North Dakota has 5,470 MW of generation and storage requested in the interconnection queue and 1,922 MW of generation planned within 36 months. Every row below links to its primary source.
Last checked Sep 18, 2026
Where the activity is
Ranked by row count. Counts are never mixed with the MW figures above.
Interconnection queue in North Dakota
5,470 MW requested across 17 active generation and storage positions. Withdrawn and in-service rows are left out, matching the national page.
| ISO | Project | Fuel | MW | Status | Source |
|---|---|---|---|---|---|
| SPP | ERAS-2025-011Stanton County | Natural gas | 750 MW | Eras | |
| SPP | ERAS-2025-012Stanton County | Natural gas | 750 MW | Eras | |
| SPP | GEN-2024-081Williams County | Natural gas | 745 MW | Disis stage | |
| SPP | GEN-2024-082Williams County | Natural gas | 745 MW | Disis stage | |
| MISO | BISONNORTHERN STATES POWER COMPANYCass County | Other hybrids | 481 MW | Active; not started | |
| MISO | EllendaleMONTANA-DAKOTA UTILITIES CO.MDUDickey County | Onshore wind | 300 MW | Active | |
| SPP | GEN-2024-141Mercer County | Onshore wind | 212 MW | Disis stage | |
| SPP | GEN-2026-SR33Oliver County County | Battery storage | 202 MW | Special study | |
| SPP | GEN-2024-327Ward County | Battery storage | 200 MW | Disis stage | |
| SPP | GEN-2024-329Williams County | Battery storage | 200 MW | Disis stage | |
| MISO | Buffalo 115 kVOTTER TAIL POWER COMPANY OTPCass County | Onshore wind | 200 MW | Active | |
| MISO | BISONNORTHERN STATES POWER COMPANYCass County | Battery storage | 200 MW | Active | |
| MISO | Hankinson - Wahpeton 230.0kVOTTER TAIL POWER COMPANYRichland County | Other hybrids | 172 MW | Active | |
| SPP | GEN-2026-SR6South Heart County | Battery storage | 150 MW | Special study | |
| SPP | GEN-2026-SR7South Heart County | Battery storage | 150 MW | Special study | |
| SPP | GEN-2025-GR5Minot County | Onshore wind | 8 MW | Special study | |
| SPP | GEN-2025-GR3Max County | Onshore wind | 5 MW | Special study |
Planned generation in North Dakota
1,922 MW across 8 EIA-860M generators scheduled to enter service within 36 months.
| Plant | Technology | MW | Planned | Status | Source |
|---|---|---|---|---|---|
| Bison Generation StationWilliams County | Natural Gas Fired Combined Cycle | 496 MW | Feb 2029 | Regulatory approvals pending. Not under construction | |
| Abercrombie SolarRichland County | Solar Photovoltaic | 295 MW | Aug 2028 | Regulatory approvals pending. Not under construction | |
| Bison Generation StationWilliams County | Natural Gas Fired Combined Cycle | 263 MW | Feb 2029 | Regulatory approvals pending. Not under construction | |
| New Salem Wind IIMorton County | Onshore Wind Turbine | 226 MW | Dec 2028 | Planned for installation, but regulatory approvals not initiated | |
| Red Butte WindMorton County | Onshore Wind Turbine | 202 MW | Dec 2027 | Planned for installation, but regulatory approvals not initiated | |
| New Salem Wind IMorton County | Onshore Wind Turbine | 200 MW | Dec 2028 | Planned for installation, but regulatory approvals not initiated | |
| Emmons-Logan Energy StorageEmmons County | Batteries | 140 MW | Dec 2026 | Under construction, more than 50 percent complete | |
| Northern Divide Energy StorageBurke County | Batteries | 100 MW | Dec 2026 | Under construction, more than 50 percent complete |
Where North Dakota stands
Across the whole tracker, 533 data center and substation permits are on record in 51 states and DC. North Dakota accounts for 0 of them, ranking #13 by that count. Ranking measures documented permit activity, not the size of the eventual buildout.