Nevada Data Center Permits Tracker

Nevada has 11 data center and substation permits on record, 5,570 MW of generation and storage requested in the interconnection queue and 6,472 MW of generation planned within 36 months. Every row below links to its primary source.

Last checked Sep 18, 2026

11
Data center & substation permits
of 11 total utility-scale permits tracked here
5,570MW
In the interconnection queue
13 active generation and storage positions
6,472MW
Planned generation
28 EIA-860M generators due within 36 months
#8
of 51 states with anything on record
Ranked by data center & substation permit count

Where the activity is

Ranked by row count. Counts are never mixed with the MW figures above.

Permit categories

Data center 8
Substation 3

Top counties · queue, substation & state air rows

Clark 8
Nye 3
Clark/Nye 2

Permits in Nevada

11 building and land-use permits tracked in Nevada.

DateCategoryAddressApplicantSource
Aug 20, 2026 Data center 9630 N VIRGINIA ST, RENO, NV 89506City of Reno NV Citizen Access records
Jul 22, 2026 Data center 9710 N VIRGINIA ST, RENO, NV 89506City of Reno NV Citizen Access records
Jul 10, 2026 Substation Washoe County NV Citizen Access records
Jul 1, 2026 Data center 265 KEYSTONE AVE, RENO, NV 89503City of Reno NV Citizen Access records
Jun 10, 2026 Data center 9710 N VIRGINIA ST, RENO, NV 89506, 0 VIRGINIA ST, RENO, NV 89506City of Reno NV Citizen Access records
May 12, 2026 Data center 9630 N VIRGINIA ST, RENO, NV 89506City of Reno NV Citizen Access records
Apr 27, 2026 Data center City of Reno NV Citizen Access records
Mar 30, 2026 Data center 265 KEYSTONE AVE, RENO, NV 89503 265 KEYSTONE AVEWashoe County NV Citizen Access records
Mar 17, 2026 Data center 9630 N VIRGINIA ST NA, RENO, NV 89506City of Reno NV Citizen Access records
Mar 16, 2026 Substation 9965 N VIRGINIA ST, RENO, NV 89506 9965 A N VIRGINIA STWashoe County NV Citizen Access records
Mar 11, 2026 Substation 0 SWEETWATER RD, INCLINE VILLAGE, NV 89451 SWEETWATER RD 130-151-03Washoe County NV Citizen Access records

Interconnection queue in Nevada

5,570 MW requested across 13 active generation and storage positions. Withdrawn and in-service rows are left out, matching the national page.

ISOProjectFuelMWStatusSource
CAISO ARIDA 2 SOLAR FARMClark County Solar plus storage 700 MW Active
CAISO SILVER STAR SOLARNye County Solar plus storage 500 MW Active
CAISO ROCK VALLEY ENERGY CENTERNye County Solar plus storage 500 MW Active
CAISO WATER ROCK SOLAR 2Nye County Solar plus storage 500 MW Active
CAISO MOSEYClark County Solar plus storage 500 MW Active
CAISO ARIDA 3 SOLAR FARMClark County Solar plus storage 450 MW Active
CAISO BONANZA PEAK SOLAR FARMClark/Nye County Solar plus storage 400 MW Active
CAISO PURPLE SAGE ENERGY CENTERClark County Solar plus storage 400 MW Active
CAISO ARIDA SOLAR FARMClark County Solar plus storage 370 MW Active
CAISO KAWICHClark County Solar plus storage 350 MW Active
CAISO TAHOEClark County Battery storage 300 MW Active
CAISO BONANZA SOLARClark/Nye County Solar plus storage 300 MW Active
CAISO LARREA SOLARClark County Solar plus storage 300 MW Active

Planned generation in Nevada

6,472 MW across 28 EIA-860M generators scheduled to enter service within 36 months.

PlantTechnologyMWPlannedStatusSource
Libra SolarLyon County Batteries 700 MW Dec 2027 Under construction, less than or equal to 50 percent complete
Libra SolarLyon County Solar Photovoltaic 700 MW Dec 2027 Under construction, less than or equal to 50 percent complete
Sierra Solar HybridChurchill County Batteries 400 MW Jul 2026 Regulatory approvals pending. Not under construction
Rough HatClark County Solar Photovoltaic 400 MW Dec 2027 Regulatory approvals pending. Not under construction
Sierra Solar HybridChurchill County Solar Photovoltaic 400 MW Dec 2026 Construction complete, but not yet in commercial operation
Purple Sage Energy CenterClark County Batteries 400 MW Nov 2028 Planned for installation, but regulatory approvals not initiated
Purple Sage Energy CenterClark County Solar Photovoltaic 400 MW Nov 2028 Planned for installation, but regulatory approvals not initiated
Arida Solar (Hybrid)Clark County Solar Photovoltaic 370 MW Jun 2029 Planned for installation, but regulatory approvals not initiated
Arida Solar (Hybrid)Clark County Batteries 370 MW Jun 2029 Planned for installation, but regulatory approvals not initiated
Southern Bighorn Solar HybridClark County Batteries 300 MW Jul 2028 Planned for installation, but regulatory approvals not initiated
Southern Bighorn Solar HybridClark County Solar Photovoltaic 300 MW Jul 2028 Planned for installation, but regulatory approvals not initiated
Bonanza Solar and Storage ProjectClark County Solar Photovoltaic 300 MW Dec 2027 Regulatory approvals pending. Not under construction
Vitex StorageClark County Batteries 300 MW Jun 2028 Regulatory approvals pending. Not under construction
Dry Lake East Energy CenterClark County Solar Photovoltaic 200 MW Dec 2026 Under construction, more than 50 percent complete
Bonanza Solar and Storage ProjectClark County Batteries 195 MW Dec 2027 Regulatory approvals pending. Not under construction
Boulder Solar III LLCClark County Solar Photovoltaic 128 MW Jun 2027 Planned for installation, but regulatory approvals not initiated
Boulder Solar III LLCClark County Batteries 128 MW Jun 2027 Planned for installation, but regulatory approvals not initiated
Roccasecca BESS LLCClark County Batteries 126 MW Feb 2027 Under construction, more than 50 percent complete
Boulder Flats SolarClark County Solar Photovoltaic 113 MW Dec 2028 Under construction, more than 50 percent complete
Southern Bighorn Solar 2Clark County Solar Photovoltaic 100 MW Jul 2028 Regulatory approvals pending. Not under construction
Southern Bighorn Solar 2Clark County Batteries 100 MW Jul 2028 Regulatory approvals pending. Not under construction
McGinness Hills 3Lander County Solar Photovoltaic 14 MW Jan 2027 Under construction, less than or equal to 50 percent complete
Fish Lake GeothermalEsmeralda County Geothermal 9 MW Sep 2027 Planned for installation, but regulatory approvals not initiated
Fish Lake GeothermalEsmeralda County Geothermal 6 MW Sep 2027 Planned for installation, but regulatory approvals not initiated
Fish Lake GeothermalEsmeralda County Geothermal 5 MW Sep 2027 Planned for installation, but regulatory approvals not initiated
Fish Lake GeothermalEsmeralda County Geothermal 3 MW Sep 2027 Planned for installation, but regulatory approvals not initiated
Fish Lake GeothermalEsmeralda County Geothermal 3 MW Sep 2027 Planned for installation, but regulatory approvals not initiated
Tesla Reno GigaFactoryStorey County Solar Photovoltaic 1 MW Sep 2026 Construction complete, but not yet in commercial operation

Other filings in Nevada

State air permits (7)

FacilityAgencyGeneratorsStatusSource
SWITCH RENO DATA CENTER CAMPUS Nevada NDEP PERMIT APPLICATION AND CORRESPONDENCE, class 2
POWERHOUSE DATA CENTER Nevada NDEP PERMIT, class SAD
DATA CENTER Nevada NDEP PERMIT APPLICATION AND CORRESPONDENCE, class 1
NOVVA DATA CENTER Nevada NDEP COMPLIANCE, class 2
AMAZON DATA CENTER - TRIC Nevada NDEP PERMIT APPLICATION AND CORRESPONDENCE, class 1
NEW GREEN FIELD FACILITY DATA CENTER Nevada NDEP PERMIT APPLICATION AND CORRESPONDENCE, class SAD
DATA CENTER Nevada NDEP PERMIT APPLICATION AND CORRESPONDENCE, class 1

Where Nevada stands

Across the whole tracker, 533 data center and substation permits are on record in 51 states and DC. Nevada accounts for 11 of them, ranking #8 by that count. Ranking measures documented permit activity, not the size of the eventual buildout.