SAVRN
Search Contact SAVRN
SAVRN Tracker

Louisiana Data Center Permits Tracker

Louisiana has 11,122 MW of generation and storage requested in the interconnection queue and 4,048 MW of generation planned within 36 months. Every row below links to its primary source.

Last checked Sep 18, 2026

0
Data center & substation permits
of 0 total utility-scale permits tracked here
11,122MW
In the interconnection queue
34 active generation and storage positions
4,048MW
Planned generation
24 EIA-860M generators due within 36 months
#13
of 51 states with anything on record
Ranked by data center & substation permit count

Where the activity is

Ranked by row count. Counts are never mixed with the MW figures above.

Top counties · queue, substation & state air rows

Beauregard 3
Iberville 3
Bossier Parish 2
Calcasieu 2
Jefferson Davis 2
Lafayette 2
Ouachita 2
Richland 2

Interconnection queue in Louisiana

11,122 MW requested across 34 active generation and storage positions. Withdrawn and in-service rows are left out, matching the national page.

ISOProjectFuelMWStatusSource
SPP GEN-2024-379Bossier Parish County Natural gas 1,350 MW Disis stage
MISO WEBREENTERGY ARKANSAS, LLCIberville County Natural gas 755 MW Active
MISO WEBREENTERGY ARKANSAS, LLC EATOIberville County Natural gas 755 MW Active
MISO SmallingENTERGY MISSISSIPPI, LLC. EMTORichland County Solar 600 MW Active; not started
MISO Big Cajun II 500kV SubstationPointe Coupee County Battery storage 593 MW Active
MISO CargasOuachita County Solar 500 MW Active; not started
MISO CargasOuachita County Solar 500 MW Active; not started
MISO MCKNIGHT - PLANT DANIEL 500.0kVENTERGY LOUISIANA, LLC ELTOSt. Tammany County Other hybrids 450 MW Active; not started
MISO Rork - Sellers Road 230.0kVCLECO POWER LLCLafayette County Natural gas 400 MW Active
MISO HinestonCLECO POWER LLC CLECRapides County Solar 350 MW Active; not started
MISO GOOS FERRYENTERGY LOUISIANA, LLCCalcasieu County Other hybrids 325 MW Active
MISO BAXTER WILSON SES SWYD - PERRYVILLE 500 SWYD 500.0kVENTERGY MISSISSIPPI, LLC. EMTOMorehouse County Solar 300 MW Active
MISO WellsCLECO POWER LLC CLECSt. Landry County Battery storage 300 MW Active
MISO Rork - Sellers Road 230.0kVCLECO POWER LLCLafayette County Battery storage 300 MW Active
MISO MOLER - COLFEL 230.0kVENTERGY LOUISIANA, LLC ELTOEast Feliciana County Battery storage 300 MW Active
MISO HARTBURG - AEP LAYFIELD 500.0kVSabine County Solar 270 MW Done; not started
MISO NELSON 500 SWYD - RICHARD 500.0kVENTERGY LOUISIANA, LLCJefferson Davis County Solar 220 MW Pending revision approval
MISO NELSON 500 SWYD - RICHARD 500.0kVENTERGY LOUISIANA, LLCJefferson Davis County Solar 220 MW Pending revision approval
MISO Coughlin - Pine Prairie 138.0kVCLECO POWER LLC CLECEvangeline County Solar 200 MW Active; not started
MISO DARNELL - TALLULAH 115.0kVEast Carroll County Solar 200 MW Active; not started
MISO Deridder - Longville 138.0kVCLECO POWER LLC CLECBeauregard County Solar 200 MW Pending revision approval
MISO VACHERIEENTERGY LOUISIANA, LLC ELTOSt. James County Battery storage 200 MW Active
MISO Cole - Penton Road 230.0kVCLECO POWER LLC CLECBeauregard County Battery storage 200 MW Active
MISO 343515 Chatham Main - 346555 North Aurburn (Ameren) 138.0kVENTERGY LOUISIANA, LLCSangamon County Fuel not stated 200 MW Active
SPP GEN-2024-177Bossier Parish County Battery storage 199 MW Disis stage
MISO Sharing substation for J1890. POI for J1890 is not in the MTEP22 model yet. Reference bus A: 48904CLECO POWER LLC CLECSabine County Solar 180 MW Active; not started
MISO DONALDSONVILLE - EVERGREEN 230.0kVENTERGY LOUISIANA, LLC ELTOIberville County Battery storage 175 MW Active
MISO DUNN - OAK RIDGE (LA) 115.0kVRichland County Other hybrids 150 MW Active; not started
MISO NELSON 230 SWYD - PENTON ROAD (CLECO) 230.0kVCLECO POWER LLC CLECCalcasieu County Battery storage 150 MW Active
MISO MISO S1137ENTERGY LOUISIANA, LLC Fuel not stated 150 MW Active
MISO Cole - Cooper 230.0kVCLECO POWER LLCBeauregard County Solar 140 MW Active
MISO CHACKBAY - VACHERIE 230.0kVENTERGY LOUISIANA, LLCSt. James County Battery storage 135 MW Active
MISO BOGALUSA - TALISHEEK (LAGEN) 230.0kVENTERGY LOUISIANA, LLC ELTOWashington County Battery storage 100 MW Active
SPP GEN-2024-220Caddo Parish County Solar plus storage 55 MW Disis stage

Planned generation in Louisiana

4,048 MW across 24 EIA-860M generators scheduled to enter service within 36 months.

PlantTechnologyMWPlannedStatusSource
Waterford 5St Charles County Natural Gas Fired Combined Cycle 478 MW Jun 2029 Regulatory approvals received. Not under construction
Franklin Farms 1&2Richland County Natural Gas Fired Combined Cycle 469 MW Dec 2028 Regulatory approvals pending. Not under construction
Franklin Farms 1&2Richland County Natural Gas Fired Combined Cycle 469 MW Dec 2028 Regulatory approvals pending. Not under construction
Waterford 5St Charles County Natural Gas Fired Combined Cycle 342 MW Jun 2029 Regulatory approvals received. Not under construction
Franklin Farms 1&2Richland County Natural Gas Fired Combined Cycle 311 MW Dec 2028 Regulatory approvals pending. Not under construction
Franklin Farms 1&2Richland County Natural Gas Fired Combined Cycle 311 MW Dec 2028 Regulatory approvals pending. Not under construction
Singer SolarBeauregard County Solar Photovoltaic 300 MW Mar 2027 Planned for installation, but regulatory approvals not initiated
Dolet Hills SolarDeSoto County Solar Photovoltaic 240 MW Sep 2026 Under construction, more than 50 percent complete
Hollis Creek SolarSabine County Solar Photovoltaic 220 MW May 2027 Under construction, less than or equal to 50 percent complete
Beekman SolarMorehouse County Solar Photovoltaic 207 MW Feb 2027 Under construction, less than or equal to 50 percent complete
Cypress Harvest Solar StationIberville County Solar Photovoltaic 200 MW Aug 2028 Planned for installation, but regulatory approvals not initiated
Bogalusa West Solar StationWashington County Solar Photovoltaic 200 MW Dec 2028 Planned for installation, but regulatory approvals not initiated
Mowata SolarAcadia County Solar Photovoltaic 150 MW Dec 2027 Regulatory approvals pending. Not under construction
Delta Solar PlantBolivar County Solar Photovoltaic 80 MW Nov 2027 Planned for installation, but regulatory approvals not initiated
Overton Hydroelectric ProjectRapides County Conventional Hydroelectric 8 MW Jun 2028 Planned for installation, but regulatory approvals not initiated
Overton Hydroelectric ProjectRapides County Conventional Hydroelectric 8 MW Jun 2028 Planned for installation, but regulatory approvals not initiated
Overton Hydroelectric ProjectRapides County Conventional Hydroelectric 8 MW Jul 2028 Planned for installation, but regulatory approvals not initiated
Overton Hydroelectric ProjectRapides County Conventional Hydroelectric 8 MW Jul 2028 Planned for installation, but regulatory approvals not initiated
Overton Hydroelectric ProjectRapides County Conventional Hydroelectric 8 MW Aug 2028 Planned for installation, but regulatory approvals not initiated
Overton Hydroelectric ProjectRapides County Conventional Hydroelectric 8 MW Aug 2028 Planned for installation, but regulatory approvals not initiated
Sherwood Forest BESSOrleans County Batteries 8 MW Jul 2027 Planned for installation, but regulatory approvals not initiated
SR South BastropMorehouse County Solar Photovoltaic 5 MW Dec 2026 Under construction, less than or equal to 50 percent complete
SR WinnsboroFranklin County Solar Photovoltaic 5 MW Dec 2026 Under construction, less than or equal to 50 percent complete
SR SunsetSt Landry County Solar Photovoltaic 4 MW Dec 2027 Regulatory approvals received. Not under construction

Other filings in Louisiana

State air permits (1)

FacilityAgencyGeneratorsStatusSource
Laidley LLC / Laidley Data Center Louisiana DEQ PROPOSED SYNTHETIC MINOR SOURCE AIR OPERATING PERMIT, comment deadline 7/30/2026

Where Louisiana stands

Across the whole tracker, 533 data center and substation permits are on record in 51 states and DC. Louisiana accounts for 0 of them, ranking #13 by that count. Ranking measures documented permit activity, not the size of the eventual buildout.