Pennsylvania Data Center Permits Tracker

Pennsylvania has 9,836 MW of generation and storage requested in the interconnection queue and 5,581 MW of generation planned within 36 months. Every row below links to its primary source.

Last checked Sep 18, 2026

0
Data center & substation permits
of 0 total utility-scale permits tracked here
9,836MW
In the interconnection queue
117 active generation and storage positions
5,581MW
Planned generation
80 EIA-860M generators due within 36 months
#13
of 51 states with anything on record
Ranked by data center & substation permit count

Where the activity is

Ranked by row count. Counts are never mixed with the MW figures above.

Top counties · queue, substation & state air rows

Clearfield 11
Centre 7
Crawford 7
Somerset 7
Columbia 6
York 6
Adams 5
Erie 5

Interconnection queue in Pennsylvania

9,836 MW requested across 117 active generation and storage positions. Withdrawn and in-service rows are left out, matching the national page.

ISOProjectFuelMWStatusSource
PJM South Bend 500 kV AH1-734Indiana County Natural gas 1,058 MW Active
PJM Three Mile Island 230 kV AH1-695Dauphin County Nuclear 859 MW Active
NYISO EVERGREEN RIDGE POWEREvergreen Ridge Power, LLCTIOGA County Natural gas 624 MW Status code 1
NYISO Mineral Basin Solar PowerMineral Basin Solar Power, LLCClearfield County Solar 402 MW Status code 10
NYISO Shallow Seam BESSShallow Seam Energy Storage, LLCClearfield County Battery storage 400 MW Status code 7
NYISO Stargazer IRWE Solar Development, LLCMcKean County Other 325 MW Status code 7
NYISO Stargazer IIRWE Solar Development, LLCMcKean County Other 325 MW Status code 7
NYISO Moonlight Flats SolarMoonlight Flats Solar Power, LLCClearfield County Solar 250 MW Status code 7
PJM Wylie Ridge-Tidd 345kV AH1-545Washington County Solar 200 MW Active
NYISO Kimberlite SolarKimberlite Solar Power, LLCClearfield County Solar 175 MW Status code 7
PJM MPG SolarCentre County Solar 162 MW Engineering and procurement
PJM Erie East EnergyErie County Battery storage 160 MW Suspended
PJM Energy MountainBucks County Battery storage 150 MW Engineering and procurement
PJM Maple Hill-Fiddlers 1 SP (Bear Rock)Cambria County Solar 150 MW Engineering and procurement
PJM Erie South-Union City 115 kV AG1-548Erie County Solar plus storage 150 MW Engineering and procurement
PJM Geneva 115 kV AG2-176Crawford County Solar 150 MW Active
PJM Hoytdale 138 kV AG2-621Beaver County Battery storage 150 MW Active
PJM Lardin - Lake Lynn 138kV AH1-249Fayette County Battery storage 145 MW Active
PJM Black Moshannon SolarCentre County Solar 135 MW Engineering and procurement
PJM Squab SolarJefferson County Solar 132 MW Under construction
PJM Clermont SolarMcKean County Solar 120 MW Under construction
PJM Black Moshannon SolarCentre County Solar 115 MW Engineering and procurement
PJM Hoodlebug Solar Energy CenterIndiana County Solar 110 MW Engineering and procurement
PJM Rogue's WindClearfield County Onshore wind 110 MW Partially in service - under construction
PJM Madera - Westover South 115 kV AH1-746Clearfield County Onshore wind 110 MW Active
PJM Bradford SolarMcKean County Solar 100 MW Engineering and procurement
PJM Rockdale SolarSomerset County Solar 100 MW Engineering and procurement
PJM Philipsburg 115 kV AG1-090Centre County Solar plus storage 95 MW Engineering and procurement
PJM Squab SolarJefferson County Solar 90 MW Under construction
PJM MPG SolarCentre County Solar 84 MW Engineering and procurement
PJM Swiftwater SolarMonroe County Solar 80 MW Partially in service - under construction
PJM Wilson SolarErie County Solar 80 MW Engineering and procurement
PJM Limestone SolarUnion County Solar 80 MW Engineering and procurement
PJM Walker Solar TwoJuniata County Solar 80 MW Under construction
PJM Strinestown Solar ProjectYork County Solar 80 MW Suspended
PJM Dover SolarYork County Solar 75 MW Engineering and procurement
PJM Granite Hill SolarAdams County Solar 70 MW Suspended
PJM Hooversville - Scalp Level 115 kV AH1-460Somerset County Solar 66 MW Active
PJM Lardin - Lake Lynn 138kV AH1-248Fayette County Solar 65 MW Active
PJM Statler Hill 115 kV AG2-411Somerset County Solar 63 MW Active
PJM Limestone SolarUnion County Solar 60 MW Engineering and procurement
PJM Mora SolarCarbon County Solar 60 MW Engineering and procurement
PJM Club Ford Energy CenterLuzerne County Solar 60 MW Engineering and procurement
PJM Potter-Harlan 69 kV AG2-236Lawrence County Solar 60 MW Engineering and procurement
PJM Bethelboro 138 kV AH1-206Fayette County Battery storage 60 MW Active
PJM Dover SolarYork County Solar 55 MW Engineering and procurement
PJM MC SolarMercer County Solar 50 MW Under construction
PJM SunEast Hooversville SolarSomerset County Solar 50 MW Suspended
PJM Burma - Armstrong 138 kV AG2-429Clarion County Solar plus storage 46 MW Active
PJM Limestone SolarUnion County Solar 40 MW Engineering and procurement
PJM SunEast Hooversville SolarSomerset County Solar 40 MW Suspended
PJM Washington West SolarSnyder County Solar plus storage 40 MW Under construction
PJM Shamrock Energy CenterAdams County Solar 40 MW Under construction
PJM Frosty Valley Energy CenterColumbia County Solar 40 MW Engineering and procurement
PJM Green Meadows SolarLawrence County Solar 40 MW Under construction
PJM Club Ford Energy CenterLuzerne County Solar 40 MW Engineering and procurement
PJM Lardin - Lake Lynn 138kV AH1-247Fayette County Solar 40 MW Active
PJM Meckesville Tap 69kV AG2-074Carbon County Solar 38 MW Active
PJM Potter SolarPotter County Solar 35 MW Partially in service - under construction
PJM Cottontail Solar 7Columbia County Solar 35 MW Suspended
PJM Boyles Run SolarNorthumberland County Solar 32 MW Pending termination
PJM Eclipse #2 34.5 kV AG2-420Venango County Solar plus storage 25 MW Active
PJM Jackson Center Solar FacilityMercer County Solar 20 MW Partially in service - under construction
PJM Confer Solar ICentre County Solar 20 MW Suspended
PJM Montour 1Columbia County Solar 20 MW Suspended
PJM HU-PaulsHuntingdon County Solar 20 MW Suspended
PJM HU-LoggingHuntingdon County Solar 20 MW Engineering and procurement
PJM UN-KylertownWestmoreland County Solar 20 MW Under construction
PJM Mountain HollyColumbia County Solar 20 MW Suspended
PJM Momentum GratzDauphin County Battery storage 20 MW Engineering and procurement
PJM Jackson Center Solar IIMercer County Solar 20 MW Partially in service - under construction
PJM Franklin SolarCrawford County Solar 20 MW Under construction
PJM CL-Green AcresClearfield County Solar 20 MW Under construction
PJM Jakes Hollow SolarElk County Solar 20 MW Suspended
PJM SunEast Hooversville SolarSomerset County Solar 20 MW Suspended
PJM Limestone SolarUnion County Solar 20 MW Engineering and procurement
PJM Abes Run SolarClearfield County Solar 20 MW Under construction
PJM Gobbler KnobCumberland County Solar 20 MW Engineering and procurement
PJM Washington East SolarSnyder County Solar plus storage 20 MW Under construction
PJM Farmers Valley SolarBradford County Solar 20 MW Engineering and procurement
PJM CL- Belsena SolarClearfield County Solar 20 MW Engineering and procurement
PJM WA-Cochecton 2Adams County Solar 20 MW Engineering and procurement
PJM Club Ford Energy CenterAdams County Solar 20 MW Engineering and procurement
PJM Shamrock Energy CenterNorthumberland County Solar 20 MW Under construction
PJM Frosty Valley Energy CenterColumbia County Solar 20 MW Engineering and procurement
PJM Nichols SolarCrawford County Solar 20 MW Under construction
PJM Henry SolarCrawford County Solar 20 MW Engineering and procurement
PJM BL-Hileman HollowBlair County Solar 20 MW Under construction
PJM South Troy - Canton 34.5 kV AG2-356Bradford County Solar 20 MW Active
PJM Hokes-Grantley 69 kV II AG2-476York County Solar 20 MW Engineering and procurement
PJM Hokes-Jackson 69 kV III AG2-477York County Solar 20 MW Engineering and procurement
PJM Hokes-Jackson 69 kV IV AG2-478York County Solar 20 MW Engineering and procurement
PJM Penns Tap-Richfield Tie 69 kV II AG2-479Snyder County Solar 20 MW Active
PJM Derry Tap-Derry Bus 69 kV III AG2-481Northumberland County Solar 20 MW Active
PJM Mifflintown Bus-Mifflintown Tap 69 kV II AG2-484Juniata County Solar 20 MW Active
PJM Glory - Glen Campbell 34.5 kV AG2-561Indiana County Solar 20 MW Active
PJM Welcome Solar, LLCMercer County Solar 20 MW Under construction
PJM Welcome Solar IICrawford County Solar 20 MW Partially in service - under construction
PJM Clementine-Clementine Jct. 25 kV AH1-452Armstrong County Solar 20 MW Active
PJM Stoneybrook SolarColumbia County Solar 20 MW Engineering and procurement

Showing the 100 largest of 117.

Planned generation in Pennsylvania

5,581 MW across 80 EIA-860M generators scheduled to enter service within 36 months.

PlantTechnologyMWPlannedStatusSource
Mineral Basin Solar PowerClearfield County Solar Photovoltaic 402 MW Dec 2028 Planned for installation, but regulatory approvals not initiated
Firefly Solar PALawrence County Solar Photovoltaic 402 MW Dec 2027 Regulatory approvals pending. Not under construction
Homer City Generating StationIndiana County Natural Gas Fired Combined Cycle 360 MW Nov 2028 Planned for installation, but regulatory approvals not initiated
Homer City Generating StationIndiana County Natural Gas Fired Combined Cycle 360 MW Nov 2028 Planned for installation, but regulatory approvals not initiated
Homer City Generating StationIndiana County Natural Gas Fired Combined Cycle 360 MW Jul 2029 Planned for installation, but regulatory approvals not initiated
Homer City Generating StationIndiana County Natural Gas Fired Combined Cycle 360 MW Jul 2028 Planned for installation, but regulatory approvals not initiated
Homer City Generating StationIndiana County Natural Gas Fired Combined Cycle 360 MW Jul 2028 Planned for installation, but regulatory approvals not initiated
Homer City Generating StationIndiana County Natural Gas Fired Combined Cycle 360 MW Mar 2029 Planned for installation, but regulatory approvals not initiated
Homer City Generating StationIndiana County Natural Gas Fired Combined Cycle 268 MW Nov 2028 Planned for installation, but regulatory approvals not initiated
Homer City Generating StationIndiana County Natural Gas Fired Combined Cycle 268 MW Nov 2028 Planned for installation, but regulatory approvals not initiated
Homer City Generating StationIndiana County Natural Gas Fired Combined Cycle 268 MW Jul 2029 Planned for installation, but regulatory approvals not initiated
Homer City Generating StationIndiana County Natural Gas Fired Combined Cycle 268 MW Jul 2028 Planned for installation, but regulatory approvals not initiated
Homer City Generating StationIndiana County Natural Gas Fired Combined Cycle 268 MW Jul 2028 Planned for installation, but regulatory approvals not initiated
Homer City Generating StationIndiana County Natural Gas Fired Combined Cycle 268 MW Mar 2029 Planned for installation, but regulatory approvals not initiated
MPG SolarCentre County Solar Photovoltaic 162 MW Jul 2028 Regulatory approvals received. Not under construction
Clermont SolarMcKean County Solar Photovoltaic 120 MW Sep 2026 Under construction, less than or equal to 50 percent complete
Bradford Solar PABradford County Solar Photovoltaic 100 MW Dec 2027 Regulatory approvals pending. Not under construction
Walker SolarJuniata County Solar Photovoltaic 80 MW Dec 2026 Under construction, less than or equal to 50 percent complete
Strinestown SolarYork County Solar Photovoltaic 80 MW Dec 2027 Regulatory approvals received. Not under construction
Dover Solar (PA)York County Solar Photovoltaic 75 MW Nov 2027 Regulatory approvals received. Not under construction
Mora SolarCarbon County Solar Photovoltaic 60 MW Dec 2027 Planned for installation, but regulatory approvals not initiated
MC SolarMercer County Solar Photovoltaic 50 MW Jan 2027 Under construction, less than or equal to 50 percent complete
Beaver Creek SolarFranklin County Solar Photovoltaic 34 MW Jun 2027 Regulatory approvals pending. Not under construction
PF Onsite BESSLuzerne County Batteries 21 MW Jun 2027 Regulatory approvals pending. Not under construction
BAI-Boyles Run-Phase INorthumberland County Solar Photovoltaic 16 MW Sep 2028 Planned for installation, but regulatory approvals not initiated
BAI-Boyles Run-Phase 2Northumberland County Solar Photovoltaic 16 MW Sep 2028 Planned for installation, but regulatory approvals not initiated
Stony Creek SolarSomerset County Solar Photovoltaic 15 MW Oct 2028 Regulatory approvals received. Not under construction
Montgomery L&D Hydroelectric ProjectBeaver County Conventional Hydroelectric 7 MW Oct 2028 Planned for installation, but regulatory approvals not initiated
Montgomery L&D Hydroelectric ProjectBeaver County Conventional Hydroelectric 7 MW Nov 2028 Planned for installation, but regulatory approvals not initiated
Montgomery L&D Hydroelectric ProjectBeaver County Conventional Hydroelectric 7 MW Dec 2028 Planned for installation, but regulatory approvals not initiated
Maxwell L&D Hydroelectric ProjectFayette County Conventional Hydroelectric 6 MW Nov 2028 Planned for installation, but regulatory approvals not initiated
Maxwell L&D Hydroelectric ProjectFayette County Conventional Hydroelectric 6 MW Dec 2028 Planned for installation, but regulatory approvals not initiated
Grays Landing L&D Hydroelectric ProjectGreene County Conventional Hydroelectric 6 MW Jun 2028 Planned for installation, but regulatory approvals not initiated
Grays Landing L&D Hydroelectric ProjectGreene County Conventional Hydroelectric 6 MW Jul 2028 Planned for installation, but regulatory approvals not initiated
Monongahela L&D4 Hydroelectric ProjectWashington County Conventional Hydroelectric 6 MW Oct 2028 Planned for installation, but regulatory approvals not initiated
Monongahela L&D4 Hydroelectric ProjectWashington County Conventional Hydroelectric 6 MW Nov 2028 Planned for installation, but regulatory approvals not initiated
Braddock Lock and DamAllegheny County Conventional Hydroelectric 5 MW Mar 2027 Regulatory approvals pending. Not under construction
Maple Ridge AFranklin County Solar Photovoltaic 3 MW Apr 2028 Under construction, less than or equal to 50 percent complete
Maple Ridge BFranklin County Solar Photovoltaic 3 MW Apr 2028 Under construction, less than or equal to 50 percent complete
Montour Tower Drive Solar LLCColumbia County Solar Photovoltaic 3 MW Sep 2027 Regulatory approvals received. Not under construction
Muncy Creek Lime Bluff Road SolarLycoming County Solar Photovoltaic 3 MW Nov 2027 Regulatory approvals received. Not under construction
Penn Hemlock Solar LLCSnyder County Solar Photovoltaic 3 MW Dec 2026 Under construction, less than or equal to 50 percent complete
Franklin White Church Road Solar LLCSnyder County Solar Photovoltaic 3 MW Mar 2027 Under construction, less than or equal to 50 percent complete
Greenwood Bottom Road Solar LLCColumbia County Solar Photovoltaic 3 MW Mar 2027 Under construction, less than or equal to 50 percent complete
Greenwood Route 254 Solar LLCColumbia County Solar Photovoltaic 3 MW Mar 2027 Under construction, less than or equal to 50 percent complete
Madison Taylor Road Solar LLCColumbia County Solar Photovoltaic 3 MW Mar 2027 Under construction, less than or equal to 50 percent complete
Monroe Route 35 Solar LLCJuniata County Solar Photovoltaic 3 MW Dec 2026 Under construction, less than or equal to 50 percent complete
Penn Shoofly Solar LLCColumbia County Solar Photovoltaic 3 MW May 2027 Regulatory approvals received. Not under construction
Perry Route 104 Solar LLCSnyder County Solar Photovoltaic 3 MW Dec 2026 Under construction, less than or equal to 50 percent complete
West Perry Planing Mill Road Solar LLCSnyder County Solar Photovoltaic 3 MW Feb 2027 Under construction, less than or equal to 50 percent complete
Beaver Gross Road Solar LLCSnyder County Solar Photovoltaic 3 MW Mar 2028 Regulatory approvals received. Not under construction
Delaware Conrath Road Solar LLCNorthumberland County Solar Photovoltaic 3 MW Mar 2028 Regulatory approvals received. Not under construction
Liberty Keefer Mill Road Solar LLCMontour County Solar Photovoltaic 3 MW Jun 2028 Regulatory approvals received. Not under construction
Bigler - PA 0409 (Flango 1)Clearfield County Solar Photovoltaic 3 MW Nov 2027 Under construction, less than or equal to 50 percent complete
Bigler - PA 0436 (Flango 2)Clearfield County Solar Photovoltaic 3 MW Feb 2028 Under construction, less than or equal to 50 percent complete
Bigler - PA 0437 (Flango 3)Clearfield County Solar Photovoltaic 3 MW Dec 2027 Under construction, less than or equal to 50 percent complete
Buckingham - PA 0151 (Crea)Wayne County Solar Photovoltaic 3 MW Nov 2027 Under construction, less than or equal to 50 percent complete
Burrell - PA 0396 (Copeland)Armstrong County Solar Photovoltaic 3 MW Nov 2027 Under construction, less than or equal to 50 percent complete
CVE US PA Dayton 379Armstrong County Solar Photovoltaic 3 MW Nov 2027 Under construction, less than or equal to 50 percent complete
Jones - PA 0399 (Rhodes)Elk County Solar Photovoltaic 3 MW Nov 2027 Under construction, less than or equal to 50 percent complete
New Alexandria - PA 0185 (Weimer)Westmoreland County Solar Photovoltaic 3 MW Dec 2027 Under construction, less than or equal to 50 percent complete
Kittanning - PA 0406 (Hoeter B)Armstrong County Solar Photovoltaic 3 MW Dec 2028 Under construction, less than or equal to 50 percent complete
Kittanning - PA 0407 (Hoeter C)Armstrong County Solar Photovoltaic 3 MW Dec 2028 Under construction, less than or equal to 50 percent complete
Unity - PA 0385 (Soccerhound)Clearfield County Solar Photovoltaic 3 MW Nov 2027 Under construction, less than or equal to 50 percent complete
Monroe - PA 0486 (Acey)Clarion County Solar Photovoltaic 3 MW Dec 2027 Under construction, less than or equal to 50 percent complete
Jones - PA 0429 (Rhodes South)Elk County Solar Photovoltaic 3 MW Oct 2027 Under construction, less than or equal to 50 percent complete
Wetmore - PA 0187 (Chittester)McKean County Solar Photovoltaic 3 MW Nov 2027 Under construction, less than or equal to 50 percent complete
Kittanning - PA 0383 (Hoeter)Armstrong County Solar Photovoltaic 3 MW Nov 2027 Under construction, less than or equal to 50 percent complete
Roulette - PA 0467Potter County Solar Photovoltaic 3 MW Dec 2027 Under construction, less than or equal to 50 percent complete
West Point (PA)Montgomery County Natural Gas Internal Combustion Engine 2 MW Sep 2026 Under construction, more than 50 percent complete
Middle Road Solar PartnersDauphin County Solar Photovoltaic 2 MW Sep 2026 Under construction, more than 50 percent complete
Point Marion L&D Hydroelectric ProjectFayette County Conventional Hydroelectric 2 MW Nov 2028 Planned for installation, but regulatory approvals not initiated
Point Marion L&D Hydroelectric ProjectFayette County Conventional Hydroelectric 2 MW Dec 2028 Planned for installation, but regulatory approvals not initiated
New Freedom Solar PartnersYork County Solar Photovoltaic 2 MW Oct 2026 Under construction, more than 50 percent complete
Dayton - PA 0404 (Good East)Armstrong County Solar Photovoltaic 2 MW Dec 2027 Under construction, less than or equal to 50 percent complete
Monroe - PA 0485 (Lawrence)Clarion County Solar Photovoltaic 2 MW Dec 2027 Under construction, less than or equal to 50 percent complete
Bigler - PA 0438 (Flango 4)Clearfield County Solar Photovoltaic 2 MW Dec 2027 Under construction, less than or equal to 50 percent complete
New Alexandria - PA 0363 (Weimer North)Westmoreland County Solar Photovoltaic 2 MW Dec 2027 Under construction, less than or equal to 50 percent complete
Roulette - PA 0479Potter County Solar Photovoltaic 1 MW Dec 2027 Under construction, less than or equal to 50 percent complete
Latrobe - PA 0408 (Soccerhound B)Clearfield County Solar Photovoltaic 1 MW Dec 2027 Under construction, less than or equal to 50 percent complete

Where Pennsylvania stands

Across the whole tracker, 533 data center and substation permits are on record in 51 states and DC. Pennsylvania accounts for 0 of them, ranking #13 by that count. Ranking measures documented permit activity, not the size of the eventual buildout.