SAVRN
Search Contact SAVRN
California · County record

Imperial County, California: Power, Data Centers and the Local Economy

Home to El Centro, Calexico and Brawley

Seal of California

Imperial County is one of the places pushing back on the data center build-out. The SAVRN Data Center Map lists 1 data center in Imperial County. Imperial County is home to El Centro, Calexico, Brawley and Imperial. Its power plants have 4,558 MW of capacity, 47% of it solar, the 7th largest fleet in California. The Moratorium Tracker holds 3 local measures here (1 in force); the latest is “County moratorium set aside by court; replacement under review”. 1 project is on the Delay Watchlist, including Imperial Data Center (Imperial Valley Computer Manufacturing / IVCM).

Rebuilt 2026-10-08 · refreshed weekly
1
data centers on the SAVRN Data Center Map
4,558 MW
of operating power plants, mostly solar
662 MW
of new generation planned here, solar leading
Population, 2025
181,411
▲ 1.0% since 2020
Jobs, 2025
67,955
▲ 7.1% since 2019
Unemployment
21.9%
▲ 0.8 pts vs 20192019: 21.1%2024: 18.4%August 2026: 21.9%
Power plants
4,558 MW
73 plants operating▲ 37.3% fleet since 2019
Planned generation
662 MW
11 units
Data centers
1
SAVRN Data Center Map
Cities and towns

Cities and towns in Imperial County

Imperial County is home to El Centro, Calexico, Brawley and Imperial.

El Centro44,382 residents
Calexico38,623 residents
Brawley28,008 residents
Imperial22,330 residents
Calipatria6,012 residents
Holtville5,591 residents
Westmorland2,015 residents

Unincorporated communities (governed by the county): Bombay Beach, Desert Shores, El Centro Naval Air Facility, Heber, Niland, Ocotillo, Palo Verde, Salton City, Salton Sea Beach, Seeley, Winterhaven.

Residents are 2025 Census estimates for the part of each city, town or township inside this county. Census publishes no annual estimate for unincorporated communities.

Then and now

What changed in Imperial County

Where Imperial County ranks in California
Population181,41131st of 58
Job growth since 2019+7.1%15th of 58
Construction growth+8.5%20th of 51
Operating power plants4,558 MW7th of 55
Planned generation662 MW8th of 30

1st = the most. Ranks cover counties with a value on record.

MeasureThenNowChangeRank in California
Population (2020 → 2025)179,532181,411▲ 1.0%31st of 58 by size
Total jobs (2019 → 2025)63,43867,955▲ 7.1%15th of 58 by growth
Average annual pay (2019 → 2025)$41,655$56,305▲ 35.2%—
Construction jobs (2019 → 2025)1,5441,676▲ 8.5%20th of 51 by growth
Unemployment rate (2019 → August 2026)21.1%21.9%▲ 0.8pts—
Generating capacity added since 2019—1,376 MW—
Generating capacity retired since 2019—137 MW—
Planned generation (Aug 2026)—662 MW15% of today's fleet8th of 30 by size

662 MW of new generation is planned here across 11 units, led by 90FI 8me, LLC (solar), the 8th largest pipeline among California's counties. 1,376 MW of that came online in 2019 or later, mostly battery storage. 137 MW has retired here since 2019, including Heber Geothermal (other technologies, 59 MW, 2023). Construction employs 1,676, up 8.5% since 2019. Owners plan to retire 82 MW more by 2035, led by El Centro Hybrid in 2029. Employers here counted 67,955 jobs in 2025, up 7.1% from 2019. Unemployment was 21.9% in August 2026, against 21.1% in 2019. Southern California Edison Co is the largest utility serving Imperial County, one of 3 with territory here. Its residential customers paid an average 32.43¢/kWh in 2024, above the 20.66¢ median for California utilities. 181,411 people live here, up 1.0% since 2020.

Power

Who powers Imperial County

Operating fleet by fuel 4,558 MW
Natural gas 513 MW 11%Wind 265 MW 6%Solar 2,156 MW 47%Battery storage 701 MW 15%Hydro 88 MW 2%Other 834 MW 18%
Added since 2019 1,376 MW
Retired since 2019 137 MW

Net change in operating capacity since 2019: +1,239 MW. Colors follow the fuel legend above.

Planned generation by fuel 662 MW
Natural gas 113 MW 17%Solar 325 MW 49%Battery storage 174 MW 26%Other 50 MW 8%
Residential price per kWh, 2024
Southern California Edison CoInvestor Owned, 56% commercial32.43¢
Imperial Irrigation DistrictPolitical Subdivision, 43% commercial17.91¢
Median for California utilities: 20.66¢

Utilities with service territory in Imperial County

UtilityOwnershipServiceResidential customers (systemwide)Residential price, 2024Commercial share of sales
Southern California Edison CoInvestor OwnedBundled4,594,41532.43¢56%
Imperial Irrigation DistrictPolitical SubdivisionBundled142,07817.91¢43%
WAPA-- Western Area Power AdministrationFederalBundled——48%

Customer counts, prices and sales shares cover each utility's whole system in the state, not only this county. Commercial sales include data centers.

Operating power plants 73

TechnologyCapacityShare
Solar2,156 MW47%
Other technologies810 MW18%
Battery storage701 MW15%
Natural gas513 MW11%
Wind265 MW6%
Hydro88 MW2%
Petroleum25 MW1%
Largest plantsOwnerTechnologyMWSince
El Centro HybridImperial Irrigation DistrictNatural gas388 MW1952
Vikings Energy FarmVikings Energy Farm, LLCSolar287 MW2024
Ocotillo Express LLCPattern Operators LPWind265 MW2012
Mount Signal Solar Farm VImperial Valley Solar 3, LLCSolar252 MW2018
Big Rock Solar FarmBig Rock ESS Assets, LLCBattery storage200 MW2025
Imperial Valley Solar, LLCImperial Valley Solar, LLCSolar200 MW2013

Planned generation 11

PlantTechnologyMWStatusYearOwner
Kingsley Solar FarmSolar Photovoltaic225 MWPlanned, approvals not started202890FI 8me, LLC
Imperial Sun SolarBatteries100 MWApprovals pending2027Imperial Sun Solar LLC
Imperial Sun SolarSolar Photovoltaic100 MWApprovals pending2027Imperial Sun Solar LLC
Kingsley Solar FarmBatteries74 MWPlanned, approvals not started202890FI 8me, LLC
CE&P Imperial Valley 1All Other50 MWApprovals received2029California Ethanol Power, LLC
El Centro HybridNatural Gas Internal Combustion Engine19 MWPlanned, approvals not started2029Imperial Irrigation District
El Centro HybridNatural Gas Internal Combustion Engine19 MWPlanned, approvals not started2029Imperial Irrigation District
El Centro HybridNatural Gas Internal Combustion Engine19 MWPlanned, approvals not started2029Imperial Irrigation District
El Centro HybridNatural Gas Internal Combustion Engine19 MWPlanned, approvals not started2029Imperial Irrigation District
El Centro HybridNatural Gas Internal Combustion Engine19 MWPlanned, approvals not started2029Imperial Irrigation District
El Centro HybridNatural Gas Internal Combustion Engine19 MWPlanned, approvals not started2029Imperial Irrigation District

Retired since 2019

PlantTechnologyMWYear
Heber GeothermalOther technologies59 MW2023
Second Imperial GeothermalOther technologies48 MW2022
Mesquite Lake Water & Power Plant 1Other technologies18 MW2022
Ormesa IOther technologies12 MW2025

Scheduled to retire

PlantTechnologyMWYear
El Centro HybridNatural gas82 MW2029
Jobs

The Imperial County labor market

Industry (2025)JobsAverage payConcentration vs U.S.
All industries67,955$56,3051.00
Construction1,676$71,1160.47
Electric utilities537$132,4112.92

Concentration is the BLS location quotient: 1.0 means the industry holds the same share of local jobs as it does nationally. Industry rows count private employers; cells BLS suppresses are left out.

Data centers and local rules

Data centers and local rules in Imperial County

1 data center in Imperial County is on the SAVRN Data Center Map.

Local measures 3

MeasureStatusDate
County moratorium set aside by court; replacement under reviewFailed / vetoed2026-08
Imperial County (data center moratorium + by-right elimination advancing), CA data center moratoriumIn force2026-06
Calipatria City Council (Imperial County, interim 5-year moratorium introduced), CA data center moratorium (proposed)Proposed2026-05

Delay Watchlist 1

ProjectStatusCauseMW
Imperial Data Center (Imperial Valley Computer Manufacturing / IVCM)delayedlocal moratoriumwater disputecommunity opposition—
Next door

Imperial County and its neighbors

Of the 4 counties that border Imperial County, Riverside County carries the most build-out activity: data centers, planned generation and operating plants combined.

Imperial CountyLa Paz CountyRiverside CountySan Diego CountyYuma CountyImperialLa PazRiversideSan DiegoYuma
CountyPopulationJobs since 2019Operating MWPlanned MWData centersLocal measures
Imperial County181,411▲ 7.1%4,558 MW662 MW13
La Paz County AZ16,711▲ 10.8%1,213 MW3,013 MW——
Riverside County2,544,916▲ 11.1%11,455 MW3,048 MW7—
San Diego County3,282,248▲ 3.1%5,055 MW224 MW31—
Yuma County AZ224,449▲ 4.1%2,353 MW1,118 MW——
Keep going

More of California

Questions

Imperial County, answered from the record

Who provides electricity in Imperial County, California?

3 utilities have service territory in Imperial County in the EIA-861 2024 report: Southern California Edison Co, Imperial Irrigation District, WAPA-- Western Area Power Administration. The largest, Southern California Edison Co, charged residential customers 32.43¢/kWh on average in 2024.

What county is El Centro, CA in?

El Centro is in Imperial County, California. About 44,382 people live there (2025 Census estimate).

What county is Calexico, CA in?

Calexico is in Imperial County, California. About 38,623 people live there (2025 Census estimate).

What county is Brawley, CA in?

Brawley is in Imperial County, California. About 28,008 people live there (2025 Census estimate).

What power plants are in Imperial County?

73 operating plants with 4,558 MW of capacity. The largest is El Centro Hybrid (388 MW, natural gas).

How much new power is planned in Imperial County?

662 MW across 11 units in the August 2026 EIA-860M inventory, 0 MW of it under construction or built. The largest owner is 90FI 8me, LLC.

Are there data centers in Imperial County?

Yes. The SAVRN Data Center Map lists 1 data center in Imperial County.

Is Imperial County adding jobs?

Employers counted 67,955 jobs in 2025 against 63,438 in 2019 (+7.1%, BLS QCEW). Construction went from 1,544 to 1,676.

Does Imperial County have a data center moratorium?

The SAVRN Moratorium Tracker holds 3 local measures for Imperial County, 1 in force.