Power Supply Chain and Demand in Oklahoma

SPP runs most of Oklahoma's grid. 5,623 MW of new generation is planned in Oklahoma, 2,671 MW of it under construction or built and awaiting operation, against 106 MW of planned retirements through 2030. 39 data centers are identified in the state. Residential electricity averaged 13.58¢/kWh in 2026 through July, +7.8% from a year earlier. Unemployment was 4.3% in August 2026, and construction employment is +12.7% against August 2019. The SAVRN trackers hold 15 local moratoria or restrictions for Oklahoma across all statuses (15 in force) and 9 named projects on the Delay Watchlist.
What the build-out changed in Oklahoma
Oklahoma is building power faster than most states, and the jobs data shows it. Power and communication line construction jobs grew 88.0% from 2019 to 2025 (3rd of 44). Commercial electricity sales, the class that includes data centers, are +3.1% year to date, 14th in the country. Developers have announced $37.0B of data center capital in Oklahoma, 13th among the 31 states with a disclosed figure. Households pay part of the cost: residential prices are +7.8% year to date, the 22nd fastest increase of 51. Factory employment is the exception: manufacturing jobs are -0.9% against August 2019.
Then and now
| Measure | Then | Now | Change | U.S. rank |
|---|---|---|---|---|
| Construction jobs (Aug 2019 → Aug 2026) | 83.0k | 93.5k | ▲ 12.7% | 27th of 48 |
| Electrical contractor jobs (2019 → 2025) | 11,970 | 12,967 | ▲ 8.3% | 40th of 48 |
| Power line construction jobs (2019 → 2025) | 3,142 | 5,906 | ▲ 88.0% | 3rd of 44 |
| Data processing and hosting jobs (2019 → 2025) | 1,437 | 1,652 | ▲ 15.0% | 38th of 46 |
| Unemployment rate (Feb 2020 → Aug 2026) | 3.2% | 4.3% | ▲ 1.1pts | — |
| Residential price, ¢/kWh (YTD Jul 2025 → 2026) | 12.60¢ | 13.58¢ | ▲ 7.8% | 22nd of 51 |
| Generation fleet → planned additions | 36.7 GW operating | 5.6 GW planned | 15% of fleet | 23rd of 51 |
Where Oklahoma ranks among 51
1st = the most. Ranks cover every state and DC that publishes the figure.
Among its neighbors, Oklahoma leads on power line construction jobs, 2019 to 2025 (+88.0%), ahead of New Mexico (+68.3%).
County spotlight
Tulsa County holds the most data centers on record in Oklahoma (17), and its electrical contractor workforce changed +20.5% since 2019 to 3,406 jobs. The largest share of planned generation sits in Comanche County: 1,373 MW, led by Public Service Co of Oklahoma (natural gas). The fastest-growing electrical trade market is Wagoner County, where contractor jobs grew 47.9% to 692.
Where Oklahoma sits in the power system
- Grid operator
- SPP
- Operating capacity
- 36.7 GW
- Planned generation
- 5,623 MW
- Under construction or built
- 2,671 MW
- Data centers identified
- 39
- Data center load in queues
- —
- Unemployment, Aug 2026
- 4.3%
- Residential price change
- +7.8%
Neighboring states are shaded. Select one to open its page.
Oklahoma, county by county
77 counties in Oklahoma. Planned generation sits in 12 of them, data centers stand in 8, and local measures are on record in 0. Pick a layer, then select a county for its full record.
County leaders
Counties on record 41
| County | Data centers | Planned MW | Building MW | Lead developer | Electrical contractor jobs | Change 2019–25 | Local measures | Watchlist | |
|---|---|---|---|---|---|---|---|---|---|
| Tulsa County | 17 | — | — | — | 3,406 | ▲ 20.5% | — | 2 | |
| Oklahoma County | 12 | 896 MW | 448 MW | Oklahoma Gas & Electric Co | 3,624 | ▲ 2.8% | — | — | |
| Muskogee County | 3 | 400 MW | — | High Spring Solar Energy | — | — | — | — | |
| Mayes County | 1 | 794 MW | 794 MW | Grand River Dam Authority | — | — | — | — | |
| Payne County | 1 | 419 MW | 419 MW | Associated Electric Coop, Inc | 135 | ▼ 25.4% | — | 1 | |
| Rogers County | 1 | — | — | — | 302 | ▲ 28.5% | — | — | |
| Cherokee County | 1 | — | — | — | 31 | ▲ 55.0% | — | — | |
| Bryan County | 1 | — | — | — | — | — | — | — | |
| Comanche County | — | 1,373 MW | — | Public Service Co of Oklahoma | 211 | ▲ 21.3% | — | — | |
| Stephens County | — | 458 MW | 458 MW | Roy Solar, LLC | 186 | ▼ 9.3% | — | — | |
| Le Flore County | — | 400 MW | — | Clenera DevCo LLC | — | — | — | — | |
| Dewey County | — | 251 MW | — | Mammoth Plains Energy Storage, LLC | — | — | — | — | |
| Grady County | — | 250 MW | 250 MW | Rumble Solar, LLC | — | — | — | — | |
| Pawnee County | — | 200 MW | 200 MW | Willow Creek Energy Storage, LLC | 21 | ▼ 12.5% | — | — | |
| Texas County | — | 102 MW | 102 MW | Panhandle Solar, LLC | 41 | ▲ 20.6% | — | — | |
| Delaware County | — | 80 MW | — | Lightsource Renewable Energy Asset Management, LLC | 181 | ▲ 170.1% | — | — | |
| Cleveland County | — | — | — | — | 742 | — | — | — | |
| Wagoner County | — | — | — | — | 692 | ▲ 47.9% | — | — | |
| Canadian County | — | — | — | — | 316 | — | — | 1 | |
| Carter County | — | — | — | — | 239 | ▼ 17.9% | — | — | |
| Garvin County | — | — | — | — | 128 | ▼ 3.8% | — | — | |
| Beckham County | — | — | — | — | 122 | ▲ 74.3% | — | — | |
| Lincoln County | — | — | — | — | 87 | ▼ 6.5% | — | — | |
| Kay County | — | — | — | — | 86 | ▼ 25.2% | — | — | |
| Washington County | — | — | — | — | 81 | — | — | — | |
| Woodward County | — | — | — | — | 76 | ▼ 6.2% | — | — | |
| Noble County | — | — | — | — | 70 | ▼ 2.8% | — | — | |
| McClain County | — | — | — | — | 69 | ▼ 20.7% | — | — | |
| Osage County | — | — | — | — | 43 | ▲ 186.7% | — | — | |
| Custer County | — | — | — | — | 41 | ▼ 8.9% | — | — | |
| Haskell County | — | — | — | — | 36 | — | — | — | |
| Kingfisher County | — | — | — | — | 30 | ▲ 20.0% | — | — | |
| Seminole County | — | — | — | — | 29 | ▼ 17.1% | — | — | |
| Okmulgee County | — | — | — | — | 28 | — | — | — | |
| Jackson County | — | — | — | — | 28 | ▼ 9.7% | — | — | |
| Ottawa County | — | — | — | — | 26 | — | — | — | |
| Sequoyah County | — | — | — | — | 23 | — | — | — | |
| Marshall County | — | — | — | — | 19 | — | — | — | |
| Johnston County | — | — | — | — | 15 | — | — | — | |
| Craig County | — | — | — | — | 9 | — | — | — | |
| McIntosh County | — | — | — | — | 6 | ▲ 50.0% | — | — |
Every county in Oklahoma 77
Each county has its own page: power plants, utilities and prices, jobs since 2019, data centers, local rules and its neighbors.
Cities and towns on record 23
| City or town | County | Data centers | Local measures | Watchlist | Latest record | |
|---|---|---|---|---|---|---|
| Tulsa | Tulsa County + Osage County | 15 | 1 (1 in force) | — | Nine-month pause on new data center construction In force | |
| Oklahoma City | Oklahoma County + Canadian County + Cleveland County | 12 | 1 (1 in force) | — | Data center moratorium through end of 2026 In force | |
| Claremore | Rogers County | 1 | — | — | — | |
| Durant | Bryan County | 1 | — | — | — | |
| Hulbert | Cherokee County | 1 | — | — | — | |
| Muskogee | Muskogee County | 1 | — | — | — | |
| Stillwater | Payne County | 1 | — | — | — | |
| Cherokee Nation | — | — | 2 (2 in force) | — | Tribal moratorium on data centers with no end date In force | |
| Broken Arrow | Tulsa County + Wagoner County | — | 1 (1 in force) | — | Local moratorium on data centers through December 31, 2026 In force | |
| Cheyenne and Arapaho Tribes | — | — | 1 (1 in force) | — | Three-year tribal moratorium on data center construction In force | |
| Choctaw | Oklahoma County | — | 1 (1 in force) | — | City moratorium on data centers through July 21, 2027 In force | |
| City of Edmond | Oklahoma County | — | 1 (1 in force) | — | City of Edmond (data center moratorium), OK data center moratorium In force | |
| Edmond | Oklahoma County | — | 1 (1 in force) | — | Data center permit moratorium (through Dec. 31, 2026) In force | |
| Kickapoo Tribe of Oklahoma | — | — | 1 (1 in force) | — | Tribal moratorium on data centers with no end date In force | |
| Luther | Oklahoma County | — | 1 (1 in force) | — | Local moratorium on data centers through December 31, 2026 In force | |
| Norman | Cleveland County | — | 1 (1 in force) | — | Local moratorium on data centers through June 9, 2027 In force | |
| Pawhuska | Osage County | — | 1 (1 in force) | — | Data center moratorium through Dec. 31, 2026 In force | |
| Seminole Nation of Oklahoma | — | — | 1 (1 in force) | — | Local moratorium on data centers with no end date In force | |
| Shawnee | Pottawatomie County | — | 1 (1 in force) | — | City moratorium on data centers through December 31, 2027 In force | |
| Oklahoma | — | — | — | 2 | HB 4424; SB 1488 | |
| Ardmore | Carter County | — | — | 1 | JRE Strategies LLC Ardmore | |
| Coweta | Wagoner County | — | — | 1 | Project Atlas | |
| Muscogee Nation | — | — | — | 1 | Mvskoke Technology and Innovation Park |
Data center counts come from every facility on the SAVRN Data Center Map, counted in the county and the city or community where each building physically stands (Census boundaries), not its mailing address. Jurisdictions appear as the Moratorium Tracker records them.
Oklahoma, from generation to the household bill
1Grid operator
- Record peak (Aug 2023)
- 56 GW
- 2026 ITP Future 2 peak 2035
- 110 GW
2Generation pipeline
- Operating capacity
- 36.7 GW
- Planned, all types
- 5,623 MW
- Under construction or built
- 2,671 MW
- Planned gas
- 3,282 MW
- Planned retirements 2026–30
- 106 MW
- Net firm additions derived
- 2,565 MW
3Data center demand
- Data centers identified
- 39
- Operators
- 23
- Load in tracked queues
- —
- Utility large-load projects
- 3
- Commercial sales, YTD change
- +3.1%
- Industry share of state GDP
- 1.0%
4Jobs and pay
- Unemployment, Aug 2026
- 4.3% (+0.9 pts y/y)
- Construction jobs vs 2019
- +12.7%
- Manufacturing jobs vs 2019
- -0.9%
- Electrical contractor jobs 2019–25
- +8.3%
- Electrician median pay
- $61,010
- Electrician ÷ cashier pay
- 2.17×
5Household bill
- Residential price, YTD Jul 2026
- 13.58¢/kWh
- Change vs YTD 2025
- +7.8%
- All-sector price change
- +6.6%
- Total retail sales change
- -0.4%
6Policy friction
- State measures on record
- 4
- Local measures (in force)
- 15 (15)
- Watchlist projects
- 9
- Lawsuits tracked
- 0
- Announced capital, disclosed
- $37.0B
- Dedicated tax incentive
- Yes
Planned power plants in Oklahoma
Every planned generator in Oklahoma in the August 2026 EIA-860M inventory, by technology, then the 15 largest units. Under construction or built covers status codes U, V and TS.
| Technology | Units | Planned MW | Under construction or built |
|---|---|---|---|
| Natural gas | 10 | 3,282 MW | 1,461 MW |
| Solar | 8 | 1,690 MW | 1,010 MW |
| Battery storage | 4 | 651 MW | 200 MW |
Largest planned generators
| Plant | County | Technology | MW | Status | Year | Owner |
|---|---|---|---|---|---|---|
| GREC | Mayes | Natural Gas Fired Combustion Turbine | 594 MW | Built, not yet operating | 2026 | Grand River Dam Authority |
| Ripley Energy Center | Payne | Natural Gas Fired Combustion Turbine | 419 MW | Under construction (>50%) | 2027 | Associated Electric Coop, Inc |
| Comanche (OK) | Comanche | Natural Gas Fired Combined Cycle | 409 MW | Planned, approvals not started | 2029 | Public Service Co of Oklahoma |
| Comanche (OK) | Comanche | Natural Gas Fired Combined Cycle | 409 MW | Planned, approvals not started | 2029 | Public Service Co of Oklahoma |
| High Spring Solar Energy | Muskogee | Solar Photovoltaic | 400 MW | Planned, approvals not started | 2027 | High Spring Solar Energy |
| Comanche (OK) | Comanche | Natural Gas Fired Combined Cycle | 278 MW | Planned, approvals not started | 2029 | Public Service Co of Oklahoma |
| Comanche (OK) | Comanche | Natural Gas Fired Combined Cycle | 278 MW | Planned, approvals not started | 2029 | Public Service Co of Oklahoma |
| Roy Solar | Stephens | Solar Photovoltaic | 258 MW | Under construction (≤50%) | 2027 | Roy Solar, LLC |
| Rumble Solar | Grady | Solar Photovoltaic | 250 MW | Under construction (≤50%) | 2026 | Rumble Solar, LLC |
| Horseshoe Lake | Oklahoma | Natural Gas Fired Combustion Turbine | 224 MW | Approvals received | 2029 | Oklahoma Gas & Electric Co |
| Horseshoe Lake | Oklahoma | Natural Gas Fired Combustion Turbine | 224 MW | Approvals received | 2029 | Oklahoma Gas & Electric Co |
| Horseshoe Lake | Oklahoma | Natural Gas Fired Combustion Turbine | 224 MW | Built, not yet operating | 2026 | Oklahoma Gas & Electric Co |
| Horseshoe Lake | Oklahoma | Natural Gas Fired Combustion Turbine | 224 MW | Built, not yet operating | 2026 | Oklahoma Gas & Electric Co |
| Solstice Solar LLC | Le Flore | Batteries | 200 MW | Planned, approvals not started | 2029 | Clenera DevCo LLC |
| Twelvemile Solar 3 | Mayes | Solar Photovoltaic | 200 MW | Under construction (>50%) | 2026 | Leeward Asset Management, LLC |
What the Oklahoma build-out runs on
Who is building generation in Oklahoma, which manufacturers and contractors have a plant, expansion or contract recorded here, and how long the critical equipment takes to arrive.
Developers and owners with planned generation
| Developer or owner | Units | Planned MW | Building MW | Main technology | Counties |
|---|---|---|---|---|---|
| Public Service Co of Oklahoma | 4 | 1,373 MW | — | Natural gas | 1 |
| Oklahoma Gas & Electric Co | 4 | 896 MW | 448 MW | Natural gas | 1 |
| Grand River Dam Authority | 1 | 594 MW | 594 MW | Natural gas | 1 |
| Associated Electric Coop, Inc | 1 | 419 MW | 419 MW | Natural gas | 1 |
| Clenera DevCo LLC | 2 | 400 MW | — | Battery storage | 1 |
| High Spring Solar Energy | 1 | 400 MW | — | Solar | 1 |
| Roy Solar, LLC | 1 | 258 MW | 258 MW | Solar | 1 |
| Rumble Solar, LLC | 1 | 250 MW | 250 MW | Solar | 1 |
| Leeward Asset Management, LLC | 1 | 200 MW | 200 MW | Solar | 1 |
| Rush Springs Solar, LLC | 1 | 200 MW | 200 MW | Solar | 1 |
| Willow Creek Energy Storage, LLC | 1 | 200 MW | 200 MW | Battery storage | 1 |
| Mammoth Plains Energy Storage, LLC | 1 | 150 MW | — | Battery storage | 1 |
| Panhandle Solar, LLC | 1 | 102 MW | 102 MW | Solar | 1 |
| Mammoth Plains Energy Center, LLC | 1 | 101 MW | — | Battery storage | 1 |
| Lightsource Renewable Energy Asset Management, LLC | 1 | 80 MW | — | Solar | 1 |
Manufacturers and contractors with a recorded Oklahoma footprint
No plant, expansion or contract in the manufacturer record names Oklahoma. The national suppliers below serve every state.
Order-by check derived
10 of the 12 planned units of 50 MW or more in Oklahoma that are not yet under construction (2,552 of 2,952 MW) are past the date their step-up transformer had to be ordered to meet the planned in-service date, and 6 gas units are (1,821 MW) past the turbine order date as well. These units hold their schedules only if the equipment is already on order.
| Plant | Technology | MW | Planned in service | Transformer order-by | Turbine order-by | Owner |
|---|---|---|---|---|---|---|
| Comanche (OK) | Natural gas | 409 MW | Sep 2029 | Aug 2026 | Sep 2024 | Public Service Co of Oklahoma |
| Comanche (OK) | Natural gas | 409 MW | Sep 2029 | Aug 2026 | Sep 2024 | Public Service Co of Oklahoma |
| High Spring Solar Energy | Solar | 400 MW | Dec 2027 | Nov 2024 | — | High Spring Solar Energy |
| Comanche (OK) | Natural gas | 278 MW | Sep 2029 | Aug 2026 | Sep 2024 | Public Service Co of Oklahoma |
| Comanche (OK) | Natural gas | 278 MW | Sep 2029 | Aug 2026 | Sep 2024 | Public Service Co of Oklahoma |
| Horseshoe Lake | Natural gas | 224 MW | Feb 2029 | Jan 2026 | Feb 2024 | Oklahoma Gas & Electric Co |
| Horseshoe Lake | Natural gas | 224 MW | Feb 2029 | Jan 2026 | Feb 2024 | Oklahoma Gas & Electric Co |
| Mammoth Plains Energy Storage | Battery storage | 150 MW | Nov 2027 | Oct 2024 | — | Mammoth Plains Energy Storage, LLC |
| Mammoth Plains Energy Storage II | Battery storage | 101 MW | May 2029 | Apr 2026 | — | Mammoth Plains Energy Center, LLC |
| Fiddle Leaf Solar, LLC | Solar | 80 MW | Oct 2027 | Sep 2024 | — | Lightsource Renewable Energy Asset Management, LLC |
Lead times, OEM backlogs and the national generation and grid contractors are on the national supply chain section.
Data center and large-load demand in Oklahoma
39 data centers run by 23 operators are identified in Oklahoma. The full list by city is on the Oklahoma Data Center Map page. Utilities report 3 large customer projects here to EEI.
| Utility | Customer or type | MW stated | Investment stated | |
|---|---|---|---|---|
| Oklahoma Gas & Electric Company (OGE) | 1,000 MW | $9 billion | ||
| Public Service Company of Oklahoma (AEP) | Emirates Global Aluminum, Century Aluminum | — | — | |
| Public Service Company of Oklahoma (AEP) | Meta | — | $1 billion |
The Oklahoma jobs report, and who the build-out employs
Payroll employment, August 2026 (preliminary)
| Industry | Jobs | Change vs Aug 2025 | Change vs Aug 2019 |
|---|---|---|---|
| Total nonfarm | 1,799.6k | ▲ 0.7% | ▲ 5.5% (+93.5k) |
| Construction | 93.5k | ▲ 4.2% | ▲ 12.7% (+10.5k) |
| Manufacturing | 139.0k | ▼ 0.8% | ▼ 0.9% (-1.3k) |
| Mining and logging | 28.4k | ▲ 0.3% | ▼ 39.2% (-18.3k) |
| Retail trade | 182.5k | ▼ 0.8% | ▲ 3.2% (+5.7k) |
Power and data industries, 2019 to 2025
| Industry | Jobs 2019 | Jobs 2025 | Change | Average pay 2025 |
|---|---|---|---|---|
| Data processing and hosting | 1,437 | 1,652 | ▲ 15.0% | $102,501 |
| Electrical contractors | 11,970 | 12,967 | ▲ 8.3% | $70,128 |
| Power and communication line construction | 3,142 | 5,906 | ▲ 88.0% | $84,044 |
| Electric power generation, transmission, distribution | — | 6,990 | — | $115,066 |
Pay ladder, May 2025
| Occupation | Employment | Median annual pay | Multiple of cashier pay |
|---|---|---|---|
| Cashiers | 41,140 | $28,180 | 1.00× |
| Fast food and counter workers | 52,520 | $23,430 | 0.83× |
| Retail salespersons | 43,830 | $29,660 | 1.05× |
| All occupations | 1,707,680 | $45,600 | 1.62× |
| Construction laborers | 13,710 | $39,360 | 1.40× |
| Welders | 9,960 | $49,720 | 1.76× |
| HVAC mechanics | 5,650 | $57,560 | 2.04× |
| Plumbers and pipefitters | 6,050 | $57,970 | 2.06× |
| Electricians | 8,500 | $61,010 | 2.17× |
| Power plant operators | 520 | $88,590 | 3.14× |
| Power-line installers | 3,290 | $76,010 | 2.70× |
| Construction supervisors | 11,520 | $73,040 | 2.59× |
| Electrical engineers | 2,080 | $107,760 | 3.82× |
County-level contractor jobs and pay are in the county record above.
What the data center industry adds to Oklahoma
PwC figures are modeled estimates commissioned by the industry.
The rules and the pipeline in Oklahoma
State measures 4
| Bill | Measure | Status | Date | |
|---|---|---|---|---|
| — | ‘Not enough data or expertise’: Oklahoma lawmakers consider future of data centers | Proposed | 2026-09 | |
| HB 2992 | Data Center Customer Ratepayer Protection Act of 2026 | In force | 2026-05 | |
| HB 4424 | Sunset of data center tax incentives | Failed / vetoed | 2026-05 | |
| SB 1488 | Moratorium on new data centers until Nov 1 2029 | Failed / vetoed | 2026-05 |
Delay Watchlist projects 9
| Project | Location | Status | Cause | MW | |
|---|---|---|---|---|---|
| Project Atlas | Coweta | cancelled | 400 MW | ||
| JRE Strategies LLC Ardmore | Ardmore | cancelled | 10 MW | ||
| Google Stillwater Data Center Campus (up to 6 buildings) | Stillwater, Payne County | under construction amid water concerns | — | ||
| Project Anthem (East Tulsa) | East Tulsa, Tulsa County | phase vote delayed | — | ||
| Sand Springs Meta-Backed Data Center | Sand Springs, Tulsa County | opposed proposed | — | ||
| HB 4424 | Oklahoma (statewide) | cancelled | — | ||
| SB 1488 | Oklahoma (statewide) | cancelled | — | ||
| Project Open Sky | Piedmont (Canadian County) | pending review | — | ||
| Mvskoke Technology and Innovation Park | Muscogee (Creek) Nation | cancelled | — |
Local moratoria and restrictions (15) appear by county and city in the county-by-county section. Counts include every status in the weekly tracker feeds as of October 5, 2026. The Oklahoma Data Center Map page counts only active local pauses and delayed or blocked projects as of its September 2 rebuild, so its figures are lower. The difference is one of definition and date.
Oklahoma's neighbors
Oklahoma power, answered from the record
How much new power generation is planned in Oklahoma?
EIA's August 2026 inventory lists 5,623 MW of planned generators in Oklahoma, 2,671 MW of it under construction or built. By capacity the pipeline is natural gas 58%, solar 30%, battery storage 12%. The largest single unit is GREC (594 MW, Grand River Dam Authority). Owners plan to retire 106 MW from 2026 to 2030.
Who runs the power grid in Oklahoma?
SPP serves most of Oklahoma as the regional wholesale market and grid operator. No data center load is tracked in its queues yet.
Is planned generation in Oklahoma on schedule?
10 of 12 planned units of 50 MW or more not yet under construction are past the latest date to order a step-up transformer (more than 160 weeks) for their planned in-service date, and 6 gas units are past the turbine order date (about five years). They hold schedule only if equipment is already on order.
What do electricians earn in Oklahoma?
The median electrician in Oklahoma earned $61,010 in May 2025, 2.17 times the median cashier, and power-line installers earned $76,010 (BLS OEWS).
Which counties in Oklahoma have the most planned generation?
By planned nameplate capacity: Comanche County (1,373 MW), Oklahoma County (896 MW), Mayes County (794 MW).
Are electricity prices rising in Oklahoma?
Residential electricity averaged 13.58¢/kWh from January to July 2026, +7.8% on a year earlier, the 22nd fastest increase of 51. Commercial sales, the class that includes data centers, changed +3.1%.
Which utilities report large-load projects in Oklahoma?
Utilities report 3 large customer projects in Oklahoma to EEI, including Oklahoma Gas & Electric Company (OGE), Public Service Company of Oklahoma (AEP).
Does Oklahoma have a data center moratorium?
The SAVRN Moratorium Tracker holds 4 state-level measures (1 enacted) and 15 local moratoria or restrictions in Oklahoma, 15 of them in force, 28th most in the country.
Oklahoma across the SAVRN trackers
Sources for this page
- BEA state GDP via FRED
- BLS LAUS
- BLS OEWS
- BLS QCEW
- BLS State Employment (CES)
- EEI large customer projects
- EIA Electric Power Monthly
- EIA-860M (Aug 2026)
- NCSL
- PwC for the Data Center Coalition
- SAVRN Capital Atlas
- SAVRN Data Center Map
- SAVRN Delay Watchlist
- SAVRN Grid Operator Watchlist
- SAVRN Moratorium Tracker
- U.S. Census Bureau cartographic boundaries (via us-atlas)
Every figure links to its original source through the Sources buttons. Values marked derived are calculated from reported figures.