SAVRN
Search Contact SAVRN
SAVRN Tracker

Kentucky Data Center Permits Tracker

Kentucky has 4,359 MW of generation and storage requested in the interconnection queue and 2,438 MW of generation planned within 36 months. Every row below links to its primary source.

Last checked Sep 18, 2026

0
Data center & substation permits
of 0 total utility-scale permits tracked here
4,359MW
In the interconnection queue
33 active generation and storage positions
2,438MW
Planned generation
42 EIA-860M generators due within 36 months
#13
of 51 states with anything on record
Ranked by data center & substation permit count

Where the activity is

Ranked by row count. Counts are never mixed with the MW figures above.

Top counties · queue, substation & state air rows

Fleming 4
N/A 4
Martin 3
Fayette 2
Green 2
Madison 2
Marion 2
Barren 1

Interconnection queue in Kentucky

4,359 MW requested across 33 active generation and storage positions. Withdrawn and in-service rows are left out, matching the national page.

ISOProjectFuelMWStatusSource
PJM Laurel-Cooper 161 kV AH1-721N/A County Natural gas 786 MW Active
MISO AB Brown 345 - Reid EHV (BREC Terminal) 345.0kVHenderson County Solar 400 MW Active; not started
PJM Goldfinch SolarMason County Solar 250 MW Engineering and procurement
PJM Harbert Metering 138 kV AG2-184Knott County Solar 210 MW Active
PJM Lynn Bark Energy CenterMartin County Solar 200 MW Engineering and procurement
PJM Harbert Metering 138 kV AH1-617N/A County Solar 200 MW Active
PJM Martin County Solar ProjectMartin County Solar 190 MW Suspended
PJM Fleming SolarFleming County Solar 188 MW Engineering and procurement
PJM Goddard-Plumsville 138 kV II AH1-665Fleming County Solar 180 MW Active
PJM Summershade-Green County 161 kV AG1-354Green County Solar 150 MW Engineering and procurement
MISO Bryan RoadBIG RIVERS ELECTRIC CORPORATION BRECGraves County Solar 150 MW Active; not started
PJM Summer Shade SolarMetcalfe County Solar plus storage 106 MW Engineering and procurement
PJM Madison SolarMadison County Solar 100 MW Engineering and procurement
PJM Threeforks Energy StorageMartin County Battery storage 100 MW Engineering and procurement
PJM Goddard-Plumville 138 kV AH1-664Fleming County Solar 100 MW Active
PJM Northern Bobwhite SolarMarion County Solar 96 MW Under construction
PJM Stonecrop SolarHardin County Solar 82 MW Engineering and procurement
PJM Bright Mountain SolarPerry County Solar 80 MW Engineering and procurement
PJM Upchurch - Zula 69 kV AH1-239Boone County Solar 80 MW Active
PJM Flemingsburg - Spurlock 138 kV AH1-666Fleming County Solar 80 MW Active
PJM Blue Moon SolarHarrison County Solar 70 MW Under construction
PJM Summersville - Magnolia 69 kV AG2-424Larue County Solar plus storage 63 MW Active
PJM Mt Olive Creek SolarRussell County Solar 60 MW Under construction
PJM Horseshoe Bend SolarGreen County Solar 60 MW Under construction
PJM Flat Run SolarBarren County Solar 55 MW Engineering and procurement
PJM BarrelheadWayne County Solar 54 MW Engineering and procurement
PJM Crooksville 69 kV AG2-073Madison County Solar 53 MW Active
PJM Millersburg 69 kV AH1-571N/A County Solar 45 MW Active
PJM Grassy PlainsFayette County Solar 40 MW Under construction
PJM Avon - Renaker 138 kV AH1-004Fayette County Solar 40 MW Active
PJM Sulphur Creek-Loretto 69 kV AG2-298Marion County Solar 35 MW Active
PJM Avon - Renaker 138 kV AG2-081Montgomery County Solar 30 MW Active
PJM Millersburg 69 kV AH1-570N/A County Solar 25 MW Active

Planned generation in Kentucky

2,438 MW across 42 EIA-860M generators scheduled to enter service within 36 months.

PlantTechnologyMWPlannedStatusSource
Mill Creek (KY)Jefferson County Natural Gas Fired Combined Cycle 740 MW Jun 2027 Under construction, more than 50 percent complete
Gage SolarMcCracken County Solar Photovoltaic 200 MW Jun 2029 Regulatory approvals pending. Not under construction
AEUG Fleming Solar, LLCFleming County Solar Photovoltaic 188 MW Jun 2027 Under construction, less than or equal to 50 percent complete
Weirs CreekHopkins County Solar Photovoltaic 150 MW May 2027 Under construction, less than or equal to 50 percent complete
E W BrownMercer County Batteries 125 MW May 2027 Under construction, more than 50 percent complete
Frontier SolarWashington County Solar Photovoltaic 120 MW Oct 2027 Regulatory approvals received. Not under construction
AEUG Madison Solar, LLCMadison County Solar Photovoltaic 100 MW Sep 2028 Under construction, less than or equal to 50 percent complete
New Frontiers SolarBreckinridge County Solar Photovoltaic 100 MW Jun 2027 Regulatory approvals pending. Not under construction
Cooperative Solar Three-MarionMarion County Solar Photovoltaic 96 MW Aug 2027 Regulatory approvals received. Not under construction
Bright Mountain SolarPerry County Solar Photovoltaic 80 MW Dec 2027 Planned for installation, but regulatory approvals not initiated
SR HorusSimpson County Solar Photovoltaic 80 MW Sep 2027 Under construction, less than or equal to 50 percent complete
Blue MoonHarrison County Solar Photovoltaic 70 MW Sep 2026 Under construction, more than 50 percent complete
Henderson County SolarHenderson County Solar Photovoltaic 51 MW Sep 2026 Under construction, less than or equal to 50 percent complete
Cooperative Solar Two-FayetteFayette County Solar Photovoltaic 40 MW Nov 2027 Under construction, less than or equal to 50 percent complete
KYMEA Energy Center IHopkins County Natural Gas Internal Combustion Engine 19 MW Jun 2027 Under construction, less than or equal to 50 percent complete
KYMEA Energy Center IHopkins County Natural Gas Internal Combustion Engine 19 MW Jun 2027 Under construction, less than or equal to 50 percent complete
KYMEA Energy Center IHopkins County Natural Gas Internal Combustion Engine 19 MW Jun 2027 Under construction, less than or equal to 50 percent complete
KYMEA Energy Center IHopkins County Natural Gas Internal Combustion Engine 19 MW Jun 2027 Under construction, less than or equal to 50 percent complete
Liberty StationCasey County Natural Gas Internal Combustion Engine 18 MW Dec 2028 Planned for installation, but regulatory approvals not initiated
Liberty StationCasey County Natural Gas Internal Combustion Engine 18 MW Dec 2028 Planned for installation, but regulatory approvals not initiated
Liberty StationCasey County Natural Gas Internal Combustion Engine 18 MW Dec 2028 Planned for installation, but regulatory approvals not initiated
Liberty StationCasey County Natural Gas Internal Combustion Engine 18 MW Dec 2028 Planned for installation, but regulatory approvals not initiated
Liberty StationCasey County Natural Gas Internal Combustion Engine 18 MW Dec 2028 Planned for installation, but regulatory approvals not initiated
Liberty StationCasey County Natural Gas Internal Combustion Engine 18 MW Dec 2028 Planned for installation, but regulatory approvals not initiated
Liberty StationCasey County Natural Gas Internal Combustion Engine 18 MW Dec 2028 Planned for installation, but regulatory approvals not initiated
Liberty StationCasey County Natural Gas Internal Combustion Engine 18 MW Dec 2028 Planned for installation, but regulatory approvals not initiated
Liberty StationCasey County Natural Gas Internal Combustion Engine 18 MW Dec 2028 Planned for installation, but regulatory approvals not initiated
Liberty StationCasey County Natural Gas Internal Combustion Engine 18 MW Dec 2028 Planned for installation, but regulatory approvals not initiated
Liberty StationCasey County Natural Gas Internal Combustion Engine 18 MW Dec 2028 Planned for installation, but regulatory approvals not initiated
Liberty StationCasey County Natural Gas Internal Combustion Engine 18 MW Dec 2028 Planned for installation, but regulatory approvals not initiated
Heidelberg Hydroelectric ProjectLee County Conventional Hydroelectric 1 MW Sep 2026 Construction complete, but not yet in commercial operation
Heidelberg Hydroelectric ProjectLee County Conventional Hydroelectric 1 MW Sep 2026 Construction complete, but not yet in commercial operation
Heidelberg Hydroelectric ProjectLee County Conventional Hydroelectric 1 MW Sep 2026 Construction complete, but not yet in commercial operation
Heidelberg Hydroelectric ProjectLee County Conventional Hydroelectric 1 MW Sep 2026 Construction complete, but not yet in commercial operation
KY No. 11 L&D Hydroelectric ProjectEstill County Conventional Hydroelectric 1 MW Nov 2027 Regulatory approvals received. Not under construction
KY No. 11 L&D Hydroelectric ProjectEstill County Conventional Hydroelectric 1 MW Nov 2027 Regulatory approvals received. Not under construction
KY No. 11 L&D Hydroelectric ProjectEstill County Conventional Hydroelectric 1 MW Nov 2027 Regulatory approvals received. Not under construction
KY No. 11 L&D Hydroelectric ProjectEstill County Conventional Hydroelectric 1 MW Nov 2027 Regulatory approvals received. Not under construction
Heidelberg Hydroelectric ProjectLee County Conventional Hydroelectric 0 MW Sep 2026 Construction complete, but not yet in commercial operation
Heidelberg Hydroelectric ProjectLee County Conventional Hydroelectric 0 MW Sep 2026 Construction complete, but not yet in commercial operation
KY No. 11 L&D Hydroelectric ProjectEstill County Conventional Hydroelectric 0 MW Nov 2027 Regulatory approvals received. Not under construction
KY No. 11 L&D Hydroelectric ProjectEstill County Conventional Hydroelectric 0 MW Nov 2027 Regulatory approvals received. Not under construction

Where Kentucky stands

Across the whole tracker, 533 data center and substation permits are on record in 51 states and DC. Kentucky accounts for 0 of them, ranking #13 by that count. Ranking measures documented permit activity, not the size of the eventual buildout.