Colorado Data Center Permits Tracker
Colorado has 6,607 MW of generation and storage requested in the interconnection queue and 5,808 MW of generation planned within 36 months. Every row below links to its primary source.
Last checked Sep 18, 2026
Where the activity is
Ranked by row count. Counts are never mixed with the MW figures above.
Interconnection queue in Colorado
6,607 MW requested across 30 active generation and storage positions. Withdrawn and in-service rows are left out, matching the national page.
| ISO | Project | Fuel | MW | Status | Source |
|---|---|---|---|---|---|
| SPP | CSUT-2025-1Lincoln County | Onshore wind | 500 MW | Disis stage | |
| SPP | CSUT-2025-7El Paso County | Natural gas | 412 MW | Disis stage | |
| SPP | GI-TC-2024-31Elbert County County | Solar plus storage | 398 MW | Ia fully executed/on schedule | |
| SPP | 21-08242Cheyenne County | Onshore wind | 350 MW | Ia fully executed/on suspension | |
| SPP | GI-TC-2024-25Weld County County | Onshore wind | 350 MW | Facility study stage | |
| SPP | GI-CS-2025-03Kit Carson County | Solar plus storage | 300 MW | Disis stage | |
| SPP | GI-CS-2025-05Weld County County | Solar | 300 MW | Disis stage | |
| SPP | GI-CS-2025-29Yuma County County | Solar plus storage | 300 MW | Disis stage | |
| SPP | 2025-G1Weld County County | Solar plus storage | 250 MW | Facility study stage | |
| SPP | GI-CS-2025-24Kit Carson County County | Onshore wind | 225 MW | Disis stage | |
| SPP | GI-RSC-2025-02Moffat County County | Battery storage | 200 MW | Ia fully executed/on schedule | |
| SPP | GI-SISS-2025-06Logan County County | Battery storage | 200 MW | Ia fully executed/on schedule | |
| SPP | GI-CS-2025-19Morgan County County | Solar plus storage | 200 MW | Disis stage | |
| SPP | GI-CS-2025-20Morgan County County | Solar plus storage | 200 MW | Disis stage | |
| SPP | GI-CS-2025-17Moffat County County | Solar plus storage | 200 MW | Disis stage | |
| SPP | GI-CS-2025-02Adams County County | Solar plus storage | 199 MW | Disis stage | |
| SPP | GI-CS-2025-07Kit Carson County | Onshore wind | 199 MW | Disis stage | |
| SPP | GI-CS-2025-08Kit Carson County | Onshore wind | 199 MW | Disis stage | |
| SPP | GI-CS-2025-11Lincoln County County | Onshore wind | 199 MW | Disis stage | |
| SPP | GI-CS-2025-26Kit Carson County County | Onshore wind | 199 MW | Disis stage | |
| SPP | GI-CS-2025-27Delta County County | Natural gas | 199 MW | Disis stage | |
| SPP | GEN-2026-SR25Burlington County | Battery storage | 150 MW | Special study | |
| SPP | GEN-2026-SR26Burlington County | Battery storage | 150 MW | Special study | |
| SPP | GI-CS-2025-16Weld County County | Solar plus storage | 150 MW | Disis stage | |
| SPP | GI-SISS-2025-05Kit Carson County County | Battery storage | 150 MW | Ia fully executed/on schedule | |
| SPP | CSUT-2025-2El Paso County | Solar | 100 MW | Disis stage | |
| SPP | CSUT-2025-6El Paso County | Battery storage | 100 MW | Disis stage | |
| SPP | CSUT-2025-8El Paso County | Battery storage | 100 MW | Disis stage | |
| SPP | GI-SISS-2025-04Kit Carson County County | Battery storage | 79 MW | Ia fully executed/on schedule | |
| SPP | GI-RSC-2025-03Montrose County County | Battery storage | 50 MW | Ia fully executed/on schedule |
Planned generation in Colorado
5,808 MW across 65 EIA-860M generators scheduled to enter service within 36 months.
| Plant | Technology | MW | Planned | Status | Source |
|---|---|---|---|---|---|
| Singing Grass WindKit Carson County | Onshore Wind Turbine | 603 MW | Aug 2026 | Under construction, less than or equal to 50 percent complete | |
| Cheyenne Ridge IICheyenne County | Onshore Wind Turbine | 438 MW | Aug 2026 | Under construction, less than or equal to 50 percent complete | |
| Mirasol Energy Center, LLC.Pueblo County | Solar Photovoltaic | 400 MW | Dec 2028 | Regulatory approvals received. Not under construction | |
| Arroyo SolarPueblo County | Solar Photovoltaic | 335 MW | Oct 2026 | Under construction, less than or equal to 50 percent complete | |
| South Platte StorageMorgan County | Batteries | 250 MW | Jun 2027 | Under construction, less than or equal to 50 percent complete | |
| Dry Land Prairie Energy StorageCheyenne County | Batteries | 250 MW | Dec 2026 | Under construction, less than or equal to 50 percent complete | |
| Fort St VrainWeld County | Natural Gas Fired Combustion Turbine | 239 MW | Dec 2027 | Under construction, less than or equal to 50 percent complete | |
| Fort St VrainWeld County | Natural Gas Fired Combustion Turbine | 239 MW | Dec 2027 | Under construction, less than or equal to 50 percent complete | |
| Turkey Creek Solar ProjectPueblo County | Solar Photovoltaic | 200 MW | Feb 2027 | Planned for installation, but regulatory approvals not initiated | |
| Elk RunLas Animas County | Solar Photovoltaic | 200 MW | Jun 2029 | Regulatory approvals pending. Not under construction | |
| Thunder Wolf II, LLCPueblo County | Solar Photovoltaic | 200 MW | Dec 2027 | Regulatory approvals received. Not under construction | |
| Fortress 1Morgan County | Solar Photovoltaic | 199 MW | Mar 2028 | Regulatory approvals pending. Not under construction | |
| Spindle BESSWeld County | Batteries | 199 MW | Dec 2026 | Under construction, more than 50 percent complete | |
| Fortress 1Morgan County | Batteries | 150 MW | Mar 2028 | Regulatory approvals pending. Not under construction | |
| South Platte SolarMorgan County | Solar Photovoltaic | 150 MW | Dec 2027 | Under construction, less than or equal to 50 percent complete | |
| Carousel Energy Storage, LLCKit Carson County | Batteries | 150 MW | Dec 2027 | Regulatory approvals received. Not under construction | |
| Canyonland SolarMontezuma County | Solar Photovoltaic | 140 MW | Dec 2027 | Planned for installation, but regulatory approvals not initiated | |
| Black Hollow SunWeld County | Solar Photovoltaic | 107 MW | Sep 2026 | Under construction, more than 50 percent complete | |
| Drennan Energy StorageEl Paso County | Batteries | 100 MW | Mar 2028 | Regulatory approvals pending. Not under construction | |
| Weld Energy StorageWeld County | Batteries | 100 MW | Dec 2026 | Under construction, less than or equal to 50 percent complete | |
| Sundance (CO)Elbert County | Solar Photovoltaic | 75 MW | Sep 2026 | Under construction, less than or equal to 50 percent complete | |
| Sundance (CO)Elbert County | Batteries | 50 MW | Sep 2026 | Under construction, less than or equal to 50 percent complete | |
| Pueblo Airport Generating StationPueblo County | Batteries | 50 MW | Dec 2027 | Regulatory approvals pending. Not under construction | |
| Fortress 1Morgan County | Batteries | 50 MW | Mar 2028 | Regulatory approvals pending. Not under construction | |
| HorizonEl Paso County | Natural Gas Fired Combustion Turbine | 48 MW | Jul 2028 | Planned for installation, but regulatory approvals not initiated | |
| HorizonEl Paso County | Natural Gas Fired Combustion Turbine | 48 MW | Jul 2028 | Planned for installation, but regulatory approvals not initiated | |
| HorizonEl Paso County | Natural Gas Fired Combustion Turbine | 48 MW | Jul 2028 | Planned for installation, but regulatory approvals not initiated | |
| HorizonEl Paso County | Natural Gas Fired Combustion Turbine | 48 MW | Jul 2028 | Planned for installation, but regulatory approvals not initiated | |
| HorizonEl Paso County | Natural Gas Fired Combustion Turbine | 48 MW | Jul 2028 | Planned for installation, but regulatory approvals not initiated | |
| HorizonEl Paso County | Natural Gas Fired Combustion Turbine | 48 MW | Jul 2028 | Planned for installation, but regulatory approvals not initiated | |
| HorizonEl Paso County | Natural Gas Fired Combustion Turbine | 48 MW | Jul 2028 | Planned for installation, but regulatory approvals not initiated | |
| HorizonEl Paso County | Natural Gas Fired Combustion Turbine | 48 MW | Jul 2028 | Planned for installation, but regulatory approvals not initiated | |
| HorizonEl Paso County | Natural Gas Fired Combustion Turbine | 48 MW | Jul 2028 | Planned for installation, but regulatory approvals not initiated | |
| HorizonEl Paso County | Natural Gas Fired Combustion Turbine | 48 MW | Jul 2028 | Planned for installation, but regulatory approvals not initiated | |
| RawhideLarimer County | Natural Gas Fired Combustion Turbine | 45 MW | Mar 2028 | Planned for installation, but regulatory approvals not initiated | |
| RawhideLarimer County | Natural Gas Fired Combustion Turbine | 45 MW | Mar 2028 | Planned for installation, but regulatory approvals not initiated | |
| RawhideLarimer County | Natural Gas Fired Combustion Turbine | 45 MW | Mar 2028 | Planned for installation, but regulatory approvals not initiated | |
| RawhideLarimer County | Natural Gas Fired Combustion Turbine | 45 MW | Mar 2028 | Planned for installation, but regulatory approvals not initiated | |
| RawhideLarimer County | Natural Gas Fired Combustion Turbine | 45 MW | Mar 2028 | Planned for installation, but regulatory approvals not initiated | |
| Canyon Peak Power StationArapahoe County | Natural Gas Fired Combustion Turbine | 26 MW | Aug 2026 | Construction complete, but not yet in commercial operation | |
| Canyon Peak Power StationArapahoe County | Natural Gas Fired Combustion Turbine | 26 MW | Aug 2026 | Construction complete, but not yet in commercial operation | |
| Canyon Peak Power StationArapahoe County | Natural Gas Fired Combustion Turbine | 26 MW | Aug 2026 | Construction complete, but not yet in commercial operation | |
| Canyon Peak Power StationArapahoe County | Natural Gas Fired Combustion Turbine | 26 MW | Aug 2026 | Construction complete, but not yet in commercial operation | |
| Canyon Peak Power StationArapahoe County | Natural Gas Fired Combustion Turbine | 26 MW | Aug 2026 | Construction complete, but not yet in commercial operation | |
| Canyon Peak Power StationArapahoe County | Natural Gas Fired Combustion Turbine | 26 MW | Aug 2026 | Construction complete, but not yet in commercial operation | |
| KeenesburgWeld County | Solar Photovoltaic | 7 MW | Oct 2026 | Under construction, less than or equal to 50 percent complete | |
| Raceway Solar - (CO)Morgan County | Solar Photovoltaic | 7 MW | Mar 2027 | Regulatory approvals pending. Not under construction | |
| Pivot Solar 36Weld County | Solar Photovoltaic | 5 MW | Jan 2027 | Under construction, more than 50 percent complete | |
| Pivot Solar 33 LLCWeld County | Solar Photovoltaic | 5 MW | Jan 2027 | Under construction, more than 50 percent complete | |
| La Junta SolarOtero County | Solar Photovoltaic | 5 MW | Feb 2027 | Regulatory approvals pending. Not under construction | |
| Lamar SolarProwers County | Solar Photovoltaic | 5 MW | Feb 2027 | Regulatory approvals pending. Not under construction | |
| Pivot Solar 58 LLCWeld County | Solar Photovoltaic | 4 MW | Nov 2026 | Under construction, more than 50 percent complete | |
| Waterton Solar IDouglas County | Solar Photovoltaic | 4 MW | Sep 2026 | Under construction, less than or equal to 50 percent complete | |
| Pivot Solar 53 LLCAdams County | Solar Photovoltaic | 4 MW | Aug 2026 | Under construction, more than 50 percent complete | |
| Waterton Solar IIDouglas County | Solar Photovoltaic | 4 MW | Sep 2026 | Under construction, less than or equal to 50 percent complete | |
| Pivot Solar 50 LLCWeld County | Solar Photovoltaic | 4 MW | Sep 2026 | Under construction, more than 50 percent complete | |
| Pivot Solar 56 LLCWeld County | Solar Photovoltaic | 4 MW | Jan 2027 | Under construction, more than 50 percent complete | |
| Pivot Solar 43 LLCAdams County | Solar Photovoltaic | 4 MW | Aug 2026 | Under construction, more than 50 percent complete | |
| Waxwing Solar CSGPueblo County | Solar Photovoltaic | 3 MW | Jan 2027 | Under construction, less than or equal to 50 percent complete | |
| Pivot Solar 57 LLCMesa County | Solar Photovoltaic | 2 MW | Sep 2026 | Under construction, more than 50 percent complete | |
| Pivot Solar 42 LLCLarimer County | Solar Photovoltaic | 2 MW | Oct 2026 | Under construction, more than 50 percent complete | |
| Fort Lyon SolarBent County | Solar Photovoltaic | 2 MW | Feb 2027 | Regulatory approvals pending. Not under construction | |
| Trinidad SolarLas Animas County | Solar Photovoltaic | 2 MW | Feb 2027 | Regulatory approvals pending. Not under construction | |
| Pivot Solar 71 LLCMorgan County | Solar Photovoltaic | 2 MW | Oct 2026 | Under construction, more than 50 percent complete | |
| Pivot Solar 60 LLCWeld County | Solar Photovoltaic | 1 MW | Sep 2026 | Under construction, more than 50 percent complete |
Where Colorado stands
Across the whole tracker, 533 data center and substation permits are on record in 51 states and DC. Colorado accounts for 0 of them, ranking #13 by that count. Ranking measures documented permit activity, not the size of the eventual buildout.