SAVRN
Search Contact SAVRN
Florida · Power Supply Chain & Demand

Power Supply Chain and Demand in Florida

Seal of Florida

Vertically integrated utilities run most of Florida's grid. 2,508 MW of new generation is planned in Florida, 2,338 MW of it under construction or built and awaiting operation, against 209 MW of planned retirements through 2030. 117 data centers are identified in the state. Residential electricity averaged 15.30¢/kWh in 2026 through July, +1.8% from a year earlier. Unemployment was 4.5% in August 2026, and construction employment is +15.4% against August 2019. The SAVRN trackers hold 45 local moratoria or restrictions for Florida across all statuses (29 in force) and 6 named projects on the Delay Watchlist.

Rebuilt 2026-10-08 · refreshed weekly
Grid operator
Non-RTO (utility-run)
main wholesale grid
Planned generation
2.5 GW
2.3 GW under construction or built
Data center load in queues
—
117 data centers identified
Residential price
15.30¢
▲ 1.8% vs 2025, YTD July
Construction jobs
+15.4%
▲ 15.4% vs Aug 2019
Local measures
45
29 in force · 6 on Delay Watchlist
The finding

What the build-out changed in Florida

Florida is in the middle of the pack, with a few sharp signals worth watching. The data center industry now accounts for 2.5% of Florida's economy, the 11th largest share of any state (the median state is 1.8%), counting the industry's in-state suppliers and payrolls. Data processing and hosting jobs grew 45.8% from 2019 to 2025, 19th of 46 states that disclose the industry. Construction employment is +15.4% against August 2019, 21st of 48 states where BLS publishes it. Pushback is organized: the SAVRN trackers hold 45 local moratoria or restrictions in Florida, 8th in the country.

Then and now

MeasureThenNowChangeU.S. rank
Construction jobs (Aug 2019 → Aug 2026)568.8k656.7k▲ 15.4%21st of 48
Electrical contractor jobs (2019 → 2025)67,59278,618▲ 16.3%30th of 48
Power line construction jobs (2019 → 2025)14,30916,548▲ 15.6%28th of 44
Data processing and hosting jobs (2019 → 2025)19,57328,540▲ 45.8%19th of 46
Unemployment rate (Feb 2020 → Aug 2026)3.0%4.5%▲ 1.5pts—
Residential price, ¢/kWh (YTD Jul 2025 → 2026)15.03¢15.30¢▲ 1.8%45th of 51
Generation fleet → planned additions81.0 GW operating2.5 GW planned3% of fleet47th of 51

Where Florida ranks among 51

Data center share of state GDP2.5%11th of 51
Planned generation vs. today's fleet3%47th of 51
Construction jobs vs. 2019+15.4%21st of 48
Electrical contractor jobs, 2019 to 2025+16.3%30th of 48
Power line construction jobs, 2019 to 2025+15.6%28th of 44
Data processing and hosting jobs, 2019 to 2025+45.8%19th of 46
Commercial electricity sales, YTD change+1.7%23rd of 51
Residential electricity price, YTD change+1.8%45th of 51
Local moratoria and restrictions458th of 49

1st = the most. Ranks cover every state and DC that publishes the figure.

Regionally, Georgia leads on data center share of state gdp at 3.3%; Florida is 2nd of 3 in its neighborhood at 2.5%.

County spotlight

Miami-Dade County holds the most data centers on record in Florida (39), and its electrical contractor workforce changed +16.5% since 2019 to 7,139 jobs. The largest share of planned generation sits in Pasco County: 629 MW, led by Shady Hills Energy Center, LLC (natural gas). The fastest-growing electrical trade market is St. Johns County, where contractor jobs grew 57.5% to 682.

The map

Where Florida sits in the power system

Grid operator
Non-RTO (utility-run)
Operating capacity
81.0 GW
Planned generation
2,508 MW
Under construction or built
2,338 MW
Data centers identified
117
Data center load in queues
—
Unemployment, Aug 2026
4.5%
Residential price change
+1.8%

Neighboring states are shaded. Select one to open its page.

Counties and cities

Florida, county by county

67 counties in Florida. Planned generation sits in 18 of them, data centers stand in 15, and local measures are on record in 33. Pick a layer, then select a county for its full record.

Okaloosa CountyGlades CountyDeSoto CountyDixie CountyMartin CountyHardee CountyBay CountyFlagler CountyOrange CountyWalton CountyPasco CountySt. Lucie CountyWashington CountySumter CountyPalm Beach CountyAlachua CountyLafayette CountyOkeechobee CountyHernando CountyCharlotte CountyLee CountyLake CountySuwannee CountyLevy CountyNassau CountyMadison CountyColumbia CountyCalhoun CountyCitrus CountyFranklin CountyGadsden CountyGulf CountyJefferson CountyPinellas CountyClay CountySanta Rosa CountySeminole CountyVolusia CountyMonroe CountySt. Johns CountyOsceola CountySarasota CountyGilchrist CountyHendry CountyHighlands CountyIndian River CountyManatee CountyUnion CountyDuval CountyWakulla CountyJackson CountyLeon CountyEscambia CountyMiami-Dade CountyBradford CountyTaylor CountyBroward CountyPolk CountyBrevard CountyHamilton CountyCollier CountyBaker CountyLiberty CountyHolmes CountyPutnam CountyMarion CountyHillsborough County

County leaders

Most planned generation
Pasco Countynatural gas629 MW
Duval Countysolar174 MW
Osceola Countysolar150 MW
Highlands Countysolar150 MW
DeSoto Countysolar149 MW
Calhoun Countysolar149 MW
Hendry Countysolar149 MW
Fastest electrical contractor growth
Walton County409 jobs+65.6%
St. Johns County682 jobs+57.5%
Pasco County1,409 jobs+49.4%
Duval County7,323 jobs+43.4%
Manatee County1,259 jobs+33.9%
Sarasota County1,522 jobs+31.3%
Clay County612 jobs+28.3%
St. Lucie County1,060 jobs+26.9%

Counties on record 57

CountyData centersPlanned MWBuilding MWLead developerElectrical contractor jobsChange 2019–25Local measuresWatchlist
Miami-Dade County39———7,139▲ 16.5%—1
Hillsborough County1774 MW74 MWTampa Electric Co6,757▲ 19.3%1 (0 in force)—
Duval County14174 MW174 MWFRP Miller Solar LLC7,323▲ 43.4%——
Orange County12———5,554▲ 17.3%1 (0 in force)—
Palm Beach County8———5,212▲ 14.3%1 (1 in force)2
Broward County6———6,568▲ 2.4%——
Polk County5112 MW92 MWTampa Electric Co1,498▲ 7.2%——
Brevard County2———1,835▲ 18.5%——
Leon County2———1,113▲ 23.0%1 (0 in force)—
DeSoto County1149 MW149 MWFlorida Power & Light Co56—1 (1 in force)—
Collier County1———1,734▲ 21.1%1 (1 in force)—
Volusia County1———1,674▲ 8.5%1 (0 in force)—
Alachua County1———911▲ 8.1%—1
Okaloosa County1———639▼ 6.9%1 (0 in force)—
Flagler County1———328—1 (1 in force)—
Pasco County—629 MW629 MWShady Hills Energy Center, LLC1,409▲ 49.4%1 (1 in force)—
Osceola County—150 MW150 MWDuke Energy Florida, LLC738▼ 7.2%——
Highlands County—150 MW75 MWPlacid Solar, LLC————
Okeechobee County—149 MW149 MWFlorida Power & Light Co101▲ 8.6%——
Calhoun County—149 MW149 MWFlorida Power & Light Co————
Hendry County—149 MW149 MWFlorida Power & Light Co——1 (0 in force)—
Citrus County—100 MW100 MWDuke Energy Florida, LLC368—1 (1 in force)—
Jackson County—75 MW—CVSO, LLC——2 (2 in force)—
Jefferson County—75 MW75 MWDuke Energy Florida, LLC21▲ 90.9%——
St. Lucie County—74 MW74 MWFlorida Power & Light Co1,060▲ 26.9%—1
Indian River County—74 MW74 MWFlorida Power & Light Co466▲ 12.8%——
Walton County—74 MW74 MWFlorida Power & Light Co409▲ 65.6%1 (1 in force)—
Madison County—74 MW74 MWFlorida Power & Light Co——1 (1 in force)—
Baker County—74 MW74 MWFlorida Power & Light Co————
Seminole County————4,332▲ 19.2%——
Lee County————3,274▲ 25.4%——
Pinellas County————2,991▼ 18.1%——
Sarasota County————1,522▲ 31.3%1 (1 in force)1
Lake County————1,378▲ 9.9%1 (1 in force)—
Manatee County————1,259▲ 33.9%1 (1 in force)—
Escambia County————1,168▼ 4.7%1 (1 in force)—
Marion County————998▲ 24.1%1 (1 in force)—
Martin County————803—1 (0 in force)—
Bay County————751▲ 11.8%1 (1 in force)—
St. Johns County————682▲ 57.5%1 (0 in force)—
Clay County————612▲ 28.3%1 (1 in force)—
Charlotte County————466———
Sumter County————448———
Monroe County————441▲ 21.5%——
Santa Rosa County————440▼ 2.7%1 (0 in force)—
Hernando County————294▲ 17.1%2 (1 in force)—
Nassau County————174—1 (1 in force)—
Putnam County————126—1 (1 in force)—
Washington County————49—1 (1 in force)—
Franklin County————47———
Gilchrist County————44▲ 100.0%——
Gulf County————36▼ 40.0%——
Taylor County————32—1 (0 in force)—
Gadsden County————17———
Levy County——————1 (1 in force)—
Wakulla County——————1 (1 in force)—
Holmes County——————2 (1 in force)—

Every county in Florida 67

Each county has its own page: power plants, utilities and prices, jobs since 2019, data centers, local rules and its neighbors.

Alachua CountyGainesville, AlachuaBaker CountyMacclennyBay CountyPanama City, Lynn HavenBradford CountyStarkeBrevard CountyPalm Bay, MelbourneBroward CountyFort Lauderdale, Pembroke PinesCalhoun CountyBlountstownCharlotte CountyPunta GordaCitrus CountyInverness, Crystal RiverClay CountyGreen Cove Springs, Orange ParkCollier CountyNaples, Marco IslandColumbia CountyLake CityDeSoto CountyArcadiaDixie CountyCross CityDuval CountyJacksonville, Jacksonville BeachEscambia CountyPensacola, CenturyFlagler CountyPalm Coast, Flagler BeachFranklin CountyCarrabelle, ApalachicolaGadsden CountyQuincy, MidwayGilchrist CountyTrentonGlades CountyMoore HavenGulf CountyPort St. Joe, WewahitchkaHamilton CountyJasperHardee CountyWauchula, Bowling GreenHendry CountyClewiston, LaBelleHernando CountyBrooksvilleHighlands CountySebring, Avon ParkHillsborough CountyTampa, Plant CityHolmes CountyBonifayIndian River CountySebastian, Vero BeachJackson CountyMarianna, GracevilleJefferson CountyMonticelloLafayette CountyMayoLake CountyClermont, LeesburgLee CountyCape Coral, Fort MyersLeon CountyTallahasseeLevy CountyWilliston, ChieflandLiberty CountyMadison CountyMadisonManatee CountyBradenton, PalmettoMarion CountyOcala, BelleviewMartin CountyStuart, IndiantownMiami-Dade CountyMiami, HialeahMonroe CountyKey West, MarathonNassau CountyFernandina Beach, HilliardOkaloosa CountyCrestview, Fort Walton BeachOkeechobee CountyOkeechobeeOrange CountyOrlando, ApopkaOsceola CountyKissimmee, St. CloudPalm Beach CountyWest Palm Beach, Boca RatonPasco CountyZephyrhills, New Port RicheyPinellas CountySt. Petersburg, ClearwaterPolk CountyLakeland, Winter HavenPutnam CountyPalatka, Crescent CitySanta Rosa CountyMilton, Gulf BreezeSarasota CountyNorth Port, SarasotaSeminole CountySanford, Altamonte SpringsSt. Johns CountySt. Augustine, St. Augustine BeachSt. Lucie CountyPort St. Lucie, Fort PierceSumter CountyWildwood, BushnellSuwannee CountyLive OakTaylor CountyPerryUnion CountyLake ButlerVolusia CountyDeltona, Daytona BeachWakulla CountyWalton CountyFreeport, DeFuniak SpringsWashington CountyChipley

Cities and towns on record 44

City or townCountyData centersLocal measuresWatchlistLatest record
MiamiMiami-Dade County24———
JacksonvilleDuval County14———
TampaHillsborough County10———
Boca RatonPalm Beach County7———
DoralMiami-Dade County5———
OrlandoOrange County5———
EatonvilleOrange County3———
Egypt Lake-LetoHillsborough County3———
SweetwaterMiami-Dade County3———
TallahasseeLeon County21 (0 in force)—Rejected proposal to define and prohibit AI data centers Failed / vetoed
East Lake-Orient ParkHillsborough County2———
Fort LauderdaleBroward County2———
LakelandPolk County11 (1 in force)—Local moratorium on data centers through August 3, 2027 In force
ArcadiaDeSoto County1———
AuburndalePolk County1———
BrandonHillsborough County1———
Daytona BeachVolusia County1———
Deerfield BeachBroward County1———
Fort Walton BeachOkaloosa County1———
Ft. Lauderdale—1———
Ft. Myers—1———
GainesvilleAlachua County1———
Lakeland HighlandsPolk County1———
MaitlandOrange County1———
MelbourneBrevard County1———
Miami GardensMiami-Dade County1———
NaplesCollier County1———
Oakland ParkBroward County1———
Palm CoastFlagler County1———
Pembroke ParkBroward County1———
Sunny Isles BeachMiami-Dade County1———
SunriseBroward County1———
Town 'n' CountryHillsborough County1———
West Palm BeachPalm Beach County1———
WestviewMiami-Dade County1———
Winter GardenOrange County1———
Winter HavenPolk County1———
AlachuaAlachua County—1 (0 in force)—Alachua City Commission moves to draft 12-month data center moratorium Proposed
EdgewaterVolusia County—1 (1 in force)—Proposed city moratorium on data centers with no end date In force
IndiantownMartin County—1 (0 in force)—Rejected pause on large-scale data center applications Failed / vetoed
North PortSarasota County—1 (1 in force)—Proposed 18-month data center moratorium In force
Panama CityBay County—1 (1 in force)—One-year ban on new large-scale data center proposals In force
Village of Palmetto BayMiami-Dade County—1 (0 in force)—Palmetto Bay weighs outright ban on data centers Proposed
ZephyrhillsPasco County—1 (1 in force)—One-year data center moratorium In force

Data center counts come from every facility on the SAVRN Data Center Map, counted in the county and the city or community where each building physically stands (Census boundaries), not its mailing address. Jurisdictions appear as the Moratorium Tracker records them.

The chain

Florida, from generation to the household bill

1Grid operator

Utility-run territory: resource planning sits with the vertically integrated utilities and the state commission.

2Generation pipeline

Operating capacity
81.0 GW
Planned, all types
2,508 MW
Under construction or built
2,338 MW
Planned gas
612 MW
Planned retirements 2026–30
209 MW
Net firm additions derived
2,129 MW

3Data center demand

Data centers identified
117
Operators
55
Load in tracked queues
—
Utility large-load projects
0
Commercial sales, YTD change
+1.7%
Industry share of state GDP
2.5%

4Jobs and pay

Unemployment, Aug 2026
4.5% (+0.5 pts y/y)
Construction jobs vs 2019
+15.4%
Manufacturing jobs vs 2019
+10.5%
Electrical contractor jobs 2019–25
+16.3%
Electrician median pay
$57,250
Electrician ÷ cashier pay
1.88×

5Household bill

Residential price, YTD Jul 2026
15.30¢/kWh
Change vs YTD 2025
+1.8%
All-sector price change
+2.5%
Total retail sales change
+1.4%

6Policy friction

State measures on record
5
Local measures (in force)
45 (29)
Watchlist projects
6
Lawsuits tracked
0
Announced capital, disclosed
—
Dedicated tax incentive
Yes
Generation

Planned power plants in Florida

Every planned generator in Florida in the August 2026 EIA-860M inventory, by technology, then the 15 largest units. Under construction or built covers status codes U, V and TS.

Planned generation by fuel 2,508 MW
Natural gas 612 MW 24%Solar 1,709 MW 68%Battery storage 170 MW 7%Other 17 MW 1%
Under construction or built 2,338 MW
Natural gas 612 MW 26%Solar 1,559 MW 67%Battery storage 150 MW 6%Other 17 MW 1%
TechnologyUnitsPlanned MWUnder construction or built
Solar241,709 MW1,559 MW
Natural gas1612 MW612 MW
Battery storage3170 MW150 MW
Other117 MW17 MW

Largest planned generators

PlantCountyTechnologyMWStatusYearOwner
Shady Hills Combined Cycle FacilityPascoNatural Gas Fired Combined Cycle612 MWBuilt, not yet operating2026Shady Hills Energy Center, LLC
Powerline Energy StorageCitrusBatteries100 MWUnder construction (≤50%)2027Duke Energy Florida, LLC
Caverns SolarJacksonSolar Photovoltaic75 MWApprovals pending2029CVSO, LLC
Turnpike Solar PlantOsceolaSolar Photovoltaic75 MWUnder construction (>50%)2027Duke Energy Florida, LLC
Highland Solar NorthHighlandsSolar Photovoltaic75 MWApprovals pending2027Placid Solar II, LLC
Lonesome Camp Solar PlantOsceolaSolar Photovoltaic75 MWUnder construction (>50%)2027Duke Energy Florida, LLC
Bailey Mill SolarJeffersonSolar Photovoltaic75 MWUnder construction (>50%)2026Duke Energy Florida, LLC
Highland Solar SouthHighlandsSolar Photovoltaic75 MWUnder construction (>50%)2026Placid Solar, LLC
FRP Miller SolarDuvalSolar Photovoltaic74 MWUnder construction (≤50%)2026FRP Miller Solar LLC
TangeloOkeechobeeSolar Photovoltaic74 MWUnder construction (≤50%)2027Florida Power & Light Co
Joshua CreekDeSotoSolar Photovoltaic74 MWUnder construction (≤50%)2027Florida Power & Light Co
Spanish MossSt LucieSolar Photovoltaic74 MWUnder construction (≤50%)2027Florida Power & Light Co
SaddleCalhounSolar Photovoltaic74 MWUnder construction (≤50%)2027Florida Power & Light Co
PineconeCalhounSolar Photovoltaic74 MWUnder construction (≤50%)2027Florida Power & Light Co
Maple TrailBakerSolar Photovoltaic74 MWUnder construction (≤50%)2027Florida Power & Light Co
Supply chain

What the Florida build-out runs on

Who is building generation in Florida, which manufacturers and contractors have a plant, expansion or contract recorded here, and how long the critical equipment takes to arrive.

Developers and owners with planned generation

Developer or ownerUnitsPlanned MWBuilding MWMain technologyCounties
Florida Power & Light Co13968 MW968 MWSolar9
Shady Hills Energy Center, LLC1612 MW612 MWNatural gas1
Duke Energy Florida, LLC4325 MW325 MWSolar3
Tampa Electric Co4186 MW166 MWSolar2
FRP Miller Solar LLC2124 MW124 MWBattery storage1
CVSO, LLC175 MW—Solar1
Placid Solar II, LLC175 MW—Solar1
Placid Solar, LLC175 MW75 MWSolar1
FRP Forest Trail Solar LLC150 MW50 MWSolar1
Pasco County - (FL)117 MW17 MWOther1

Manufacturers and contractors with a recorded Florida footprint

No plant, expansion or contract in the manufacturer record names Florida. The national suppliers below serve every state.

Order-by check derived

1 of the 2 planned units of 50 MW or more in Florida that are not yet under construction (75 of 150 MW) are past the date their step-up transformer had to be ordered to meet the planned in-service date. These units hold their schedules only if the equipment is already on order.

PlantTechnologyMWPlanned in serviceTransformer order-byTurbine order-byOwner
Highland Solar NorthSolar75 MWMay 2027Apr 2024—Placid Solar II, LLC

Lead times, OEM backlogs and the national generation and grid contractors are on the national supply chain section.

Demand

Data center and large-load demand in Florida

117 data centers run by 55 operators are identified in Florida. The full list by city is on the Florida Data Center Map page. Utilities report 0 large customer projects here to EEI.

No large customer projects reported to EEI for this state.

Jobs and pay

The Florida jobs report, and who the build-out employs

Median pay, May 2025
Cashiers$30,530
Fast food and counter workers$29,080
Retail salespersons$34,010
All occupations$47,880
Construction laborers$44,030
Welders$50,640
HVAC mechanics$56,670
Plumbers and pipefitters$52,910
Electricians$57,250
Power plant operators$94,290
Power-line installers$86,870
Construction supervisors$75,790
Electrical engineers$104,780
Cashier median: $30,530

Payroll employment, August 2026 (preliminary)

IndustryJobsChange vs Aug 2025Change vs Aug 2019
Total nonfarm10,051.6k▲ 0.6%▲ 11.7% (+1,055.4k)
Construction656.7k▲ 0.3%▲ 15.4% (+87.9k)
Manufacturing429.1k▲ 0.5%▲ 10.5% (+40.9k)
Retail trade1,151.7k▲ 0.4%▲ 5.3% (+57.9k)

Power and data industries, 2019 to 2025

IndustryJobs 2019Jobs 2025ChangeAverage pay 2025
Data processing and hosting19,57328,540▲ 45.8%$160,238
Electrical contractors67,59278,618▲ 16.3%$68,438
Power and communication line construction14,30916,548▲ 15.6%$93,884
Electric power generation, transmission, distribution—19,797—$139,390
Transformer manufacturing—1,002—$80,721

Pay ladder, May 2025

OccupationEmploymentMedian annual payMultiple of cashier pay
Cashiers201,370$30,5301.00×
Fast food and counter workers235,400$29,0800.95×
Retail salespersons333,460$34,0101.11×
All occupations9,929,860$47,8801.57×
Construction laborers87,040$44,0301.44×
Welders16,420$50,6401.66×
HVAC mechanics39,160$56,6701.86×
Plumbers and pipefitters29,260$52,9101.73×
Electricians49,700$57,2501.88×
Power plant operators1,640$94,2903.09×
Power-line installers6,420$86,8702.85×
Construction supervisors69,830$75,7902.48×
Electrical engineers9,220$104,7803.43×

County-level contractor jobs and pay are in the county record above.

Economy

What the data center industry adds to Florida

73,330
Direct data center jobs (2024)
307,590
Total jobs supported, in state
$42.3B
Total GDP contribution
2.5%
Share of state GDP
$3.6B
State and local taxes

PwC figures are modeled estimates commissioned by the industry.

Policy

The rules and the pipeline in Florida

State measures 5

BillMeasureStatusDate
SB 484Data center ratepayer, water and local-authority lawIn force2026-06
SB 1118Florida SB 1118 creates a public records exemption allowing local governments to keep data center siting plans confidential for up to 12 months when requestedFailed / vetoed2026-03
HB 1007Florida HB 1007 (2026) regulates data center siting and operations by: (1) limiting the use of non-disclosure agreements in local permittingFailed / vetoed2026-02
HB 1517Florida SB 1517, 'Approval of Data Center Facilities,' sponsored by Rep. Joseph, required developers to disclose projected energy, water, carbon emissionsFailed / vetoed2026-02
HB 7031Data-center sales-tax exemption rollbackIn force2025-06

Delay Watchlist projects 6

ProjectLocationStatusCauseMW
Sentinel Grove Technology Park / Project JarvisSt. Lucie Countycancelledcommunity opposition1,000 MW
MIA-1 Data Center (Iron Mountain, Westview)Westview, unincorporated Miami-Dade Countyunder construction amid oppositioncommunity oppositiontransparency concerns16 MW
Project TangoPalm Beach County / Ardencancelledcommunity oppositionwater disputezoning denial—
Project Tango (Palm Beach County)Palm Beach County (near Arden / Loxahatchee)denied without prejudicepermit denialcommunity opposition—
XF Group Sarasota County Hyperscale Data Center FreezeSarasota County (Cattlemen Road)moratorium in forcecounty moratorium—
Alachua Phoenix Commercial Park (rumored data center)Alachua, Alachua Countyrumored no application filedcommunity oppositionmeeting postponed—

Local moratoria and restrictions (45) appear by county and city in the county-by-county section. Counts include every status in the weekly tracker feeds as of October 5, 2026. The Florida Data Center Map page counts only active local pauses and delayed or blocked projects as of its September 2 rebuild, so its figures are lower. The difference is one of definition and date.

Nearby states

Florida's neighbors

Questions

Florida power, answered from the record

How much new power generation is planned in Florida?

EIA's August 2026 inventory lists 2,508 MW of planned generators in Florida, 2,338 MW of it under construction or built. By capacity the pipeline is solar 68%, natural gas 24%, battery storage 7%. The largest single unit is Shady Hills Combined Cycle Facility (612 MW, Shady Hills Energy Center, LLC). Owners plan to retire 209 MW from 2026 to 2030.

Who runs the power grid in Florida?

Non-RTO (utility-run) serves most of Florida, which means vertically integrated utilities plan and dispatch generation under the state commission. No data center load is tracked in its queues yet.

Are electricity prices rising in Florida?

Residential electricity averaged 15.30¢/kWh from January to July 2026, +1.8% on a year earlier, the 45th fastest increase of 51. Commercial sales, the class that includes data centers, changed +1.7%.

How much do data centers add to the Florida economy?

PwC's 2026 study for the Data Center Coalition credits the industry with 307,590 in-state jobs, $42.3B of GDP (2.5% of the state economy, 11th of 51) and $3.6B in state and local taxes in 2024. These are modeled estimates commissioned by the industry.

Is planned generation in Florida on schedule?

1 of 2 planned units of 50 MW or more not yet under construction are past the latest date to order a step-up transformer (more than 160 weeks) for their planned in-service date. They hold schedule only if equipment is already on order.

Where are the data centers in Florida?

117 data centers run by 55 operators are identified in Florida. The largest clusters are in Miami-Dade County (39), Hillsborough County (17), Duval County (14).

Which counties in Florida have the most planned generation?

By planned nameplate capacity: Pasco County (629 MW), Duval County (174 MW), Osceola County (150 MW).

Does Florida have a data center moratorium?

The SAVRN Moratorium Tracker holds 5 state-level measures (2 enacted) and 45 local moratoria or restrictions in Florida, 29 of them in force, 8th most in the country.

Across SAVRN

Florida across the SAVRN trackers

Sources

Sources for this page

Every figure links to its original source through the Sources buttons. Values marked derived are calculated from reported figures.