SAVRN Tracker
Utah Data Center Permits Tracker
Utah has 3,345 MW of generation planned within 36 months. Every row below links to its primary source.
Last checked Sep 18, 2026
0
Data center & substation permits
of 0 total utility-scale permits tracked here
0MW
In the interconnection queue
0 active generation and storage positions
3,345MW
Planned generation
28 EIA-860M generators due within 36 months
#13
of 51 states with anything on record
Ranked by data center & substation permit count
Planned generation in Utah
3,345 MW across 28 EIA-860M generators scheduled to enter service within 36 months.
| Plant | Technology | MW | Planned | Status | Source |
|---|---|---|---|---|---|
| Notch Peak Solar LLCMillard County | Solar Photovoltaic | 324 MW | Sep 2028 | Regulatory approvals received. Not under construction | |
| Milford Solar Phase IIBeaver County | Solar Photovoltaic | 310 MW | Sep 2027 | Under construction, less than or equal to 50 percent complete | |
| Utah Solar 1Millard County | Solar Photovoltaic | 300 MW | Dec 2027 | Planned for installation, but regulatory approvals not initiated | |
| Red Butte Solar and StorageIron County | Solar Photovoltaic | 300 MW | Apr 2029 | Regulatory approvals pending. Not under construction | |
| Red Butte Solar and StorageIron County | Batteries | 300 MW | Apr 2029 | Regulatory approvals pending. Not under construction | |
| Intermountain Pumped Storage ProjectMillard County | Hydroelectric Pumped Storage | 250 MW | Jul 2028 | Planned for installation, but regulatory approvals not initiated | |
| Intermountain Pumped Storage ProjectMillard County | Hydroelectric Pumped Storage | 250 MW | Jul 2028 | Planned for installation, but regulatory approvals not initiated | |
| Intermountain Pumped Storage ProjectMillard County | Hydroelectric Pumped Storage | 250 MW | Jul 2028 | Planned for installation, but regulatory approvals not initiated | |
| Intermountain Pumped Storage ProjectMillard County | Hydroelectric Pumped Storage | 250 MW | Jul 2028 | Planned for installation, but regulatory approvals not initiated | |
| Fremont SolarIron County | Batteries | 198 MW | Jun 2027 | Under construction, less than or equal to 50 percent complete | |
| Faraday Energy StorageUtah County | Batteries | 150 MW | Sep 2026 | Under construction, less than or equal to 50 percent complete | |
| Fremont SolarIron County | Solar Photovoltaic | 99 MW | Jun 2027 | Under construction, less than or equal to 50 percent complete | |
| Glen Canyon Solar A, LLCKane County | Solar Photovoltaic | 95 MW | Dec 2028 | Under construction, less than or equal to 50 percent complete | |
| Parowan SolarIron County | Batteries | 58 MW | Feb 2028 | Planned for installation, but regulatory approvals not initiated | |
| Parowan SolarIron County | Solar Photovoltaic | 58 MW | Feb 2028 | Planned for installation, but regulatory approvals not initiated | |
| Cape Generating StationBeaver County | Geothermal | 43 MW | Oct 2026 | Construction complete, but not yet in commercial operation | |
| Cape Generating StationBeaver County | Geothermal | 43 MW | Jan 2027 | Construction complete, but not yet in commercial operation | |
| Cape Generating StationBeaver County | Geothermal | 43 MW | Jan 2027 | Under construction, more than 50 percent complete | |
| Brigham City GasBox Elder County | Natural Gas Internal Combustion Engine | 2 MW | Aug 2027 | Regulatory approvals received. Not under construction | |
| Brigham City GasBox Elder County | Natural Gas Internal Combustion Engine | 2 MW | Aug 2027 | Regulatory approvals received. Not under construction | |
| Brigham City GasBox Elder County | Natural Gas Internal Combustion Engine | 2 MW | Aug 2027 | Regulatory approvals received. Not under construction | |
| PaysonUtah County | Natural Gas Internal Combustion Engine | 2 MW | Aug 2026 | Construction complete, but not yet in commercial operation | |
| PaysonUtah County | Natural Gas Internal Combustion Engine | 2 MW | Aug 2026 | Construction complete, but not yet in commercial operation | |
| PaysonUtah County | Natural Gas Internal Combustion Engine | 2 MW | Aug 2026 | Construction complete, but not yet in commercial operation | |
| PaysonUtah County | Natural Gas Internal Combustion Engine | 2 MW | Aug 2026 | Construction complete, but not yet in commercial operation | |
| PaysonUtah County | Natural Gas Internal Combustion Engine | 2 MW | Aug 2026 | Construction complete, but not yet in commercial operation | |
| PaysonUtah County | Natural Gas Internal Combustion Engine | 2 MW | Aug 2026 | Construction complete, but not yet in commercial operation | |
| Rodatherm Milford 1Beaver County | Geothermal | 2 MW | Jan 2028 | Under construction, less than or equal to 50 percent complete |
Other filings in Utah
State air permits (2)
| Facility | Agency | Generators | Status | Source |
|---|---|---|---|---|
| Stadion LLC - Eagle Mountain Data Center | Utah Division of Air Quality | document | ||
| Aligned Energy Data Centers (SLC), LLC- West Jordan Data Center | Utah Division of Air Quality | document |
Where Utah stands
Across the whole tracker, 533 data center and substation permits are on record in 51 states and DC. Utah accounts for 0 of them, ranking #13 by that count. Ranking measures documented permit activity, not the size of the eventual buildout.