Vermont Data Center Permits Tracker
Vermont has 634 MW of generation and storage requested in the interconnection queue and 108 MW of generation planned within 36 months. Every row below links to its primary source.
Last checked Sep 18, 2026
Where the activity is
Ranked by row count. Counts are never mixed with the MW figures above.
Interconnection queue in Vermont
634 MW requested across 1 active generation and storage position. Withdrawn and in-service rows are left out, matching the national page.
| ISO | Project | Fuel | MW | Status | Source |
|---|---|---|---|---|---|
| ISO-NE | VT Yankee Nuclear Power Station Upgrade7Windham County | Nuclear | 634 MW | Interconnection agreement |
Planned generation in Vermont
108 MW across 5 EIA-860M generators scheduled to enter service within 36 months.
| Plant | Technology | MW | Planned | Status | Source |
|---|---|---|---|---|---|
| PantonAddison County | Solar Photovoltaic | 50 MW | Dec 2028 | Regulatory approvals pending. Not under construction | |
| Shaftsbury SolarBennington County | Solar Photovoltaic | 20 MW | Dec 2028 | Regulatory approvals pending. Not under construction | |
| Fair Haven SolarRutland County | Solar Photovoltaic | 20 MW | Mar 2028 | Regulatory approvals received. Not under construction | |
| Essex VT BESS 1Chittenden County | Batteries | 16 MW | Dec 2026 | Under construction, less than or equal to 50 percent complete | |
| Apple Hill SolarBennington County | Solar Photovoltaic | 2 MW | Dec 2026 | Under construction, less than or equal to 50 percent complete |
Where Vermont stands
Across the whole tracker, 533 data center and substation permits are on record in 51 states and DC. Vermont accounts for 0 of them, ranking #13 by that count. Ranking measures documented permit activity, not the size of the eventual buildout.