Washington · Power Supply Chain & Demand

Power Supply Chain and Demand in Washington

Seal of Washington

Vertically integrated utilities run most of Washington's grid. 3,601 MW of new generation is planned in Washington, 355 MW of it under construction or built and awaiting operation, against 2 MW of planned retirements through 2030. 112 data centers are identified in the state. Residential electricity averaged 14.40¢/kWh in 2026 through July, +13.0% from a year earlier. Unemployment was 4.9% in August 2026, and construction employment is -2.4% against August 2019. The SAVRN trackers hold 21 local moratoria or restrictions for Washington across all statuses (20 in force) and 4 named projects on the Delay Watchlist.

Rebuilt 2026-10-08 · refreshed weekly
Grid operator
Non-RTO (utility-run)
main wholesale grid
Planned generation
3.6 GW
0.4 GW under construction or built
Data center load in queues
—
112 data centers identified
Residential price
14.40¢
▲ 13.0% vs 2025, YTD July
Construction jobs
-2.4%
▼ 2.4% vs Aug 2019
Local measures
21
20 in force · 4 on Delay Watchlist
The finding

What the build-out changed in Washington

Washington carries more data center demand than most states, and the question now is whether its grid and workforce keep pace. The data center industry now accounts for 4.0% of Washington's economy, the largest share of any state (the median state is 1.8%), counting the industry's in-state suppliers and payrolls. Data processing and hosting jobs grew 68.0% from 2019 to 2025, 7th of 46 states that disclose the industry. Commercial electricity sales, the class that includes data centers, are +1.5% year to date, 26th in the country. Households pay part of the cost: residential prices are +13.0% year to date, the 7th fastest increase of 51.

Then and now

MeasureThenNowChangeU.S. rank
Construction jobs (Aug 2019 → Aug 2026)221.3k216.0k▼ 2.4%46th of 48
Electrical contractor jobs (2019 → 2025)23,96925,436▲ 6.1%42nd of 48
Power line construction jobs (2019 → 2025)4,2923,924▼ 8.6%41st of 44
Data processing and hosting jobs (2019 → 2025)13,89223,335▲ 68.0%7th of 46
Unemployment rate (Feb 2020 → Aug 2026)3.8%4.9%▲ 1.1pts—
Residential price, ¢/kWh (YTD Jul 2025 → 2026)12.74¢14.40¢▲ 13.0%7th of 51
Generation fleet → planned additions31.8 GW operating3.6 GW planned11% of fleet32nd of 51

Where Washington ranks among 51

Data center share of state GDP4.0%1st of 51
Planned generation vs. today's fleet11%32nd of 51
Construction jobs vs. 2019-2.4%46th of 48
Electrical contractor jobs, 2019 to 2025+6.1%42nd of 48
Power line construction jobs, 2019 to 2025-8.6%41st of 44
Data processing and hosting jobs, 2019 to 2025+68.0%7th of 46
Commercial electricity sales, YTD change+1.5%26th of 51
Residential electricity price, YTD change+13.0%7th of 51
Local moratoria and restrictions2125th of 49

1st = the most. Ranks cover every state and DC that publishes the figure.

Among its neighbors, Washington leads on data center share of state gdp (4.0%), ahead of Oregon (3.3%).

County spotlight

King County holds the most data centers on record in Washington (45), and its electrical contractor workforce changed +4.7% since 2019 to 9,492 jobs. The largest share of planned generation sits in Benton County: 1,200 MW, led by HOHI bn, LLC (solar). The fastest-growing electrical trade market is Spokane County, where contractor jobs grew 16.0% to 1,557.

The map

Where Washington sits in the power system

Grid operator
Non-RTO (utility-run)
Operating capacity
31.8 GW
Planned generation
3,601 MW
Under construction or built
355 MW
Data centers identified
112
Data center load in queues
—
Unemployment, Aug 2026
4.9%
Residential price change
+13.0%

Neighboring states are shaded. Select one to open its page.

Counties and cities

Washington, county by county

39 counties in Washington. Planned generation sits in 11 of them, data centers stand in 9, and local measures are on record in 8. Pick a layer, then select a county for its full record.

Pierce CountyAdams CountyPend Oreille CountyKing CountyChelan CountyKittitas CountyGarfield CountyGrant CountyOkanogan CountyFranklin CountyKlickitat CountyClark CountySkagit CountyWalla Walla CountyPacific CountyCowlitz CountyWahkiakum CountyLewis CountyClallam CountyGrays Harbor CountyJefferson CountyLincoln CountyMason CountySan Juan CountyStevens CountyWhatcom CountyDouglas CountySnohomish CountyThurston CountyColumbia CountyYakima CountyBenton CountyIsland CountySpokane CountyWhitman CountyFerry CountySkamania CountyAsotin CountyKitsap County

County leaders

Most planned generation
Benton Countysolar1,200 MW
Grant Countysolar650 MW
Garfield Countysolar600 MW
Klickitat Countysolar300 MW
Pierce Countybattery storage200 MW
Thurston Countybattery storage200 MW
Kitsap Countybattery storage170 MW
Adams Countywind126 MW
Fastest electrical contractor growth
Cowlitz County382 jobs+21.7%
Spokane County1,557 jobs+16.0%
Yakima County567 jobs+13.4%
Kitsap County446 jobs+10.7%
King County9,492 jobs+4.7%
Pierce County2,172 jobs+0.1%

Counties on record 33

CountyData centersPlanned MWBuilding MWLead developerElectrical contractor jobsChange 2019–25Local measuresWatchlist
King County45———9,492▲ 4.7%——
Grant County27650 MW130 MWRoyal Slope Solar LLC268▲ 8.5%—1
Snohomish County925 MW25 MWPUD No 1 of Snohomish County - (WA)2,384▼ 10.2%1 (1 in force)—
Douglas County8———22———
Spokane County7———1,557▲ 16.0%1 (1 in force)—
Pierce County6200 MW200 MWGREE bn, LLC2,172▲ 0.1%1 (1 in force)—
Whatcom County2———————
Benton County11,200 MW—HOHI bn, LLC————
Yakima County180 MW—Cypress Creek Renewables567▲ 13.4%1 (1 in force)—
Garfield County—600 MW—LOSN, LLC————
Klickitat County—300 MW—Cypress Creek Renewables17▼ 5.6%——
Thurston County—200 MW—CENT bn, LLC796———
Kitsap County—170 MW—BrightNight Power446▲ 10.7%——
Adams County—126 MW—EDP Renewables North America LLC————
Chelan County—50 MW—Helion Energy, Inc.————
Clark County————2,260▼ 6.4%——
Skagit County————976▼ 9.3%1 (1 in force)—
Franklin County————423———
Cowlitz County————382▲ 21.7%——
Grays Harbor County————272▲ 65.9%——
Clallam County————206———
Asotin County————186———
Island County————147▲ 30.1%——
Walla Walla County————137———
Whitman County————103▲ 49.3%——
Jefferson County————91▲ 23.0%——
San Juan County————67▲ 19.6%——
Lincoln County————54—1 (1 in force)—
Okanogan County————45▲ 25.0%——
Mason County————41———
Pacific County————25———
Kittitas County——————1 (1 in force)—
Skamania County——————1 (1 in force)—

Every county in Washington 39

Each county has its own page: power plants, utilities and prices, jobs since 2019, data centers, local rules and its neighbors.

Cities and towns on record 32

City or townCountyData centersLocal measuresWatchlistLatest record
SeattleKing County251 (1 in force)1Emergency one-year data center moratorium (Council Bill 121214) In force
QuincyGrant County25———
TukwilaKing County13———
LynnwoodSnohomish County4———
SpokaneSpokane County31 (1 in force)1One-year data center permit moratorium In force
PuyallupPierce County3———
TacomaPierce County3———
Moses LakeGrant County21 (1 in force)—City moratorium on data centers for a stated term In force
BellinghamWhatcom County2———
BothellKing County + Snohomish County2———
EverettSnohomish County2———
KentKing County2———
Liberty LakeSpokane County2———
Federal WayKing County11 (1 in force)1Local moratorium on data centers through July 7, 2027 In force
BellevueKing County1———
East WenatcheeDouglas County1———
KennewickBenton County1———
KirklandKing County1———
Malaga—1———
Picnic PointSnohomish County1———
RedmondKing County1———
White CenterKing County1———
YakimaYakima County1———
BurienKing County—1 (1 in force)—Local moratorium on data centers through June 29, 2027 In force
Cle ElumKittitas County—1 (1 in force)—Local moratorium on data centers through January 31, 2027 In force
La ConnerSkagit County—1 (1 in force)—City moratorium on data centers through January 29, 2027 In force
MarysvilleSnohomish County—1 (1 in force)—Local moratorium on data centers through January 14, 2027 In force
Mount VernonSkagit County—1 (1 in force)—Local moratorium on data centers through February 12, 2027 In force
PascoFranklin County—1 (1 in force)—Local moratorium on data centers through January 20, 2027 In force
Port AngelesClallam County—1 (1 in force)—Six-month data center moratorium In force
RentonKing County—1 (1 in force)—Local moratorium on data centers through August 17, 2027 In force
Washington County——1 (0 in force)—Washington County Statement on Temporary Moratorium for Data Centers in Washington County Proposed

Data center counts come from every facility on the SAVRN Data Center Map, counted in the county and the city or community where each building physically stands (Census boundaries), not its mailing address. Jurisdictions appear as the Moratorium Tracker records them.

The chain

Washington, from generation to the household bill

1Grid operator

Utility-run territory: resource planning sits with the vertically integrated utilities and the state commission.

2Generation pipeline

Operating capacity
31.8 GW
Planned, all types
3,601 MW
Under construction or built
355 MW
Planned gas
0 MW
Planned retirements 2026–30
2 MW
Net firm additions derived
353 MW

3Data center demand

Data centers identified
112
Operators
47
Load in tracked queues
—
Utility large-load projects
0
Commercial sales, YTD change
+1.5%
Industry share of state GDP
4.0%

4Jobs and pay

Unemployment, Aug 2026
4.9% (+0.3 pts y/y)
Construction jobs vs 2019
-2.4%
Manufacturing jobs vs 2019
-6.3%
Electrical contractor jobs 2019–25
+6.1%
Electrician median pay
$95,220
Electrician ÷ cashier pay
2.46×

5Household bill

Residential price, YTD Jul 2026
14.40¢/kWh
Change vs YTD 2025
+13.0%
All-sector price change
+10.9%
Total retail sales change
-1.2%

6Policy friction

State measures on record
9
Local measures (in force)
21 (20)
Watchlist projects
4
Lawsuits tracked
0
Announced capital, disclosed
—
Dedicated tax incentive
Yes
Generation

Planned power plants in Washington

Every planned generator in Washington in the August 2026 EIA-860M inventory, by technology, then the 15 largest units. Under construction or built covers status codes U, V and TS.

Planned generation by fuel 3,601 MW
Wind 326 MW 9%Solar 1,570 MW 44%Battery storage 1,655 MW 46%Other 50 MW 1%
Under construction or built 355 MW
Solar 130 MW 37%Battery storage 225 MW 63%
TechnologyUnitsPlanned MWUnder construction or built
Battery storage71,655 MW225 MW
Solar71,570 MW130 MW
Wind2326 MW—
Other150 MW—

Largest planned generators

PlantCountyTechnologyMWStatusYearOwner
Hop Hill Solar Generation and BESSBentonBatteries500 MWApprovals pending2031HOHI bn, LLC
Hop Hill Solar Generation and BESSBentonSolar Photovoltaic500 MWApprovals pending2031HOHI bn, LLC
Lower Snake Solar Generation BESSGarfieldSolar Photovoltaic300 MWApprovals pending2029LOSN, LLC
Lower Snake Solar Generation BESSGarfieldBatteries300 MWApprovals pending2029LOSN, LLC
Royal SlopeGrantBatteries260 MWApprovals received2027Royal Slope Solar LLC
Royal SlopeGrantSolar Photovoltaic260 MWApprovals received2027Royal Slope Solar LLC
Greenwater BESSPierceBatteries200 MWUnder construction (>50%)2026GREE bn, LLC
Centralia Battery Energy Storage SystemThurstonBatteries200 MWApprovals pending2028CENT bn, LLC
Hop Hill Solar Generation and BESSBentonOnshore Wind Turbine200 MWApprovals pending2031HOHI bn, LLC
AGATE BESSKitsapBatteries170 MWApprovals pending2029BrightNight Power
CarrigerKlickitatSolar Photovoltaic160 MWApprovals pending2028Cypress Creek Renewables
Bluebird SolarKlickitatSolar Photovoltaic140 MWApprovals received2027Avangrid Power LLC
SR Quincy ValleyGrantSolar Photovoltaic130 MWUnder construction (>50%)2026SR Quincy Valley, LLC
Saddle Mountain East Wind FarmAdamsOnshore Wind Turbine126 MWPlanned, approvals not started2029EDP Renewables North America LLC
High Top SolarYakimaSolar Photovoltaic80 MWApprovals received2029Cypress Creek Renewables
Supply chain

What the Washington build-out runs on

Who is building generation in Washington, which manufacturers and contractors have a plant, expansion or contract recorded here, and how long the critical equipment takes to arrive.

Developers and owners with planned generation

Developer or ownerUnitsPlanned MWBuilding MWMain technologyCounties
HOHI bn, LLC31,200 MW—Wind1
LOSN, LLC2600 MW—Solar1
Royal Slope Solar LLC2520 MW—Battery storage1
Cypress Creek Renewables2240 MW—Solar2
CENT bn, LLC1200 MW—Battery storage1
GREE bn, LLC1200 MW200 MWBattery storage1
BrightNight Power1170 MW—Battery storage1
Avangrid Power LLC1140 MW—Solar1
SR Quincy Valley, LLC1130 MW130 MWSolar1
EDP Renewables North America LLC1126 MW—Wind1
Helion Energy, Inc.150 MW—Other1
PUD No 1 of Snohomish County - (WA)125 MW25 MWBattery storage1

Manufacturers and contractors with a recorded Washington footprint

No plant, expansion or contract in the manufacturer record names Washington. The national suppliers below serve every state.

Order-by check derived

11 of the 14 planned units of 50 MW or more in Washington that are not yet under construction (2,046 of 3,246 MW) are past the date their step-up transformer had to be ordered to meet the planned in-service date. These units hold their schedules only if the equipment is already on order.

PlantTechnologyMWPlanned in serviceTransformer order-byTurbine order-byOwner
Lower Snake Solar Generation BESSSolar300 MWOct 2029Sep 2026—LOSN, LLC
Lower Snake Solar Generation BESSBattery storage300 MWOct 2029Sep 2026—LOSN, LLC
Royal SlopeBattery storage260 MWOct 2027Sep 2024—Royal Slope Solar LLC
Royal SlopeSolar260 MWOct 2027Sep 2024—Royal Slope Solar LLC
Centralia Battery Energy Storage SystemBattery storage200 MWDec 2028Nov 2025—CENT bn, LLC
AGATE BESSBattery storage170 MWFeb 2029Jan 2026—BrightNight Power
CarrigerSolar160 MWNov 2028Oct 2025—Cypress Creek Renewables
Bluebird SolarSolar140 MWDec 2027Nov 2024—Avangrid Power LLC
Saddle Mountain East Wind FarmWind126 MWOct 2029Sep 2026—EDP Renewables North America LLC
High Top SolarSolar80 MWJan 2029Dec 2025—Cypress Creek Renewables
Orion - HelionOther50 MWDec 2028Nov 2025—Helion Energy, Inc.

Lead times, OEM backlogs and the national generation and grid contractors are on the national supply chain section.

Demand

Data center and large-load demand in Washington

112 data centers run by 47 operators are identified in Washington. The full list by city is on the Washington Data Center Map page. Utilities report 0 large customer projects here to EEI.

No large customer projects reported to EEI for this state.

Jobs and pay

The Washington jobs report, and who the build-out employs

Median pay, May 2025
Cashiers$38,720
Fast food and counter workers$37,710
Retail salespersons$39,560
All occupations$62,990
Construction laborers$57,720
Welders$63,020
HVAC mechanics$75,660
Plumbers and pipefitters$81,030
Electricians$95,220
Power plant operators$131,620
Power-line installers$133,060
Construction supervisors$109,570
Electrical engineers$132,710
Cashier median: $38,720

Payroll employment, August 2026 (preliminary)

IndustryJobsChange vs Aug 2025Change vs Aug 2019
Total nonfarm3,647.0k▲ 0.4%▲ 4.8% (+168.8k)
Construction216.0k▼ 0.6%▼ 2.4% (-5.3k)
Manufacturing276.0k▲ 2.5%▼ 6.3% (-18.7k)
Mining and logging5.1k▲ 2.0%▼ 10.5% (-0.6k)
Retail trade331.2k▲ 0.6%▼ 2.2% (-7.6k)

Power and data industries, 2019 to 2025

IndustryJobs 2019Jobs 2025ChangeAverage pay 2025
Data processing and hosting13,89223,335▲ 68.0%$267,744
Electrical contractors23,96925,436▲ 6.1%$101,610
Power and communication line construction4,2923,924▼ 8.6%$119,782
Electric power generation, transmission, distribution—4,025—$161,765
Transformer manufacturing—not disclosed——

Pay ladder, May 2025

OccupationEmploymentMedian annual payMultiple of cashier pay
Cashiers61,050$38,7201.00×
Fast food and counter workers94,710$37,7100.97×
Retail salespersons84,850$39,5601.02×
All occupations3,550,970$62,9901.63×
Construction laborers25,060$57,7201.49×
Welders7,720$63,0201.63×
HVAC mechanics7,370$75,6601.95×
Plumbers and pipefitters12,470$81,0302.09×
Electricians19,380$95,2202.46×
Power plant operators430$131,6203.40×
Power-line installers2,340$133,0603.44×
Construction supervisors19,550$109,5702.83×
Electrical engineers7,610$132,7103.43×

County-level contractor jobs and pay are in the county record above.

Economy

What the data center industry adds to Washington

38,450
Direct data center jobs (2024)
127,700
Total jobs supported, in state
$33.8B
Total GDP contribution
4.0%
Share of state GDP
$2.4B
State and local taxes

PwC figures are modeled estimates commissioned by the industry.

State studies and incentive costs

Economic study findingsDisclosed tax-incentive cost
DOR workgroup: Grant County's top 10 taxpayers paid $54.3M in 2025 vs. $4.2M in 2006; Quincy's levy rate fell ~70% since 2006; 8,990 direct jobs statewide (2023, PwC as cited by DOR); ~900 direct jobs in Quincy; ~$584M in exemptions 2012–23$118M+ (2023); $132M (2026)
Policy

The rules and the pipeline in Washington

State measures 9

BillMeasureStatusDate
—Amazon’s Walla Walla data center plan sparks tension between protesters, local officialsPaused2026-10
ESSB 6231Rolling back data-center tax exemptionsIn force2026-04
HB 2655Providing a retail sales and use tax exemption for the construction and equipping of new data centers located in a county east of the Cascades that bordersProposed2026-02
HB 2708Removing a tax exemption for the replacement of equipment for data centers.Proposed2026-01
HB 2515Clean energy procurement and cost obligationsProposed2026
Executive Order 25Washington: Governor Ferguson issued Executive Order 25-05 on February 3, 2025 creating the Data Center Workgroup, convened by the Department of RevenueIn force2025-02
SB 5262Broadening the eligibility requirements and extending the expiration date for the data center tax incentive.Failed / vetoed2022-02
HB 1459Broadening the eligibility requirements and extending the expiration date for the data center tax incentive.Failed / vetoed2022-01
HB 2962Broadening the eligibility requirements and extending the expiration date for the data center tax incentive.Failed / vetoed2020-03

Delay Watchlist projects 4

ProjectLocationStatusCauseMW
Seattle Data Center Pipeline (citywide moratorium)Seattlehaltedcommunity opposition—
Spokane Data Center Pipeline (citywide moratorium)Spokanehaltedlocal moratorium—
Federal Way Data Center MoratoriumFederal Wayhaltedlocal moratorium—
Grant County PUD Data Center Load Growth CapGrant County (Quincy/Moses Lake)delayedcommunity opposition—

Local moratoria and restrictions (21) appear by county and city in the county-by-county section. Counts include every status in the weekly tracker feeds as of October 5, 2026. The Washington Data Center Map page counts only active local pauses and delayed or blocked projects as of its September 2 rebuild, so its figures are lower. The difference is one of definition and date.

Nearby states

Washington's neighbors

Questions

Washington power, answered from the record

How much new power generation is planned in Washington?

EIA's August 2026 inventory lists 3,601 MW of planned generators in Washington, 355 MW of it under construction or built. By capacity the pipeline is battery storage 46%, solar 44%, wind 9%. The largest single unit is Hop Hill Solar Generation and BESS (500 MW, HOHI bn, LLC). Owners plan to retire 2 MW from 2026 to 2030.

Who runs the power grid in Washington?

Non-RTO (utility-run) serves most of Washington, which means vertically integrated utilities plan and dispatch generation under the state commission. No data center load is tracked in its queues yet.

How much do data centers add to the Washington economy?

PwC's 2026 study for the Data Center Coalition credits the industry with 127,700 in-state jobs, $33.8B of GDP (4.0% of the state economy, 1st of 51) and $2.4B in state and local taxes in 2024. These are modeled estimates commissioned by the industry.

Are electricity prices rising in Washington?

Residential electricity averaged 14.40¢/kWh from January to July 2026, +13.0% on a year earlier, the 7th fastest increase of 51. Commercial sales, the class that includes data centers, changed +1.5%.

Where are the data centers in Washington?

112 data centers run by 47 operators are identified in Washington. The largest clusters are in King County (45), Grant County (27), Snohomish County (9).

Is planned generation in Washington on schedule?

11 of 14 planned units of 50 MW or more not yet under construction are past the latest date to order a step-up transformer (more than 160 weeks) for their planned in-service date. They hold schedule only if equipment is already on order.

What do electricians earn in Washington?

The median electrician in Washington earned $95,220 in May 2025, 2.46 times the median cashier, and power-line installers earned $133,060 (BLS OEWS).

Does Washington have a data center moratorium?

The SAVRN Moratorium Tracker holds 9 state-level measures (2 enacted) and 21 local moratoria or restrictions in Washington, 20 of them in force, 25th most in the country.

Across SAVRN

Washington across the SAVRN trackers

Sources

Sources for this page

Every figure links to its original source through the Sources buttons. Values marked derived are calculated from reported figures.