROVIDING NOTICE OF PREHEARING CONFERENCE, AND REVISING PROCEDURAL SCHEDULE in PUCT Project 59220 on Jun 9, 2026. | |
| PUCT Project 59220: ORDER NO. 7- CLARIFYING DEADLINE FOR APPLICANTS TO FILE CORRECTED NOTICE OF HEARINGPUCT Project 59220, Item 29 |
Filed · Jun 10, 2026
PUC OPDM
|
PUC OPDM filed ORDER NO. 7- CLARIFYING DEADLINE FOR APPLICANTS TO FILE CORRECTED NOTICE OF HEARING in PUCT Project 59220 on Jun 10, 2026. | |
| PUCT Project 59220: Correction to the Joint Application for Net Metering ApprovalPUCT Project 59220, Item 2 |
Filed · Jan 12, 2026
CRUSOE ENERGY SYSTEMS LLC
|
CRUSOE ENERGY SYSTEMS LLC filed Correction to the Joint Application for Net Metering Approval in PUCT Project 59220 on Jan 12, 2026. | |
| PUCT Project 59220: ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S RESPONSE TO OTHER PARTIES’ FILINGSPUCT Project 59220, Item 32 |
Filed · Jun 15, 2026
ERCOT
|
ERCOT filed ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S RESPONSE TO OTHER PARTIES’ FILINGS in PUCT Project 59220 on Jun 15, 2026. | |
| PUCT Project 59220: Commission Staff's Statement of Position and RecommendationsPUCT Project 59220, Item 33 |
Filed · Jun 17, 2026
PUC MARKET ANALYSIS
|
PUC MARKET ANALYSIS filed Commission Staff's Statement of Position and Recommendations in PUCT Project 59220 on Jun 17, 2026. | |
| PUCT Project 59220: Commission Staff's Objections and Motion to StrikePUCT Project 59220, Item 34 |
Filed · Jun 18, 2026
PUC MARKET ANALYSIS
|
PUC MARKET ANALYSIS filed Commission Staff's Objections and Motion to Strike in PUCT Project 59220 on Jun 18, 2026. | |
| PUCT Project 59220: ORDER NO. 8- DENYING REQUEST FOR A VIRTUAL PREHEARING CONFERENCEPUCT Project 59220, Item 36 |
Filed · Jun 18, 2026
PUC OPDM
|
PUC OPDM filed ORDER NO. 8- DENYING REQUEST FOR A VIRTUAL PREHEARING CONFERENCE in PUCT Project 59220 on Jun 18, 2026. | |
| PUCT Project 59220: ENSIGN INFRASTRUCTURE, LLC RESPONSE TO COMMISSION STAFF’S MOTION TO STRIKEPUCT Project 59220, Item 37 |
Filed · Jun 19, 2026
ENSIGN INFRASTRUCTURE LLC
|
ENSIGN INFRASTRUCTURE LLC filed ENSIGN INFRASTRUCTURE, LLC RESPONSE TO COMMISSION STAFF’S MOTION TO STRIKE in PUCT Project 59220 on Jun 19, 2026. | |
| PUCT Project 59220: ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S RESPONSE TO ENSIGN INFRASTRUCTURE, LLC’S INFORMAL FIRST SET OF REQUESTS FOR INFORMATIONPUCT Project 59220, Item 38 |
Filed · Jun 19, 2026
ERCOT
|
ERCOT filed ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S RESPONSE TO ENSIGN INFRASTRUCTURE, LLC’S INFORMAL FIRST SET OF REQUESTS FOR INFORMATION in PUCT Project 59220 on Jun 19, 2026. | |
| PUCT Project 59220: Notice of Protective Order CertificationsPUCT Project 59220, Item 39 |
Filed · Jun 19, 2026
Greenbelt Electric Cooperative, Inc. and Golden Spread Electric Cooperative, Inc.
|
Greenbelt Electric Cooperative, Inc. and Golden Spread Electric Cooperative, Inc. filed Notice of Protective Order Certifications in PUCT Project 59220 on Jun 19, 2026. | |
| PUCT Project 59220: ORDER NO. 1 - ESTABLISHING PROCEDURAL REQUIREMENTS AND ENTERING PROTECTIVE ORDERPUCT Project 59220, Item 3 |
Filed · Jan 13, 2026
PUC OPDM
|
PUC OPDM filed ORDER NO. 1 - ESTABLISHING PROCEDURAL REQUIREMENTS AND ENTERING PROTECTIVE ORDER in PUCT Project 59220 on Jan 13, 2026. | |
| PUCT Project 59220: ORDER NO. 9 - MEMORIALIZING PREHEARING CONFERENCE, CANCELING HEARING ON THE MERITS, AND ADOPTING REVISED PROCEDURAL SCHEDULEPUCT Project 59220, Item 40 |
Filed · Jun 19, 2026
PUC OPDM
|
PUC OPDM filed ORDER NO. 9 - MEMORIALIZING PREHEARING CONFERENCE, CANCELING HEARING ON THE MERITS, AND ADOPTING REVISED PROCEDURAL SCHEDULE in PUCT Project 59220 on Jun 19, 2026. | |
| PUCT Project 59220: CRUSOE ENERGY SYSTEMS LLC EXHIBIT LIST AND EXHIBITPUCT Project 59220, Item 41 |
Filed · Jun 22, 2026
CRUSOE ENERGY SYSTEMS LLC
|
CRUSOE ENERGY SYSTEMS LLC filed CRUSOE ENERGY SYSTEMS LLC EXHIBIT LIST AND EXHIBIT in PUCT Project 59220 on Jun 22, 2026. | |
| PUCT Project 59220: ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S EXHIBIT LISTPUCT Project 59220, Item 44 |
Filed · Jun 22, 2026
ERCOT
|
ERCOT filed ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S EXHIBIT LIST in PUCT Project 59220 on Jun 22, 2026. | |
| PUCT Project 59220: ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S NITIAL BRIEFPUCT Project 59220, Item 45 |
Filed · Jun 26, 2026
ERCOT
|
ERCOT filed ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S NITIAL BRIEF in PUCT Project 59220 on Jun 26, 2026. | |
| PUCT Project 59220: Commission Staff's Initial BriefPUCT Project 59220, Item 47 |
Filed · Jun 26, 2026
PUC MARKET ANALYSIS
|
PUC MARKET ANALYSIS filed Commission Staff's Initial Brief in PUCT Project 59220 on Jun 26, 2026. | |
| PUCT Project 59220: ONCOR ELECTRIC DELIVERY COMPANY LLC'S MOTION TO INTERVENEPUCT Project 59220, Item 4 |
Filed · Jan 21, 2026
ONCOR ELECTRIC DELIVERY COMPANY LLC
|
ONCOR ELECTRIC DELIVERY COMPANY LLC filed ONCOR ELECTRIC DELIVERY COMPANY LLC'S MOTION TO INTERVENE in PUCT Project 59220 on Jan 21, 2026. | |
| PUCT Project 59220: ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S REPLY BRIEFPUCT Project 59220, Item 51 |
Filed · Jul 2, 2026
ERCOT
|
ERCOT filed ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S REPLY BRIEF in PUCT Project 59220 on Jul 2, 2026. | |
| PUCT Project 59220: ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S AND COMMISSION STAFF’S JOINT PROPOSED FINDINGS OF FACT AND CONCLUSIONS OF LAWPUCT Project 59220, Item 52 |
Filed · Jul 2, 2026
ERCOT
|
ERCOT filed ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S AND COMMISSION STAFF’S JOINT PROPOSED FINDINGS OF FACT AND CONCLUSIONS OF LAW in PUCT Project 59220 on Jul 2, 2026. | |
| PUCT Project 59220: Commission Staff's Reply BriefPUCT Project 59220, Item 54 |
Filed · Jul 2, 2026
PUC MARKET ANALYSIS
|
PUC MARKET ANALYSIS filed Commission Staff's Reply Brief in PUCT Project 59220 on Jul 2, 2026. | |
| PUCT Project 59220: JOINT PROPOSED ORDERPUCT Project 59220, Item 56 |
Filed · Jul 2, 2026
ENSIGN INFRASTRUCTURE LLC
|
ENSIGN INFRASTRUCTURE LLC filed JOINT PROPOSED ORDER in PUCT Project 59220 on Jul 2, 2026. | |
| PUCT Project 59220: Commission Staff's Change of CounselPUCT Project 59220, Item 59 |
Filed · Jul 8, 2026
PUC MARKET ANALYSIS
|
PUC MARKET ANALYSIS filed Commission Staff's Change of Counsel in PUCT Project 59220 on Jul 8, 2026. | |
| PUCT Project 59220: NOTICE OF APPEARANCE OF COUNSEL ON BEHALF OF ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.PUCT Project 59220, Item 5 |
Filed · Jan 29, 2026
ERCOT
|
ERCOT filed NOTICE OF APPEARANCE OF COUNSEL ON BEHALF OF ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC. in PUCT Project 59220 on Jan 29, 2026. | |
| PUCT Project 59220: PROPOSED ORDER WITH MEMORANDUMPUCT Project 59220, Item 60 |
Filed · Jul 9, 2026
PUC OPDM
|
PUC OPDM filed PROPOSED ORDER WITH MEMORANDUM in PUCT Project 59220 on Jul 9, 2026. | |
| PUCT Project 59220: ENSIGN INFRASTRUCTURE, LLC’S AND CRUSOE ENERGY SYSTEMS LLC’S CORRECTIONS AND EXCEPTIONS TO PROPOSED ORDERPUCT Project 59220, Item 61 |
Filed · Jul 14, 2026
ENSIGN INFRASTRUCTURE LLC
|
ENSIGN INFRASTRUCTURE LLC filed ENSIGN INFRASTRUCTURE, LLC’S AND CRUSOE ENERGY SYSTEMS LLC’S CORRECTIONS AND EXCEPTIONS TO PROPOSED ORDER in PUCT Project 59220 on Jul 14, 2026. | |
| PUCT Project 59220: FGE Goodnight I, LLC's Corrections and Exceptions to the Proposed OrderPUCT Project 59220, Item 62 |
Filed · Jul 14, 2026
FGE Goodnight I, LLC
|
FGE Goodnight I, LLC filed FGE Goodnight I, LLC's Corrections and Exceptions to the Proposed Order in PUCT Project 59220 on Jul 14, 2026. | |
| PUCT Project 59220: NOTICE MEMORANDUMPUCT Project 59220, Item 63 |
Filed · Jul 15, 2026
PUC OPDM
|
PUC OPDM filed NOTICE MEMORANDUM in PUCT Project 59220 on Jul 15, 2026. | |
| PUCT Project 59220: PROPOSED ORDER MEMORANDUMPUCT Project 59220, Item 64 |
Filed · Jul 16, 2026
PUC OPDM
|
PUC OPDM filed PROPOSED ORDER MEMORANDUM in PUCT Project 59220 on Jul 16, 2026. | |
| PUCT Project 59220: Amicus BriefPUCT Project 59220, Item 65 |
Filed · Jul 16, 2026
TEXAS COMPETITIVE POWER ADVOCATES
|
TEXAS COMPETITIVE POWER ADVOCATES filed Amicus Brief in PUCT Project 59220 on Jul 16, 2026. | |
| PUCT Project 59220: Commission Staff's Motion to Strike Amicus BriefsPUCT Project 59220, Item 67 |
Filed · Jul 17, 2026
PUC MARKET ANALYSIS
|
PUC MARKET ANALYSIS filed Commission Staff's Motion to Strike Amicus Briefs in PUCT Project 59220 on Jul 17, 2026. | |
| PUCT Project 59220: CHAIRMAN GLEESON MEMORANDUMPUCT Project 59220, Item 68 |
Filed · Jul 23, 2026
PUC OPDM
|
PUC OPDM filed CHAIRMAN GLEESON MEMORANDUM in PUCT Project 59220 on Jul 23, 2026. | |
| PUCT Project 59220: ORDERPUCT Project 59220, Item 69 |
Filed · Jul 24, 2026
PUC OPDM
|
PUC OPDM filed ORDER in PUCT Project 59220 on Jul 24, 2026. | |
| PUCT Project 59220: Protective Order Certifications for Crusoe Energy Systems and FGE Goodnight I, LLC (Goodnight Wind)PUCT Project 59220, Item 6 |
Filed · Jan 29, 2026
Crusoe Energy Systems and FGE Goodnight I, LLC
|
Crusoe Energy Systems and FGE Goodnight I, LLC filed Protective Order Certifications for Crusoe Energy Systems and FGE Goodnight I, LLC (Goodnight Wind) in PUCT Project 59220 on Jan 29, 2026. | |
| PUCT Project 59220: OUTGOING COMMISSION-SIGNED ORDER MAIL LOGPUCT Project 59220, Item 70 |
Filed · Jul 24, 2026
PUC OPDM
|
PUC OPDM filed OUTGOING COMMISSION-SIGNED ORDER MAIL LOG in PUCT Project 59220 on Jul 24, 2026. | |
| PUCT Project 59220: VOID SEE ITEM 72PUCT Project 59220, Item 71 |
Filed · Jul 24, 2026
ERCOT
|
ERCOT filed VOID SEE ITEM 72 in PUCT Project 59220 on Jul 24, 2026. | |
| PUCT Project 59220: VOID LETTERPUCT Project 59220, Item 72 |
Filed · Jul 24, 2026
ERCOT
|
ERCOT filed VOID LETTER in PUCT Project 59220 on Jul 24, 2026. | |
| PUCT Project 59220: BALLOT MEMORANDUMPUCT Project 59220, Item 74 |
Filed · Aug 31, 2026
PUC OPDM
|
PUC OPDM filed BALLOT MEMORANDUM in PUCT Project 59220 on Aug 31, 2026. | |
| PUCT Project 59220: ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S NOTICE OF COMMENCEMENT OF STUDYPUCT Project 59220, Item 7 |
Filed · Jan 29, 2026
ERCOT
|
ERCOT filed ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S NOTICE OF COMMENCEMENT OF STUDY in PUCT Project 59220 on Jan 29, 2026. | |
| PUCT Project 59220: ORDER NO. 2 - GRANTING MOTION TO INTERVENEPUCT Project 59220, Item 9 |
Filed · Feb 2, 2026
PUC OPDM
|
PUC OPDM filed ORDER NO. 2 - GRANTING MOTION TO INTERVENE in PUCT Project 59220 on Feb 2, 2026. | |
| PUCT Project 58317: OPUC NOTICE OF PARTICIPATION LETTERPUCT Project 58317, Item 10 |
Filed · Sep 24, 2025
OPUC
|
OPUC filed OPUC NOTICE OF PARTICIPATION LETTER in PUCT Project 58317 on Sep 24, 2025. | |
| PUCT Project 58317: Joint Comments of Google LLC and Lancium LLC on SB6 ImplementationPUCT Project 58317, Item 11 |
Filed · Dec 18, 2025
GOOGLE LLC, LANCIUM LLC
|
GOOGLE LLC, LANCIUM LLC filed Joint Comments of Google LLC and Lancium LLC on SB6 Implementation in PUCT Project 58317 on Dec 18, 2025. | |
| PUCT Project 58317: OM Item No. 46 - Staff Memo and Updated RoadmapPUCT Project 58317, Item 12 |
Filed · Jan 30, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed OM Item No. 46 - Staff Memo and Updated Roadmap in PUCT Project 58317 on Jan 30, 2026. | |
| PUCT Project 58317: Staff Memo_New Rulemaking ProjectPUCT Project 58317, Item 14 |
Filed · May 27, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Staff Memo_New Rulemaking Project in PUCT Project 58317 on May 27, 2026. | |
| PUCT Project 58317: Staff Memo and Updated RoadmapPUCT Project 58317, Item 15 |
Filed · May 27, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Staff Memo and Updated Roadmap in PUCT Project 58317 on May 27, 2026. | |
| PUCT Project 58317: Governor Abbott's June 10, 2026 letter to PUCT and ERCOT re: Data Center Infrastructure CostsPUCT Project 58317, Item 16 |
Filed · Jun 22, 2026
PUC DEPUTY EXECUTIVE DIRECTOR
|
PUC DEPUTY EXECUTIVE DIRECTOR filed Governor Abbott's June 10, 2026 letter to PUCT and ERCOT re: Data Center Infrastructure Costs in PUCT Project 58317 on Jun 22, 2026. | |
| PUCT Project 58317: Response to Governor Abbott's June 10, 2026 letterPUCT Project 58317, Item 18 |
Filed · Jul 20, 2026
PUC DEPUTY EXECUTIVE DIRECTOR
|
PUC DEPUTY EXECUTIVE DIRECTOR filed Response to Governor Abbott's June 10, 2026 letter in PUCT Project 58317 on Jul 20, 2026. | |
| PUCT Project 58317: SB6 Implementation Roadmap Updated July 2026PUCT Project 58317, Item 19 |
Filed · Jul 21, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed SB6 Implementation Roadmap Updated July 2026 in PUCT Project 58317 on Jul 21, 2026. | |
| PUCT Project 58317: CHAIRMAN GLEESON MEMORANDUMPUCT Project 58317, Item 25 |
Filed · Aug 6, 2026
PUC OPDM
|
PUC OPDM filed CHAIRMAN GLEESON MEMORANDUM in PUCT Project 58317 on Aug 6, 2026. | |
| PUCT Project 58317: Governor Abbott's August 3, 2026 letter to PUCT and ERCOT re: Verification of Data Center InformationPUCT Project 58317, Item 26 |
Filed · Aug 6, 2026
PUC DEPUTY EXECUTIVE DIRECTOR
|
PUC DEPUTY EXECUTIVE DIRECTOR filed Governor Abbott's August 3, 2026 letter to PUCT and ERCOT re: Verification of Data Center Information in PUCT Project 58317 on Aug 6, 2026. | |
| PUCT Project 58317: ERCOT LETTER REGARDING PROJECT NO. 59142 FILINGPUCT Project 58317, Item 27 |
Filed · Aug 10, 2026
ERCOT
|
ERCOT filed ERCOT LETTER REGARDING PROJECT NO. 59142 FILING in PUCT Project 58317 on Aug 10, 2026. | |
| PUCT Project 58317: SENATE BILL 6 IMPLEMENTATION WORKSHOP PROJECT NO. 58317 MONDAY, JULY 21, 2025PUCT Project 58317, Item 6 |
Filed · Aug 5, 2025
KENNEDY REPORTING SERVICE
|
KENNEDY REPORTING SERVICE filed SENATE BILL 6 IMPLEMENTATION WORKSHOP PROJECT NO. 58317 MONDAY, JULY 21, 2025 in PUCT Project 58317 on Aug 5, 2025. | |
| PUCT Project 58317: ERCOT LETTER RE NET METERING STUDY DETAILSPUCT Project 58317, Item 7 |
Filed · Sep 2, 2025
ERCOT
|
ERCOT filed ERCOT LETTER RE NET METERING STUDY DETAILS in PUCT Project 58317 on Sep 2, 2025. | |
| PUCT Project 58317: ERCOT LETTER RE STAND-ALONE GENERATION RESOURCE LIST UPDATEPUCT Project 58317, Item 9 |
Filed · Sep 19, 2025
ERCOT
|
ERCOT filed ERCOT LETTER RE STAND-ALONE GENERATION RESOURCE LIST UPDATE in PUCT Project 58317 on Sep 19, 2025. | |
| PUCT Project 58480: EDF comments on large load forecast proposed rulePUCT Project 58480, Item 14 |
Filed · Oct 17, 2025
ENVIRONMENTAL DEFENSE FUND INC
|
ENVIRONMENTAL DEFENSE FUND INC filed EDF comments on large load forecast proposed rule in PUCT Project 58480 on Oct 17, 2025. | |
| PUCT Project 58480: ERCOT STEEL MILLS’ COMMENTS ON PROJECT NO. 58480 - ERCOT LARGE LOAD FORECASTING CRITERIAPUCT Project 58480, Item 15 |
Filed · Oct 17, 2025
ERCOT STEEL MILLS
|
ERCOT STEEL MILLS filed ERCOT STEEL MILLS’ COMMENTS ON PROJECT NO. 58480 - ERCOT LARGE LOAD FORECASTING CRITERIA in PUCT Project 58480 on Oct 17, 2025. | |
| PUCT Project 58480: Targa Resources LLC's Comments to Staff Recommendation for Proposal for Publication of New 16 TAC §25.370PUCT Project 58480, Item 16 |
Filed · Oct 17, 2025
Targa Resources LLC
|
Targa Resources LLC filed Targa Resources LLC's Comments to Staff Recommendation for Proposal for Publication of New 16 TAC §25.370 in PUCT Project 58480 on Oct 17, 2025. | |
| PUCT Project 58480: NRG Energy, Inc.'s Comments on the Proposed RulePUCT Project 58480, Item 17 |
Filed · Oct 17, 2025
NRG ENERGY, INC.
|
NRG ENERGY, INC. filed NRG Energy, Inc.'s Comments on the Proposed Rule in PUCT Project 58480 on Oct 17, 2025. | |
| PUCT Project 58480: Texas Public Policy Foundation Comments on Proposal for Publication of New 16 TAC §25.370PUCT Project 58480, Item 18 |
Filed · Oct 17, 2025
Texas Public Policy Foundation
|
Texas Public Policy Foundation filed Texas Public Policy Foundation Comments on Proposal for Publication of New 16 TAC §25.370 in PUCT Project 58480 on Oct 17, 2025. | |
| PUCT Project 58480: Request for Control NumberPUCT Project 58480, Item 1 |
Filed · Jul 31, 2025
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Request for Control Number in PUCT Project 58480 on Jul 31, 2025. | |
| PUCT Project 58480: OCSC and TCAP's Comments on Proposed Large Load Forecasting CriteriaPUCT Project 58480, Item 20 |
Filed · Oct 17, 2025
THE STEERING COMMITTEE OF CITIES SERVED BY ONCOR (CITIES)
|
THE STEERING COMMITTEE OF CITIES SERVED BY ONCOR (CITIES) filed OCSC and TCAP's Comments on Proposed Large Load Forecasting Criteria in PUCT Project 58480 on Oct 17, 2025. | |
| PUCT Project 58480: SCHAPER ENERGY CONSULTING LLC SUPPLEMENTAL RESPONSE TO STAFF’s QUESTIONS ON PROJECT NO. 58480; ERCOT LARGE LOAD FORECASTING CRITERIA UNDER PROPOSED 16 TAC §25.370PUCT Project 58480, Item 21 |
Filed · Oct 17, 2025
Schaper Energy Consulting LLC
|
Schaper Energy Consulting LLC filed SCHAPER ENERGY CONSULTING LLC SUPPLEMENTAL RESPONSE TO STAFF’s QUESTIONS ON PROJECT NO. 58480; ERCOT LARGE LOAD FORECASTING CRITERIA UNDER PROPOSED 16 TAC §25.370 in PUCT Project 58480 on Oct 17, 2025. | |
| PUCT Project 58480: TCPA Comments and Recommendations on PfPPUCT Project 58480, Item 22 |
Filed · Oct 17, 2025
TCPA
|
TCPA filed TCPA Comments and Recommendations on PfP in PUCT Project 58480 on Oct 17, 2025. | |
| PUCT Project 58480: TEXAS INDUSTRIAL ENERGY CONSUMERS’ PROPOSED COMMENTS TO DRAFT RULE 25.504PUCT Project 58480, Item 23 |
Filed · Oct 17, 2025
TIEC
|
TIEC filed TEXAS INDUSTRIAL ENERGY CONSUMERS’ PROPOSED COMMENTS TO DRAFT RULE 25.504 in PUCT Project 58480 on Oct 17, 2025. | |
| PUCT Project 58480: OFFICE OF PUBLIC UTILITY COUNSEL’S COMMENTS ON PROPOSAL FOR PUBLICATION OF NEW 16 TAC § 25.370PUCT Project 58480, Item 24 |
Filed · Oct 17, 2025
OPUC
|
OPUC filed OFFICE OF PUBLIC UTILITY COUNSEL’S COMMENTS ON PROPOSAL FOR PUBLICATION OF NEW 16 TAC § 25.370 in PUCT Project 58480 on Oct 17, 2025. | |
| PUCT Project 58480: TEBA's Comments on Project No. 58480 Proposal for PublicationPUCT Project 58480, Item 25 |
Filed · Oct 17, 2025
TEXAS ENERGY BUYERS ALLIANCE
|
TEXAS ENERGY BUYERS ALLIANCE filed TEBA's Comments on Project No. 58480 Proposal for Publication in PUCT Project 58480 on Oct 17, 2025. | |
| PUCT Project 58480: ONCOR ELECTRIC DELIVERY’S COMMENTS ON THE PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.370PUCT Project 58480, Item 26 |
Filed · Oct 17, 2025
ONCOR ELECTRIC DELIVERY COMPANY LLC
|
ONCOR ELECTRIC DELIVERY COMPANY LLC filed ONCOR ELECTRIC DELIVERY’S COMMENTS ON THE PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.370 in PUCT Project 58480 on Oct 17, 2025. | |
| PUCT Project 58480: CenterPoint Energy Houston Electric CommentsPUCT Project 58480, Item 27 |
Filed · Oct 17, 2025
CENTERPOINT ENERGY HOUSTON ELECTRIC
|
CENTERPOINT ENERGY HOUSTON ELECTRIC filed CenterPoint Energy Houston Electric Comments in PUCT Project 58480 on Oct 17, 2025. | |
| PUCT Project 58480: Comments of Texas Electric Cooperatives, Inc.PUCT Project 58480, Item 28 |
Filed · Oct 17, 2025
Texas Electric Cooperatives, Inc.
|
Texas Electric Cooperatives, Inc. filed Comments of Texas Electric Cooperatives, Inc. in PUCT Project 58480 on Oct 17, 2025. | |
| PUCT Project 58480: AEP TEXAS’ COMMENTS ON PROPOSAL FOR PUBLICATIONPUCT Project 58480, Item 29 |
Filed · Oct 17, 2025
AEP TEXAS INC.
|
AEP TEXAS INC. filed AEP TEXAS’ COMMENTS ON PROPOSAL FOR PUBLICATION in PUCT Project 58480 on Oct 17, 2025. | |
| PUCT Project 58480: OPUC NOTICE OF PARTICIPATION LETTERPUCT Project 58480, Item 2 |
Filed · Aug 11, 2025
OPUC
|
OPUC filed OPUC NOTICE OF PARTICIPATION LETTER in PUCT Project 58480 on Aug 11, 2025. | |
| PUCT Project 58480: LCRA AND LCRA TSC COMMENTSPUCT Project 58480, Item 30 |
Filed · Oct 17, 2025
LOWER COLORADO RIVER AUTHORITY AND LCRA TRANSMISSION SERVICES CORPORATION
|
LOWER COLORADO RIVER AUTHORITY AND LCRA TRANSMISSION SERVICES CORPORATION filed LCRA AND LCRA TSC COMMENTS in PUCT Project 58480 on Oct 17, 2025. | |
| PUCT Project 58480: Comments from the City of Red Oak on SB6 Rule Making Project 58480PUCT Project 58480, Item 31 |
Filed · Oct 17, 2025
CITY OF RED OAK
|
CITY OF RED OAK filed Comments from the City of Red Oak on SB6 Rule Making Project 58480 in PUCT Project 58480 on Oct 17, 2025. | |
| PUCT Project 58480: ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S COMMENTS REGARDING PROPOSED 16 TAC § 25.370PUCT Project 58480, Item 32 |
Filed · Oct 17, 2025
ERCOT
|
ERCOT filed ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S COMMENTS REGARDING PROPOSED 16 TAC § 25.370 in PUCT Project 58480 on Oct 17, 2025. | |
| PUCT Project 58480: Texas-New Mexico Power Company’s Public Comments Regarding Staff’s Proposal for Publication of New 16 TAC § 25.370PUCT Project 58480, Item 33 |
Filed · Oct 17, 2025
TEXAS- NEW MEXICO POWER COMPANY
|
TEXAS- NEW MEXICO POWER COMPANY filed Texas-New Mexico Power Company’s Public Comments Regarding Staff’s Proposal for Publication of New 16 TAC § 25.370 in PUCT Project 58480 on Oct 17, 2025. | |
| PUCT Project 58480: Data Center Coalition's CommentsPUCT Project 58480, Item 35 |
Filed · Oct 17, 2025
Data Center Coalition
|
Data Center Coalition filed Data Center Coalition's Comments in PUCT Project 58480 on Oct 17, 2025. | |
| PUCT Project 58480: Sharyland Utilities, L.L.C.'s Initial Comments on the Proposal for Publication of New 16 TAC § 25.370PUCT Project 58480, Item 36 |
Filed · Oct 17, 2025
SHARYLAND UTILITIES, L.L.C.
|
SHARYLAND UTILITIES, L.L.C. filed Sharyland Utilities, L.L.C.'s Initial Comments on the Proposal for Publication of New 16 TAC § 25.370 in PUCT Project 58480 on Oct 17, 2025. | |
| PUCT Project 58480: REPLY COMMENTSPUCT Project 58480, Item 38 |
Filed · Oct 30, 2025
AEP TEXAS INC.
|
AEP TEXAS INC. filed REPLY COMMENTS in PUCT Project 58480 on Oct 30, 2025. | |
| PUCT Project 58480: REPLY COMMENTSPUCT Project 58480, Item 39 |
Filed · Oct 31, 2025
CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC
|
CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC filed REPLY COMMENTS in PUCT Project 58480 on Oct 31, 2025. | |
| PUCT Project 58480: Staff Memo and Notice of 9/2 WorkshopPUCT Project 58480, Item 3 |
Filed · Aug 15, 2025
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Staff Memo and Notice of 9/2 Workshop in PUCT Project 58480 on Aug 15, 2025. | |
| PUCT Project 58480: ONCOR ELECTRIC DELIVERY’S REPLY COMMENTS ON THE PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.370PUCT Project 58480, Item 40 |
Filed · Oct 31, 2025
ONCOR ELECTRIC DELIVERY COMPANY LLC
|
ONCOR ELECTRIC DELIVERY COMPANY LLC filed ONCOR ELECTRIC DELIVERY’S REPLY COMMENTS ON THE PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.370 in PUCT Project 58480 on Oct 31, 2025. | |
| PUCT Project 58480: TCPA REPLY COMMENTS TO THE PFP REGARDING LARGE LOAD FORECASTING CRITERIAPUCT Project 58480, Item 42 |
Filed · Oct 31, 2025
TCPA
|
TCPA filed TCPA REPLY COMMENTS TO THE PFP REGARDING LARGE LOAD FORECASTING CRITERIA in PUCT Project 58480 on Oct 31, 2025. | |
| PUCT Project 58480: Joint Reply Comments of Wind Energy Transmission Texas, LLC; Cross Texas Transmission, LLC; and Lone Start Transmission, LLC on the Proposal for Publication of New 16 TAC § 25.370PUCT Project 58480, Item 43 |
Filed · Oct 31, 2025
WIND ENERGY TRANSMISSION LLC
|
WIND ENERGY TRANSMISSION LLC filed Joint Reply Comments of Wind Energy Transmission Texas, LLC; Cross Texas Transmission, LLC; and Lone Start Transmission, LLC on the Proposal for Publication of New 16 TAC § 25.370 in PUCT Project 58480 on Oct 31, 2025. | |
| PUCT Project 58480: OCSC and TCAP's Reply CommentsPUCT Project 58480, Item 44 |
Filed · Oct 31, 2025
STEERING COMMITTEE OF CITIES SERVED BY ONCOR AND TEXAS COALITION FOR AFFORDABLE POWER
|
STEERING COMMITTEE OF CITIES SERVED BY ONCOR AND TEXAS COALITION FOR AFFORDABLE POWER filed OCSC and TCAP's Reply Comments in PUCT Project 58480 on Oct 31, 2025. | |
| PUCT Project 58480: REPLY COMMENTSPUCT Project 58480, Item 45 |
Filed · Oct 31, 2025
LOWER COLORADO RIVER AUTHORITY AND LCRA TRANSMISSION SERVICES CORPORATION
|
LOWER COLORADO RIVER AUTHORITY AND LCRA TRANSMISSION SERVICES CORPORATION filed REPLY COMMENTS in PUCT Project 58480 on Oct 31, 2025. | |
| PUCT Project 58480: OPUC’S REPLY COMMENTS ON THE PROPOSAL FOR PUBLICATION OF NEW 16 TAC § 25.370PUCT Project 58480, Item 48 |
Filed · Oct 31, 2025
OPUC
|
OPUC filed OPUC’S REPLY COMMENTS ON THE PROPOSAL FOR PUBLICATION OF NEW 16 TAC § 25.370 in PUCT Project 58480 on Oct 31, 2025. | |
| PUCT Project 58480: CRUSOE ENERGY SYSTEMS LLC REPLY COMMENTSPUCT Project 58480, Item 49 |
Filed · Oct 31, 2025
CRUSOE ENERGY SYSTEMS LLC
|
CRUSOE ENERGY SYSTEMS LLC filed CRUSOE ENERGY SYSTEMS LLC REPLY COMMENTS in PUCT Project 58480 on Oct 31, 2025. | |
| PUCT Project 58480: Staff memo, workshop agenda, and discussion draftPUCT Project 58480, Item 4 |
Filed · Aug 25, 2025
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Staff memo, workshop agenda, and discussion draft in PUCT Project 58480 on Aug 25, 2025. | |
| PUCT Project 58480: ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S REPLY COMMENTS REGARDING PROPOSED 16 TAC § 25.370PUCT Project 58480, Item 50 |
Filed · Oct 31, 2025
ERCOT
|
ERCOT filed ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S REPLY COMMENTS REGARDING PROPOSED 16 TAC § 25.370 in PUCT Project 58480 on Oct 31, 2025. | |
| PUCT Project 58480: Eolian L.P.'s Reply Comments on Proposal for PublicationPUCT Project 58480, Item 51 |
Filed · Oct 31, 2025
EOLIAN, L.P.
|
EOLIAN, L.P. filed Eolian L.P.'s Reply Comments on Proposal for Publication in PUCT Project 58480 on Oct 31, 2025. | |
| PUCT Project 58480: Data Center Coalition's Reply CommentsPUCT Project 58480, Item 52 |
Filed · Oct 31, 2025
Data Center Coalition (DCC)
|
Data Center Coalition (DCC) filed Data Center Coalition's Reply Comments in PUCT Project 58480 on Oct 31, 2025. | |
| PUCT Project 58480: OM Item No. 10 - (Staff Recommendation) Order Adopting New §25.370PUCT Project 58480, Item 53 |
Filed · Jan 22, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed OM Item No. 10 - (Staff Recommendation) Order Adopting New §25.370 in PUCT Project 58480 on Jan 22, 2026. | |
| PUCT Project 58480: ERCOT’S PROPOSED COMPLIANCE PLAN FOR INCLUDING LARGE LOADS IN THE LOAD FORECAST FOR THE 2026 REGIONAL TRANSMISSION PLANPUCT Project 58480, Item 54 |
Filed · Jan 22, 2026
ERCOT
|
ERCOT filed ERCOT’S PROPOSED COMPLIANCE PLAN FOR INCLUDING LARGE LOADS IN THE LOAD FORECAST FOR THE 2026 REGIONAL TRANSMISSION PLAN in PUCT Project 58480 on Jan 22, 2026. | |
| PUCT Project 58480: COMMISSIONER HJALTMAN MEMORANDUMPUCT Project 58480, Item 56 |
Filed · Jan 28, 2026
PUC OPDM
|
PUC OPDM filed COMMISSIONER HJALTMAN MEMORANDUM in PUCT Project 58480 on Jan 28, 2026. | |
| PUCT Project 58480: OM Item No. 33 - Staff Memo with Proposed Redline ChangesPUCT Project 58480, Item 57 |
Filed · Feb 4, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed OM Item No. 33 - Staff Memo with Proposed Redline Changes in PUCT Project 58480 on Feb 4, 2026. | |
| PUCT Project 58480: ERCOT PRESENTATION ON SB 6 LOAD FORECASTING PROCESSESPUCT Project 58480, Item 5 |
Filed · Sep 2, 2025
ERCOT
|
ERCOT filed ERCOT PRESENTATION ON SB 6 LOAD FORECASTING PROCESSES in PUCT Project 58480 on Sep 2, 2025. | |
| PUCT Project 58480: OPUC’S INITIAL COMMENTS ON DISCUSSION DRAFT ATTACHMENT B TO COMMISSION STAFF’S MEMORANDUM ON RULEMAKING TO ESTABLISH LARGE LOAD FORECASTING CRITERIAPUCT Project 58480, Item 6 |
Filed · Sep 3, 2025
OPUC
|
OPUC filed OPUC’S INITIAL COMMENTS ON DISCUSSION DRAFT ATTACHMENT B TO COMMISSION STAFF’S MEMORANDUM ON RULEMAKING TO ESTABLISH LARGE LOAD FORECASTING CRITERIA in PUCT Project 58480 on Sep 3, 2025. | |
| PUCT Project 58480: OM Item No. 10 - Staff Memo & PFP w/Oct. 17 Comment DeadlinePUCT Project 58480, Item 7 |
Filed · Sep 12, 2025
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed OM Item No. 10 - Staff Memo & PFP w/Oct. 17 Comment Deadline in PUCT Project 58480 on Sep 12, 2025. | |
| PUCT Project 58480: PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.370PUCT Project 58480, Item 8 |
Filed · Sep 18, 2025
PUC OPDM
|
PUC OPDM filed PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.370 in PUCT Project 58480 on Sep 18, 2025. | |
| PUCT Project 58481: ORDER ADOPTING NEW 16 TAC §25.194PUCT Project 58481, Item 218 |
Filed · Sep 18, 2026
PUC OPDM
|
PUC OPDM filed ORDER ADOPTING NEW 16 TAC §25.194 in PUCT Project 58481 on Sep 18, 2026. | |
| PUCT Project 58479: SATOSHI ENERGY COMMENTS ON STAFF’S DRAFT DISCUSSION RULE § 25.205PUCT Project 58479, Item 10 |
Filed · Sep 10, 2025
SATOSHI ENERGY CORP.
|
SATOSHI ENERGY CORP. filed SATOSHI ENERGY COMMENTS ON STAFF’S DRAFT DISCUSSION RULE § 25.205 in PUCT Project 58479 on Sep 10, 2025. | |
| PUCT Project 58479: OM Item No. 9 - Staff Memo & PFP w/Oct. 17 Comment DeadlinePUCT Project 58479, Item 11 |
Filed · Sep 12, 2025
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed OM Item No. 9 - Staff Memo & PFP w/Oct. 17 Comment Deadline in PUCT Project 58479 on Sep 12, 2025. | |
| PUCT Project 58479: LETTER & PRESENTATION REGARDING ERCOT STUDIES OF PROPOSED NET METERING ARRANGEMENTSPUCT Project 58479, Item 12 |
Filed · Sep 18, 2025
ERCOT
|
ERCOT filed LETTER & PRESENTATION REGARDING ERCOT STUDIES OF PROPOSED NET METERING ARRANGEMENTS in PUCT Project 58479 on Sep 18, 2025. | |
| PUCT Project 58479: PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.205PUCT Project 58479, Item 13 |
Filed · Sep 18, 2025
PUC OPDM
|
PUC OPDM filed PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.205 in PUCT Project 58479 on Sep 18, 2025. | |
| PUCT Project 58479: ERCOT LETTER RE STAND-ALONE GENERATION RESOURCE LIST UPDATEPUCT Project 58479, Item 15 |
Filed · Sep 19, 2025
ERCOT
|
ERCOT filed ERCOT LETTER RE STAND-ALONE GENERATION RESOURCE LIST UPDATE in PUCT Project 58479 on Sep 19, 2025. | |
| PUCT Project 58479: SPLIGHT COMMENTS ON STAFF'S DRAFT DISCUSSION RULE § 25.205PUCT Project 58479, Item 17 |
Filed · Oct 17, 2025
Splight Inc.
|
Splight Inc. filed SPLIGHT COMMENTS ON STAFF'S DRAFT DISCUSSION RULE § 25.205 in PUCT Project 58479 on Oct 17, 2025. | |
| PUCT Project 58479: Request for Control NumberPUCT Project 58479, Item 1 |
Filed · Jul 31, 2025
PUC RULES AND PROJECTS
|
PUC RULES AND PROJECTS filed Request for Control Number in PUCT Project 58479 on Jul 31, 2025. | |
| PUCT Project 58479: VOID SEE ITEM 35PUCT Project 58479, Item 20 |
Filed · Oct 17, 2025
TCPA
|
TCPA filed VOID SEE ITEM 35 in PUCT Project 58479 on Oct 17, 2025. | |
| PUCT Project 58479: Initial Comments of the Texas Advanced Energy Business Alliance on Commission Staff's Draft Rule §25.205PUCT Project 58479, Item 21 |
Filed · Oct 17, 2025
TEXAS ADVANCED ENERGY BUSINESS ALLIANCE
|
TEXAS ADVANCED ENERGY BUSINESS ALLIANCE filed Initial Comments of the Texas Advanced Energy Business Alliance on Commission Staff's Draft Rule §25.205 in PUCT Project 58479 on Oct 17, 2025. | |
| PUCT Project 58479: TEXAS INDUSTRIAL ENERGY CONSUMERS’ PROPOSED COMMENTS TO DRAFT RULE 25.504PUCT Project 58479, Item 22 |
Filed · Oct 17, 2025
TIEC
|
TIEC filed TEXAS INDUSTRIAL ENERGY CONSUMERS’ PROPOSED COMMENTS TO DRAFT RULE 25.504 in PUCT Project 58479 on Oct 17, 2025. | |
| PUCT Project 58479: SATOSHI'S COMMENTS ON STAFF'S PROPOSAL FOR PUBLICATIONPUCT Project 58479, Item 23 |
Filed · Oct 17, 2025
SATOSHI ENERGY CORP.
|
SATOSHI ENERGY CORP. filed SATOSHI'S COMMENTS ON STAFF'S PROPOSAL FOR PUBLICATION in PUCT Project 58479 on Oct 17, 2025. | |
| PUCT Project 58479: EDGECONNEX COMMENTS ON COMMISSION STAFF'S DRAFT RULE 16 TAC § 25.205PUCT Project 58479, Item 24 |
Filed · Oct 17, 2025
EdgeConneX
|
EdgeConneX filed EDGECONNEX COMMENTS ON COMMISSION STAFF'S DRAFT RULE 16 TAC § 25.205 in PUCT Project 58479 on Oct 17, 2025. | |
| PUCT Project 58479: CALPINE CORPORATION’S COMMENTS ON COMMISSION STAFF’S PROPOSAL FOR PUBLICATION OF NEW 16 TAC § 25.205PUCT Project 58479, Item 25 |
Filed · Oct 17, 2025
CALPINE CORPORATION
|
CALPINE CORPORATION filed CALPINE CORPORATION’S COMMENTS ON COMMISSION STAFF’S PROPOSAL FOR PUBLICATION OF NEW 16 TAC § 25.205 in PUCT Project 58479 on Oct 17, 2025. | |
| PUCT Project 58479: ONCOR ELECTRIC DELIVERY’S COMMENTS ON THE PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.205 AND ACCOMPANYING QUESTIONSPUCT Project 58479, Item 26 |
Filed · Oct 17, 2025
ONCOR ELECTRIC DELIVERY COMPANY LLC
|
ONCOR ELECTRIC DELIVERY COMPANY LLC filed ONCOR ELECTRIC DELIVERY’S COMMENTS ON THE PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.205 AND ACCOMPANYING QUESTIONS in PUCT Project 58479 on Oct 17, 2025. | |
| PUCT Project 58479: OFFICE OF PUBLIC UTILITY COUNSEL’S INITIAL COMMENTS ON PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.205PUCT Project 58479, Item 27 |
Filed · Oct 17, 2025
OPUC
|
OPUC filed OFFICE OF PUBLIC UTILITY COUNSEL’S INITIAL COMMENTS ON PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.205 in PUCT Project 58479 on Oct 17, 2025. | |
| PUCT Project 58479: Comments of Texas Electric Cooperatives, Inc.PUCT Project 58479, Item 28 |
Filed · Oct 17, 2025
Texas Electric Cooperatives, Inc.
|
Texas Electric Cooperatives, Inc. filed Comments of Texas Electric Cooperatives, Inc. in PUCT Project 58479 on Oct 17, 2025. | |
| PUCT Project 58479: LCRA RESPONSE TO PFPPUCT Project 58479, Item 29 |
Filed · Oct 17, 2025
LOWER COLORADO RIVER AUTHORITY AND LCRA TRANSMISSION SERVICES CORPORATION
|
LOWER COLORADO RIVER AUTHORITY AND LCRA TRANSMISSION SERVICES CORPORATION filed LCRA RESPONSE TO PFP in PUCT Project 58479 on Oct 17, 2025. | |
| PUCT Project 58479: OPUC NOTICE OF PARTICIPATION LETTERPUCT Project 58479, Item 2 |
Filed · Aug 8, 2025
OPUC
|
OPUC filed OPUC NOTICE OF PARTICIPATION LETTER in PUCT Project 58479 on Aug 8, 2025. | |
| PUCT Project 58479: Vistra Corp.'s CommentsPUCT Project 58479, Item 30 |
Filed · Oct 17, 2025
VISTRA CORP.
|
VISTRA CORP. filed Vistra Corp.'s Comments in PUCT Project 58479 on Oct 17, 2025. | |
| PUCT Project 58479: CORRECTION: RESPONSE TO STAFF QUESTIONS & RECOMMENDATIONS FOR PFPPUCT Project 58479, Item 31 |
Filed · Oct 17, 2025
TCPA
|
TCPA filed CORRECTION: RESPONSE TO STAFF QUESTIONS & RECOMMENDATIONS FOR PFP in PUCT Project 58479 on Oct 17, 2025. | |
| PUCT Project 58479: COMMENTS ON PROPOSAL FOR PUBLICATION OF NEW 16 TAC § 25.505PUCT Project 58479, Item 32 |
Filed · Oct 17, 2025
ELECTRIC TRANSMISSION TEXAS, LLC
|
ELECTRIC TRANSMISSION TEXAS, LLC filed COMMENTS ON PROPOSAL FOR PUBLICATION OF NEW 16 TAC § 25.505 in PUCT Project 58479 on Oct 17, 2025. | |
| PUCT Project 58479: COMMENTS OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLCPUCT Project 58479, Item 33 |
Filed · Oct 17, 2025
CENTERPOINT ENERGY HOUSTON ELECTRIC
|
CENTERPOINT ENERGY HOUSTON ELECTRIC filed COMMENTS OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC in PUCT Project 58479 on Oct 17, 2025. | |
| PUCT Project 58479: AEP TEXAS’ COMMENTS ON PROPOSAL FOR PUBLICATIONPUCT Project 58479, Item 34 |
Filed · Oct 17, 2025
AEP TEXAS INC.
|
AEP TEXAS INC. filed AEP TEXAS’ COMMENTS ON PROPOSAL FOR PUBLICATION in PUCT Project 58479 on Oct 17, 2025. | |
| PUCT Project 58479: REQUEST TO VOID ITEM 20, FILED IN ERRORPUCT Project 58479, Item 35 |
Filed · Oct 17, 2025
TCPA
|
TCPA filed REQUEST TO VOID ITEM 20, FILED IN ERROR in PUCT Project 58479 on Oct 17, 2025. | |
| PUCT Project 58479: ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S RESPONSES TO COMMISSION QUESTIONS AND COMMENTS REGARDING PROPOSED 16 TAC § 25.205PUCT Project 58479, Item 36 |
Filed · Oct 17, 2025
ERCOT
|
ERCOT filed ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S RESPONSES TO COMMISSION QUESTIONS AND COMMENTS REGARDING PROPOSED 16 TAC § 25.205 in PUCT Project 58479 on Oct 17, 2025. | |
| PUCT Project 58479: Eolian, L.P.'s Comments on the Proposal for Publication and Request for HearingPUCT Project 58479, Item 37 |
Filed · Oct 17, 2025
EOLIAN, L.P.
|
EOLIAN, L.P. filed Eolian, L.P.'s Comments on the Proposal for Publication and Request for Hearing in PUCT Project 58479 on Oct 17, 2025. | |
| PUCT Project 58479: Data Center Coalition's CommentsPUCT Project 58479, Item 38 |
Filed · Oct 17, 2025
Data Center Coalition
|
Data Center Coalition filed Data Center Coalition's Comments in PUCT Project 58479 on Oct 17, 2025. | |
| PUCT Project 58479: Texas-New Mexico Power Company’s Comments to Commission Staff’s Questions and Comments on Proposal For PublicationPUCT Project 58479, Item 39 |
Filed · Oct 17, 2025
TEXAS- NEW MEXICO POWER COMPANY
|
TEXAS- NEW MEXICO POWER COMPANY filed Texas-New Mexico Power Company’s Comments to Commission Staff’s Questions and Comments on Proposal For Publication in PUCT Project 58479 on Oct 17, 2025. | |
| PUCT Project 58479: Staff Memo and Notice of 9/2 WorkshopPUCT Project 58479, Item 3 |
Filed · Aug 15, 2025
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Staff Memo and Notice of 9/2 Workshop in PUCT Project 58479 on Aug 15, 2025. | |
| PUCT Project 58479: TCPA Reply CommentsPUCT Project 58479, Item 42 |
Filed · Oct 31, 2025
TCPA
|
TCPA filed TCPA Reply Comments in PUCT Project 58479 on Oct 31, 2025. | |
| PUCT Project 58479: REPLY COMMENTS OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLCPUCT Project 58479, Item 45 |
Filed · Oct 31, 2025
CENTERPOINT ENERGY HOUSTON ELECTRIC
|
CENTERPOINT ENERGY HOUSTON ELECTRIC filed REPLY COMMENTS OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC in PUCT Project 58479 on Oct 31, 2025. | |
| PUCT Project 58479: ONCOR ELECTRIC DELIVERY’S REPLY COMMENTS ON THE PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.205 AND ACCOMPANYING QUESTIONSPUCT Project 58479, Item 46 |
Filed · Oct 31, 2025
ONCOR ELECTRIC DELIVERY COMPANY LLC
|
ONCOR ELECTRIC DELIVERY COMPANY LLC filed ONCOR ELECTRIC DELIVERY’S REPLY COMMENTS ON THE PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.205 AND ACCOMPANYING QUESTIONS in PUCT Project 58479 on Oct 31, 2025. | |
| PUCT Project 58479: Vistra Reply CommentsPUCT Project 58479, Item 47 |
Filed · Oct 31, 2025
VISTRA CORP.
|
VISTRA CORP. filed Vistra Reply Comments in PUCT Project 58479 on Oct 31, 2025. | |
| PUCT Project 58479: Comments of Texas Electric Cooperatives, Inc.PUCT Project 58479, Item 49 |
Filed · Oct 31, 2025
TEXAS ELECTRIC COOPERATIVES, INC.
|
TEXAS ELECTRIC COOPERATIVES, INC. filed Comments of Texas Electric Cooperatives, Inc. in PUCT Project 58479 on Oct 31, 2025. | |
| PUCT Project 58479: Staff memo, workshop agenda, and discussion draftPUCT Project 58479, Item 4 |
Filed · Aug 25, 2025
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Staff memo, workshop agenda, and discussion draft in PUCT Project 58479 on Aug 25, 2025. | |
| PUCT Project 58479: CALPINE CORPORATION’S REPLY COMMENTS ON COMMISSION STAFF’S PROPOSAL FOR PUBLICATION OF NEW 16 TAC § 25.205PUCT Project 58479, Item 52 |
Filed · Oct 31, 2025
CALPINE CORPORATION
|
CALPINE CORPORATION filed CALPINE CORPORATION’S REPLY COMMENTS ON COMMISSION STAFF’S PROPOSAL FOR PUBLICATION OF NEW 16 TAC § 25.205 in PUCT Project 58479 on Oct 31, 2025. | |
| PUCT Project 58479: CRUSOE ENERGY SYSTEMS LLC REPLY COMMENTSPUCT Project 58479, Item 54 |
Filed · Oct 31, 2025
CRUSOE ENERGY SYSTEMS LLC
|
CRUSOE ENERGY SYSTEMS LLC filed CRUSOE ENERGY SYSTEMS LLC REPLY COMMENTS in PUCT Project 58479 on Oct 31, 2025. | |
| PUCT Project 58479: ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S REPLY COMMENTS REGARDING PROPOSED 16 TAC § 25.205PUCT Project 58479, Item 55 |
Filed · Oct 31, 2025
ERCOT
|
ERCOT filed ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S REPLY COMMENTS REGARDING PROPOSED 16 TAC § 25.205 in PUCT Project 58479 on Oct 31, 2025. | |
| PUCT Project 58479: Texas-New Mexico Power Company’s Reply Comments Regarding Proposal for PublicationPUCT Project 58479, Item 56 |
Filed · Oct 31, 2025
TEXAS NEW MEXICO POWER COMPANY
|
TEXAS NEW MEXICO POWER COMPANY filed Texas-New Mexico Power Company’s Reply Comments Regarding Proposal for Publication in PUCT Project 58479 on Oct 31, 2025. | |
| PUCT Project 58479: OPUC’S REPLY COMMENTS ON PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.205PUCT Project 58479, Item 57 |
Filed · Oct 31, 2025
OPUC
|
OPUC filed OPUC’S REPLY COMMENTS ON PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.205 in PUCT Project 58479 on Oct 31, 2025. | |
| PUCT Project 58479: ENCHANTED ROCK, LLC REPLY COMMENTS ON PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.205PUCT Project 58479, Item 58 |
Filed · Oct 31, 2025
ENCHANTED ROCK, LLC
|
ENCHANTED ROCK, LLC filed ENCHANTED ROCK, LLC REPLY COMMENTS ON PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.205 in PUCT Project 58479 on Oct 31, 2025. | |
| PUCT Project 58479: Eolian's Reply Comments on Proposal for PublicationPUCT Project 58479, Item 59 |
Filed · Oct 31, 2025
EOLIAN, L.P.
|
EOLIAN, L.P. filed Eolian's Reply Comments on Proposal for Publication in PUCT Project 58479 on Oct 31, 2025. | |
| PUCT Project 58479: ERCOT LETTER RE NET METERING STUDY DETAILSPUCT Project 58479, Item 5 |
Filed · Sep 2, 2025
ERCOT
|
ERCOT filed ERCOT LETTER RE NET METERING STUDY DETAILS in PUCT Project 58479 on Sep 2, 2025. | |
| PUCT Project 58479: Data Center Coalition's Reply CommentsPUCT Project 58479, Item 60 |
Filed · Oct 31, 2025
Data Center Coalition (DCC)
|
Data Center Coalition (DCC) filed Data Center Coalition's Reply Comments in PUCT Project 58479 on Oct 31, 2025. | |
| PUCT Project 58479: OM Item No. 26 - (Staff Recommendation) Order Adopting New §25.205PUCT Project 58479, Item 62 |
Filed · Feb 13, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed OM Item No. 26 - (Staff Recommendation) Order Adopting New §25.205 in PUCT Project 58479 on Feb 13, 2026. | |
| PUCT Project 58479: OM Item No. 43 - Staff Memo with Proposed Redline ChangesPUCT Project 58479, Item 63 |
Filed · Mar 5, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed OM Item No. 43 - Staff Memo with Proposed Redline Changes in PUCT Project 58479 on Mar 5, 2026. | |
| PUCT Project 58479: CHAIRMAN GLEESON MEMORANDUMPUCT Project 58479, Item 64 |
Filed · Mar 11, 2026
PUC OPDM
|
PUC OPDM filed CHAIRMAN GLEESON MEMORANDUM in PUCT Project 58479 on Mar 11, 2026. | |
| PUCT Project 58479: Vistra Corp.'s Comments on Planning Guide Revision Request 145PUCT Project 58479, Item 65 |
Filed · Mar 20, 2026
VISTRA CORP.
|
VISTRA CORP. filed Vistra Corp.'s Comments on Planning Guide Revision Request 145 in PUCT Project 58479 on Mar 20, 2026. | |
| PUCT Project 58479: ORDER ADOPTING NEW 16 TAC §25.205PUCT Project 58479, Item 66 |
Filed · Mar 26, 2026
PUC OPDM
|
PUC OPDM filed ORDER ADOPTING NEW 16 TAC §25.205 in PUCT Project 58479 on Mar 26, 2026. | |
| PUCT Project 58479: Texas Register Acknowledgement of Receipt-Proposal for AdoptionPUCT Project 58479, Item 67 |
Filed · Mar 26, 2026
RULES & PROJECTS
|
RULES & PROJECTS filed Texas Register Acknowledgement of Receipt-Proposal for Adoption in PUCT Project 58479 on Mar 26, 2026. | |
| PUCT Project 58479: ERCOT PRESENTATION ON SB6 NET METERING ARRANGEMENT REVIEW PROCESSPUCT Project 58479, Item 6 |
Filed · Sep 2, 2025
ERCOT
|
ERCOT filed ERCOT PRESENTATION ON SB6 NET METERING ARRANGEMENT REVIEW PROCESS in PUCT Project 58479 on Sep 2, 2025. | |
| PUCT Project 58479: ONCOR'S COMMENTS ON STRANDED/UNDERUTILIZED ASSET COST TREATMENTPUCT Project 58479, Item 7 |
Filed · Sep 4, 2025
ONCOR ELECTRIC DELIVERY COMPANY LLC
|
ONCOR ELECTRIC DELIVERY COMPANY LLC filed ONCOR'S COMMENTS ON STRANDED/UNDERUTILIZED ASSET COST TREATMENT in PUCT Project 58479 on Sep 4, 2025. | |
| PUCT Project 58479: OPUC’S INITIAL COMMENTS ON DISCUSSION DRAFT ATTACHMENT B TO COMMISSION STAFF’S MEMORANDUM ON RULEMAKING FOR NET METERING ARRANGEMENTS INVOLVING A LARGE LOAD CO-LOCATED WITH AN EXISTING GENERATION RESOURCEPUCT Project 58479, Item 8 |
Filed · Sep 4, 2025
OPUC
|
OPUC filed OPUC’S INITIAL COMMENTS ON DISCUSSION DRAFT ATTACHMENT B TO COMMISSION STAFF’S MEMORANDUM ON RULEMAKING FOR NET METERING ARRANGEMENTS INVOLVING A LARGE LOAD CO-LOCATED WITH AN EXISTING GENERATION RESOURCE in PUCT Project 58479 on Sep 4, 2025. | |
| PUCT Project 58479: Crusoe's Comments on Staff's Draft Discussion Rule § 25.205PUCT Project 58479, Item 9 |
Filed · Sep 5, 2025
Crusoe Energy Systems, Inc.
|
Crusoe Energy Systems, Inc. filed Crusoe's Comments on Staff's Draft Discussion Rule § 25.205 in PUCT Project 58479 on Sep 5, 2025. | |
| PUCT Project 58480: ORDER ADOPTING NEW 16 TAC § 25.370PUCT Project 58480, Item 58 |
Filed · Feb 6, 2026
PUC OPDM
|
PUC OPDM filed ORDER ADOPTING NEW 16 TAC § 25.370 in PUCT Project 58480 on Feb 6, 2026. | |
| PUCT Project 58480: Texas Register Acknowledgement of Receipt-Proposal for AdoptionPUCT Project 58480, Item 59 |
Filed · Feb 9, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Texas Register Acknowledgement of Receipt-Proposal for Adoption in PUCT Project 58480 on Feb 9, 2026. | |
| PUCT Project 58482: Request for Control NumberPUCT Project 58482, Item 1 |
Filed · Aug 1, 2025
PUC RULES AND PROJECTS
|
PUC RULES AND PROJECTS filed Request for Control Number in PUCT Project 58482 on Aug 1, 2025. | |
| PUCT Project 58482: Staff Memo_Restyle RequestPUCT Project 58482, Item 2 |
Filed · Mar 23, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Staff Memo_Restyle Request in PUCT Project 58482 on Mar 23, 2026. | |
| PUCT Project 58482: Staff Memo and Questions for Comment w/April 8 DeadlinePUCT Project 58482, Item 3 |
Filed · Mar 23, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Staff Memo and Questions for Comment w/April 8 Deadline in PUCT Project 58482 on Mar 23, 2026. | |
| PUCT Project 58482: OPUC NOTICE OF PARTICIPATION LETTERPUCT Project 58482, Item 4 |
Filed · Mar 24, 2026
OPUC
|
OPUC filed OPUC NOTICE OF PARTICIPATION LETTER in PUCT Project 58482 on Mar 24, 2026. | |
| PUCT Project 58482: DCC Comments Regarding the Large Load Demand Management ServicePUCT Project 58482, Item 10 |
Filed · Apr 8, 2026
Data Center Coalition
|
Data Center Coalition filed DCC Comments Regarding the Large Load Demand Management Service in PUCT Project 58482 on Apr 8, 2026. | |
| PUCT Project 58482: RESPONSE TO QUESTIONS FOR COMMENTPUCT Project 58482, Item 11 |
Filed · Apr 8, 2026
LOWER COLORADO RIVER AUTHORITY
|
LOWER COLORADO RIVER AUTHORITY filed RESPONSE TO QUESTIONS FOR COMMENT in PUCT Project 58482 on Apr 8, 2026. | |
| PUCT Project 58482: RESPONSES OF TEXAS ELECTRIC COOPERATIVES, INC.PUCT Project 58482, Item 13 |
Filed · Apr 8, 2026
TEXAS ELECTRIC COOPERATIVES, INC.
|
TEXAS ELECTRIC COOPERATIVES, INC. filed RESPONSES OF TEXAS ELECTRIC COOPERATIVES, INC. in PUCT Project 58482 on Apr 8, 2026. | |
| PUCT Project 58482: NRG Energy, Inc.'s Comments in Response to Staff's QuestionsPUCT Project 58482, Item 14 |
Filed · Apr 8, 2026
NRG ENERGY, INC.
|
NRG ENERGY, INC. filed NRG Energy, Inc.'s Comments in Response to Staff's Questions in PUCT Project 58482 on Apr 8, 2026. | |
| PUCT Project 58482: VOLTUS RESPONSE TO PUCT STAFF'S QUESTIONS ON PROPOSED LARGE LOAD DEMAND MANAGEMENT SERVICEPUCT Project 58482, Item 15 |
Filed · Apr 8, 2026
Voltus Inc.
|
Voltus Inc. filed VOLTUS RESPONSE TO PUCT STAFF'S QUESTIONS ON PROPOSED LARGE LOAD DEMAND MANAGEMENT SERVICE in PUCT Project 58482 on Apr 8, 2026. | |
| PUCT Project 58482: Texas Energy Buyers Alliance Response to Commission Staff QuestionsPUCT Project 58482, Item 16 |
Filed · Apr 8, 2026
TEXAS ENERGY BUYERS ALLIANCE
|
TEXAS ENERGY BUYERS ALLIANCE filed Texas Energy Buyers Alliance Response to Commission Staff Questions in PUCT Project 58482 on Apr 8, 2026. | |
| PUCT Project 58482: ONCOR ELECTRIC DELIVERY’S RESPONSE TO COMMISSION STAFF’S FIRST SET OF QUESTIONS FOR COMMENTSPUCT Project 58482, Item 18 |
Filed · Apr 8, 2026
ONCOR ELECTRIC DELIVERY COMPANY LLC
|
ONCOR ELECTRIC DELIVERY COMPANY LLC filed ONCOR ELECTRIC DELIVERY’S RESPONSE TO COMMISSION STAFF’S FIRST SET OF QUESTIONS FOR COMMENTS in PUCT Project 58482 on Apr 8, 2026. | |
| PUCT Project 58482: Enchanted Rock, LLC's Comments to Commission Staff's March 23 Memo and Questions for CommentPUCT Project 58482, Item 20 |
Filed · Apr 8, 2026
ENCHANTED ROCK, LLC
|
ENCHANTED ROCK, LLC filed Enchanted Rock, LLC's Comments to Commission Staff's March 23 Memo and Questions for Comment in PUCT Project 58482 on Apr 8, 2026. | |
| PUCT Project 58482: AEP Texas Inc.’s Responses to Commission Staff’s Memo and Questions for CommentPUCT Project 58482, Item 21 |
Filed · Apr 8, 2026
AEP TEXAS INC.
|
AEP TEXAS INC. filed AEP Texas Inc.’s Responses to Commission Staff’s Memo and Questions for Comment in PUCT Project 58482 on Apr 8, 2026. | |
| PUCT Project 58482: ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S RESPONSE TO COMMISSION STAFF’S LIST OF QUESTIONSPUCT Project 58482, Item 22 |
Filed · Apr 8, 2026
ERCOT
|
ERCOT filed ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S RESPONSE TO COMMISSION STAFF’S LIST OF QUESTIONS in PUCT Project 58482 on Apr 8, 2026. | |
| PUCT Project 58482: Vistra Corporate Services Company's Comments in Response to Commission Staff's QuestionsPUCT Project 58482, Item 23 |
Filed · Apr 8, 2026
VISTRA CORPORATE SERVICES COMPANY
|
VISTRA CORPORATE SERVICES COMPANY filed Vistra Corporate Services Company's Comments in Response to Commission Staff's Questions in PUCT Project 58482 on Apr 8, 2026. | |
| PUCT Project 58482: EOLIAN, L.P.'s Comments to Commission Staff's March 23, 2026 Memo and Questions for CommentPUCT Project 58482, Item 24 |
Filed · Apr 8, 2026
EOLIAN, L.P.
|
EOLIAN, L.P. filed EOLIAN, L.P.'s Comments to Commission Staff's March 23, 2026 Memo and Questions for Comment in PUCT Project 58482 on Apr 8, 2026. | |
| PUCT Project 58482: CyrusOne, LP Comments in Response to Commission Staff's QuestionsPUCT Project 58482, Item 25 |
Filed · Apr 8, 2026
CyrusOne, LP
|
CyrusOne, LP filed CyrusOne, LP Comments in Response to Commission Staff's Questions in PUCT Project 58482 on Apr 8, 2026. | |
| PUCT Project 58482: Public Comments in Response to Staff's Questions for Comment - Project No. 58482PUCT Project 58482, Item 28 |
Filed · Jul 16, 2026
Fedor Mikheev | Texas A&M University Energy Institute
|
Fedor Mikheev | Texas A&M University Energy Institute filed Public Comments in Response to Staff's Questions for Comment - Project No. 58482 in PUCT Project 58482 on Jul 16, 2026. | |
| PUCT Project 58482: OM Item No. 29 - Staff Memo & PFP w/Sept. 4 Comment DeadlinePUCT Project 58482, Item 29 |
Filed · Jul 24, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed OM Item No. 29 - Staff Memo & PFP w/Sept. 4 Comment Deadline in PUCT Project 58482 on Jul 24, 2026. | |
| PUCT Project 58482: PROPOSAL FOR PUBLICATION NEW §25.521PUCT Project 58482, Item 30 |
Filed · Jul 30, 2026
PUC OPDM
|
PUC OPDM filed PROPOSAL FOR PUBLICATION NEW §25.521 in PUCT Project 58482 on Jul 30, 2026. | |
| PUCT Project 58482: Texas Register Acknowledgement of Receipt - Comment Deadline 09/04/2026PUCT Project 58482, Item 31 |
Filed · Jul 30, 2026
RULES & PROJECTS
|
RULES & PROJECTS filed Texas Register Acknowledgement of Receipt - Comment Deadline 09/04/2026 in PUCT Project 58482 on Jul 30, 2026. | |
| PUCT Project 58482: Objection to rule changePUCT Project 58482, Item 33 |
Filed · Aug 3, 2026
Helen Bryant
|
Helen Bryant filed Objection to rule change in PUCT Project 58482 on Aug 3, 2026. | |
| PUCT Project 58482: ERCOT Steel Mills Comments_Project 58482_4.8.2026PUCT Project 58482, Item 6 |
Filed · Apr 8, 2026
ERCOT STEEL MILLS
|
ERCOT STEEL MILLS filed ERCOT Steel Mills Comments_Project 58482_4.8.2026 in PUCT Project 58482 on Apr 8, 2026. | |
| PUCT Project 58482: TCPA’S RESPONSES TO STAFF’S QUESTIONS REGARDING THE LARGE LOAD DEMAND MANAGEMENT SERVICEPUCT Project 58482, Item 7 |
Filed · Apr 8, 2026
TCPA
|
TCPA filed TCPA’S RESPONSES TO STAFF’S QUESTIONS REGARDING THE LARGE LOAD DEMAND MANAGEMENT SERVICE in PUCT Project 58482 on Apr 8, 2026. | |
| PUCT Project 58482: Texas Public Power Association (TPPA) Response to Questions for CommentPUCT Project 58482, Item 9 |
Filed · Apr 8, 2026
TPPA
|
TPPA filed Texas Public Power Association (TPPA) Response to Questions for Comment in PUCT Project 58482 on Apr 8, 2026. | |
| PUCT Project 58484: CPS Energy's Response to Questions for CommentPUCT Project 58484, Item 10 |
Filed · Sep 9, 2025
CPS ENERGY
|
CPS ENERGY filed CPS Energy's Response to Questions for Comment in PUCT Project 58484 on Sep 9, 2025. | |
| PUCT Project 58484: TCPA Response to Staff QuestionsPUCT Project 58484, Item 11 |
Filed · Sep 9, 2025
TCPA
|
TCPA filed TCPA Response to Staff Questions in PUCT Project 58484 on Sep 9, 2025. | |
| PUCT Project 58484: Texas Public Policy Foundation's Response to PUC Staff Questions for CommentPUCT Project 58484, Item 12 |
Filed · Sep 9, 2025
Texas Public Policy Foundation
|
Texas Public Policy Foundation filed Texas Public Policy Foundation's Response to PUC Staff Questions for Comment in PUCT Project 58484 on Sep 9, 2025. | |
| PUCT Project 58484: Sharyland Utilities LLC's Initial Comments to Commission Staff's Questions for CommentPUCT Project 58484, Item 13 |
Filed · Sep 9, 2025
SHARYLAND UTILITIES LLC
|
SHARYLAND UTILITIES LLC filed Sharyland Utilities LLC's Initial Comments to Commission Staff's Questions for Comment in PUCT Project 58484 on Sep 9, 2025. | |
| PUCT Project 58484: Comments of NRG Energy, Inc. in Response to Staff's August 5, 2025, QuestionsPUCT Project 58484, Item 14 |
Filed · Sep 9, 2025
NRG ENERGY, INC.
|
NRG ENERGY, INC. filed Comments of NRG Energy, Inc. in Response to Staff's August 5, 2025, Questions in PUCT Project 58484 on Sep 9, 2025. | |
| PUCT Project 58484: TEXAS ADVANCED ENERGY BUSINESS ALLIANCE RESPONSES TO COMMISSION STAFF QUESTIONS AUG. 5 2025PUCT Project 58484, Item 17 |
Filed · Sep 9, 2025
TEXAS ADVANCED ENERGY BUSINESS ALLIANCE
|
TEXAS ADVANCED ENERGY BUSINESS ALLIANCE filed TEXAS ADVANCED ENERGY BUSINESS ALLIANCE RESPONSES TO COMMISSION STAFF QUESTIONS AUG. 5 2025 in PUCT Project 58484 on Sep 9, 2025. | |
| PUCT Project 58484: Texas Public Power Association (TPPA) Comments on Transmission Cost Recovery Questions for CommentPUCT Project 58484, Item 18 |
Filed · Sep 9, 2025
TPPA
|
TPPA filed Texas Public Power Association (TPPA) Comments on Transmission Cost Recovery Questions for Comment in PUCT Project 58484 on Sep 9, 2025. | |
| PUCT Project 58484: LCRA AND LCRA TRANSMISSION SERVICES CORPORATION'S RESPONSE TO QUESTIONS FOR COMMENTPUCT Project 58484, Item 19 |
Filed · Sep 9, 2025
LCRA AND LCRA TRANSMISSION SERVICES CORPORATION
|
LCRA AND LCRA TRANSMISSION SERVICES CORPORATION filed LCRA AND LCRA TRANSMISSION SERVICES CORPORATION'S RESPONSE TO QUESTIONS FOR COMMENT in PUCT Project 58484 on Sep 9, 2025. | |
| PUCT Project 58484: Request for Control NumberPUCT Project 58484, Item 1 |
Filed · Aug 1, 2025
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Request for Control Number in PUCT Project 58484 on Aug 1, 2025. | |
| PUCT Project 58484: Joint Comments of Wind Energy Transmission Texas, LLC; Lone Star Transmission Texas, LLC; and Cross Texas Transmission, LLC in Response to Commission Staff’s Request for CommentsPUCT Project 58484, Item 20 |
Filed · Sep 9, 2025
Wind Energy Transmission Texas, LLC; Lone Star Transmission Texas, LLC; and Cross Texas Transmission, LLC
|
Wind Energy Transmission Texas, LLC; Lone Star Transmission Texas, LLC; and Cross Texas Transmission, LLC filed Joint Comments of Wind Energy Transmission Texas, LLC; Lone Star Transmission Texas, LLC; and Cross Texas Transmission, LLC in Response to Commission Staff’s Request for Comments in PUCT Project 58484 on Sep 9, 2025. | |
| PUCT Project 58484: AEP COMPANIES’ COMMENTS ON QUESTIONS FOR PUBLIC COMMENTPUCT Project 58484, Item 21 |
Filed · Sep 9, 2025
AEP COMPANIES
|
AEP COMPANIES filed AEP COMPANIES’ COMMENTS ON QUESTIONS FOR PUBLIC COMMENT in PUCT Project 58484 on Sep 9, 2025. | |
| PUCT Project 58484: OPUC’S INITIAL COMMENTS ON QUESTIONS FOR PUBLIC COMMENT RELATING TO THE EVALUATION OF TRANSMISSION COST RECOVERYPUCT Project 58484, Item 23 |
Filed · Sep 9, 2025
OPUC
|
OPUC filed OPUC’S INITIAL COMMENTS ON QUESTIONS FOR PUBLIC COMMENT RELATING TO THE EVALUATION OF TRANSMISSION COST RECOVERY in PUCT Project 58484 on Sep 9, 2025. | |
| PUCT Project 58484: ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S RESPONSES TO STAFF QUESTIONSPUCT Project 58484, Item 24 |
Filed · Sep 9, 2025
ERCOT
|
ERCOT filed ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S RESPONSES TO STAFF QUESTIONS in PUCT Project 58484 on Sep 9, 2025. | |
| PUCT Project 58484: CenterPoint Energy Houston Electric, LLC’s Responses to Commission Staff’s Request for CommentsPUCT Project 58484, Item 26 |
Filed · Sep 9, 2025
CENTERPOINT ENERGY HOUSTON ELECTRIC
|
CENTERPOINT ENERGY HOUSTON ELECTRIC filed CenterPoint Energy Houston Electric, LLC’s Responses to Commission Staff’s Request for Comments in PUCT Project 58484 on Sep 9, 2025. | |
| PUCT Project 58484: Staff Memo and First Set of Questions for CommentPUCT Project 58484, Item 2 |
Filed · Aug 5, 2025
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Staff Memo and First Set of Questions for Comment in PUCT Project 58484 on Aug 5, 2025. | |
| PUCT Project 58484: OPUC NOTICE OF PARTICIPATION LETTERPUCT Project 58484, Item 3 |
Filed · Aug 8, 2025
OPUC
|
OPUC filed OPUC NOTICE OF PARTICIPATION LETTER in PUCT Project 58484 on Aug 8, 2025. | |
| PUCT Project 58484: ONCOR ELECTRIC DELIVERY'S RESPONSE TO COMMISSION STAFF'S FIRST SET OF QUESTIONS FOR COMMENTSPUCT Project 58484, Item 5 |
Filed · Sep 9, 2025
ONCOR ELECTRIC DELIVERY COMPANY LLC
|
ONCOR ELECTRIC DELIVERY COMPANY LLC filed ONCOR ELECTRIC DELIVERY'S RESPONSE TO COMMISSION STAFF'S FIRST SET OF QUESTIONS FOR COMMENTS in PUCT Project 58484 on Sep 9, 2025. | |
| PUCT Project 58484: ERCOT Steel Mills' Response to PUC Staff's Initial Request for Comments on Transmission Cost RecoveryPUCT Project 58484, Item 6 |
Filed · Sep 9, 2025
ERCOT STEEL MILLS
|
ERCOT STEEL MILLS filed ERCOT Steel Mills' Response to PUC Staff's Initial Request for Comments on Transmission Cost Recovery in PUCT Project 58484 on Sep 9, 2025. | |
| PUCT Project 58484: RESPONSES OF TEXAS ELECTRIC COOPERATIVES, INC.PUCT Project 58484, Item 7 |
Filed · Sep 9, 2025
TEXAS ELECTRIC COOPERATIVES, INC.
|
TEXAS ELECTRIC COOPERATIVES, INC. filed RESPONSES OF TEXAS ELECTRIC COOPERATIVES, INC. in PUCT Project 58484 on Sep 9, 2025. | |
| PUCT Project 58484: Joint Responses to Staff Questions of H-E-B and STECPUCT Project 58484, Item 8 |
Filed · Sep 9, 2025
H-E-B, LP and South Texas Electric Cooperative, Inc.
|
H-E-B, LP and South Texas Electric Cooperative, Inc. filed Joint Responses to Staff Questions of H-E-B and STEC in PUCT Project 58484 on Sep 9, 2025. | |
| PUCT Project 58484: Steering Committee of Cities Served by Oncor and Texas Coalition for Affordable Power's Responses to Commission Staff's First Set of Questions for CommentPUCT Project 58484, Item 9 |
Filed · Sep 9, 2025
STEERING COMMITTEE OF CITIES SERVED BY ONCOR AND TEXAS COALITION FOR AFFORDABLE POWER
|
STEERING COMMITTEE OF CITIES SERVED BY ONCOR AND TEXAS COALITION FOR AFFORDABLE POWER filed Steering Committee of Cities Served by Oncor and Texas Coalition for Affordable Power's Responses to Commission Staff's First Set of Questions for Comment in PUCT Project 58484 on Sep 9, 2025. | |
| PUCT Project 54445: NOTICE OF RECOMMENDED APPROVAL OF REVISION REQUESTS BY ERCOT BOARD OF DIRECTORSPUCT Project 54445, Item 164 |
Filed · Sep 21, 2026
ERCOT
|
ERCOT filed NOTICE OF RECOMMENDED APPROVAL OF REVISION REQUESTS BY ERCOT BOARD OF DIRECTORS in PUCT Project 54445 on Sep 21, 2026. | |
| PUCT Project 58484: Texas REP Coalition Response to PUC Staff Request for CommentsPUCT Project 58484, Item 100 |
Filed · Apr 13, 2026
TEXAS REP COALITION
|
TEXAS REP COALITION filed Texas REP Coalition Response to PUC Staff Request for Comments in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 58484: RWE Americas, LLC's Comments to Commission Staff's Draft RecommendationsPUCT Project 58484, Item 102 |
Filed · Apr 13, 2026
RWE Americas, LLC
|
RWE Americas, LLC filed RWE Americas, LLC's Comments to Commission Staff's Draft Recommendations in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 58484: Vistra's Third Set of Comments in Response to Staff's Second Set of QuestionsPUCT Project 58484, Item 103 |
Filed · Apr 13, 2026
VISTRA CORPORATE SERVICES COMPANY
|
VISTRA CORPORATE SERVICES COMPANY filed Vistra's Third Set of Comments in Response to Staff's Second Set of Questions in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 58484: ONCOR ELECTRIC DELIVERY'S COMMENTS ON COMMISSION STAFF'S DRAFT SET OF RECOMMENDATIONSPUCT Project 58484, Item 105 |
Filed · Apr 13, 2026
ONCOR ELECTRIC DELIVERY COMPANY LLC
|
ONCOR ELECTRIC DELIVERY COMPANY LLC filed ONCOR ELECTRIC DELIVERY'S COMMENTS ON COMMISSION STAFF'S DRAFT SET OF RECOMMENDATIONS in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 58484: CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC’S RESPONSES TO COMMISSON STAFF’S REQUEST FOR COMMENTSPUCT Project 58484, Item 106 |
Filed · Apr 13, 2026
CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC
|
CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC filed CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC’S RESPONSES TO COMMISSON STAFF’S REQUEST FOR COMMENTS in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 58484: VOID SEE ITEM 114PUCT Project 58484, Item 107 |
Filed · Apr 13, 2026
OPUC
|
OPUC filed VOID SEE ITEM 114 in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 58484: AEP COMPANIES’ RESPONSE TO COMMISSION STAFF’S DRAFT REPORTPUCT Project 58484, Item 108 |
Filed · Apr 13, 2026
AEP COMPANIES
|
AEP COMPANIES filed AEP COMPANIES’ RESPONSE TO COMMISSION STAFF’S DRAFT REPORT in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 58484: Crusoe Technologies LLC's Responses to Staff's Request for Comments on Draft RecommendationsPUCT Project 58484, Item 110 |
Filed · Apr 13, 2026
Crusoe Technologies LLC
|
Crusoe Technologies LLC filed Crusoe Technologies LLC's Responses to Staff's Request for Comments on Draft Recommendations in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 58484: TEBA Comments on Commission Staff's Draft RecommendationsPUCT Project 58484, Item 111 |
Filed · Apr 13, 2026
TEXAS ENERGY BUYERS ALLIANCE
|
TEXAS ENERGY BUYERS ALLIANCE filed TEBA Comments on Commission Staff's Draft Recommendations in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 58484: Eolian, L.P.'s Response to Commission Staff's RecommendationsPUCT Project 58484, Item 112 |
Filed · Apr 13, 2026
EOLIAN, L.P.
|
EOLIAN, L.P. filed Eolian, L.P.'s Response to Commission Staff's Recommendations in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 58484: Joint Comments of Google LLC and Lancium LLC to PUC Staff Memo and Draft Report in 58484PUCT Project 58484, Item 113 |
Filed · Apr 13, 2026
GOOGLE LLC, LANCIUM LLC
|
GOOGLE LLC, LANCIUM LLC filed Joint Comments of Google LLC and Lancium LLC to PUC Staff Memo and Draft Report in 58484 in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 58484: PEC Responses to Commission Staff’s Request for CommentsPUCT Project 58484, Item 27 |
Filed · Sep 9, 2025
PEDERNALES ELECTRIC COOPERATIVE, INC
|
PEDERNALES ELECTRIC COOPERATIVE, INC filed PEC Responses to Commission Staff’s Request for Comments in PUCT Project 58484 on Sep 9, 2025. | |
| PUCT Project 58484: Vistra CommentsPUCT Project 58484, Item 29 |
Filed · Sep 9, 2025
VISTRA CORPORATE SERVICES COMPANY LLC
|
VISTRA CORPORATE SERVICES COMPANY LLC filed Vistra Comments in PUCT Project 58484 on Sep 9, 2025. | |
| PUCT Project 58484: Staff's Request for Information to TDUs w/11.14 Response DeadlinePUCT Project 58484, Item 35 |
Filed · Oct 17, 2025
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Staff's Request for Information to TDUs w/11.14 Response Deadline in PUCT Project 58484 on Oct 17, 2025. | |
| PUCT Project 58484: Staff Memo & Notice of 11/10 WorkshopPUCT Project 58484, Item 36 |
Filed · Oct 21, 2025
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Staff Memo & Notice of 11/10 Workshop in PUCT Project 58484 on Oct 21, 2025. | |
| PUCT Project 58484: Staff Memo & Nov. 10 Workshop Agenda w/Nov. 21 Written Comment DeadlinePUCT Project 58484, Item 37 |
Filed · Oct 28, 2025
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Staff Memo & Nov. 10 Workshop Agenda w/Nov. 21 Written Comment Deadline in PUCT Project 58484 on Oct 28, 2025. | |
| PUCT Project 58484: Staff Memo Extending Comment Deadline to 11/25PUCT Project 58484, Item 38 |
Filed · Oct 31, 2025
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Staff Memo Extending Comment Deadline to 11/25 in PUCT Project 58484 on Oct 31, 2025. | |
| PUCT Project 58484: RESPONSE TO COMMISSION STAFF’S REQUEST FOR INFORMATION ISSUED ON OCTOBER 17, 2025 RELATED TO WHOLESALE TRANSMISSION SERVICE CHARGESPUCT Project 58484, Item 39 |
Filed · Nov 12, 2025
AEP TEXAS INC.
|
AEP TEXAS INC. filed RESPONSE TO COMMISSION STAFF’S REQUEST FOR INFORMATION ISSUED ON OCTOBER 17, 2025 RELATED TO WHOLESALE TRANSMISSION SERVICE CHARGES in PUCT Project 58484 on Nov 12, 2025. | |
| PUCT Project 58484: TNMP Response to Staff Request for InformationPUCT Project 58484, Item 40 |
Filed · Nov 13, 2025
TEXAS-NEW MEXICO POWER COMPANY
|
TEXAS-NEW MEXICO POWER COMPANY filed TNMP Response to Staff Request for Information in PUCT Project 58484 on Nov 13, 2025. | |
| PUCT Project 58484: VOID SEE ITEM 44PUCT Project 58484, Item 41 |
Filed · Nov 14, 2025
CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC
|
CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC filed VOID SEE ITEM 44 in PUCT Project 58484 on Nov 14, 2025. | |
| PUCT Project 58484: ONCOR'S RESPONSE TO STAFF'S REQUEST FOR INFORMATION RELATED TO WHOLESALE TRANSMISSION SERVICE CHARGESPUCT Project 58484, Item 42 |
Filed · Nov 14, 2025
ONCOR ELECTRIC DELIVERY COMPANY LLC
|
ONCOR ELECTRIC DELIVERY COMPANY LLC filed ONCOR'S RESPONSE TO STAFF'S REQUEST FOR INFORMATION RELATED TO WHOLESALE TRANSMISSION SERVICE CHARGES in PUCT Project 58484 on Nov 14, 2025. | |
| PUCT Project 58484: SUPPLEMENTAL RESPONSE TO COMMISSION STAFF’S REQUEST FOR INFORMATION ISSUED ON OCTOBER 17, 2025 RELATED TO WHOLESALE TRANSMISSION SERVICE CHARGESPUCT Project 58484, Item 43 |
Filed · Nov 17, 2025
AEP TEXAS INC.
|
AEP TEXAS INC. filed SUPPLEMENTAL RESPONSE TO COMMISSION STAFF’S REQUEST FOR INFORMATION ISSUED ON OCTOBER 17, 2025 RELATED TO WHOLESALE TRANSMISSION SERVICE CHARGES in PUCT Project 58484 on Nov 17, 2025. | |
| PUCT Project 58484: Letter to Void Item #41PUCT Project 58484, Item 44 |
Filed · Nov 20, 2025
CENTERPOINT ENERGY HOUSTON ELECTRIC
|
CENTERPOINT ENERGY HOUSTON ELECTRIC filed Letter to Void Item #41 in PUCT Project 58484 on Nov 20, 2025. | |
| PUCT Project 58484: CEHE’s Updated Response to Commission Staff’s Request for Information Issued October 17, 2025, Regarding Wholesale Transmission Service ChargesPUCT Project 58484, Item 45 |
Filed · Nov 20, 2025
CENTERPOINT ENERGY HOUSTON ELECTRIC
|
CENTERPOINT ENERGY HOUSTON ELECTRIC filed CEHE’s Updated Response to Commission Staff’s Request for Information Issued October 17, 2025, Regarding Wholesale Transmission Service Charges in PUCT Project 58484 on Nov 20, 2025. | |
| PUCT Project 58484: Comments and answers to staff questionsPUCT Project 58484, Item 50 |
Filed · Nov 25, 2025
Sierra Club
|
Sierra Club filed Comments and answers to staff questions in PUCT Project 58484 on Nov 25, 2025. | |
| PUCT Project 58484: ONCOR'S RESPONSE TO COMMISSION STAFF’S SECOND SET OF QUESTIONS FOR COMMENTSPUCT Project 58484, Item 52 |
Filed · Nov 25, 2025
ONCOR ELECTRIC DELIVERY COMPANY LLC
|
ONCOR ELECTRIC DELIVERY COMPANY LLC filed ONCOR'S RESPONSE TO COMMISSION STAFF’S SECOND SET OF QUESTIONS FOR COMMENTS in PUCT Project 58484 on Nov 25, 2025. | |
| PUCT Project 58484: LCRA AND LCRA TSC'S RESPONSE TO COMMISSION STAFF'S SECOND SET OF QUESTIONS FOR COMMENTPUCT Project 58484, Item 53 |
Filed · Nov 25, 2025
LOWER COLORADO RIVER AUTHORITY AND LCRA TRANSMISSION SERVICES CORPORATION
|
LOWER COLORADO RIVER AUTHORITY AND LCRA TRANSMISSION SERVICES CORPORATION filed LCRA AND LCRA TSC'S RESPONSE TO COMMISSION STAFF'S SECOND SET OF QUESTIONS FOR COMMENT in PUCT Project 58484 on Nov 25, 2025. | |
| PUCT Project 58484: Joint Responses to Staff Questions of H-E-B, LP and South Texas Electric Cooperative, Inc.PUCT Project 58484, Item 54 |
Filed · Nov 25, 2025
H-E-B LP and South Texas Electric Cooperative, Inc.
|
H-E-B LP and South Texas Electric Cooperative, Inc. filed Joint Responses to Staff Questions of H-E-B, LP and South Texas Electric Cooperative, Inc. in PUCT Project 58484 on Nov 25, 2025. | |
| PUCT Project 58484: Comments of NRG Energy, Inc. in Response to Staff's Second Set of Questions on Transmission Cost RecoveryPUCT Project 58484, Item 55 |
Filed · Nov 25, 2025
NRG ENERGY, INC.
|
NRG ENERGY, INC. filed Comments of NRG Energy, Inc. in Response to Staff's Second Set of Questions on Transmission Cost Recovery in PUCT Project 58484 on Nov 25, 2025. | |
| PUCT Project 58484: Responses of Texas Electric Cooperatives, Inc.PUCT Project 58484, Item 57 |
Filed · Nov 25, 2025
Texas Electric Cooperatives, Inc.
|
Texas Electric Cooperatives, Inc. filed Responses of Texas Electric Cooperatives, Inc. in PUCT Project 58484 on Nov 25, 2025. | |
| PUCT Project 58484: DCC's Comments in Response to Staff's Second Set of QuestionsPUCT Project 58484, Item 59 |
Filed · Nov 25, 2025
Data Center Coalition
|
Data Center Coalition filed DCC's Comments in Response to Staff's Second Set of Questions in PUCT Project 58484 on Nov 25, 2025. | |
| PUCT Project 58484: TCA Comments on Staff QuestionsPUCT Project 58484, Item 60 |
Filed · Nov 25, 2025
TEXAS CONSUMER ASSOCIATION
|
TEXAS CONSUMER ASSOCIATION filed TCA Comments on Staff Questions in PUCT Project 58484 on Nov 25, 2025. | |
| PUCT Project 58484: Texas Energy Association for Marketers' Response to Questions for CommentPUCT Project 58484, Item 61 |
Filed · Nov 25, 2025
TEXAS ENERGY ASSOCIATION FOR MARKETERS
|
TEXAS ENERGY ASSOCIATION FOR MARKETERS filed Texas Energy Association for Marketers' Response to Questions for Comment in PUCT Project 58484 on Nov 25, 2025. | |
| PUCT Project 58484: Vistra's Comments in Response to Staff's Second Set of QuestionsPUCT Project 58484, Item 63 |
Filed · Nov 25, 2025
VISTRA CORPORATE SERVICES COMPANY LLC
|
VISTRA CORPORATE SERVICES COMPANY LLC filed Vistra's Comments in Response to Staff's Second Set of Questions in PUCT Project 58484 on Nov 25, 2025. | |
| PUCT Project 58484: CPS Energy's Comments in Response to Second Set of Questions.PUCT Project 58484, Item 64 |
Filed · Nov 25, 2025
CPS ENERGY
|
CPS ENERGY filed CPS Energy's Comments in Response to Second Set of Questions. in PUCT Project 58484 on Nov 25, 2025. | |
| PUCT Project 58484: ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S RESPONSE TO STAFF QUESTIONSPUCT Project 58484, Item 65 |
Filed · Nov 25, 2025
ERCOT
|
ERCOT filed ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S RESPONSE TO STAFF QUESTIONS in PUCT Project 58484 on Nov 25, 2025. | |
| PUCT Project 58484: TAEBA Response to Staff's Second Set of Questions Proj. No. 58484PUCT Project 58484, Item 67 |
Filed · Nov 25, 2025
TEXAS ADVANCED ENERGY BUSINESS ALLIANCE
|
TEXAS ADVANCED ENERGY BUSINESS ALLIANCE filed TAEBA Response to Staff's Second Set of Questions Proj. No. 58484 in PUCT Project 58484 on Nov 25, 2025. | |
| PUCT Project 58484: CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC’S RESPONSES TO COMMISSON STAFF’S REQUEST FOR COMMENTSPUCT Project 58484, Item 68 |
Filed · Nov 25, 2025
CENTERPOINT ENERGY HOUSTON ELECTRIC
|
CENTERPOINT ENERGY HOUSTON ELECTRIC filed CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC’S RESPONSES TO COMMISSON STAFF’S REQUEST FOR COMMENTS in PUCT Project 58484 on Nov 25, 2025. | |
| PUCT Project 58484: RESPONSES TO COMMISSION STAFF’S SECOND SET OF QUESTIONS FOR COMMENTSPUCT Project 58484, Item 69 |
Filed · Nov 25, 2025
AEP TEXAS INC.
|
AEP TEXAS INC. filed RESPONSES TO COMMISSION STAFF’S SECOND SET OF QUESTIONS FOR COMMENTS in PUCT Project 58484 on Nov 25, 2025. | |
| PUCT Project 58484: OPUC’S COMMENTS ON THE SECOND SET OF QUESTIONS FOR PUBLIC COMMENT TO ATTACHMENTS A AND B RELATING TO THE EVALUATION OF TRANSMISSION COST RECOVERYPUCT Project 58484, Item 70 |
Filed · Nov 25, 2025
OPUC
|
OPUC filed OPUC’S COMMENTS ON THE SECOND SET OF QUESTIONS FOR PUBLIC COMMENT TO ATTACHMENTS A AND B RELATING TO THE EVALUATION OF TRANSMISSION COST RECOVERY in PUCT Project 58484 on Nov 25, 2025. | |
| PUCT Project 58484: ERCOT Steel Mills' Comments on Commission Staff Questions and Draft Report Outline for Project No. 58484 - Evaluation of Transmission Cost RecoveryPUCT Project 58484, Item 71 |
Filed · Nov 25, 2025
ERCOT STEEL MILLS
|
ERCOT STEEL MILLS filed ERCOT Steel Mills' Comments on Commission Staff Questions and Draft Report Outline for Project No. 58484 - Evaluation of Transmission Cost Recovery in PUCT Project 58484 on Nov 25, 2025. | |
| PUCT Project 58484: CenterPoint Energy Houston Electric Second Updated Response to Commission Staff’s Request for CommentsPUCT Project 58484, Item 76 |
Filed · Jan 14, 2026
CENTERPOINT ENERGY HOUSTON ELECTRIC
|
CENTERPOINT ENERGY HOUSTON ELECTRIC filed CenterPoint Energy Houston Electric Second Updated Response to Commission Staff’s Request for Comments in PUCT Project 58484 on Jan 14, 2026. | |
| PUCT Project 58484: Staff Memo and Draft Report w/April 13 Comment DeadlinePUCT Project 58484, Item 77 |
Filed · Mar 16, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Staff Memo and Draft Report w/April 13 Comment Deadline in PUCT Project 58484 on Mar 16, 2026. | |
| PUCT Project 58484: Vitol Inc. comments in response Commission Staff's Draft Evaluation of Transmission Cost RecoveryPUCT Project 58484, Item 80 |
Filed · Apr 12, 2026
VITOL INC.
|
VITOL INC. filed Vitol Inc. comments in response Commission Staff's Draft Evaluation of Transmission Cost Recovery in PUCT Project 58484 on Apr 12, 2026. | |
| PUCT Project 58484: Comments on Commission Staff Report Filed Jointly by Base Power Company, Octopus Energy, Rhythm Energy, and Tesla Energy Ventures, LLCPUCT Project 58484, Item 82 |
Filed · Apr 13, 2026
Retail Electric Providers for Affordable, Innovative Rates
|
Retail Electric Providers for Affordable, Innovative Rates filed Comments on Commission Staff Report Filed Jointly by Base Power Company, Octopus Energy, Rhythm Energy, and Tesla Energy Ventures, LLC in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 58484: Texas Public Power Association (TPPA) Comments on Draft Report and RecommendationsPUCT Project 58484, Item 84 |
Filed · Apr 13, 2026
TPPA
|
TPPA filed Texas Public Power Association (TPPA) Comments on Draft Report and Recommendations in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 58484: H-E-B and South Texas Electric Cooperative, Inc.'s Joint Comments on Staff's Memorandum and Draft ReportPUCT Project 58484, Item 87 |
Filed · Apr 13, 2026
H-E-B, LP AND SOUTH TEXAS ELECTRIC COOPERATIVE, INC.
|
H-E-B, LP AND SOUTH TEXAS ELECTRIC COOPERATIVE, INC. filed H-E-B and South Texas Electric Cooperative, Inc.'s Joint Comments on Staff's Memorandum and Draft Report in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 58484: Comments of NRG Energy, Inc. in Response to Staff Memo and Draft Report on Transmission Cost RecoveryPUCT Project 58484, Item 88 |
Filed · Apr 13, 2026
NRG ENERGY, INC.
|
NRG ENERGY, INC. filed Comments of NRG Energy, Inc. in Response to Staff Memo and Draft Report on Transmission Cost Recovery in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 58484: Comments on Staff's Report and RecommendationsPUCT Project 58484, Item 89 |
Filed · Apr 13, 2026
Data Center Coalition (DCC)
|
Data Center Coalition (DCC) filed Comments on Staff's Report and Recommendations in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 58484: COMMENTS OF TEXAS ELECTRIC COOPERATIVES, INC.PUCT Project 58484, Item 90 |
Filed · Apr 13, 2026
TEXAS ELECTRIC COOPERATIVES, INC.
|
TEXAS ELECTRIC COOPERATIVES, INC. filed COMMENTS OF TEXAS ELECTRIC COOPERATIVES, INC. in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 58484: Steering Committee of Cities Served by Oncor and Texas Coalition for Affordable Power's Comments on Commission Staff’s Draft Report on Transmission Cost RecoveryPUCT Project 58484, Item 91 |
Filed · Apr 13, 2026
STEERING COMMITTEE OF CITIES SERVED BY ONCOR AND TEXAS COALITION FOR AFFORDABLE POWER
|
STEERING COMMITTEE OF CITIES SERVED BY ONCOR AND TEXAS COALITION FOR AFFORDABLE POWER filed Steering Committee of Cities Served by Oncor and Texas Coalition for Affordable Power's Comments on Commission Staff’s Draft Report on Transmission Cost Recovery in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 58484: LCRA'S COMMENTS ON COMMISSION STAFF'S DRAFT RECOMMENDATIONS FOR TRANSMISSION COST RECOVERYPUCT Project 58484, Item 92 |
Filed · Apr 13, 2026
LOWER COLORADO RIVER AUTHORITY
|
LOWER COLORADO RIVER AUTHORITY filed LCRA'S COMMENTS ON COMMISSION STAFF'S DRAFT RECOMMENDATIONS FOR TRANSMISSION COST RECOVERY in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 58484: ERCOT Steel Mills Comments on PUCT Staff's Draft Report_Project 58484PUCT Project 58484, Item 93 |
Filed · Apr 13, 2026
ERCOT STEEL MILLS
|
ERCOT STEEL MILLS filed ERCOT Steel Mills Comments on PUCT Staff's Draft Report_Project 58484 in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 58484: CPS Energy's Response to Staff's Draft RecommendationsPUCT Project 58484, Item 95 |
Filed · Apr 13, 2026
CPS ENERGY
|
CPS ENERGY filed CPS Energy's Response to Staff's Draft Recommendations in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 58484: TCPA Comments on Staff Draft Report on Evaluation of Transmission Cost AllocationPUCT Project 58484, Item 96 |
Filed · Apr 13, 2026
TCPA
|
TCPA filed TCPA Comments on Staff Draft Report on Evaluation of Transmission Cost Allocation in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 58484: TCA Comments on Draft Report for Transmission Cost RecoveryPUCT Project 58484, Item 97 |
Filed · Apr 13, 2026
TEXAS CONSUMER ASSOCIATION
|
TEXAS CONSUMER ASSOCIATION filed TCA Comments on Draft Report for Transmission Cost Recovery in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 58484: Texas-New Mexico Power Company's Comments to Commission Staff's March 16, 2026 Request for Public CommentPUCT Project 58484, Item 98 |
Filed · Apr 13, 2026
TEXAS-NEW MEXICO POWER COMPANY
|
TEXAS-NEW MEXICO POWER COMPANY filed Texas-New Mexico Power Company's Comments to Commission Staff's March 16, 2026 Request for Public Comment in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 58484: GVEC's Comments Regarding Staff's Memo & Draft ReportPUCT Project 58484, Item 99 |
Filed · Apr 13, 2026
GUADALUPE VALLEY ELECTRIC COOPERATIVE, INC
|
GUADALUPE VALLEY ELECTRIC COOPERATIVE, INC filed GVEC's Comments Regarding Staff's Memo & Draft Report in PUCT Project 58484 on Apr 13, 2026. | |
| PUCT Project 59142: ERCOT UPDATE - BATCH ZERO ELIGIBILITY VERIFICATION AND STATE AND COMMUNITY IMPACT RFI PROCESSPUCT Project 59142, Item 73 |
Filed · Sep 21, 2026
ERCOT
|
ERCOT filed ERCOT UPDATE - BATCH ZERO ELIGIBILITY VERIFICATION AND STATE AND COMMUNITY IMPACT RFI PROCESS in PUCT Project 59142 on Sep 21, 2026. | |
| PUCT Project 58317: SB6 Implementation Roadmap Updated September 2026PUCT Project 58317, Item 69 |
Filed · Sep 22, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed SB6 Implementation Roadmap Updated September 2026 in PUCT Project 58317 on Sep 22, 2026. | |
| PUCT Project 58317: Governor’s auditPUCT Project 58317, Item 71 |
Filed · Sep 22, 2026
Mary Balmain
|
Mary Balmain filed Governor’s audit in PUCT Project 58317 on Sep 22, 2026. | |
| PUCT Project 58317: Public comments on data centers. 765kV Governor's auditPUCT Project 58317, Item 74 |
Filed · Sep 22, 2026
Toni Williams
|
Toni Williams filed Public comments on data centers. 765kV Governor's audit in PUCT Project 58317 on Sep 22, 2026. | |
| PUCT Project 58484: OPUC'S LETTER TO CENTRAL RECORDS- REQUEST TO VOID ITEM NO. 107PUCT Project 58484, Item 114 |
Filed · Apr 14, 2026
OPUC
|
OPUC filed OPUC'S LETTER TO CENTRAL RECORDS- REQUEST TO VOID ITEM NO. 107 in PUCT Project 58484 on Apr 14, 2026. | |
| PUCT Project 58484: OPUC’S INITIAL COMMENTS ON STAFF OF THE PUBLIC UTILITY COMMISSION OF TEXAS’S MEMORANDUM AND DRAFT EVALUATION OF TRANSMISSION COST RECOVERYPUCT Project 58484, Item 115 |
Filed · Apr 14, 2026
OPUC
|
OPUC filed OPUC’S INITIAL COMMENTS ON STAFF OF THE PUBLIC UTILITY COMMISSION OF TEXAS’S MEMORANDUM AND DRAFT EVALUATION OF TRANSMISSION COST RECOVERY in PUCT Project 58484 on Apr 14, 2026. | |
| PUCT Project 58484: Staff Memo and Draft ReportPUCT Project 58484, Item 117 |
Filed · May 4, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Staff Memo and Draft Report in PUCT Project 58484 on May 4, 2026. | |
| PUCT Project 58484: Staff Memo_New Rulemaking ProjectPUCT Project 58484, Item 118 |
Filed · May 27, 2026
PUC RULES & PROJECTS
|
PUC RULES & PROJECTS filed Staff Memo_New Rulemaking Project in PUCT Project 58484 on May 27, 2026. | |
| PUCT Project 58484: LETTER REGARDING EVALUATION OF TRANSMISSION COST RECOVERYPUCT Project 58484, Item 119 |
Filed · Jun 30, 2026
CHAIRMAN DREW DARBY
|
CHAIRMAN DREW DARBY filed LETTER REGARDING EVALUATION OF TRANSMISSION COST RECOVERY in PUCT Project 58484 on Jun 30, 2026. | |
| ERCOT market notice M-C092126-01: Batch Zero Verification and Community Impact RFIs: RIOO RFI Tool Update to Restrict Visibility of Other Respondents' Submissions, and Posting of Question Reference Guides on the ERCOT WebsiteERCOT Market Notice M-C092126-01 |
Issued · Sep 21, 2026
Market notice
|
ERCOT issued market notice M-C092126-01, Batch Zero Verification and Community Impact RFIs: RIOO RFI Tool Update to Restrict Visibility of Other Respondents' Submissions, and Posting of Question Reference Guides on the ERCOT Website, on Sep 21, 2026. | |
| PUCT Project 59948: Joint Motion to Admit Evidence and Parties' Proposed Finding of Fact, Conclusions of Law, and Ordering ParagraphsPUCT Project 59948, Item 14 |
Filed · Sep 22, 2026
EL PASO ELECTRIC COMPANY
|
EL PASO ELECTRIC COMPANY filed Joint Motion to Admit Evidence and Parties' Proposed Finding of Fact, Conclusions of Law, and Ordering Paragraphs in PUCT Project 59948 on Sep 22, 2026. | |
| PUCT Project 58317: Public comments on data centers, 765 kV, and the Governor’s auditPUCT Project 58317, Item 80 |
Filed · Sep 23, 2026
Tim Morin
|
Tim Morin filed Public comments on data centers, 765 kV, and the Governor’s audit in PUCT Project 58317 on Sep 23, 2026. | |
| PUCT Project 58317: data centers, 765 kV, and the Governor's audit. I’m Very concerned and upset to find out that 8,300 acres has been purchased for a proposed DATA CENTER JIM HOGG. Co Property is surrounded by farms, wildlife and historic sites. Drought has been declared.PUCT Project 58317, Item 81 |
Filed · Sep 23, 2026
Lynda Soliz
|
Lynda Soliz filed data centers, 765 kV, and the Governor's audit. I’m Very concerned and upset to find out that 8,300 acres has been purchased for a proposed DATA CENTER JIM HOGG. Co Property is surrounded by farms, wildlife and historic sites. Drought has been declared. in PUCT Project 58317 on Sep 23, 2026. | |
| PUCT Project 58317: Overwhelming the state with data centers. 765 kV, governors audit. 520 acres of data center near atmos gas line. Drought. Farm land/agriculture, wildlife and historical sites.PUCT Project 58317, Item 83 |
Filed · Sep 24, 2026
Ashly Sanchez
|
Ashly Sanchez filed Overwhelming the state with data centers. 765 kV, governors audit. 520 acres of data center near atmos gas line. Drought. Farm land/agriculture, wildlife and historical sites. in PUCT Project 58317 on Sep 24, 2026. | |
| PUCT Project 58796: OPUC'S NOTICE OF CHANGE OF COUNSELPUCT Project 58796, Item 105 |
Filed · Sep 24, 2026
OPUC
|
OPUC filed OPUC'S NOTICE OF CHANGE OF COUNSEL in PUCT Project 58796 on Sep 24, 2026. | |
| PUCT Project 59948: ORDER NO. 5- FINDING NOTICE SUFFICIENTPUCT Project 59948, Item 15 |
Filed · Sep 24, 2026
PUC OPDM
|
PUC OPDM filed ORDER NO. 5- FINDING NOTICE SUFFICIENT in PUCT Project 59948 on Sep 24, 2026. | |
| PUCT Project 59142: Request for Audit for Project RaptorPUCT Project 59142, Item 74 |
Filed · Sep 25, 2026
Douglas Lindemann
|
Douglas Lindemann filed Request for Audit for Project Raptor in PUCT Project 59142 on Sep 25, 2026. | |
| PUCT Project 59142: Request for Audit for Project RaptorPUCT Project 59142, Item 75 |
Filed · Sep 25, 2026
Jennifer Lindemann
|
Jennifer Lindemann filed Request for Audit for Project Raptor in PUCT Project 59142 on Sep 25, 2026. | |
| PUCT Project 59142: Request for Audit for Project RaptorPUCT Project 59142, Item 76 |
Filed · Sep 25, 2026
Bob Lindemann
|
Bob Lindemann filed Request for Audit for Project Raptor in PUCT Project 59142 on Sep 25, 2026. | |
| PUCT Project 59142: Request for Audit for Project RaptorPUCT Project 59142, Item 77 |
Filed · Sep 25, 2026
Becky Lindemann
|
Becky Lindemann filed Request for Audit for Project Raptor in PUCT Project 59142 on Sep 25, 2026. | |
| PUCT Project 58317: I oppose the data centers, 765 kV, and I have no faith in the Governor’s audit. We moved to rural area to avoid what you are bringin here. I will not pay for these data centers to ruin our state!PUCT Project 58317, Item 87 |
Filed · Sep 26, 2026
Leslie Wiltse
|
Leslie Wiltse filed I oppose the data centers, 765 kV, and I have no faith in the Governor’s audit. We moved to rural area to avoid what you are bringin here. I will not pay for these data centers to ruin our state! in PUCT Project 58317 on Sep 26, 2026. | |
| PUCT Project 58317: Public comments on data centers, 765 KV and Governors auditPUCT Project 58317, Item 101 |
Filed · Oct 2, 2026
Kimberly Weiland
|
Kimberly Weiland filed Public comments on data centers, 765 KV and Governors audit in PUCT Project 58317 on Oct 2, 2026. | |
| PUCT Project 58796: SOAH ORDER NO. 12- ADMITTING EVIDENCE; REMANDING CASE TO THE COMMISSION; AND DISMISSING FROM SOAH’S DOCKETPUCT Project 58796, Item 106 |
Filed · Oct 5, 2026
SOAH
|
SOAH filed SOAH ORDER NO. 12- ADMITTING EVIDENCE; REMANDING CASE TO THE COMMISSION; AND DISMISSING FROM SOAH’S DOCKET in PUCT Project 58796 on Oct 5, 2026. | |
| PUCT Project 58317: Public comments on data centers, 765 kV, and the Governor’s audit. Specifically near La Grange, TxPUCT Project 58317, Item 102 |
Filed · Oct 7, 2026
Mark D Owens
|
Mark D Owens filed Public comments on data centers, 765 kV, and the Governor’s audit. Specifically near La Grange, Tx in PUCT Project 58317 on Oct 7, 2026. |