Gray Wolf Data Centers data centers

Listed below are 5 data centers operated by Gray Wolf Data Centers in the United States, identified from primary sources across 4 states and 3 cities.

Colocation 5 buildings 4 states 3 cities Gray Wolf Data Centers website ↗
Data centers
5
identified from primary sources
States
4
each links to its own state page
Cities
3
cities and counties with at least one
Floor area published
0
of 5; shown per building, never summed
Power published
5
of 5; shown per building, never summed
The company

What Gray Wolf Data Centers does, and what this map holds

Designs, builds and franchises small high-density AI and HPC data centers selling colocation for GPU clusters, with flagship facilities in Connecticut. It also does franchising independently owned edge facilities, on-site power generation (fuel cells, linear generators, waste-to-energy), ATLAS Cloud orchestration layer. This map identifies 5 data centers operated by Gray Wolf Data Centers across 4 states and 3 cities. Its largest presence is Connecticut, with 2 buildings.

After Connecticut, Gray Wolf Data Centers has the most data centers in Florida (1), Massachusetts (1), New Mexico (1). Each state below links to that state's own page, which carries every operator in it, the grid operator, and the moratorium, water and delay record that applies there.

Disclosure is uneven and this page does not paper over it. 5 publish a power figure. Each figure is shown against the building it belongs to and never added into a single total, because operators do not measure the same thing: one states the floor area of one hall, another the full capacity of a campus it has only announced.

3 of these records are marked planned, permitted or under construction rather than operating, and each is labeled as such in the list below.

The list

Every Gray Wolf Data Centers data center, by state and city

All 5 Gray Wolf Data Centers data centers this map identifies, grouped by the state and then the city each one stands in. Every entry carries the source that names it.

Gray Wolf Data Centers data centers in Connecticut

All Connecticut data centers ↗

Gray Wolf Data Centers has 2 data centers in Connecticut, in Bristol and Colchester. 2 publish a power figure, shown against each one below.

Bristol, Connecticut1

  1. Gray Wolf Data Centers data center Gray Wolf Data Centers data center stands in Bristol, Hartford County, Connecticut. The record puts it at 3 MW. 3 MW

Colchester, Connecticut1

  1. Gray Wolf Data Centers data center Gray Wolf Data Centers data center stands in Colchester, New London County, Connecticut. The record puts it at 4 MW. 4 MW

Gray Wolf Data Centers data centers in Florida

All Florida data centers ↗

Gray Wolf Data Centers has 1 data center in Florida, in Arcadia. 1 publishes a power figure, shown against each one below.

Arcadia, Florida1

  1. Desoto Power Plant site, Arcadia, FL Desoto Power Plant site, Arcadia, FL stands in Arcadia, DeSoto County, Florida. The record puts it at 115 MW. It is recorded as planned rather than operating. 115 MW

Gray Wolf Data Centers data centers in Massachusetts

All Massachusetts data centers ↗

Gray Wolf Data Centers has 1 data center in Massachusetts, in Elsewhere in Massachusetts. 1 publishes a power figure, shown against each one below.

Elsewhere in Massachusetts, Massachusetts1

  1. Southeastern Massachusetts site Southeastern Massachusetts site is recorded in Massachusetts. The record puts it at 500 MW. It is recorded as planned rather than operating. 500 MW

Gray Wolf Data Centers data centers in New Mexico

All New Mexico data centers ↗

Gray Wolf Data Centers has 1 data center in New Mexico, in Elsewhere in New Mexico. 1 publishes a power figure, shown against each one below.

Elsewhere in New Mexico, New Mexico1

  1. New Mexico site (Green Data Corp) New Mexico site (Green Data Corp) is recorded in New Mexico. The record puts it at 1500 MW. It is recorded as planned rather than operating. 1500 MW

Floor area and power appear only where the operator or a government record publishes them, and are never added into one figure. A building a source describes without naming it is listed as a Gray Wolf Data Centers data center at the city or county it stands in.

Distribution

Where Gray Wolf Data Centers data centers cluster

Gray Wolf Data Centers's 5 data centers across 4 states. Each state links to its own page, which carries every operator in that state alongside the grid operator and the policy record.

Questions

Gray Wolf Data Centers data centers, answered

How many data centers does Gray Wolf Data Centers have?

This map identifies 5 US data centers operated by Gray Wolf Data Centers, across 4 states and 3 cities. Each one is listed below with the city and county it stands in and the source that names it. This is a count of what primary sources describe in the United States, not a company-reported global total.

Where are Gray Wolf Data Centers data centers located?

They are grouped below by state and then by city. Gray Wolf Data Centers's largest presence is Connecticut with 2 buildings, followed by Florida (1), Massachusetts (1), New Mexico (1).

How big are Gray Wolf Data Centers data centers?

0 of the 5 publish a floor area and 5 publish a power figure. Both are shown against the individual building rather than summed, because a floor area for one hall and an announced campus capacity are not the same measurement.

Who is Gray Wolf Data Centers?

Designs, builds and franchises small high-density AI and HPC data centers selling colocation for GPU clusters, with flagship facilities in Connecticut. It also does franchising independently owned edge facilities, on-site power generation (fuel cells, linear generators, waste-to-energy), ATLAS Cloud orchestration layer. On this map it is classified as colocation. Its own site is at https://graywolfdatacenters.com.

Counts are what primary sources describe in the United States as of 2026-09-02: the operator's own published facility list, PeeringDB, OpenStreetMap, Wikidata, and county and state building registers. They are not company-reported global totals, and this page never states a figure the record does not carry.