Wyoming Data Center Permits Tracker

Wyoming has 1,530 MW of generation and storage requested in the interconnection queue and 2,993 MW of generation planned within 36 months. Every row below links to its primary source.

Last checked Sep 18, 2026

0
Data center & substation permits
of 2 total utility-scale permits tracked here
1,530MW
In the interconnection queue
3 active generation and storage positions
2,993MW
Planned generation
11 EIA-860M generators due within 36 months
#13
of 51 states with anything on record
Ranked by data center & substation permit count

Where the activity is

Ranked by row count. Counts are never mixed with the MW figures above.

Permit categories

Site plan or rezoning 2

Top counties · queue, substation & state air rows

Laramie County 2
Platte County 1

Permits in Wyoming

2 building and land-use permits tracked in Wyoming.

DateCategoryAddressApplicantSource
Sep 1, 2026 Site plan or rezoning Laramie County WY Planning Commission and Board of County Commissioners matters Vantage Data Centers Palma Land Planning, LLC
Aug 13, 2026 Site plan or rezoning Laramie County WY Planning Commission and Board of County Commissioners matters Vantage Data Centers Palma Land Planning, LLC

Interconnection queue in Wyoming

1,530 MW requested across 3 active generation and storage positions. Withdrawn and in-service rows are left out, matching the national page.

ISOProjectFuelMWStatusSource
SPP GI-CS-2025-25Platte County County Solar plus storage 800 MW Disis stage
SPP GI-TC-2024-16Laramie County County Onshore wind 400 MW Ia fully executed/on schedule
SPP GI-CS-2025-04Laramie County County Other hybrids 330 MW Disis stage

Planned generation in Wyoming

2,993 MW across 11 EIA-860M generators scheduled to enter service within 36 months.

PlantTechnologyMWPlannedStatusSource
Rail Tie WindAlbany County Onshore Wind Turbine 504 MW Jun 2029 Regulatory approvals pending. Not under construction
Dutchman Solar generation and BESSConverse County Solar Photovoltaic 499 MW Jun 2029 Regulatory approvals pending. Not under construction
Dutchman Solar generation and BESSConverse County Batteries 499 MW Jun 2029 Regulatory approvals pending. Not under construction
Cowboy Solar ILaramie County Solar Photovoltaic 400 MW Mar 2028 Planned for installation, but regulatory approvals not initiated
Cowboy Solar ILaramie County Batteries 400 MW Dec 2028 Planned for installation, but regulatory approvals not initiated
Cowboy Solar IILaramie County Solar Photovoltaic 365 MW Dec 2027 Regulatory approvals received. Not under construction
Cowboy Solar IILaramie County Batteries 200 MW Dec 2027 Planned for installation, but regulatory approvals not initiated
Cheyenne Prairie Generating StationLaramie County Natural Gas Fired Combustion Turbine 40 MW Dec 2028 Planned for installation, but regulatory approvals not initiated
Cheyenne Prairie Generating StationLaramie County Natural Gas Fired Combustion Turbine 40 MW Dec 2028 Planned for installation, but regulatory approvals not initiated
Cheyenne Prairie Generating StationLaramie County Natural Gas Fired Combustion Turbine 40 MW Dec 2028 Planned for installation, but regulatory approvals not initiated
Two Rivers Wind FacilityCarbon County Onshore Wind Turbine 6 MW Oct 2028 Regulatory approvals pending. Not under construction

Where Wyoming stands

Across the whole tracker, 533 data center and substation permits are on record in 51 states and DC. Wyoming accounts for 0 of them, ranking #13 by that count. Ranking measures documented permit activity, not the size of the eventual buildout.