South Dakota Data Center Permits Tracker
South Dakota has 3,801 MW of generation and storage requested in the interconnection queue and 235 MW of generation planned within 36 months. Every row below links to its primary source.
Last checked Sep 18, 2026
Where the activity is
Ranked by row count. Counts are never mixed with the MW figures above.
Interconnection queue in South Dakota
3,801 MW requested across 12 active generation and storage positions. Withdrawn and in-service rows are left out, matching the national page.
| ISO | Project | Fuel | MW | Status | Source |
|---|---|---|---|---|---|
| MISO | Astoria 345kV substationOTTER TAIL POWER COMPANY OTPDeuel County | Natural gas | 1,144 MW | Active | |
| MISO | BROOKINGS COUNTYNORTHERN STATES POWER COMPANYBrookings County | Solar | 490 MW | Active | |
| MISO | Split Rock - White (WAPA) 345.0kVNORTHERN STATES POWER COMPANYBrookings County | Solar | 490 MW | Active | |
| SPP | GEN-2017-014Haakon County County | Onshore wind | 300 MW | Ia fully executed/on schedule | |
| MISO | Ellendale - Twin Brooks 345.0kVOTTER TAIL POWER COMPANY OTPDay County | Onshore wind | 300 MW | Active | |
| SPP | GEN-2024-035Brown County | Solar plus storage | 270 MW | Disis stage | |
| MISO | Big Stone South 345 kV substationOTTER TAIL POWER COMPANYGrant County | Battery storage | 250 MW | Active | |
| MISO | Big Stone South 345 kV substationOTTER TAIL POWER COMPANYGrant County | Battery storage | 250 MW | Active | |
| MISO | MISO S1160OTTER TAIL POWER COMPANY OTP | Fuel not stated | 150 MW | Active | |
| SPP | ERAS-2025-035Aberdeen County | Natural gas | 138 MW | Ia fully executed/on schedule | |
| SPP | GEN-2025-GR4Plankinton County | Onshore wind | 11 MW | Special study | |
| SPP | ASGI-2024-004Redfield County | Fuel not stated | 8 MW | None |
Planned generation in South Dakota
235 MW across 10 EIA-860M generators scheduled to enter service within 36 months.
| Plant | Technology | MW | Planned | Status | Source |
|---|---|---|---|---|---|
| Grant Solar, LLCMcCook County | Solar Photovoltaic | 99 MW | Oct 2027 | Regulatory approvals pending. Not under construction | |
| Lange Generating StationPennington County | Natural Gas Internal Combustion Engine | 17 MW | Dec 2026 | Under construction, more than 50 percent complete | |
| Lange Generating StationPennington County | Natural Gas Internal Combustion Engine | 17 MW | Dec 2026 | Under construction, more than 50 percent complete | |
| Lange Generating StationPennington County | Natural Gas Internal Combustion Engine | 17 MW | Dec 2026 | Under construction, more than 50 percent complete | |
| Lange Generating StationPennington County | Natural Gas Internal Combustion Engine | 17 MW | Dec 2026 | Under construction, more than 50 percent complete | |
| Lange Generating StationPennington County | Natural Gas Internal Combustion Engine | 17 MW | Dec 2026 | Under construction, more than 50 percent complete | |
| Lange Generating StationPennington County | Natural Gas Internal Combustion Engine | 17 MW | Dec 2026 | Under construction, more than 50 percent complete | |
| Aberdeen CTBrown County | Natural Gas Fired Combustion Turbine | 16 MW | Oct 2026 | Under construction, more than 50 percent complete | |
| Aberdeen CTBrown County | Natural Gas Fired Combustion Turbine | 16 MW | Oct 2026 | Under construction, more than 50 percent complete | |
| Brookings SolarBrookings County | Solar Photovoltaic | 5 MW | Aug 2026 | Under construction, less than or equal to 50 percent complete |
Where South Dakota stands
Across the whole tracker, 533 data center and substation permits are on record in 51 states and DC. South Dakota accounts for 0 of them, ranking #13 by that count. Ranking measures documented permit activity, not the size of the eventual buildout.