Utah Data Center Permits Tracker

Utah has 3,345 MW of generation planned within 36 months. Every row below links to its primary source.

Last checked Oct 6, 2026

0
Data center & substation permits
of 1 total utility-scale permits tracked here
0MW
In the interconnection queue
0 active generation and storage positions
3,345MW
Planned generation
28 EIA-860M generators due within 36 months
#13
of 51 states with anything on record
Ranked by data center & substation permit count

Where the activity is

Ranked by row count. Counts are never mixed with the MW figures above.

Permit categories

zoning 1

Top counties · queue, substation & state air rows

Millard 1
Salt Lake 1

Permits in Utah

1 building and land-use permit tracked in Utah.

DateCategoryAddressApplicantSource
Aug 25, 2026 Zoning Building J8, Freeport Center, Clearfield, UTClearfield City Council minutes

Planned generation in Utah

3,345 MW across 28 EIA-860M generators scheduled to enter service within 36 months.

PlantTechnologyMWPlannedStatusSource
Notch Peak Solar LLCMillard County Solar Photovoltaic 324 MW Sep 2028 Regulatory approvals received. Not under construction
Milford Solar Phase IIBeaver County Solar Photovoltaic 310 MW Sep 2027 Under construction, less than or equal to 50 percent complete
Utah Solar 1Millard County Solar Photovoltaic 300 MW Dec 2027 Planned for installation, but regulatory approvals not initiated
Red Butte Solar and StorageIron County Solar Photovoltaic 300 MW Apr 2029 Regulatory approvals pending. Not under construction
Red Butte Solar and StorageIron County Batteries 300 MW Apr 2029 Regulatory approvals pending. Not under construction
Intermountain Pumped Storage ProjectMillard County Hydroelectric Pumped Storage 250 MW Jul 2028 Planned for installation, but regulatory approvals not initiated
Intermountain Pumped Storage ProjectMillard County Hydroelectric Pumped Storage 250 MW Jul 2028 Planned for installation, but regulatory approvals not initiated
Intermountain Pumped Storage ProjectMillard County Hydroelectric Pumped Storage 250 MW Jul 2028 Planned for installation, but regulatory approvals not initiated
Intermountain Pumped Storage ProjectMillard County Hydroelectric Pumped Storage 250 MW Jul 2028 Planned for installation, but regulatory approvals not initiated
Fremont SolarIron County Batteries 198 MW Jun 2027 Under construction, less than or equal to 50 percent complete
Faraday Energy StorageUtah County Batteries 150 MW Sep 2026 Under construction, less than or equal to 50 percent complete
Fremont SolarIron County Solar Photovoltaic 99 MW Jun 2027 Under construction, less than or equal to 50 percent complete
Glen Canyon Solar A, LLCKane County Solar Photovoltaic 95 MW Dec 2028 Under construction, less than or equal to 50 percent complete
Parowan SolarIron County Batteries 58 MW Feb 2028 Planned for installation, but regulatory approvals not initiated
Parowan SolarIron County Solar Photovoltaic 58 MW Feb 2028 Planned for installation, but regulatory approvals not initiated
Cape Generating StationBeaver County Geothermal 43 MW Oct 2026 Construction complete, but not yet in commercial operation
Cape Generating StationBeaver County Geothermal 43 MW Jan 2027 Construction complete, but not yet in commercial operation
Cape Generating StationBeaver County Geothermal 43 MW Jan 2027 Under construction, more than 50 percent complete
Brigham City GasBox Elder County Natural Gas Internal Combustion Engine 2 MW Aug 2027 Regulatory approvals received. Not under construction
Brigham City GasBox Elder County Natural Gas Internal Combustion Engine 2 MW Aug 2027 Regulatory approvals received. Not under construction
Brigham City GasBox Elder County Natural Gas Internal Combustion Engine 2 MW Aug 2027 Regulatory approvals received. Not under construction
PaysonUtah County Natural Gas Internal Combustion Engine 2 MW Aug 2026 Construction complete, but not yet in commercial operation
PaysonUtah County Natural Gas Internal Combustion Engine 2 MW Aug 2026 Construction complete, but not yet in commercial operation
PaysonUtah County Natural Gas Internal Combustion Engine 2 MW Aug 2026 Construction complete, but not yet in commercial operation
PaysonUtah County Natural Gas Internal Combustion Engine 2 MW Aug 2026 Construction complete, but not yet in commercial operation
PaysonUtah County Natural Gas Internal Combustion Engine 2 MW Aug 2026 Construction complete, but not yet in commercial operation
PaysonUtah County Natural Gas Internal Combustion Engine 2 MW Aug 2026 Construction complete, but not yet in commercial operation
Rodatherm Milford 1Beaver County Geothermal 2 MW Jan 2028 Under construction, less than or equal to 50 percent complete

Other filings in Utah

State air permits (4)

FacilityAgencyGeneratorsStatusSource
Joule Capital Partners, LLCMillard County Utah Division of Air Quality Issued
Stadion LLC - Eagle Mountain Data Center Utah Division of Air Quality document
Aligned Energy Data Centers (SLC), LLC- West Jordan Data Center Utah Division of Air Quality document
Aligned Data Centers (WJU) PropCo, LLC West Jordan Data Center, 6800 West 9800 SouthSalt Lake County Utah Division of Air Quality Public notice

Where Utah stands

Across the whole tracker, 652 data center and substation permits are on record in 51 states and DC. Utah accounts for 0 of them, ranking #13 by that count. Ranking measures documented permit activity, not the size of the eventual buildout.