SAVRN Tracker
South Carolina Data Center Permits Tracker
South Carolina has 1,958 MW of generation planned within 36 months. Every row below links to its primary source.
Last checked Sep 18, 2026
0
Data center & substation permits
of 0 total utility-scale permits tracked here
0MW
In the interconnection queue
0 active generation and storage positions
1,958MW
Planned generation
28 EIA-860M generators due within 36 months
#13
of 51 states with anything on record
Ranked by data center & substation permit count
Planned generation in South Carolina
1,958 MW across 28 EIA-860M generators scheduled to enter service within 36 months.
| Plant | Technology | MW | Planned | Status | Source |
|---|---|---|---|---|---|
| Pinopolis BESSBerkeley County | Batteries | 300 MW | Sep 2027 | Planned for installation, but regulatory approvals not initiated | |
| SR CordovaOrangeburg County | Solar Photovoltaic | 100 MW | Dec 2027 | Regulatory approvals received. Not under construction | |
| Robinson Solar PlantChesterfield County | Solar Photovoltaic | 76 MW | Dec 2027 | Regulatory approvals pending. Not under construction | |
| Lotus SolarDarlington County | Solar Photovoltaic | 75 MW | Oct 2027 | Regulatory approvals received. Not under construction | |
| Kingstree West 115Williamsburg County | Solar Photovoltaic | 75 MW | Aug 2026 | Construction complete, but not yet in commercial operation | |
| B & K SolarDarlington County | Solar Photovoltaic | 75 MW | Nov 2026 | Under construction, more than 50 percent complete | |
| Big Fork SolarBarnwell County | Solar Photovoltaic | 75 MW | Nov 2028 | Regulatory approvals received. Not under construction | |
| Big Fork SolarBarnwell County | Batteries | 75 MW | Feb 2027 | Regulatory approvals received. Not under construction | |
| Colleton SolarColleton County | Solar Photovoltaic | 75 MW | Nov 2028 | Regulatory approvals received. Not under construction | |
| Culpepper SolarDarlington County | Solar Photovoltaic | 75 MW | Nov 2027 | Regulatory approvals received. Not under construction | |
| Juniper SolarChesterfield County | Solar Photovoltaic | 75 MW | Mar 2027 | Regulatory approvals received. Not under construction | |
| Rollins SolarDarlington County | Solar Photovoltaic | 75 MW | Nov 2027 | Regulatory approvals received. Not under construction | |
| Ross SolarDarlington County | Solar Photovoltaic | 75 MW | Nov 2027 | Regulatory approvals received. Not under construction | |
| Holliday Solar IHorry County | Solar Photovoltaic | 74 MW | Nov 2028 | Regulatory approvals received. Not under construction | |
| Shining Sun SolarOrangeburg County | Solar Photovoltaic | 74 MW | Nov 2028 | Regulatory approvals received. Not under construction | |
| Hudson Place Solar PlantNewberry County | Solar Photovoltaic | 71 MW | Jan 2028 | Regulatory approvals pending. Not under construction | |
| Melsam SolarDillon County | Solar Photovoltaic | 65 MW | Nov 2028 | Regulatory approvals received. Not under construction | |
| Shorthorn SolarLee County | Solar Photovoltaic | 60 MW | Nov 2027 | Regulatory approvals received. Not under construction | |
| WinyahGeorgetown County | Petroleum Liquids | 57 MW | Dec 2027 | Planned for installation, but regulatory approvals not initiated | |
| WinyahGeorgetown County | Petroleum Liquids | 57 MW | Dec 2027 | Planned for installation, but regulatory approvals not initiated | |
| Crossroads SolarBarnwell County | Solar Photovoltaic | 50 MW | Nov 2028 | Regulatory approvals received. Not under construction | |
| GEB SolarDarlington County | Solar Photovoltaic | 50 MW | Nov 2028 | Regulatory approvals received. Not under construction | |
| Quest SolarAllendale County | Solar Photovoltaic | 50 MW | Nov 2028 | Regulatory approvals received. Not under construction | |
| SR GeorgetownGeorgetown County | Solar Photovoltaic | 50 MW | Dec 2026 | Under construction, more than 50 percent complete | |
| Bush River Solar PlantLaurens County | Solar Photovoltaic | 45 MW | Jan 2028 | Regulatory approvals pending. Not under construction | |
| Cotton SolarDillon County | Solar Photovoltaic | 16 MW | Jun 2027 | Regulatory approvals received. Not under construction | |
| Rhubarb One SCMarion County | Solar Photovoltaic | 10 MW | Jun 2027 | Regulatory approvals pending. Not under construction | |
| Longtown Energy StorageFairfield County | Batteries | 4 MW | Sep 2026 | Under construction, more than 50 percent complete |
Where South Carolina stands
Across the whole tracker, 533 data center and substation permits are on record in 51 states and DC. South Carolina accounts for 0 of them, ranking #13 by that count. Ranking measures documented permit activity, not the size of the eventual buildout.