Nebraska Data Center Permits Tracker

Nebraska has 11 data center and substation permits on record, 7,176 MW of generation and storage requested in the interconnection queue and 1,615 MW of generation planned within 36 months. Every row below links to its primary source.

Last checked Sep 18, 2026

11
Data center & substation permits
of 11 total utility-scale permits tracked here
7,176MW
In the interconnection queue
27 active generation and storage positions
1,615MW
Planned generation
27 EIA-860M generators due within 36 months
#8
of 51 states with anything on record
Ranked by data center & substation permit count

Where the activity is

Ranked by row count. Counts are never mixed with the MW figures above.

Permit categories

Data center 9
Substation 2

Top counties · queue, substation & state air rows

Lancaster 6
Gage 5
Burt 3
Cass 3
Blair 1
Dodge 1
Douglas 1
Funk 1

Permits in Nebraska

11 building and land-use permits tracked in Nebraska.

DateCategoryAddressApplicantSource
Sep 8, 2026 Data center City of Papillion NE Citizen Access records
Sep 8, 2026 Data center 11050 Cornhusker Rd NE 68046City of Papillion NE Citizen Access records
Aug 31, 2026 Data center City of Papillion NE Citizen Access records
Aug 31, 2026 Data center 11684 S 158th St Bldg , United States, NE 68138City of Papillion NE Citizen Access records
Aug 12, 2026 Data center City of Papillion NE Citizen Access records
Aug 12, 2026 Data center 10917 Harry Watanabe pkwy Wy, La Vista, NE 68128City of Papillion NE Citizen Access records
Aug 5, 2026 Data center 11050 Cornhusker Rd NE 68046City of Papillion NE Citizen Access records
Mar 16, 2026 Substation City of Papillion NE Citizen Access records
Mar 16, 2026 Substation 15235 Gold Coast Rd, Papillion, NE 68138City of Papillion NE Citizen Access records
Nov 25, 2025 Data center City of Papillion NE Citizen Access records
Nov 25, 2025 Data center 11684 S 158th St, Papillion, NE 68138City of Papillion NE Citizen Access records

Interconnection queue in Nebraska

7,176 MW requested across 27 active generation and storage positions. Withdrawn and in-service rows are left out, matching the national page.

ISOProjectFuelMWStatusSource
SPP GEN-2024-021Lancaster County Natural gas 540 MW Disis stage
SPP GEN-2018-043Burt County Solar 500 MW Ia fully executed/on schedule
SPP GEN-2023-222Gage County Natural gas 478 MW Ia fully executed/on schedule
SPP GEN-2023-224Lancaster County Natural gas 478 MW Ia fully executed/on schedule
SPP 2023-G1Scotts Bluff County County Solar plus storage 400 MW Facility study stage
SPP GEN-2024-020Lancaster County Natural gas 390 MW Disis stage
SPP GEN-2024-022Gage County Natural gas 390 MW Disis stage
SPP GEN-2024-213Cass County Natural gas 360 MW Disis stage
SPP GEN-2020-084Burt County Solar 350 MW Ia fully executed/on schedule
SPP GEN-2020-011Funk County Solar plus storage 320 MW Ia fully executed/on schedule
SPP GEN-2024-211Cass County Natural gas 303 MW Disis stage
SPP GEN-2024-212Cass County Natural gas 303 MW Disis stage
SPP GEN-2017-181Lancaster County Onshore wind 300 MW Ia fully executed/on schedule
SPP GEN-2024-023Gage County Natural gas 270 MW Disis stage
SPP GEN-2024-372Douglas County Battery storage 250 MW Disis stage
SPP GEN-2026-SR20Lincoln County Battery storage 225 MW Special study
SPP GEN-2024-234Burt County Solar 200 MW Disis stage
SPP GEN-2025-SR24Blair County Other 200 MW Facility study stage
SPP GEN-2025-SR26Plattsmouth County Other 200 MW Facility study stage
SPP GEN-2025-SR31Meadow Grove County Battery storage 170 MW Special study
SPP GEN-2024-065Dodge County Battery storage 150 MW Disis stage
SPP ERAS-2025-001Lancaster County Natural gas 104 MW Ia fully executed/on schedule
SPP GEN-2025-SR20Omaha County Other 100 MW Ia pending
SPP GEN-2024-017Lancaster County Natural gas 62 MW Disis stage
SPP GEN-2024-019Gage County Natural gas 62 MW Disis stage
SPP GEN-2025-SR5Hallam County Battery storage 40 MW Facility study stage
SPP GEN-2024-018Gage County Natural gas 31 MW Disis stage

Planned generation in Nebraska

1,615 MW across 27 EIA-860M generators scheduled to enter service within 36 months.

PlantTechnologyMWPlannedStatusSource
Cass CountyCass County Natural Gas Fired Combustion Turbine 264 MW Feb 2029 Regulatory approvals received. Not under construction
Cass CountyCass County Natural Gas Fired Combustion Turbine 264 MW Feb 2029 Regulatory approvals received. Not under construction
Cass CountyCass County Natural Gas Fired Combustion Turbine 264 MW Feb 2029 Regulatory approvals received. Not under construction
Turtle CreekSarpy County Natural Gas Fired Combustion Turbine 264 MW Aug 2028 Regulatory approvals received. Not under construction
Big Elk SolarWashington County Solar Photovoltaic 100 MW Dec 2027 Regulatory approvals pending. Not under construction
Burt County WindBurt County Onshore Wind Turbine 75 MW Jul 2027 Regulatory approvals pending. Not under construction
Terry Bundy Generating StationLancaster County Natural Gas Fired Combustion Turbine 52 MW Jun 2029 Regulatory approvals pending. Not under construction
Terry Bundy Generating StationLancaster County Natural Gas Fired Combustion Turbine 52 MW Jun 2029 Regulatory approvals pending. Not under construction
Steele Flats Energy StorageJefferson County Batteries 50 MW Dec 2026 Under construction, more than 50 percent complete
Princeton Road StationLancaster County Natural Gas Internal Combustion Engine 18 MW Jun 2029 Planned for installation, but regulatory approvals not initiated
Princeton Road StationLancaster County Natural Gas Internal Combustion Engine 18 MW Jun 2029 Planned for installation, but regulatory approvals not initiated
Princeton Road StationLancaster County Natural Gas Internal Combustion Engine 18 MW Jun 2029 Planned for installation, but regulatory approvals not initiated
Princeton Road StationLancaster County Natural Gas Internal Combustion Engine 18 MW Jun 2029 Planned for installation, but regulatory approvals not initiated
Princeton Road StationLancaster County Natural Gas Internal Combustion Engine 18 MW Jun 2029 Planned for installation, but regulatory approvals not initiated
Princeton Road StationLancaster County Natural Gas Internal Combustion Engine 18 MW Jun 2029 Planned for installation, but regulatory approvals not initiated
Princeton Road StationLancaster County Natural Gas Internal Combustion Engine 18 MW Jun 2029 Planned for installation, but regulatory approvals not initiated
Princeton Road StationLancaster County Natural Gas Internal Combustion Engine 18 MW Jun 2029 Planned for installation, but regulatory approvals not initiated
Princeton Road StationLancaster County Natural Gas Internal Combustion Engine 18 MW Jun 2029 Planned for installation, but regulatory approvals not initiated
Princeton Road StationLancaster County Natural Gas Internal Combustion Engine 18 MW Jun 2029 Planned for installation, but regulatory approvals not initiated
Princeton Road StationLancaster County Natural Gas Internal Combustion Engine 18 MW Jun 2029 Planned for installation, but regulatory approvals not initiated
Princeton Road StationLancaster County Natural Gas Internal Combustion Engine 18 MW Jun 2029 Planned for installation, but regulatory approvals not initiated
Papillion Creek WastewaterSarpy County Natural Gas Internal Combustion Engine 2 MW Nov 2026 Under construction, more than 50 percent complete
Papillion Creek WastewaterSarpy County Natural Gas Internal Combustion Engine 2 MW Nov 2026 Under construction, more than 50 percent complete
Papillion Creek WastewaterSarpy County Natural Gas Internal Combustion Engine 2 MW Nov 2026 Under construction, more than 50 percent complete
TecumsehJohnson County Petroleum Liquids 2 MW Aug 2027 Regulatory approvals received. Not under construction
TecumsehJohnson County Petroleum Liquids 2 MW Aug 2027 Regulatory approvals received. Not under construction
WisnerCuming County Petroleum Liquids 2 MW Dec 2026 Construction complete, but not yet in commercial operation

Where Nebraska stands

Across the whole tracker, 533 data center and substation permits are on record in 51 states and DC. Nebraska accounts for 11 of them, ranking #8 by that count. Ranking measures documented permit activity, not the size of the eventual buildout.