New Mexico · Power Supply Chain & Demand

Power Supply Chain and Demand in New Mexico

Seal of New Mexico

Vertically integrated utilities run most of New Mexico's grid. 3,965 MW of new generation is planned in New Mexico, 1,540 MW of it under construction or built and awaiting operation, against 354 MW of planned retirements through 2030. 27 data centers are identified in the state. Residential electricity averaged 15.08¢/kWh in 2026 through July, +2.8% from a year earlier. Unemployment was 4.7% in August 2026, and construction employment is +12.3% against August 2019. The SAVRN trackers hold 12 local moratoria or restrictions for New Mexico across all statuses (8 in force) and 5 named projects on the Delay Watchlist.

Rebuilt 2026-10-08 · refreshed weekly
Grid operator
Non-RTO (utility-run)
main wholesale grid
Planned generation
4.0 GW
1.5 GW under construction or built
Data center load in queues
—
27 data centers identified
Residential price
15.08¢
▲ 2.8% vs 2025, YTD July
Construction jobs
+12.3%
▲ 12.3% vs Aug 2019
Local measures
12
8 in force · 5 on Delay Watchlist
The finding

What the build-out changed in New Mexico

New Mexico is building power faster than most states, and the jobs data shows it. Data processing and hosting jobs grew 103.1% from 2019 to 2025, 3rd of 46 states that disclose the industry. Power and communication line construction jobs grew 68.3% from 2019 to 2025 (5th of 44). Planned generation equals 22% of the power plants New Mexico runs today, one of the steepest build-outs in the country (15th). The weak spot: data center share of state gdp ranks 43rd of 51 at 1.1%. Factory employment is the exception: manufacturing jobs are -1.7% against August 2019.

Then and now

MeasureThenNowChangeU.S. rank
Construction jobs (Aug 2019 → Aug 2026)51.3k57.6k▲ 12.3%28th of 48
Electrical contractor jobs (2019 → 2025)7,1528,443▲ 18.1%27th of 48
Power line construction jobs (2019 → 2025)1,5432,597▲ 68.3%5th of 44
Data processing and hosting jobs (2019 → 2025)491997▲ 103.1%3rd of 46
Unemployment rate (Feb 2020 → Aug 2026)5.3%4.7%▼ 0.6pts—
Residential price, ¢/kWh (YTD Jul 2025 → 2026)14.67¢15.08¢▲ 2.8%42nd of 51
Generation fleet → planned additions18.2 GW operating4.0 GW planned22% of fleet15th of 51

Where New Mexico ranks among 51

Data center share of state GDP1.1%43rd of 51
Planned generation vs. today's fleet22%15th of 51
Construction jobs vs. 2019+12.3%28th of 48
Electrical contractor jobs, 2019 to 2025+18.1%27th of 48
Power line construction jobs, 2019 to 2025+68.3%5th of 44
Data processing and hosting jobs, 2019 to 2025+103.1%3rd of 46
Commercial electricity sales, YTD change-0.3%40th of 51
Residential electricity price, YTD change+2.8%42nd of 51
Local moratoria and restrictions1231st of 49

1st = the most. Ranks cover every state and DC that publishes the figure.

Among its neighbors, New Mexico leads on data processing and hosting jobs, 2019 to 2025 (+103.1%), ahead of Utah (+42.1%).

County spotlight

Bernalillo County holds the most data centers on record in New Mexico (14), and its electrical contractor workforce changed +20.6% since 2019 to 3,954 jobs. The largest share of planned generation sits in San Juan County: 1,729 MW, led by Navajo Transitional Energy Company (natural gas).

The map

Where New Mexico sits in the power system

Grid operator
Non-RTO (utility-run)
Operating capacity
18.2 GW
Planned generation
3,965 MW
Under construction or built
1,540 MW
Data centers identified
27
Data center load in queues
—
Unemployment, Aug 2026
4.7%
Residential price change
+2.8%

Neighboring states are shaded. Select one to open its page.

Counties and cities

New Mexico, county by county

33 counties in New Mexico. Planned generation sits in 14 of them, data centers stand in 4, and local measures are on record in 5. Pick a layer, then select a county for its full record.

Luna CountyTorrance CountyGrant CountySierra CountyUnion CountyDe Baca CountyValencia CountySan Miguel CountyOtero CountyHidalgo CountyCibola CountyEddy CountyRio Arriba CountyMcKinley CountyLincoln CountySocorro CountyTaos CountySan Juan CountyCatron CountyLos Alamos CountySanta Fe CountyMora CountySandoval CountyQuay CountyDoña Ana CountyLea CountyCurry CountyBernalillo CountyChaves CountyHarding CountyColfax CountyGuadalupe CountyRoosevelt County

County leaders

Most planned generation
San Juan Countynatural gas1,729 MW
Lea Countysolar721 MW
Bernalillo Countybattery storage250 MW
Valencia Countysolar203 MW
Otero Countybattery storage200 MW
Roosevelt Countysolar200 MW
Union Countywind190 MW
De Baca Countysolar158 MW
Fastest electrical contractor growth
Sandoval County356 jobs+73.7%
Eddy County453 jobs+26.5%
Bernalillo County3,954 jobs+20.6%
Valencia County637 jobs+9.3%

Counties on record 25

CountyData centersPlanned MWBuilding MWLead developerElectrical contractor jobsChange 2019–25Local measuresWatchlist
Bernalillo County14250 MW—Corazon Energy Storage, LLC3,954▲ 20.6%——
Valencia County6203 MW203 MWStar Light Energy Center637▲ 9.3%—1
Doña Ana County5155 MW155 MWSanta Teresa Solar———1
Santa Fe County1—————2 (2 in force)—
San Juan County—1,729 MW510 MWNavajo Transitional Energy Company391———
Lea County—721 MW295 MWLydian Energy725▼ 5.5%—1
Otero County—200 MW200 MWBuena Vista Energy Center III, LLC125▲ 0.8%——
Roosevelt County—200 MW—Blackwater Solar Center, LLC20▼ 39.4%——
Union County—190 MW—Gallegos Wind Farm LLC————
De Baca County—158 MW158 MWWindy Lane Energy Center, LLC————
McKinley County—140 MW—Solariant Capital, LLC105▲ 54.4%——
Luna County—8 MW8 MWUSS Gold Solar LLC64▲ 204.8%——
Sandoval County—5 MW5 MWAffordable Solar Silver City, LLC356▲ 73.7%——
Grant County—5 MW5 MWStandard Solar69▲ 50.0%1 (0 in force)—
Hidalgo County—2 MW2 MWUSS Fletcher Solar LLC————
Eddy County————453▲ 26.5%——
Chaves County————95——1
Rio Arriba County————79▲ 16.2%——
San Miguel County————53▲ 6.0%——
Taos County————53▼ 19.7%——
Lincoln County————34▲ 70.0%——
Cibola County————23———
Sierra County——————1 (1 in force)—
Socorro County——————2 (2 in force)—
Colfax County——————1 (1 in force)—

Every county in New Mexico 33

Each county has its own page: power plants, utilities and prices, jobs since 2019, data centers, local rules and its neighbors.

Cities and towns on record 12

City or townCountyData centersLocal measuresWatchlistLatest record
AlbuquerqueBernalillo County12———
Los LunasValencia County6———
Kirtland AFBBernalillo County2———
Las CrucesDoña Ana County2———
Santa FeSanta Fe County1———
Santa TeresaDoña Ana County1———
White SandsDoña Ana County1———
ClovisCurry County—1 (0 in force)—120-day data center moratorium voted down Failed / vetoed
Doña Ana County——1 (1 in force)—New Mexico Supreme Court rejects 2 Project Jupiter challenges, allows permitting process to resume In force
Haaland——1 (0 in force)—Haaland backs data center moratorium in New Mexico Proposed
RatonColfax County—1 (0 in force)—Proposed city moratorium on data centers Failed / vetoed
Rio CommunitiesValencia County—1 (1 in force)—City moratorium on data centers through August 26, 2027 In force

Data center counts come from every facility on the SAVRN Data Center Map, counted in the county and the city or community where each building physically stands (Census boundaries), not its mailing address. Jurisdictions appear as the Moratorium Tracker records them.

The chain

New Mexico, from generation to the household bill

1Grid operator

Utility-run territory: resource planning sits with the vertically integrated utilities and the state commission.

2Generation pipeline

Operating capacity
18.2 GW
Planned, all types
3,965 MW
Under construction or built
1,540 MW
Planned gas
1,149 MW
Planned retirements 2026–30
354 MW
Net firm additions derived
1,186 MW

3Data center demand

Data centers identified
27
Operators
19
Load in tracked queues
—
Utility large-load projects
1
Commercial sales, YTD change
-0.3%
Industry share of state GDP
1.1%

4Jobs and pay

Unemployment, Aug 2026
4.7% (+0.6 pts y/y)
Construction jobs vs 2019
+12.3%
Manufacturing jobs vs 2019
-1.7%
Electrical contractor jobs 2019–25
+18.1%
Electrician median pay
$58,390
Electrician ÷ cashier pay
1.94×

5Household bill

Residential price, YTD Jul 2026
15.08¢/kWh
Change vs YTD 2025
+2.8%
All-sector price change
-6.4%
Total retail sales change
+5.7%

6Policy friction

State measures on record
4
Local measures (in force)
12 (8)
Watchlist projects
5
Lawsuits tracked
0
Announced capital, disclosed
—
Dedicated tax incentive
None listed
Generation

Planned power plants in New Mexico

Every planned generator in New Mexico in the August 2026 EIA-860M inventory, by technology, then the 15 largest units. Under construction or built covers status codes U, V and TS.

Planned generation by fuel 3,965 MW
Natural gas 1,149 MW 29%Wind 190 MW 5%Solar 1,698 MW 43%Battery storage 928 MW 23%
Under construction or built 1,540 MW
Natural gas 60 MW 4%Solar 882 MW 57%Battery storage 598 MW 39%
TechnologyUnitsPlanned MWUnder construction or built
Solar191,698 MW882 MW
Natural gas211,149 MW60 MW
Battery storage10928 MW598 MW
Wind1190 MW—

Largest planned generators

PlantCountyTechnologyMWStatusYearOwner
AC Ranch IILeaSolar Photovoltaic230 MWApprovals pending2029Lydian Energy
Tip Top Solar Energy Center LLCLeaSolar Photovoltaic220 MWUnder construction (>50%)2026Invenergy Services LLC
Blackwater Solar Center - NMRooseveltSolar Photovoltaic200 MWApprovals received2027Blackwater Solar Center, LLC
Cunningham Solar IILeaSolar Photovoltaic196 MWApprovals received2027Southwestern Public Service Co
Gallegos Wind Farm, Phase 1UnionOnshore Wind Turbine190 MWPlanned, approvals not started2028Gallegos Wind Farm LLC
Foxtail Flats Solar, LLCSan JuanSolar Photovoltaic170 MWUnder construction (≤50%)2027Foxtail Flats Solar, LLC
Santa Teresa SolarDona AnaBatteries150 MWUnder construction (>50%)2026Santa Teresa Solar
Corazon Energy StorageBernalilloBatteries150 MWApprovals received2027Corazon Energy Storage, LLC
Rockmont Solar and Storage ProjectSan JuanSolar Photovoltaic100 MWApprovals pending2027201LC 8me LLC
Four Mile Mesa Solar, LLCSan JuanBatteries100 MWUnder construction (≤50%)2027Four Mile Mesa Solar, LLC
Four Mile Mesa Solar, LLCSan JuanSolar Photovoltaic100 MWUnder construction (≤50%)2027Four Mile Mesa Solar, LLC
Oso NegroBernalilloBatteries100 MWApprovals received2028Oso Negro, LLC
Buena Vista Energy Center IIIOteroBatteries100 MWUnder construction (≤50%)2026Buena Vista Energy Center III, LLC
Buena Vista Energy Center IIIOteroSolar Photovoltaic100 MWUnder construction (≤50%)2026Buena Vista Energy Center III, LLC
Star Light Energy CenterValenciaSolar Photovoltaic100 MWUnder construction (≤50%)2026Star Light Energy Center
Supply chain

What the New Mexico build-out runs on

Who is building generation in New Mexico, which manufacturers and contractors have a plant, expansion or contract recorded here, and how long the critical equipment takes to arrive.

Developers and owners with planned generation

Developer or ownerUnitsPlanned MWBuilding MWMain technologyCounties
Navajo Transitional Energy Company181,089 MW—Natural gas1
Lydian Energy2305 MW75 MWSolar1
Foxtail Flats Solar, LLC2250 MW250 MWBattery storage1
Invenergy Services LLC1220 MW220 MWSolar1
Blackwater Solar Center, LLC1200 MW—Solar1
Buena Vista Energy Center III, LLC2200 MW200 MWBattery storage1
Four Mile Mesa Solar, LLC2200 MW200 MWSolar1
Star Light Energy Center2200 MW200 MWBattery storage1
Southwestern Public Service Co1196 MW—Solar1
Gallegos Wind Farm LLC1190 MW—Wind1
Windy Lane Energy Center, LLC2158 MW158 MWBattery storage1
Corazon Energy Storage, LLC1150 MW—Battery storage1
Santa Teresa Solar1150 MW150 MWBattery storage1
Solariant Capital, LLC2140 MW—Battery storage1
201LC 8me LLC2130 MW—Solar1

Manufacturers and contractors with a recorded New Mexico footprint

No plant, expansion or contract in the manufacturer record names New Mexico. The national suppliers below serve every state.

Order-by check derived

27 of the 27 planned units of 50 MW or more in New Mexico that are not yet under construction (2,395 of 2,395 MW) are past the date their step-up transformer had to be ordered to meet the planned in-service date. These units hold their schedules only if the equipment is already on order.

PlantTechnologyMWPlanned in serviceTransformer order-byTurbine order-byOwner
AC Ranch IISolar230 MWJun 2029May 2026—Lydian Energy
Blackwater Solar Center - NMSolar200 MWDec 2027Nov 2024—Blackwater Solar Center, LLC
Cunningham Solar IISolar196 MWApr 2027Mar 2024—Southwestern Public Service Co
Gallegos Wind Farm, Phase 1Wind190 MWNov 2028Oct 2025—Gallegos Wind Farm LLC
Corazon Energy StorageBattery storage150 MWSep 2027Aug 2024—Corazon Energy Storage, LLC
Rockmont Solar and Storage ProjectSolar100 MWDec 2027Nov 2024—201LC 8me LLC
Oso NegroBattery storage100 MWMay 2028Apr 2025—Oso Negro, LLC
Wildcat Solar Power Plant LLCSolar90 MWDec 2028Nov 2025—Solariant Capital, LLC
NTEC Gas PlantNatural gas60 MWJun 2028May 2025—Navajo Transitional Energy Company
NTEC Gas PlantNatural gas60 MWJun 2028May 2025—Navajo Transitional Energy Company
NTEC Gas PlantNatural gas60 MWJun 2028May 2025—Navajo Transitional Energy Company
NTEC Gas PlantNatural gas60 MWJun 2028May 2025—Navajo Transitional Energy Company

Lead times, OEM backlogs and the national generation and grid contractors are on the national supply chain section.

Demand

Data center and large-load demand in New Mexico

27 data centers run by 19 operators are identified in New Mexico. The full list by city is on the New Mexico Data Center Map page. Utilities report 1 large customer projects here to EEI.

UtilityCustomer or typeMW statedInvestment stated
PNM (TXNM)Meta—$800 million
Jobs and pay

The New Mexico jobs report, and who the build-out employs

Median pay, May 2025
Cashiers$30,120
Fast food and counter workers$28,700
Retail salespersons$33,300
All occupations$47,210
Construction laborers$38,400
Welders$59,840
HVAC mechanics$50,270
Plumbers and pipefitters$61,440
Electricians$58,390
Power plant operators$105,510
Power-line installers$76,470
Construction supervisors$75,130
Electrical engineers$158,520
Cashier median: $30,120

Payroll employment, August 2026 (preliminary)

IndustryJobsChange vs Aug 2025Change vs Aug 2019
Total nonfarm907.4k▲ 1.6%▲ 5.7% (+49.1k)
Construction57.6k▲ 4.7%▲ 12.3% (+6.3k)
Manufacturing28.2k▲ 1.4%▼ 1.7% (-0.5k)
Mining and logging26.5k▲ 5.6%▲ 1.1% (+0.3k)
Retail trade97.8k▲ 3.5%▲ 9.3% (+8.3k)

Power and data industries, 2019 to 2025

IndustryJobs 2019Jobs 2025ChangeAverage pay 2025
Data processing and hosting491997▲ 103.1%$143,827
Electrical contractors7,1528,443▲ 18.1%$77,364
Power and communication line construction1,5432,597▲ 68.3%$98,857
Electric power generation, transmission, distribution—2,699—$114,528
Transformer manufacturing—not disclosed——

Pay ladder, May 2025

OccupationEmploymentMedian annual payMultiple of cashier pay
Cashiers19,020$30,1201.00×
Fast food and counter workers28,250$28,7000.95×
Retail salespersons23,800$33,3001.11×
All occupations870,970$47,2101.57×
Construction laborers12,470$38,4001.27×
Welders2,390$59,8401.99×
HVAC mechanics1,950$50,2701.67×
Plumbers and pipefitters2,830$61,4402.04×
Electricians5,020$58,3901.94×
Power plant operators130$105,5103.50×
Power-line installers1,020$76,4702.54×
Construction supervisors6,790$75,1302.49×
Electrical engineers2,560$158,5205.26×

County-level contractor jobs and pay are in the county record above.

Economy

What the data center industry adds to New Mexico

3,920
Direct data center jobs (2024)
12,880
Total jobs supported, in state
$1.6B
Total GDP contribution
1.1%
Share of state GDP
$0.2B
State and local taxes

PwC figures are modeled estimates commissioned by the industry.

Policy

The rules and the pipeline in New Mexico

State measures 4

BillMeasureStatusDate
Executive OrderData center moratoriumProposed2026-09
Announced bill (2027 session)Proposed statewide data center moratoriumProposed2026-08
Proposed statewide moratorium on data centersProposed statewide moratorium on data centersProposed2026-07
SB 235New Mexico: SB 235 (Microgrid Oversight Act) would have required the Public Regulation Commission to develop rules for any microgrid producing more than 20 MWFailed / vetoed2026-01

Delay Watchlist projects 5

ProjectLocationStatusCauseMW
Project Jupiter (Santa Teresa / Doña Ana County)Santa Teresa (Doña Ana County)litigation activelitigationzoning denialcommunity oppositionfinancing—
Project Zenith (Roswell)Roswell (Chaves County)pending reviewcommunity opposition—
Meta Los Lunas Expansion (Phase 3)Los Lunas (Valencia County)pending reviewwater disputecommunity opposition—
Google Lea County data centerLea Countypending review—
Green Chile Project (gas pipeline for Project Jupiter)Dona Ana County (Project Jupiter pipeline)deniedzoning denialpermitinterconnectioncommunity opposition—

Local moratoria and restrictions (12) appear by county and city in the county-by-county section. Counts include every status in the weekly tracker feeds as of October 5, 2026. The New Mexico Data Center Map page counts only active local pauses and delayed or blocked projects as of its September 2 rebuild, so its figures are lower. The difference is one of definition and date.

Nearby states

New Mexico's neighbors

Questions

New Mexico power, answered from the record

How much new power generation is planned in New Mexico?

EIA's August 2026 inventory lists 3,965 MW of planned generators in New Mexico, 1,540 MW of it under construction or built. By capacity the pipeline is solar 43%, natural gas 29%, battery storage 23%. The largest single unit is AC Ranch II (230 MW, Lydian Energy). Owners plan to retire 354 MW from 2026 to 2030.

Who runs the power grid in New Mexico?

Non-RTO (utility-run) serves most of New Mexico, which means vertically integrated utilities plan and dispatch generation under the state commission. No data center load is tracked in its queues yet.

Is planned generation in New Mexico on schedule?

27 of 27 planned units of 50 MW or more not yet under construction are past the latest date to order a step-up transformer (more than 160 weeks) for their planned in-service date. They hold schedule only if equipment is already on order.

Are electricity prices rising in New Mexico?

Residential electricity averaged 15.08¢/kWh from January to July 2026, +2.8% on a year earlier, the 42nd fastest increase of 51. Commercial sales, the class that includes data centers, changed -0.3%.

Which counties in New Mexico have the most planned generation?

By planned nameplate capacity: San Juan County (1,729 MW), Lea County (721 MW), Bernalillo County (250 MW).

Which utilities report large-load projects in New Mexico?

Utilities report 1 large customer project in New Mexico to EEI, including PNM (TXNM).

Which data center projects are delayed in New Mexico?

The SAVRN Delay Watchlist names 5 projects in New Mexico, among them Project Jupiter (Santa Teresa / Doña Ana County), Project Zenith (Roswell), Meta Los Lunas Expansion (Phase 3).

Does New Mexico have a data center moratorium?

The SAVRN Moratorium Tracker holds 4 state-level measures (0 enacted) and 12 local moratoria or restrictions in New Mexico, 8 of them in force, 31st most in the country.

Across SAVRN

New Mexico across the SAVRN trackers

Sources

Sources for this page

Every figure links to its original source through the Sources buttons. Values marked derived are calculated from reported figures.