Massachusetts Data Center Permits Tracker

Massachusetts has 14,275 MW of generation and storage requested in the interconnection queue and 727 MW of generation planned within 36 months. Every row below links to its primary source.

Last checked Sep 18, 2026

0
Data center & substation permits
of 0 total utility-scale permits tracked here
14,275MW
In the interconnection queue
20 active generation and storage positions
727MW
Planned generation
31 EIA-860M generators due within 36 months
#13
of 51 states with anything on record
Ranked by data center & substation permit count

Where the activity is

Ranked by row count. Counts are never mixed with the MW figures above.

Top counties · queue, substation & state air rows

NA 6
Norfolk 3
Barnstable 2
Berkshire 2
Middlesex 2
Bristol 1
Essex 1
Franklin 1

Interconnection queue in Massachusetts

14,275 MW requested across 20 active generation and storage positions. Withdrawn and in-service rows are left out, matching the national page.

ISOProjectFuelMWStatusSource
ISO-NE SouthCoast Wind 1PDNA County Onshore wind 1,200 MW Interconnection agreement
ISO-NE Somerset Wind Link - 1200 MW HVDC Line (Controllable) into Brayton PointPDBristol County Fuel not stated 1,200 MW Interconnection agreement
ISO-NE Bay State Wind 4 Offshore WindPDNA County Onshore wind 1,200 MW Interconnection agreement
ISO-NE Northfield Mt. Equipment ReplacementFranklin County Hydro and pumped storage 1,180 MW Interconnection agreement
ISO-NE Vineyard Offshore Wind CNRNAN/A County Onshore wind 843 MW Active
ISO-NE Park City Offshore Wind CNRNA County Onshore wind 838 MW Active
ISO-NE Fore River CNR IncreaseNorfolk County Natural gas 800 MW Active
ISO-NE Vineyard Offshore WindPDNA County Onshore wind 800 MW Interconnection agreement
ISO-NE Fore River CNR UprateNorfolk County Natural gas 800 MW Active
ISO-NE Vineyard Offshore Wind CNR OnlyNA County Onshore wind 800 MW Active
ISO-NE Park City Offshore WindPDNA County Onshore wind 791 MW Interconnection agreement
ISO-NE Footprint Combined Cycle UnitBLEssex County Natural gas 716 MW Interconnection agreement
ISO-NE Battery StorageNAMiddlesex County Battery storage 508 MW Interconnection agreement
ISO-NE Battery StoragePDBarnstable County Battery storage 500 MW Active
ISO-NE Battery StoragePDMiddlesex County Battery storage 500 MW Active
ISO-NE Bear Swamp Pumping Load IncreaseBerkshire County Hydro and pumped storage 333 MW Active
ISO-NE Bear Swamp Pump Load increasePDBerkshire County Hydro and pumped storage 333 MW System impact study complete
ISO-NE Canal 3Barnstable County Natural gas 333 MW Interconnection agreement
ISO-NE Lite Brite Battery StorageSuffolk County Battery storage 300 MW Interconnection agreement
ISO-NE Battery StoragePDNorfolk County Battery storage 300 MW Active

Planned generation in Massachusetts

727 MW across 31 EIA-860M generators scheduled to enter service within 36 months.

PlantTechnologyMWPlannedStatusSource
Energizar BESSSuffolk County Batteries 250 MW Sep 2027 Regulatory approvals pending. Not under construction
Taft BESSWorcester County Batteries 200 MW Feb 2027 Under construction, more than 50 percent complete
Salt Cod BESSBristol County Batteries 168 MW Dec 2028 Regulatory approvals pending. Not under construction
Town of Sharon Portfolio -Mt St LandfillNorfolk County Batteries 6 MW Jan 2027 Under construction, more than 50 percent complete
Sturbridge Road SolarWorcester County Solar Photovoltaic 5 MW Oct 2026 Construction complete, but not yet in commercial operation
Borrego - Highland AveBristol County Solar Photovoltaic 5 MW Nov 2026 Under construction, less than or equal to 50 percent complete
Borrego - Highland AveBristol County Batteries 5 MW Nov 2026 Under construction, less than or equal to 50 percent complete
Braley Hill North SolarPlymouth County Batteries 5 MW Mar 2027 Regulatory approvals pending. Not under construction
Braley Hill North SolarPlymouth County Solar Photovoltaic 5 MW Mar 2027 Regulatory approvals pending. Not under construction
Randall Lane SolarPlymouth County Batteries 5 MW Mar 2027 Regulatory approvals pending. Not under construction
Randall Lane SolarPlymouth County Solar Photovoltaic 5 MW Mar 2027 Regulatory approvals pending. Not under construction
Town of Sharon Portfolio -Mt St LandfillNorfolk County Solar Photovoltaic 5 MW Jan 2027 Under construction, more than 50 percent complete
Holyoke MA BESS 1Hampden County Batteries 5 MW Sep 2026 Under construction, less than or equal to 50 percent complete
Ipswich MA BESS 1Essex County Batteries 5 MW Oct 2026 Under construction, less than or equal to 50 percent complete
Chicopee BESSHampden County Batteries 5 MW Sep 2026 Under construction, less than or equal to 50 percent complete
Framingham BESSMiddlesex County Batteries 5 MW Sep 2026 Under construction, less than or equal to 50 percent complete
Clems Way SolarBristol County Solar Photovoltaic 5 MW Jul 2027 Regulatory approvals received. Not under construction
Logging Swamp NorthPlymouth County Solar Photovoltaic 5 MW Aug 2027 Regulatory approvals received. Not under construction
Logging Swamp SouthPlymouth County Solar Photovoltaic 5 MW Aug 2027 Regulatory approvals received. Not under construction
MA Acushnet 540R Main StBristol County Solar Photovoltaic 4 MW Mar 2027 Regulatory approvals pending. Not under construction
Snipatuit Road SolarPlymouth County Batteries 4 MW Mar 2027 Regulatory approvals pending. Not under construction
Snipatuit Road SolarPlymouth County Solar Photovoltaic 4 MW Mar 2027 Regulatory approvals pending. Not under construction
Cushman Road SolarPlymouth County Batteries 3 MW May 2027 Regulatory approvals pending. Not under construction
Cushman Road SolarPlymouth County Solar Photovoltaic 3 MW May 2027 Regulatory approvals pending. Not under construction
Solar Carver 1 HybridPlymouth County Batteries 2 MW Sep 2026 Under construction, more than 50 percent complete
Solar Carver 1 HybridPlymouth County Solar Photovoltaic 2 MW Sep 2026 Under construction, more than 50 percent complete
MA Acushnet 540R Main StBristol County Batteries 2 MW Mar 2027 Regulatory approvals pending. Not under construction
Solar Carver 3 HybridPlymouth County Batteries 1 MW Sep 2026 Under construction, more than 50 percent complete
Solar Carver 3 HybridPlymouth County Solar Photovoltaic 1 MW Sep 2026 Under construction, more than 50 percent complete
Featherbed Lane South SolarPlymouth County Batteries 1 MW Mar 2027 Regulatory approvals pending. Not under construction
Featherbed Lane South SolarPlymouth County Solar Photovoltaic 1 MW Mar 2027 Regulatory approvals pending. Not under construction

Where Massachusetts stands

Across the whole tracker, 533 data center and substation permits are on record in 51 states and DC. Massachusetts accounts for 0 of them, ranking #13 by that count. Ranking measures documented permit activity, not the size of the eventual buildout.