SAVRN
Search Contact SAVRN
SAVRN Tracker

Indiana Data Center Permits Tracker

Indiana has 26,423 MW of generation and storage requested in the interconnection queue and 5,003 MW of generation planned within 36 months. Every row below links to its primary source.

Last checked Sep 18, 2026

0
Data center & substation permits
of 0 total utility-scale permits tracked here
26,423MW
In the interconnection queue
111 active generation and storage positions
5,003MW
Planned generation
28 EIA-860M generators due within 36 months
#13
of 51 states with anything on record
Ranked by data center & substation permit count

Where the activity is

Ranked by row count. Counts are never mixed with the MW figures above.

Top counties · queue, substation & state air rows

Sullivan 15
Pulaski 9
Randolph 8
Blackford 7
White 7
Grant 6
Delaware 5
St. Joseph 5

Interconnection queue in Indiana

26,423 MW requested across 111 active generation and storage positions. Withdrawn and in-service rows are left out, matching the national page.

ISOProjectFuelMWStatusSource
MISO Sugar Creek - Cayuga CT 345.0kVDUKE ENERGY INDIANA, LLC CINVermillion County Natural gas 1,540 MW Active
PJM Elderberry 345 kV AG2-562St. Joseph County Natural gas 767 MW Active
PJM Rockport 765 kV AG2-072Spencer County Natural gas 700 MW Active
PJM Dequine-Eugene 345 kV AG2-163Fountain County Solar 700 MW Active
MISO Reynolds--Burr Oak 345kV lineNORTHERN INDIANA PUBLIC SERVICE COMPANY LLC NIPSPulaski County Solar 700 MW Active; not started
MISO Merom (HED) - Dresser 345.0kVDUKE ENERGY INDIANA, LLC CINSullivan County Natural gas 650 MW Active
MISO Merom (HED) - Dresser 345.0kVDUKE ENERGY INDIANA, LLC CINSullivan County Natural gas 642 MW Pending revision approval; not started
MISO Merom Primary - Worthington Primary 345.0kVHOOSIER ENERGYSullivan County Other hybrids 560 MW Pending revision approval; not started
MISO CAYUGA STATIONDUKE ENERGY INDIANA, LLC CINVermillion County Natural gas 500 MW Active
MISO Other_NORTHERN INDIANA PUBLIC SERVICE COMPANY LLC NIPSJasper County Solar 500 MW Active
MISO Petersburg - Sullivan (AEP/PJM) 345.0kVHOOSIER ENERGYSullivan County Natural gas 500 MW Active
PJM Sullivan Generating Station 1Sullivan County Natural gas 480 MW Under construction
PJM Sullivan Generating Station 2Sullivan County Natural gas 480 MW Engineering and procurement
MISO Petersburg - Sullivan (AEP/PJM) 345.0kVINDIANAPOLIS POWER & LIGHT COMPANYSullivan County Natural gas 470 MW Active
MISO Petersburg - Sullivan (AEP/PJM) 345.0kVINDIANAPOLIS POWER & LIGHT COMPANYSullivan County Natural gas 470 MW Active
PJM Dequine-Eugene 345 kV AG1-226Fountain County Solar 450 MW Engineering and procurement
MISO Reynolds 345 kV SubstationNORTHERN INDIANA PUBLIC SERVICE COMPANY LLC NIPSWhite County Battery storage 400 MW Active; not started
MISO SandfordDUKE ENERGY INDIANA, LLC CINVigo County Solar 365 MW Active
PJM Olive - Reynolds #2 345 kV AH1-482Pulaski County Battery storage 338 MW Active
PJM Bluestem SolarLaPorte County Battery storage 305 MW Engineering and procurement
PJM Mammoth Central Energy CenterPulaski County Solar 300 MW Under construction
PJM Mammoth South Energy CenterPulaski County Solar 300 MW Partially in service - under construction
PJM Mammoth Central II Energy CenterPulaski County Solar 300 MW Under construction
MISO SCHAHFER GEN STA - ST. JOHN 345.0kVNORTHERN INDIANA PUBLIC SERVICE COMPANY LLC NIPSLake County Battery storage 300 MW Active; not started
MISO Merom 345 kVHOOSIER ENERGYSullivan County Solar 300 MW Active; not started
MISO Sandborn Primary - Worthington Primary 161.0kVHOOSIER ENERGYGreene County Other hybrids 300 MW Active; not started
MISO Other_NORTHERN INDIANA PUBLIC SERVICE COMPANY LLC NIPSNewton County Other hybrids 300 MW Active
MISO Gibson Sta - Bedford 345 345.0kVDUKE ENERGY INDIANA, LLC CINKnox County Onshore wind 300 MW Active
PJM Olive - Reynolds 345 kV AH1-302Pulaski County Battery storage 275 MW Active
PJM Olive - Reynolds 345 kV AH1-305Pulaski County Solar 275 MW Active
PJM Mayapple SolarPulaski County Solar 260 MW Engineering and procurement
PJM Vermilion Grove WindVermillion County Onshore wind 255 MW Engineering and procurement
PJM Bluestem SolarLaPorte County Solar 250 MW Engineering and procurement
PJM Forest G. Hipple-Dunton Lake 345 kV AG2-029Noble County Solar 250 MW Active
PJM Lake Trout SolarBlackford County Solar 245 MW Engineering and procurement
PJM Olive - Reynolds #1 345 kV AG2-245Starke County Solar 210 MW Active
PJM Headwaters Wind Farm IIIRandolph County Onshore wind 200 MW Suspended
PJM Bottlebrush SolarLake County Solar 200 MW Engineering and procurement
PJM Golden Aster Solar Energy CenterGrant County Battery storage 200 MW Suspended
PJM Lake Trout SolarBlackford County Solar plus storage 200 MW Engineering and procurement
PJM Blackford Wind Energy ProjectBlackford County Onshore wind 200 MW Under construction
PJM Black Prairie Solar ParkWhite County Solar 200 MW Under construction
PJM Honey Creek SolarWhite County Solar plus storage 200 MW Under construction
PJM Teays River Wind FarmBlackford County Onshore wind 200 MW Engineering and procurement
PJM Moss Creek SolarPulaski County Solar 200 MW Engineering and procurement
PJM Prairie Creek WindBlackford County Onshore wind 200 MW Engineering and procurement
PJM Warren County Wind Energy CenterN/A County Onshore wind 200 MW Engineering and procurement
PJM East Elkhart - Elcona Tap 138 kV AG2-332Elkhart County Battery storage 200 MW Active
PJM Losantville 345 kV AG2-401Randolph County Solar 200 MW Active
PJM Dumont 345 kV AH1-153St. Joseph County Solar 200 MW Active
PJM Sullivan 345 kV AH1-292Sullivan County Solar 200 MW Active
PJM Mississinewa-Gaston 138 kV AH1-306Grant County Solar 200 MW Active
MISO Speed - Trimble (LGEE) 345.0kVDUKE ENERGY INDIANA, LLC CINClark County Solar 200 MW Active; not started
MISO Noblesville - Fall Creek (AEP) 345.0kVINDIANAPOLIS POWER & LIGHT COMPANYHamilton County Solar 200 MW Active; not started
MISO Owensville PrimaryHOOSIER ENERGYGibson County Battery storage 200 MW Pending revision approval
MISO Petersburg - Sullivan (AEP/PJM) 345.0kVHOOSIER ENERGYSullivan County Other hybrids 200 MW Active
MISO Petersburg - Sullivan (AEP/PJM) 345.0kVHOOSIER ENERGYSullivan County Other hybrids 200 MW Active
MISO Gibson Sta - Merom (HED) 345.0kVDUKE ENERGY INDIANA, LLC CINSullivan County Other hybrids 200 MW Active
MISO Gibson Sta - Merom (HED) 345.0kVDUKE ENERGY INDIANA, LLC CINSullivan County Other hybrids 200 MW Active
MISO SCHAHFER GEN STA - ST. JOHN 345.0kVLake County Battery storage 200 MW Active
MISO Walton 230DUKE ENERGY INDIANA, LLC CINCass County Battery storage 200 MW Pending transfer
PJM Sculpin SolarDeKalb County Solar 180 MW Engineering and procurement
PJM Hoosier Line SolarWhite County Solar 180 MW Engineering and procurement
PJM Meadow Forge Solar Energy CenterDelaware County Solar 163 MW Suspended
PJM Delaware-Van Buren 138 kV AH1-304Delaware County Solar 163 MW Active
PJM Golden Aster Solar Energy CenterGrant County Solar 160 MW Suspended
PJM Skycrest Solar Energy CenterJay County Solar 155 MW Suspended
PJM Madison - Tanners Creek 138 kV AG2-487Henry County Solar 152 MW Active
PJM Blackford Solar Energy ProjectJay County Solar 150 MW Under construction
PJM Rosegold SolarBlackford County Solar 150 MW Engineering and procurement
PJM Eugene 345 kV AG2-126Vermillion County Solar plus storage 150 MW Active
PJM Dumont 345 kV AG2-230St. Joseph County Solar 150 MW Active
PJM Eugene - Dequine 345 kV AG2-345Fountain County Battery storage 150 MW Active
PJM Bluff Point - Randolph 138 kV AG2-551Randolph County Battery storage 150 MW Active
PJM Randolph - Hodgin 138 kV AG2-637Randolph County Solar 150 MW Active
MISO WorthingtonHOOSIER ENERGYGreene County Battery storage 150 MW Active
MISO Edwardsport - Washington MunDUKE ENERGY INDIANA, LLCKnox County Battery storage 150 MW Active
MISO MORRISON DITCHNORTHERN INDIANA PUBLIC SERVICE COMPANY LLCNewton County Battery storage 150 MW Active
PJM Magley Solar Energy CenterAdams County Solar 135 MW Engineering and procurement
PJM Meadow Forge Solar Energy CenterDelaware County Solar 130 MW Suspended
MISO Cato 138/69kV (facilities above 100kV)SOUTHERN INDIANA GAS & ELECTRIC COMPANY D/B/A CENTERPOINT ENERGY INDIANA SOUTHPike County Battery storage 130 MW Active
PJM Riverstart Solar Park IIRandolph County Solar 125 MW Engineering and procurement
PJM Bluestem SolarLaPorte County Solar 125 MW Engineering and procurement
PJM Rainbow TroutTippecance County Solar plus storage 120 MW Engineering and procurement
PJM Madison County SolarMadison County Solar 100 MW Suspended
PJM Headwaters Wind Farm IIIRandolph County Onshore wind 100 MW Suspended
PJM Riverstart Solar Park VRandolph County Solar 100 MW Engineering and procurement
PJM Flatrock Creek Solar IAllen County Solar 100 MW Engineering and procurement
PJM Sun Chief Solar FarmJay County Solar 100 MW Engineering and procurement
PJM Flatrock Creek Solar IIAllen County Solar 100 MW Engineering and procurement
PJM Keystone-DeSoto 345 kV AG1-433Blackford County Onshore wind 100 MW Engineering and procurement
PJM East Elkhart - Elcona Tap 138 kV AG2-248Elkhart County Battery storage 100 MW Active
PJM Eugene - Dequine 345 kV AG2-343Fountain County Battery storage 100 MW Active
PJM Meadow Lake 345 kV AG2-491White County Solar 100 MW Active
PJM Bluff Point - Randolph 138 kV AG2-550Randolph County Solar 100 MW Active
MISO NIPSCO Green Acres 138kV SubNORTHERN INDIANA PUBLIC SERVICE COMPANY LLC NIPSLake County Battery storage 100 MW Active
MISO LAGRANGENORTHERN INDIANA PUBLIC SERVICE COMPANY LLC NIPSLaGrange County Battery storage 100 MW Active
PJM Gravel Pit-Kankakee 138 kV AH1-392St. Joseph County Solar 90 MW Active
PJM Hawthorn SolarDelaware County Solar 83 MW Pending termination
PJM Fall Creek Energy StorageMadison County Battery storage 80 MW Engineering and procurement

Showing the 100 largest of 111.

Planned generation in Indiana

5,003 MW across 28 EIA-860M generators scheduled to enter service within 36 months.

PlantTechnologyMWPlannedStatusSource
Sycamore Riverside Energy, LLCSullivan County Natural Gas Fired Combustion Turbine 964 MW Mar 2029 Planned for installation, but regulatory approvals not initiated
Mammoth South Solar ProjectPulaski County Solar Photovoltaic 300 MW Sep 2026 Under construction, more than 50 percent complete
Mammoth Central Solar ProjectPulaski County Solar Photovoltaic 300 MW Oct 2026 Under construction, less than or equal to 50 percent complete
Mammoth Central II Solar FacilityPulaski County Solar Photovoltaic 300 MW Oct 2026 Under construction, less than or equal to 50 percent complete
Patoka SolarPosey County Solar Photovoltaic 250 MW Sep 2027 Planned for installation, but regulatory approvals not initiated
Lake Trout SolarBlackford County Solar Photovoltaic 245 MW Dec 2027 Planned for installation, but regulatory approvals not initiated
R M SchahferJasper County Natural Gas Fired Combustion Turbine 234 MW Dec 2027 Regulatory approvals received. Not under construction
Mayapple Solar 1Pulaski County Solar Photovoltaic 224 MW Mar 2029 Regulatory approvals received. Not under construction
Templeton WindBenton County Onshore Wind Turbine 200 MW Jun 2027 Regulatory approvals received. Not under construction
Honey Creek SolarWhite County Solar Photovoltaic 200 MW Dec 2027 Planned for installation, but regulatory approvals not initiated
Blackford WindBlackford County Onshore Wind Turbine 200 MW Dec 2026 Under construction, more than 50 percent complete
Vermillion Rise SolarVermillion County Solar Photovoltaic 185 MW Dec 2027 Planned for installation, but regulatory approvals not initiated
Sculpin SolarDeKalb County Solar Photovoltaic 180 MW Dec 2028 Planned for installation, but regulatory approvals not initiated
Hoosier Line SolarWhite County Solar Photovoltaic 180 MW Oct 2027 Planned for installation, but regulatory approvals not initiated
Blackford SolarBlackford County Solar Photovoltaic 150 MW Oct 2026 Under construction, more than 50 percent complete
Rose Gold SolarJay County Solar Photovoltaic 100 MW Dec 2027 Planned for installation, but regulatory approvals not initiated
Merrillville SolarLake County Solar Photovoltaic 100 MW Nov 2028 Planned for installation, but regulatory approvals not initiated
Crossvine SolarDubois County Solar Photovoltaic 100 MW Mar 2027 Under construction, less than or equal to 50 percent complete
Rustic Hills Solar IWarrick County Solar Photovoltaic 100 MW Oct 2028 Regulatory approvals received. Not under construction
Rustic Hills Solar II LLCWarrick County Solar Photovoltaic 100 MW Oct 2028 Regulatory approvals received. Not under construction
Duff Solar ParkDubois County Solar Photovoltaic 100 MW Oct 2026 Under construction, more than 50 percent complete
R M SchahferJasper County Natural Gas Fired Combustion Turbine 72 MW Dec 2027 Regulatory approvals received. Not under construction
R M SchahferJasper County Natural Gas Fired Combustion Turbine 72 MW Dec 2027 Regulatory approvals received. Not under construction
R M SchahferJasper County Natural Gas Fired Combustion Turbine 72 MW Dec 2027 Regulatory approvals received. Not under construction
New Jay PV & BESSJay County Solar Photovoltaic 39 MW Sep 2028 Planned for installation, but regulatory approvals not initiated
Honey Creek SolarWhite County Batteries 20 MW Dec 2027 Planned for installation, but regulatory approvals not initiated
Crawfordsville Power PlantMontgomery County Natural Gas Fired Combined Cycle 16 MW Mar 2027 Regulatory approvals received. Not under construction
Bos Dairy, LLCJasper County Natural Gas Internal Combustion Engine 1 MW Aug 2026 Construction complete, but not yet in commercial operation

Other filings in Indiana

State air permits (1)

FacilityAgencyGeneratorsStatusSource
Amazon Data Services, Inc.St. Joseph County Indiana IDEM Notice of 30-Day Public Comment Period for Draft Air Permit , comment period 08/17/2026 - 09/16/2026

Where Indiana stands

Across the whole tracker, 533 data center and substation permits are on record in 51 states and DC. Indiana accounts for 0 of them, ranking #13 by that count. Ranking measures documented permit activity, not the size of the eventual buildout.