Colorado Data Center Permits Tracker

Colorado has 6,607 MW of generation and storage requested in the interconnection queue and 5,808 MW of generation planned within 36 months. Every row below links to its primary source.

Last checked Sep 18, 2026

0
Data center & substation permits
of 0 total utility-scale permits tracked here
6,607MW
In the interconnection queue
30 active generation and storage positions
5,808MW
Planned generation
65 EIA-860M generators due within 36 months
#13
of 51 states with anything on record
Ranked by data center & substation permit count

Where the activity is

Ranked by row count. Counts are never mixed with the MW figures above.

Top counties · queue, substation & state air rows

El Paso 4
Kit Carson County 4
Weld County 4
Kit Carson 3
Burlington 2
Moffat County 2
Morgan County 2
Adams County 1

Interconnection queue in Colorado

6,607 MW requested across 30 active generation and storage positions. Withdrawn and in-service rows are left out, matching the national page.

ISOProjectFuelMWStatusSource
SPP CSUT-2025-1Lincoln County Onshore wind 500 MW Disis stage
SPP CSUT-2025-7El Paso County Natural gas 412 MW Disis stage
SPP GI-TC-2024-31Elbert County County Solar plus storage 398 MW Ia fully executed/on schedule
SPP 21-08242Cheyenne County Onshore wind 350 MW Ia fully executed/on suspension
SPP GI-TC-2024-25Weld County County Onshore wind 350 MW Facility study stage
SPP GI-CS-2025-03Kit Carson County Solar plus storage 300 MW Disis stage
SPP GI-CS-2025-05Weld County County Solar 300 MW Disis stage
SPP GI-CS-2025-29Yuma County County Solar plus storage 300 MW Disis stage
SPP 2025-G1Weld County County Solar plus storage 250 MW Facility study stage
SPP GI-CS-2025-24Kit Carson County County Onshore wind 225 MW Disis stage
SPP GI-RSC-2025-02Moffat County County Battery storage 200 MW Ia fully executed/on schedule
SPP GI-SISS-2025-06Logan County County Battery storage 200 MW Ia fully executed/on schedule
SPP GI-CS-2025-19Morgan County County Solar plus storage 200 MW Disis stage
SPP GI-CS-2025-20Morgan County County Solar plus storage 200 MW Disis stage
SPP GI-CS-2025-17Moffat County County Solar plus storage 200 MW Disis stage
SPP GI-CS-2025-02Adams County County Solar plus storage 199 MW Disis stage
SPP GI-CS-2025-07Kit Carson County Onshore wind 199 MW Disis stage
SPP GI-CS-2025-08Kit Carson County Onshore wind 199 MW Disis stage
SPP GI-CS-2025-11Lincoln County County Onshore wind 199 MW Disis stage
SPP GI-CS-2025-26Kit Carson County County Onshore wind 199 MW Disis stage
SPP GI-CS-2025-27Delta County County Natural gas 199 MW Disis stage
SPP GEN-2026-SR25Burlington County Battery storage 150 MW Special study
SPP GEN-2026-SR26Burlington County Battery storage 150 MW Special study
SPP GI-CS-2025-16Weld County County Solar plus storage 150 MW Disis stage
SPP GI-SISS-2025-05Kit Carson County County Battery storage 150 MW Ia fully executed/on schedule
SPP CSUT-2025-2El Paso County Solar 100 MW Disis stage
SPP CSUT-2025-6El Paso County Battery storage 100 MW Disis stage
SPP CSUT-2025-8El Paso County Battery storage 100 MW Disis stage
SPP GI-SISS-2025-04Kit Carson County County Battery storage 79 MW Ia fully executed/on schedule
SPP GI-RSC-2025-03Montrose County County Battery storage 50 MW Ia fully executed/on schedule

Planned generation in Colorado

5,808 MW across 65 EIA-860M generators scheduled to enter service within 36 months.

PlantTechnologyMWPlannedStatusSource
Singing Grass WindKit Carson County Onshore Wind Turbine 603 MW Aug 2026 Under construction, less than or equal to 50 percent complete
Cheyenne Ridge IICheyenne County Onshore Wind Turbine 438 MW Aug 2026 Under construction, less than or equal to 50 percent complete
Mirasol Energy Center, LLC.Pueblo County Solar Photovoltaic 400 MW Dec 2028 Regulatory approvals received. Not under construction
Arroyo SolarPueblo County Solar Photovoltaic 335 MW Oct 2026 Under construction, less than or equal to 50 percent complete
South Platte StorageMorgan County Batteries 250 MW Jun 2027 Under construction, less than or equal to 50 percent complete
Dry Land Prairie Energy StorageCheyenne County Batteries 250 MW Dec 2026 Under construction, less than or equal to 50 percent complete
Fort St VrainWeld County Natural Gas Fired Combustion Turbine 239 MW Dec 2027 Under construction, less than or equal to 50 percent complete
Fort St VrainWeld County Natural Gas Fired Combustion Turbine 239 MW Dec 2027 Under construction, less than or equal to 50 percent complete
Turkey Creek Solar ProjectPueblo County Solar Photovoltaic 200 MW Feb 2027 Planned for installation, but regulatory approvals not initiated
Elk RunLas Animas County Solar Photovoltaic 200 MW Jun 2029 Regulatory approvals pending. Not under construction
Thunder Wolf II, LLCPueblo County Solar Photovoltaic 200 MW Dec 2027 Regulatory approvals received. Not under construction
Fortress 1Morgan County Solar Photovoltaic 199 MW Mar 2028 Regulatory approvals pending. Not under construction
Spindle BESSWeld County Batteries 199 MW Dec 2026 Under construction, more than 50 percent complete
Fortress 1Morgan County Batteries 150 MW Mar 2028 Regulatory approvals pending. Not under construction
South Platte SolarMorgan County Solar Photovoltaic 150 MW Dec 2027 Under construction, less than or equal to 50 percent complete
Carousel Energy Storage, LLCKit Carson County Batteries 150 MW Dec 2027 Regulatory approvals received. Not under construction
Canyonland SolarMontezuma County Solar Photovoltaic 140 MW Dec 2027 Planned for installation, but regulatory approvals not initiated
Black Hollow SunWeld County Solar Photovoltaic 107 MW Sep 2026 Under construction, more than 50 percent complete
Drennan Energy StorageEl Paso County Batteries 100 MW Mar 2028 Regulatory approvals pending. Not under construction
Weld Energy StorageWeld County Batteries 100 MW Dec 2026 Under construction, less than or equal to 50 percent complete
Sundance (CO)Elbert County Solar Photovoltaic 75 MW Sep 2026 Under construction, less than or equal to 50 percent complete
Sundance (CO)Elbert County Batteries 50 MW Sep 2026 Under construction, less than or equal to 50 percent complete
Pueblo Airport Generating StationPueblo County Batteries 50 MW Dec 2027 Regulatory approvals pending. Not under construction
Fortress 1Morgan County Batteries 50 MW Mar 2028 Regulatory approvals pending. Not under construction
HorizonEl Paso County Natural Gas Fired Combustion Turbine 48 MW Jul 2028 Planned for installation, but regulatory approvals not initiated
HorizonEl Paso County Natural Gas Fired Combustion Turbine 48 MW Jul 2028 Planned for installation, but regulatory approvals not initiated
HorizonEl Paso County Natural Gas Fired Combustion Turbine 48 MW Jul 2028 Planned for installation, but regulatory approvals not initiated
HorizonEl Paso County Natural Gas Fired Combustion Turbine 48 MW Jul 2028 Planned for installation, but regulatory approvals not initiated
HorizonEl Paso County Natural Gas Fired Combustion Turbine 48 MW Jul 2028 Planned for installation, but regulatory approvals not initiated
HorizonEl Paso County Natural Gas Fired Combustion Turbine 48 MW Jul 2028 Planned for installation, but regulatory approvals not initiated
HorizonEl Paso County Natural Gas Fired Combustion Turbine 48 MW Jul 2028 Planned for installation, but regulatory approvals not initiated
HorizonEl Paso County Natural Gas Fired Combustion Turbine 48 MW Jul 2028 Planned for installation, but regulatory approvals not initiated
HorizonEl Paso County Natural Gas Fired Combustion Turbine 48 MW Jul 2028 Planned for installation, but regulatory approvals not initiated
HorizonEl Paso County Natural Gas Fired Combustion Turbine 48 MW Jul 2028 Planned for installation, but regulatory approvals not initiated
RawhideLarimer County Natural Gas Fired Combustion Turbine 45 MW Mar 2028 Planned for installation, but regulatory approvals not initiated
RawhideLarimer County Natural Gas Fired Combustion Turbine 45 MW Mar 2028 Planned for installation, but regulatory approvals not initiated
RawhideLarimer County Natural Gas Fired Combustion Turbine 45 MW Mar 2028 Planned for installation, but regulatory approvals not initiated
RawhideLarimer County Natural Gas Fired Combustion Turbine 45 MW Mar 2028 Planned for installation, but regulatory approvals not initiated
RawhideLarimer County Natural Gas Fired Combustion Turbine 45 MW Mar 2028 Planned for installation, but regulatory approvals not initiated
Canyon Peak Power StationArapahoe County Natural Gas Fired Combustion Turbine 26 MW Aug 2026 Construction complete, but not yet in commercial operation
Canyon Peak Power StationArapahoe County Natural Gas Fired Combustion Turbine 26 MW Aug 2026 Construction complete, but not yet in commercial operation
Canyon Peak Power StationArapahoe County Natural Gas Fired Combustion Turbine 26 MW Aug 2026 Construction complete, but not yet in commercial operation
Canyon Peak Power StationArapahoe County Natural Gas Fired Combustion Turbine 26 MW Aug 2026 Construction complete, but not yet in commercial operation
Canyon Peak Power StationArapahoe County Natural Gas Fired Combustion Turbine 26 MW Aug 2026 Construction complete, but not yet in commercial operation
Canyon Peak Power StationArapahoe County Natural Gas Fired Combustion Turbine 26 MW Aug 2026 Construction complete, but not yet in commercial operation
KeenesburgWeld County Solar Photovoltaic 7 MW Oct 2026 Under construction, less than or equal to 50 percent complete
Raceway Solar - (CO)Morgan County Solar Photovoltaic 7 MW Mar 2027 Regulatory approvals pending. Not under construction
Pivot Solar 36Weld County Solar Photovoltaic 5 MW Jan 2027 Under construction, more than 50 percent complete
Pivot Solar 33 LLCWeld County Solar Photovoltaic 5 MW Jan 2027 Under construction, more than 50 percent complete
La Junta SolarOtero County Solar Photovoltaic 5 MW Feb 2027 Regulatory approvals pending. Not under construction
Lamar SolarProwers County Solar Photovoltaic 5 MW Feb 2027 Regulatory approvals pending. Not under construction
Pivot Solar 58 LLCWeld County Solar Photovoltaic 4 MW Nov 2026 Under construction, more than 50 percent complete
Waterton Solar IDouglas County Solar Photovoltaic 4 MW Sep 2026 Under construction, less than or equal to 50 percent complete
Pivot Solar 53 LLCAdams County Solar Photovoltaic 4 MW Aug 2026 Under construction, more than 50 percent complete
Waterton Solar IIDouglas County Solar Photovoltaic 4 MW Sep 2026 Under construction, less than or equal to 50 percent complete
Pivot Solar 50 LLCWeld County Solar Photovoltaic 4 MW Sep 2026 Under construction, more than 50 percent complete
Pivot Solar 56 LLCWeld County Solar Photovoltaic 4 MW Jan 2027 Under construction, more than 50 percent complete
Pivot Solar 43 LLCAdams County Solar Photovoltaic 4 MW Aug 2026 Under construction, more than 50 percent complete
Waxwing Solar CSGPueblo County Solar Photovoltaic 3 MW Jan 2027 Under construction, less than or equal to 50 percent complete
Pivot Solar 57 LLCMesa County Solar Photovoltaic 2 MW Sep 2026 Under construction, more than 50 percent complete
Pivot Solar 42 LLCLarimer County Solar Photovoltaic 2 MW Oct 2026 Under construction, more than 50 percent complete
Fort Lyon SolarBent County Solar Photovoltaic 2 MW Feb 2027 Regulatory approvals pending. Not under construction
Trinidad SolarLas Animas County Solar Photovoltaic 2 MW Feb 2027 Regulatory approvals pending. Not under construction
Pivot Solar 71 LLCMorgan County Solar Photovoltaic 2 MW Oct 2026 Under construction, more than 50 percent complete
Pivot Solar 60 LLCWeld County Solar Photovoltaic 1 MW Sep 2026 Under construction, more than 50 percent complete

Where Colorado stands

Across the whole tracker, 533 data center and substation permits are on record in 51 states and DC. Colorado accounts for 0 of them, ranking #13 by that count. Ranking measures documented permit activity, not the size of the eventual buildout.