Connecticut Data Center Permits Tracker

Connecticut has 5,777 MW of generation and storage requested in the interconnection queue and 575 MW of generation planned within 36 months. Every row below links to its primary source.

Last checked Sep 18, 2026

0
Data center & substation permits
of 0 total utility-scale permits tracked here
5,777MW
In the interconnection queue
8 active generation and storage positions
575MW
Planned generation
7 EIA-860M generators due within 36 months
#13
of 51 states with anything on record
Ranked by data center & substation permit count

Where the activity is

Ranked by row count. Counts are never mixed with the MW figures above.

Top counties · queue, substation & state air rows

Fairfield 2
New Haven 2
New London 2
Middlesex 1
Windham 1

Interconnection queue in Connecticut

5,777 MW requested across 8 active generation and storage positions. Withdrawn and in-service rows are left out, matching the national page.

ISOProjectFuelMWStatusSource
ISO-NE Millstone 3 Upgrade7New London County Nuclear 1,195 MW Interconnection agreement
ISO-NE Millstone 2 Upgrade7New London County Nuclear 898 MW Interconnection agreement
ISO-NE Lake Road CNR Only (see Q534)PDWindham County Natural gas 882 MW Active
ISO-NE CPV Towantic Energy CenterPDNew Haven County Natural gas 745 MW Interconnection agreement
ISO-NE Kleen Energy ProjectMiddlesex County Natural gas 620 MW Interconnection agreement
ISO-NE Bridgeport Energy PSS TuningFairfield County Natural gas 578 MW Interconnection agreement
ISO-NE PSEG Bridgeport Harbor CCGT ExpansionBLFairfield County Natural gas 510 MW Interconnection agreement
ISO-NE Wallingford GT UprateNew Haven County Natural gas 350 MW Active

Planned generation in Connecticut

575 MW across 7 EIA-860M generators scheduled to enter service within 36 months.

PlantTechnologyMWPlannedStatusSource
Elevate MiddletownMiddlesex County Batteries 275 MW Dec 2027 Planned for installation, but regulatory approvals not initiated
Broadleaf SolarHartford County Solar Photovoltaic 200 MW Apr 2028 Regulatory approvals pending. Not under construction
Pure Hedge LLCWindham County Solar Photovoltaic 70 MW Oct 2027 Under construction, less than or equal to 50 percent complete
Pure Hedge LLCWindham County Batteries 20 MW Oct 2027 Under construction, less than or equal to 50 percent complete
CT Airport Authority Solar OneHartford County Solar Photovoltaic 4 MW Dec 2027 Planned for installation, but regulatory approvals not initiated
Putnam Meadow Solar StationWindham County Solar Photovoltaic 4 MW Mar 2027 Regulatory approvals pending. Not under construction
Windsor LocksHartford County Solar Photovoltaic 2 MW Nov 2026 Under construction, less than or equal to 50 percent complete

Where Connecticut stands

Across the whole tracker, 533 data center and substation permits are on record in 51 states and DC. Connecticut accounts for 0 of them, ranking #13 by that count. Ranking measures documented permit activity, not the size of the eventual buildout.