ISO-NE runs most of Rhode Island's grid. 718 MW of new generation is planned in Rhode Island, 715 MW of it under construction or built and awaiting operation, against 0 MW of planned retirements through 2030. 7 data centers are identified in the state. Residential electricity averaged 29.22¢/kWh in 2026 through July, -1.1% from a year earlier. Unemployment was 3.7% in August 2026, and construction employment is +9.4% against August 2019. The SAVRN trackers hold 5 local moratoria or restrictions for Rhode Island across all statuses (4 in force) and 1 named projects on the Delay Watchlist.

Rebuilt 2026-10-08 · refreshed weekly
Grid operator
ISO-NE
main wholesale grid
Planned generation
0.7 GW
0.7 GW under construction or built
Data center load in queues
—
7 data centers identified
Residential price
29.22¢
▼ 1.1% vs 2025, YTD July
Construction jobs
+9.4%
▲ 9.4% vs Aug 2019
Local measures
5
4 in force · 1 on Delay Watchlist
The finding

What the build-out changed in Rhode Island

Rhode Island is in the middle of the pack, with a few sharp signals worth watching. Planned generation equals 28% of the power plants Rhode Island runs today, one of the steepest build-outs in the country (10th). Commercial electricity sales, the class that includes data centers, are +1.6% year to date, 25th in the country. Electrical contractor jobs, the trade every data center, substation and plant needs first, grew 18.1% from 2019 to 2025, 28th in the country. The weak spot: data processing and hosting jobs, 2019 to 2025 ranks 36th of 46 at +21.4%.

Then and now

MeasureThenNowChangeU.S. rank
Construction jobs (Aug 2019 → Aug 2026)20.1k22.0k▲ 9.4%35th of 48
Electrical contractor jobs (2019 → 2025)2,4032,839▲ 18.1%28th of 48
Data processing and hosting jobs (2019 → 2025)569691▲ 21.4%36th of 46
Unemployment rate (Feb 2020 → Aug 2026)3.6%3.7%▲ 0.1pts—
Residential price, ¢/kWh (YTD Jul 2025 → 2026)29.55¢29.22¢▼ 1.1%50th of 51
Generation fleet → planned additions2.6 GW operating0.7 GW planned28% of fleet10th of 51

Where Rhode Island ranks among 51

Data center share of state GDP1.5%34th of 51
Planned generation vs. today's fleet28%10th of 51
Construction jobs vs. 2019+9.4%35th of 48
Electrical contractor jobs, 2019 to 2025+18.1%28th of 48
Data processing and hosting jobs, 2019 to 2025+21.4%36th of 46
Commercial electricity sales, YTD change+1.6%25th of 51
Residential electricity price, YTD change-1.1%50th of 51
Local moratoria and restrictions540th of 49

1st = the most. Ranks cover every state and DC that publishes the figure.

Among its neighbors, Rhode Island leads on planned generation vs. today's fleet (28%), ahead of Connecticut (6%).

County spotlight

Providence County holds the most data centers on record in Rhode Island (7), and its electrical contractor workforce changed +25.9% since 2019 to 1,492 jobs. The largest share of planned generation sits in Washington County: 715 MW, led by Orsted Wind Power North America LLC (wind).

The map

Where Rhode Island sits in the power system

Grid operator
ISO-NE
Operating capacity
2.6 GW
Planned generation
718 MW
Under construction or built
715 MW
Data centers identified
7
Data center load in queues
—
Unemployment, Aug 2026
3.7%
Residential price change
-1.1%

Neighboring states are shaded. Select one to open its page.

Counties and cities

Rhode Island, county by county

5 counties in Rhode Island. Planned generation sits in 2 of them, data centers stand in 1, and local measures are on record in 0. Pick a layer, then select a county for its full record.

Newport CountyKent CountyProvidence CountyWashington CountyBristol County

County leaders

Most planned generation
Most data centers
Fastest electrical contractor growth
Providence County1,492 jobs+25.9%

Counties on record 2

CountyData centersPlanned MWBuilding MWLead developerElectrical contractor jobsChange 2019–25Local measuresWatchlist
Providence County74 MW—Hope Solar One, LLC1,492▲ 25.9%——
Washington County—715 MW715 MWOrsted Wind Power North America LLC————

Every county in Rhode Island 5

Each county has its own page: power plants, utilities and prices, jobs since 2019, data centers, local rules and its neighbors.

Cities and towns on record 6

City or townCountyData centersLocal measuresWatchlistLatest record
ProvidenceProvidence County7———
SmithfieldProvidence County—1 (1 in force)1Zoning ban on data centers in all districts In force
CharlestownWashington County + Washington County—1 (1 in force)—Zoning ban on data centers and battery storage In force
CumberlandProvidence County—1 (1 in force)—Zoning ordinance listing data centers as a prohibited use In force
HopkintonWashington County + Washington County—1 (0 in force)—Zoning amendment prohibiting data centers, hearing set Proposed
WesterlyWashington County + Washington County—1 (1 in force)—Town moratorium on data centers through July 27, 2027 In force

Data center counts come from every facility on the SAVRN Data Center Map, counted in the county and the city or community where each building physically stands (Census boundaries), not its mailing address. Jurisdictions appear as the Moratorium Tracker records them.

The chain

Rhode Island, from generation to the household bill

1Grid operator

Data center projects in forecast framework
2 projects

2Generation pipeline

Operating capacity
2.6 GW
Planned, all types
718 MW
Under construction or built
715 MW
Planned gas
0 MW
Planned retirements 2026–30
0 MW
Net firm additions derived
715 MW

3Data center demand

Data centers identified
7
Operators
3
Load in tracked queues
—
Utility large-load projects
0
Commercial sales, YTD change
+1.6%
Industry share of state GDP
1.5%

4Jobs and pay

Unemployment, Aug 2026
3.7% (-0.6 pts y/y)
Construction jobs vs 2019
+9.4%
Manufacturing jobs vs 2019
+1.2%
Electrical contractor jobs 2019–25
+18.1%
Electrician median pay
$74,090
Electrician ÷ cashier pay
2.13×

5Household bill

Residential price, YTD Jul 2026
29.22¢/kWh
Change vs YTD 2025
-1.1%
All-sector price change
-0.4%
Total retail sales change
+0.7%

6Policy friction

State measures on record
3
Local measures (in force)
5 (4)
Watchlist projects
1
Lawsuits tracked
0
Announced capital, disclosed
—
Dedicated tax incentive
None listed
Generation

Planned power plants in Rhode Island

Every planned generator in Rhode Island in the August 2026 EIA-860M inventory, by technology, then the 15 largest units. Under construction or built covers status codes U, V and TS.

Planned generation by fuel 718 MW
Wind 715 MW 100%Solar 4 MW <1%
Under construction or built 715 MW
Wind 715 MW 100%
TechnologyUnitsPlanned MWUnder construction or built
Wind1715 MW715 MW
Solar14 MW—

Largest planned generators

PlantCountyTechnologyMWStatusYearOwner
Revolution WindWashingtonOffshore Wind Turbine715 MWUnder construction (>50%)2026Orsted Wind Power North America LLC
Hope Solar OneProvidenceSolar Photovoltaic4 MWPlanned, approvals not started2028Hope Solar One, LLC
Supply chain

What the Rhode Island build-out runs on

Who is building generation in Rhode Island, which manufacturers and contractors have a plant, expansion or contract recorded here, and how long the critical equipment takes to arrive.

Developers and owners with planned generation

Developer or ownerUnitsPlanned MWBuilding MWMain technologyCounties
Orsted Wind Power North America LLC1715 MW715 MWWind1
Hope Solar One, LLC14 MW—Solar1

Manufacturers and contractors with a recorded Rhode Island footprint

No plant, expansion or contract in the manufacturer record names Rhode Island. The national suppliers below serve every state.

Order-by check

No planned unit of 50 MW or more in Rhode Island is still waiting on equipment orders.

Lead times, OEM backlogs and the national generation and grid contractors are on the national supply chain section.

Demand

Data center and large-load demand in Rhode Island

7 data centers run by 3 operators are identified in Rhode Island. The full list by city is on the Rhode Island Data Center Map page. Utilities report 0 large customer projects here to EEI.

No large customer projects reported to EEI for this state.

Jobs and pay

The Rhode Island jobs report, and who the build-out employs

Median pay, May 2025
Cashiers$34,860
Fast food and counter workers$31,490
Retail salespersons$34,860
All occupations$56,780
Construction laborers$57,240
Welders$50,580
HVAC mechanics$67,370
Plumbers and pipefitters$76,470
Electricians$74,090
Power plant operators$98,050
Power-line installers$104,620
Construction supervisors$98,590
Cashier median: $34,860

Payroll employment, August 2026 (preliminary)

IndustryJobsChange vs Aug 2025Change vs Aug 2019
Total nonfarm515.1k▲ 0.1%▲ 1.9% (+9.8k)
Construction22.0k▼ 3.1%▲ 9.4% (+1.9k)
Manufacturing40.4k▲ 3.3%▲ 1.2% (+0.5k)
Mining and logging0.2k● 0.0%● 0.0% (+0.0k)
Retail trade46.0k▼ 0.7%▼ 3.8% (-1.8k)

Power and data industries, 2019 to 2025

IndustryJobs 2019Jobs 2025ChangeAverage pay 2025
Data processing and hosting569691▲ 21.4%$196,406
Electrical contractors2,4032,839▲ 18.1%$85,224
Power and communication line construction—not disclosed——
Electric power generation, transmission, distribution—1,268—$139,715

Pay ladder, May 2025

OccupationEmploymentMedian annual payMultiple of cashier pay
Cashiers9,260$34,8601.00×
Fast food and counter workers13,310$31,4900.90×
Retail salespersons12,830$34,8601.00×
All occupations501,340$56,7801.63×
Construction laborers2,110$57,2401.64×
Welders2,300$50,5801.45×
HVAC mechanics1,450$67,3701.93×
Plumbers and pipefitters1,820$76,4702.19×
Electricians2,420$74,0902.13×
Power plant operators50$98,0502.81×
Power-line installers120$104,6203.00×
Construction supervisors2,060$98,5902.83×
Electrical engineers670——

County-level contractor jobs and pay are in the county record above.

Economy

What the data center industry adds to Rhode Island

2,190
Direct data center jobs (2024)
9,180
Total jobs supported, in state
$1.2B
Total GDP contribution
1.5%
Share of state GDP
$0.1B
State and local taxes

PwC figures are modeled estimates commissioned by the industry.

Policy

The rules and the pipeline in Rhode Island

State measures 3

BillMeasureStatusDate
S2776Data-center grid-cost and water guardrailsFailed / vetoed2026-06
H7695Establishes property, tangible, sales and use tax exemptions as incentives for the location of qualified data centers in Rhode Island.Proposed2026-05
HB 6476AN ACT RELATING TO STATE AFFAIRS AND GOVERNMENT -- QUALIFIED DATA CENTERS LOCATION INCENTIVE (Establishes incentives for property sales and use tax exemptions)Failed / vetoed2021-06

Delay Watchlist projects 1

ProjectLocationStatusCauseMW
Smithfield Data Center (Hanton City Investments)Smithfieldlitigation activezoning denial—

Local moratoria and restrictions (5) appear by county and city in the county-by-county section. Counts include every status in the weekly tracker feeds as of October 5, 2026. The Rhode Island Data Center Map page counts only active local pauses and delayed or blocked projects as of its September 2 rebuild, so its figures are lower. The difference is one of definition and date.

Nearby states

Rhode Island's neighbors

Questions

Rhode Island power, answered from the record

How much new power generation is planned in Rhode Island?

EIA's August 2026 inventory lists 718 MW of planned generators in Rhode Island, 715 MW of it under construction or built. By capacity the pipeline is wind 100%, solar 0%. The largest single unit is Revolution Wind (715 MW, Orsted Wind Power North America LLC). Owners plan to retire 0 MW from 2026 to 2030.

Who runs the power grid in Rhode Island?

ISO-NE serves most of Rhode Island as the regional wholesale market and grid operator. No data center load is tracked in its queues yet.

Are electricity prices rising in Rhode Island?

Residential electricity averaged 29.22¢/kWh from January to July 2026, -1.1% on a year earlier, one of the few jurisdictions where it fell. Commercial sales, the class that includes data centers, changed +1.6%.

What do electricians earn in Rhode Island?

The median electrician in Rhode Island earned $74,090 in May 2025, 2.13 times the median cashier, and power-line installers earned $104,620 (BLS OEWS).

Which counties in Rhode Island have the most planned generation?

By planned nameplate capacity: Washington County (715 MW), Providence County (4 MW).

Which data center projects are delayed in Rhode Island?

The SAVRN Delay Watchlist names 1 project in Rhode Island, among them Smithfield Data Center (Hanton City Investments).

Who is building power plants in Rhode Island?

The largest owners of planned generation are Orsted Wind Power North America LLC (715 MW, mostly wind), Hope Solar One, LLC (4 MW, mostly solar) (EIA-860M).

Does Rhode Island have a data center moratorium?

The SAVRN Moratorium Tracker holds 3 state-level measures (0 enacted) and 5 local moratoria or restrictions in Rhode Island, 4 of them in force, 40th most in the country.

Across SAVRN

Rhode Island across the SAVRN trackers

Sources

Sources for this page