Montana Data Center Permits Tracker

Montana has 300 MW of generation and storage requested in the interconnection queue and 454 MW of generation planned within 36 months. Every row below links to its primary source.

Last checked Sep 18, 2026

0
Data center & substation permits
of 0 total utility-scale permits tracked here
300MW
In the interconnection queue
1 active generation and storage position
454MW
Planned generation
4 EIA-860M generators due within 36 months
#13
of 51 states with anything on record
Ranked by data center & substation permit count

Where the activity is

Ranked by row count. Counts are never mixed with the MW figures above.

Top counties · queue, substation & state air rows

Big Horn 1

Interconnection queue in Montana

300 MW requested across 1 active generation and storage position. Withdrawn and in-service rows are left out, matching the national page.

ISOProjectFuelMWStatusSource
SPP ASGI-2024-012Big Horn County Solar 300 MW None

Planned generation in Montana

454 MW across 4 EIA-860M generators scheduled to enter service within 36 months.

PlantTechnologyMWPlannedStatusSource
Anthelope Hills Solar Generation BESSBeaverhead County Solar Photovoltaic 200 MW Dec 2027 Regulatory approvals pending. Not under construction
Anthelope Hills Solar Generation BESSBeaverhead County Batteries 200 MW Dec 2027 Regulatory approvals pending. Not under construction
Beartooth Energy Storage LLCYellowstone County Batteries 50 MW Dec 2027 Regulatory approvals pending. Not under construction
HauserLewis and Clark County Conventional Hydroelectric 4 MW Jun 2028 Planned for installation, but regulatory approvals not initiated

Where Montana stands

Across the whole tracker, 533 data center and substation permits are on record in 51 states and DC. Montana accounts for 0 of them, ranking #13 by that count. Ranking measures documented permit activity, not the size of the eventual buildout.