Georgia Data Center Permits Tracker

Georgia has 20 data center and substation permits on record and 4,641 MW of generation planned within 36 months. Every row below links to its primary source.

Last checked Sep 18, 2026

20
Data center & substation permits
of 20 total utility-scale permits tracked here
0MW
In the interconnection queue
0 active generation and storage positions
4,641MW
Planned generation
26 EIA-860M generators due within 36 months
#7
of 51 states with anything on record
Ranked by data center & substation permit count

Where the activity is

Ranked by row count. Counts are never mixed with the MW figures above.

Permit categories

Data center 20

Permits in Georgia

20 building and land-use permits tracked in Georgia.

DateCategoryAddressApplicantSource
Sep 16, 2026 Data center City of Atlanta GA Citizen Access records
Sep 16, 2026 Data center City of Atlanta GA Citizen Access records
Aug 20, 2026 Data center City of Atlanta GA Citizen Access records
Aug 20, 2026 Data center City of Atlanta GA Citizen Access records
Aug 20, 2026 Data center$44,445,620 1968 MARIETTA NW, ATLANTA, GA 30318City of Atlanta GA building permits
Aug 11, 2026 Data center City of Atlanta GA Citizen Access records
Aug 11, 2026 Data center City of Atlanta GA Citizen Access records
Aug 11, 2026 Data center City of Atlanta GA Citizen Access records
Aug 11, 2026 Data center City of Atlanta GA Citizen Access records
Aug 11, 2026 Data center City of Atlanta GA Citizen Access records
Aug 11, 2026 Data center$44,445,620 1968 MARIETTA NW, ATLANTA, GA 30318City of Atlanta GA building permits
Jul 30, 2026 Data center City of Atlanta GA Citizen Access records
Jul 22, 2026 Data center$4,000,000 3344 PEACHTREE NE, ATLANTA, GA 30326City of Atlanta GA building permits
Jul 6, 2026 Data center$100 1055 HOWELL MILL NW, ATLANTA, GA 30318City of Atlanta GA building permits
Jul 6, 2026 Data center$100 1055 HOWELL MILL NW, ATLANTA, GA 30318City of Atlanta GA building permits
Mar 31, 2026 Data center$800,000 345 COURTLAND NE, ATLANTA, GA 30308City of Atlanta GA building permits
Dec 5, 2025 Data center$14,931 760 WEST PEACHTREE NW, ATLANTA, GA 30308City of Atlanta GA building permits
Nov 25, 2025 Data center$14,931 760 WEST PEACHTREE NW, ATLANTA, GA 30308City of Atlanta GA building permits
Nov 20, 2025 Data center$661,500 760 WEST PEACHTREE NW, ATLANTA, GA 30308City of Atlanta GA building permits
Oct 9, 2025 Data center$17,400 760 WEST PEACHTREE NW, ATLANTA, GA 30308City of Atlanta GA building permits

Planned generation in Georgia

4,641 MW across 26 EIA-860M generators scheduled to enter service within 36 months.

PlantTechnologyMWPlannedStatusSource
YatesCoweta County Natural Gas Fired Combustion Turbine 483 MW Dec 2027 Planned for installation, but regulatory approvals not initiated
YatesCoweta County Natural Gas Fired Combustion Turbine 483 MW Dec 2026 Under construction, more than 50 percent complete
YatesCoweta County Natural Gas Fired Combustion Turbine 483 MW Dec 2027 Planned for installation, but regulatory approvals not initiated
Smarr Combined Cycle Energy FacilityMonroe County Natural Gas Fired Combined Cycle 459 MW Jun 2029 Planned for installation, but regulatory approvals not initiated
Smarr Combined Cycle Energy FacilityMonroe County Natural Gas Fired Combined Cycle 345 MW Jun 2029 Planned for installation, but regulatory approvals not initiated
McGrau Ford Battery Storage FacilityCherokee County Batteries 265 MW Aug 2026 Under construction, less than or equal to 50 percent complete
McGrau Ford Battery Storage FacilityCherokee County Batteries 265 MW Aug 2026 Under construction, less than or equal to 50 percent complete
Talbot County EnergyTalbot County Natural Gas Fired Combustion Turbine 262 MW Jan 2029 Planned for installation, but regulatory approvals not initiated
Rock House SolarMcDuffie County Solar Photovoltaic 250 MW Nov 2027 Planned for installation, but regulatory approvals not initiated
Conez Solar, LLCEmanuel County Solar Photovoltaic 150 MW Jun 2027 Planned for installation, but regulatory approvals not initiated
Crossroads Solar - GALiberty County Solar Photovoltaic 150 MW Jul 2029 Regulatory approvals pending. Not under construction
Laurens SolarLaurens County Solar Photovoltaic 150 MW Jun 2028 Regulatory approvals pending. Not under construction
SR Bacon IIBacon County Solar Photovoltaic 115 MW Dec 2027 Regulatory approvals received. Not under construction
SR NorwoodWarren County Solar Photovoltaic 107 MW Dec 2027 Regulatory approvals received. Not under construction
SR Bacon IIIBacon County Solar Photovoltaic 100 MW Dec 2027 Regulatory approvals received. Not under construction
SR Rochelle IWilcox County Solar Photovoltaic 90 MW Dec 2026 Under construction, more than 50 percent complete
SR BaconBacon County Solar Photovoltaic 85 MW Dec 2026 Under construction, more than 50 percent complete
Drawhorn SolarHancock County Solar Photovoltaic 80 MW Nov 2027 Regulatory approvals pending. Not under construction
Alligator Creek SolarWheeler County Solar Photovoltaic 80 MW Sep 2026 Under construction, more than 50 percent complete
Cabokenze Energy StorageBurke County Batteries 76 MW Nov 2027 Planned for installation, but regulatory approvals not initiated
HammondFloyd County Batteries 58 MW Sep 2026 Under construction, less than or equal to 50 percent complete
Sandersville SolarWashington County Solar Photovoltaic 50 MW Oct 2027 Regulatory approvals pending. Not under construction
SR Rochelle IIWilcox County Solar Photovoltaic 50 MW Dec 2027 Regulatory approvals received. Not under construction
Solar BESS HybridCobb County Natural Gas Fired Combustion Turbine 2 MW May 2027 Under construction, less than or equal to 50 percent complete
Solar BESS HybridCobb County Natural Gas Fired Combustion Turbine 2 MW May 2027 Under construction, less than or equal to 50 percent complete
Solar BESS HybridCobb County Natural Gas Fired Combustion Turbine 2 MW May 2027 Under construction, less than or equal to 50 percent complete

Other filings in Georgia

State air permits (27)

FacilityAgencyGeneratorsStatusSource
Westside Parkway Owner LLC Georgia EPD issued, SIP permit
Equinix Atlanta Data Center Georgia EPD issued, SIP permit
Rosewall Pines Holdings LLC Georgia EPD issued, SIP permit
SDC ATLA Georgia EPD issued, SIP permit
Amazon Data Services, Inc. ATL089 Campus Georgia EPD issued, SIP permit
ATL2 Data Center Georgia EPD issued, SIP permit
Core Scientific-Dalton 4 Enterprise Drive Georgia EPD issued, SIP permit
Flexential Corporation Georgia EPD issued, SIP permit
Edgeconnex ATL11, LLC Georgia EPD issued, SIP permit
Edged Energy Atlanta Data Center Georgia EPD issued, SIP permit
DCB Atlanta West, LLC Georgia EPD issued, SIP permit
Amazon Data Services, Inc. ATL068 and ATL078 Campuses Georgia EPD issued, SIP permit
GA1 Georgia EPD issued, SIP permit
DB Data Center Boulder Park, LLC Georgia EPD issued, SIP permit
Vantage Data Centers GA1, LLC Georgia EPD issued, SIP permit
Vantage Data Centers GA2, LLC Georgia EPD issued, SIP permit
Flexential Corporation Georgia EPD issued, SIP permit
DCB Atlanta East, LLC Georgia EPD issued, SIP permit
QTS Fayetteville I, LLC Georgia EPD issued, SIP permit
Edgeconnex ATL11, LLC Georgia EPD issued, SIP permit
Edged Energy Atlanta Data Center Georgia EPD issued, SIP permit
Aligned Data Centers ATL01 Georgia EPD issued, SIP permit
QTS Fayetteville I, LLC Georgia EPD issued, SIP permit
Data Center Fulton, LLC Georgia EPD issued, SIP permit
Morning Hornet, LLC Georgia EPD issued, SIP permit
QTS Fayetteville I, LLC Georgia EPD issued, SIP permit
Amazon Data Services, Inc. ATL057 Georgia EPD issued, SIP permit

Where Georgia stands

Across the whole tracker, 533 data center and substation permits are on record in 51 states and DC. Georgia accounts for 20 of them, ranking #7 by that count. Ranking measures documented permit activity, not the size of the eventual buildout.