Mubadala Data Center Capex and Sites
Mubadala invested in Aligned Data Centers on August 2, 2023, amount not disclosed, when Aligned planned more than 2.5GW across 40 plus data centers at full build-out. Its related digital investments include $350 million into Princeton Digital Group in 2022 and £800 million into CityFibre. Mubadala also invested $500 million into Cologix alongside Stonepeak.
Reported and guided spending
Where Mubadala builds
Financing transactions
Transactions that name Mubadala as a party or attach to one of its named sites. Amounts are as stated; overlapping commitments are never summed.
| Parties | Instrument | Amount | Date | Site | Sources |
|---|---|---|---|---|---|
Crusoe Energy + Valor Equity Partners + Mubadala Capital Series E co-led by Valor Equity Partners and Mubadala Capital, disclosed with a 45GW pipeline, 1.2GW at Abilene and 1.8GW in Wyoming. |
equity raise | ≥$1.4B | October 24, 2025 | n.a. | |
Crusoe Energy + Founders Fund + Fidelity + Mubadala + Nvidia + Ribbit + Valor + Crusoe Series D led by Founders Fund. |
equity raise | $600M | closed December 12, 2024 | n.a. | |
Mubadala + Cologix + Stonepeak Mubadala invested $500 million into Cologix alongside Stonepeak for data center expansion. |
equity raise | $500M | n.a. | n.a. | |
Lambda + Mubadala Capital Lambda reportedly targets an IPO in H2 2026, slightly later than a previously reported H1 target, with Morgan Stanley, J.P. Morgan and Citi engaged. Bloomberg reported on 25 August 2026 that Lambda was in talks to raise as much as $3 billion at a valuation of as much as $12 billion or more, had received multiple term sheets, and could go public as soon as 2027; terms were not finalized. Reported by Bloomberg. The Wall Street Journal reported on Tuesday 6 October 2026, citing unnamed sources, that Lambda is raising as much as $4 billion in a final round before its planned IPO, at a valuation of $14.5 billion excluding the new money. Reported, not closed; amount field unchanged. |
equity raise | ~$350M | reported; IPO targeted H2 2026 | n.a. | |
Mubadala + Princeton Digital Group Mubadala's related digital investments include $350 million into Princeton Digital Group in 2022. |
jv equity | $350M | 2022 | n.a. | |
Mubadala + Aligned Data Centers Mubadala invested in Aligned Data Centers on August 2, 2023, amount not disclosed, when Aligned planned more than 2.5GW across 40 plus data centers at full build-out. |
jv equity | n.a. | August 2, 2023 | n.a. | |
Mubadala + CityFibre Mubadala's related digital investments include £800 million into CityFibre. |
jv equity | n.a. | n.a. in source | n.a. |
Sourced facts on Mubadala
- Mubadala invested in Aligned Data Centers on August 2, 2023, amount not disclosed, when Aligned planned more than 2.5GW across 40 plus data centers at full build-out.
- Mubadala's related digital investments include $350 million into Princeton Digital Group (2022) and £800 million into CityFibre.
- Mubadala invested $500 million into Cologix alongside Stonepeak.
Sources for Mubadala
Every source cited on this page, once each. The full atlas source register is at Capital Atlas sources.
- crusoe.aiCrusoe
- crusoe.aiCrusoe
- datacenterdynamics.comDCD
- datacenterdynamics.comDCD
- finance.yahoo.comBloomberg via Yahoo Finance
- pymnts.comPYMNTS citing The Wall Street Journal, 6 October 2026
- mubadala.comMubadala
Pension and sovereign wealth: one page each
The figure beside each provider is its count of named sites in the atlas.
Seven references, one system
Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.