New Jersey Data Center Permits Tracker
New Jersey has 8,003 MW of generation and storage requested in the interconnection queue and 42 MW of generation planned within 36 months. Every row below links to its primary source.
Last checked Sep 18, 2026
Where the activity is
Ranked by row count. Counts are never mixed with the MW figures above.
Interconnection queue in New Jersey
8,003 MW requested across 39 active generation and storage positions. Withdrawn and in-service rows are left out, matching the national page.
| ISO | Project | Fuel | MW | Status | Source |
|---|---|---|---|---|---|
| PJM | Salem 500kV AH1-710Salem County | Nuclear | 2,651 MW | Active | |
| PJM | Ocean WindOcean County | Offshore wind | 816 MW | Suspended | |
| PJM | Linden 230kV AH1-722Union County | Natural gas | 806 MW | Active | |
| PJM | Linden 138kV & 230kV AH1-715Union County | Natural gas | 803 MW | Active | |
| PJM | Bergen 230kV AH1-703Bergen County | Natural gas | 671 MW | Active | |
| PJM | Ocean Wind LLCCape May County | Offshore wind | 432 MW | Suspended | |
| PJM | New Freedom - Monroe 230 kV AH1-260Camden County | Battery storage | 300 MW | Active | |
| PJM | Woods Landing Energy StorageAtlantic County | Battery storage | 250 MW | Engineering and procurement | |
| PJM | Hudson Energy Storage FacilityHudson County | Battery storage | 200 MW | Engineering and procurement | |
| PJM | Lamberton Road BatteryMercer County | Battery storage | 170 MW | Engineering and procurement | |
| PJM | Two Rivers StorageHudson County | Battery storage | 150 MW | Engineering and procurement | |
| PJM | South OrchardCumberland County | Battery storage | 80 MW | Engineering and procurement | |
| PJM | Harmony Plains Solar and Storage FacilityWarren County | Solar plus storage | 70 MW | Engineering and procurement | |
| PJM | Churchtown - Upper Pittsgrove 138kV AH1-641Salem County | Solar | 65 MW | Active | |
| PJM | Valero 69 kV AH1-701Gloucester County | Natural gas | 61 MW | Active | |
| PJM | South OrchardCumberland County | Battery storage | 50 MW | Engineering and procurement | |
| PJM | Churchtown - Upper Pittsgrove 138 kV AG2-616Salem County | Solar | 50 MW | Active | |
| PJM | Fenwick Creek SolarAtlantic County | Solar plus storage | 38 MW | Engineering and procurement | |
| PJM | Warren Glen StorageWarren County | Battery storage | 20 MW | Partially in service - under construction | |
| PJM | Houses Corner StorageSussex County | Battery storage | 20 MW | Engineering and procurement | |
| PJM | Mansfield #3Warren County | Battery storage | 20 MW | Engineering and procurement | |
| PJM | Middle Battery StorageCape May County | Battery storage | 20 MW | Engineering and procurement | |
| PJM | Missouri Avenue Battery Storage ProjectAtlantic County | Battery storage | 20 MW | Pending termination | |
| PJM | Washington Solar PH IIWarren County | Solar | 20 MW | Partially in service - under construction | |
| PJM | Lacey Sand SolarOcean County | Solar | 20 MW | Pending termination | |
| PJM | Ridge Road Solar FarmHunterdon County | Solar | 20 MW | Engineering and procurement | |
| PJM | Oyster Creek-Whitings 34.5 kV AG2-016Ocean County | Solar | 20 MW | Active | |
| PJM | Pequest River-Furnace Brook Tap 34.5 kV II AG2-625Warren County | Solar | 20 MW | Active | |
| PJM | Broadway - Washington 34.5 kV AH1-257Warren County | Solar | 19 MW | Active | |
| PJM | Belford - Keansburg 34.5 kV AH1-258Monmouth County | Solar | 19 MW | Active | |
| PJM | Lakehurst - Whitings 34.5 kV AH1-334Ocean County | Solar | 19 MW | Active | |
| PJM | Cumberland 230 kV AG2-297Cumberland County | Solar | 19 MW | Active | |
| PJM | Monmouth Solar 1Monmouth County | Solar | 15 MW | Under construction | |
| PJM | Pequest River-Furnace Brook Tap 34.5 kV III AG2-626Warren County | Solar | 12 MW | Active | |
| PJM | Southern Ocean Waretown SolarOcean County | Solar | 12 MW | Pending termination | |
| PJM | Esky Solar ProjectGloucester County | Solar | 10 MW | Under construction | |
| PJM | Upton-Whitings 34.5 kV AH1-054Ocean County | Solar | 8 MW | Active | |
| PJM | NAESBurlington County | Battery storage | 5 MW | Engineering and procurement | |
| PJM | Monroe-Sicklerville Road LF SolarGloucester County | Solar | 2 MW | Partially in service - under construction |
Planned generation in New Jersey
42 MW across 11 EIA-860M generators scheduled to enter service within 36 months.
| Plant | Technology | MW | Planned | Status | Source |
|---|---|---|---|---|---|
| Milltown Onsite BESSMiddlesex County | Batteries | 13 MW | Aug 2026 | Under construction, more than 50 percent complete | |
| Esky SolarGloucester County | Solar Photovoltaic | 7 MW | Aug 2026 | Construction complete, but not yet in commercial operation | |
| Hamms LandfillSussex County | Solar Photovoltaic | 6 MW | Sep 2026 | Under construction, more than 50 percent complete | |
| Prologis - SLCNJ001 - Community SolarMiddlesex County | Solar Photovoltaic | 3 MW | Sep 2026 | Under construction, less than or equal to 50 percent complete | |
| Carneys Point Solar 1 LLCSalem County | Solar Photovoltaic | 3 MW | Sep 2026 | Under construction, less than or equal to 50 percent complete | |
| Harrah's Atlantic City - POI 1 (MeetingAtlantic County | Solar Photovoltaic | 2 MW | Dec 2026 | Under construction, less than or equal to 50 percent complete | |
| BPL NJ - BelmontSomerset County | Solar Photovoltaic | 2 MW | Sep 2026 | Construction complete, but not yet in commercial operation | |
| BPL NJ - Union Distribution CenterUnion County | Solar Photovoltaic | 2 MW | Aug 2026 | Construction complete, but not yet in commercial operation | |
| 50 Meister AveSomerset County | Solar Photovoltaic | 2 MW | Sep 2026 | Under construction, more than 50 percent complete | |
| East Windsor Solar 1 LLCMercer County | Solar Photovoltaic | 1 MW | Mar 2027 | Regulatory approvals received. Not under construction | |
| Elizabeth Metropolitan Logistics CenterUnion County | Solar Photovoltaic | 1 MW | Sep 2026 | Construction complete, but not yet in commercial operation |
Where New Jersey stands
Across the whole tracker, 533 data center and substation permits are on record in 51 states and DC. New Jersey accounts for 0 of them, ranking #13 by that count. Ranking measures documented permit activity, not the size of the eventual buildout.