Maine Data Center Permits Tracker
Maine has 1,200 MW of generation and storage requested in the interconnection queue and 523 MW of generation planned within 36 months. Every row below links to its primary source.
Last checked Sep 18, 2026
Where the activity is
Ranked by row count. Counts are never mixed with the MW figures above.
Interconnection queue in Maine
1,200 MW requested across 1 active generation and storage position. Withdrawn and in-service rows are left out, matching the national page.
| ISO | Project | Fuel | MW | Status | Source |
|---|---|---|---|---|---|
| ISO-NE | NECEC 1200 MW HVDC (import only) - controllablePDAndroscoggin County | Fuel not stated | 1,200 MW | Interconnection agreement |
Planned generation in Maine
523 MW across 13 EIA-860M generators scheduled to enter service within 36 months.
| Plant | Technology | MW | Planned | Status | Source |
|---|---|---|---|---|---|
| Freedom Pine SolarYork County | Solar Photovoltaic | 250 MW | Jan 2029 | Planned for installation, but regulatory approvals not initiated | |
| Three Rivers Solar Power, LLCHancock County | Solar Photovoltaic | 100 MW | Dec 2026 | Under construction, more than 50 percent complete | |
| Warren Meadow Solar StationKnox County | Solar Photovoltaic | 74 MW | Mar 2028 | Regulatory approvals received. Not under construction | |
| Turner Meadow Solar StationAndroscoggin County | Solar Photovoltaic | 20 MW | Sep 2027 | Regulatory approvals received. Not under construction | |
| Topsham Meadow Solar StationSagadahoc County | Solar Photovoltaic | 17 MW | Oct 2028 | Regulatory approvals pending. Not under construction | |
| West Baldwin Solar StationCumberland County | Solar Photovoltaic | 17 MW | Dec 2028 | Regulatory approvals received. Not under construction | |
| Emery Meadow Solar StationYork County | Solar Photovoltaic | 16 MW | Dec 2027 | Regulatory approvals received. Not under construction | |
| South Portland ESS, LLCCumberland County | Batteries | 10 MW | Dec 2027 | Regulatory approvals received. Not under construction | |
| Auburn PV - BD Solar Auburn LLCAndroscoggin County | Solar Photovoltaic | 5 MW | Mar 2028 | Regulatory approvals pending. Not under construction | |
| Lewiston Jn PV - BD Solar Lewiston Jn LLAndroscoggin County | Solar Photovoltaic | 5 MW | Mar 2028 | Regulatory approvals pending. Not under construction | |
| Sanford ESS, LLCYork County | Batteries | 5 MW | Dec 2027 | Regulatory approvals received. Not under construction | |
| Hogs BayHancock County | Solar Photovoltaic | 2 MW | Sep 2026 | Under construction, more than 50 percent complete | |
| Emery Shute Solar OneWaldo County | Solar Photovoltaic | 1 MW | Dec 2026 | Under construction, more than 50 percent complete |
Where Maine stands
Across the whole tracker, 533 data center and substation permits are on record in 51 states and DC. Maine accounts for 0 of them, ranking #13 by that count. Ranking measures documented permit activity, not the size of the eventual buildout.