Fuel cell powered AI data centers

The data center sites with fuel cell power on record in the Capital Atlas, the fuel cell generators planned nationally in EIA-860M, and the fuel cell plant behind a SAVRN Atom.

Sites with fuel cells
4
Developers
4
Planned fuel cell generators (EIA)
0
Planned fuel cell MW (EIA)
n.a.
Data as of October 2, 2026Every figure traces to a source on its company or site record

Fuel cells make electricity from fuel without burning it. For a data center that cannot wait for a grid interconnection, or cannot be permitted with a turbine plant next to a town, that is the difference between building and not building. The sites below have put a fuel cell arrangement on the record.

Data center sites with fuel cell power on record

#DeveloperSiteStateCapacityStatusPower arrangement, as recordedSources
1Alphabet / Google Project Tembo (formerly Project Jade), Switchgrass Industrial ParkWyoming2,700 MWapprovedTallgrass Energy to combine energy resources from Black Hills Energy, fuel cells and its power plant to serve the campuscowboystatedaily.comdatacenterknowledge.comoilcity.news
2VolitionVolition data center, former Fingerhut warehouse (4000 E. U.S. 6), Spanish Fork CanyonUtah250 MWproposedSelf-generated, fuel cell powered; the city amendment requires energy grid isolation; air permits sought from the Utah Division of Air Qualitymsn.comsltrib.comfox13now.com
3Amazon (AWS) AWS data center campus, Scioto Darby Road (Hilliard area) with AEP Ohio fuel cell plantOhiounder construction72.9 MW AEP Ohio fuel cell facility using 228 Bloom Energy units, supplied by natural gasmsn.comwosu.org
4DataOneDataOne AI factory campus (Logix Innovation Campus)Indianaannounced350 MW of utility power through IMPA plus 175 MW from Bloom Energy natural gas fuel cells, per the project electrical engineer at the 21 September 2026 open houseclintoncountydailynews.comjconline.comclintoncountydailynews.com
Questions this page answers
Which AI data centers are powered by fuel cells?

4 named sites in the SAVRN Capital Atlas record fuel cell generation: Alphabet / Google at Project Tembo (formerly Project Jade), Switchgrass Industrial Park, Wyoming; Volition at Volition data center, former Fingerhut warehouse (4000 E. U.S. 6), Spanish Fork Canyon, Utah; Amazon (AWS) at AWS data center campus, Scioto Darby Road (Hilliard area) with AEP Ohio fuel cell plant, Ohio; DataOne at DataOne AI factory campus (Logix Innovation Campus), Indiana.

Why fuel cells instead of gas turbines?

A fuel cell converts fuel electrochemically, without combustion, so it runs quiet, emits no NOx and can be permitted and sited where a turbine plant cannot. It produces firm baseload rather than variable output, which is what a constant compute load needs.

How does SAVRN use fuel cells?

SAVRN's Proton plant is the on-site baseload for an Atom block: fuel cells sized to the block's 13.2 MW envelope, with grid-forming storage for transients, islanding and black start, so the campus never waits on a utility interconnection queue. Proton is a reference design verified per site; it is described on its solutions page, not ranked against operating sites here.

How much fuel cell capacity is planned nationally?

The permits tracker's EIA-860M read has no planned fuel cell generators on file at the moment.

Keep going
The SAVRN reference set

Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.

Have a specific address? Site Intelligence reads all seven references against one location, county, utility and grid operator included, and cites every finding.