Power Supply Chain and Demand in Massachusetts

Seal of Massachusetts

ISO-NE runs most of Massachusetts's grid. 727 MW of new generation is planned in Massachusetts, 252 MW of it under construction or built and awaiting operation, against 1 MW of planned retirements through 2030. 53 data centers are identified in the state. Residential electricity averaged 30.14¢/kWh in 2026 through July, -0.3% from a year earlier. Unemployment was 4.3% in August 2026, and construction employment is +2.4% against August 2019. The SAVRN trackers hold 17 local moratoria or restrictions for Massachusetts across all statuses (10 in force) and 4 named projects on the Delay Watchlist.

Rebuilt 2026-10-08 · refreshed weekly
Grid operator
ISO-NE
main wholesale grid
Planned generation
0.7 GW
0.3 GW under construction or built
Data center load in queues
—
53 data centers identified
Residential price
30.14¢
▼ 0.3% vs 2025, YTD July
Construction jobs
+2.4%
▲ 2.4% vs Aug 2019
Local measures
17
10 in force · 4 on Delay Watchlist
The finding

What the build-out changed in Massachusetts

Massachusetts is in the middle of the pack, with a few sharp signals worth watching. The data center industry now accounts for 2.6% of Massachusetts's economy, the 10th largest share of any state (the median state is 1.8%), counting the industry's in-state suppliers and payrolls. Data processing and hosting jobs grew 22.6% from 2019 to 2025, 34th of 46 states that disclose the industry. Commercial electricity sales, the class that includes data centers, are -0.2% year to date, 39th in the country. The weak spot: electrical contractor jobs, 2019 to 2025 ranks 45th of 48 at +3.4%. Factory employment is the exception: manufacturing jobs are -5.9% against August 2019.

Then and now

MeasureThenNowChangeU.S. rank
Construction jobs (Aug 2019 → Aug 2026)163.9k167.9k▲ 2.4%41st of 48
Electrical contractor jobs (2019 → 2025)24,34225,179▲ 3.4%45th of 48
Power line construction jobs (2019 → 2025)3,2103,187▼ 0.7%35th of 44
Data processing and hosting jobs (2019 → 2025)8,1229,960▲ 22.6%34th of 46
Unemployment rate (Feb 2020 → Aug 2026)3.1%4.3%▲ 1.2pts—
Residential price, ¢/kWh (YTD Jul 2025 → 2026)30.22¢30.14¢▼ 0.3%49th of 51
Generation fleet → planned additions14.0 GW operating0.7 GW planned5% of fleet44th of 51

Where Massachusetts ranks among 51

Data center share of state GDP2.6%10th of 51
Planned generation vs. today's fleet5%44th of 51
Construction jobs vs. 2019+2.4%41st of 48
Electrical contractor jobs, 2019 to 2025+3.4%45th of 48
Power line construction jobs, 2019 to 2025-0.7%35th of 44
Data processing and hosting jobs, 2019 to 2025+22.6%34th of 46
Commercial electricity sales, YTD change-0.2%39th of 51
Residential electricity price, YTD change-0.3%49th of 51
Local moratoria and restrictions1727th of 49

1st = the most. Ranks cover every state and DC that publishes the figure.

Among its neighbors, Massachusetts leads on data center share of state gdp (2.6%), ahead of New Hampshire (2.4%).

County spotlight

Middlesex County holds the most data centers on record in Massachusetts (22), and its electrical contractor workforce changed -7.5% since 2019 to 6,744 jobs. The largest share of planned generation sits in Suffolk County: 250 MW, led by Energizar Storage LLC (battery storage). The fastest-growing electrical trade market is Plymouth County, where contractor jobs grew 23.9% to 3,101.

The map

Where Massachusetts sits in the power system

Grid operator
ISO-NE
Operating capacity
14.0 GW
Planned generation
727 MW
Under construction or built
252 MW
Data centers identified
53
Data center load in queues
—
Unemployment, Aug 2026
4.3%
Residential price change
-0.3%

Neighboring states are shaded. Select one to open its page.

Counties and cities

Massachusetts, county by county

14 counties in Massachusetts. Planned generation sits in 8 of them, data centers stand in 7, and local measures are on record in 1. Pick a layer, then select a county for its full record.

Suffolk CountyFranklin CountyPlymouth CountyBerkshire CountyBristol CountyNorfolk CountyNantucket CountyHampden CountyEssex CountyWorcester CountyHampshire CountyDukes CountyBarnstable CountyMiddlesex County

County leaders

Most planned generation
Suffolk Countybattery storage250 MW
Worcester Countybattery storage205 MW
Bristol Countybattery storage189 MW
Plymouth Countysolar52 MW
Norfolk Countybattery storage11 MW
Hampden Countybattery storage10 MW
Essex Countybattery storage5 MW
Middlesex Countybattery storage5 MW
Fastest electrical contractor growth
Plymouth County3,101 jobs+23.9%
Bristol County1,855 jobs+20.5%
Hampden County1,405 jobs+13.5%
Essex County2,175 jobs+7.1%
Worcester County2,117 jobs+5.0%
Berkshire County477 jobs+4.6%
Norfolk County3,794 jobs+4.0%

Counties on record 9

CountyData centersPlanned MWBuilding MWLead developerElectrical contractor jobsChange 2019–25Local measuresWatchlist
Middlesex County225 MW5 MWUriel Renovables S.A6,744▼ 7.5%1 (0 in force)—
Worcester County8205 MW205 MWFE Taft LLC2,117▲ 5.0%——
Hampden County710 MW10 MWHolyoke MA BESS 1 LLC1,405▲ 13.5%——
Suffolk County6250 MW—Energizar Storage LLC1,719▼ 21.5%——
Plymouth County352 MW6 MWReWild Renewables, LLC3,101▲ 23.9%——
Essex County35 MW5 MWIpswich MA BESS 1 LLC2,175▲ 7.1%——
Norfolk County211 MW11 MWMountain Street Solar Project 2019, LLC3,794▲ 4.0%——
Bristol County—189 MW10 MWSomerset Energy Storage, LLC1,855▲ 20.5%——
Berkshire County————477▲ 4.6%——

Every county in Massachusetts 14

Each county has its own page: power plants, utilities and prices, jobs since 2019, data centers, local rules and its neighbors.

Cities and towns on record 28

City or townCountyData centersLocal measuresWatchlistLatest record
BostonSuffolk County61 (0 in force)—Proposed citywide zoning ban on data centers Proposed
SpringfieldHampden County6———
WalthamMiddlesex County5———
SomervilleMiddlesex County4———
CambridgeMiddlesex County3———
WorcesterWorcester County3———
LowellMiddlesex County21 (1 in force)2360-day data center moratorium In force
NeedhamNorfolk County + Norfolk County2———
RocklandPlymouth County2———
HolyokeHampden County11 (1 in force)—City moratorium on data centers with no end date In force
LynnEssex County1———
MarlboroughMiddlesex County1———
MedfordMiddlesex County1———
WakefieldMiddlesex County + Middlesex County1———
WatertownMiddlesex County1———
WestfieldHampden County—1 (1 in force)2City moratorium on data centers through July 6, 2027 In force
Agawam——1 (1 in force)—City moratorium on data centers through June 3, 2027 In force
City of WestfieldHampden County—1 (1 in force)—City of Westfield (1-year data center moratorium, final vote) data center moratorium In force
GreenfieldFranklin County—1 (1 in force)—Greenfield one-year data center moratorium In force
LeominsterWorcester County—1 (1 in force)—Data center moratorium through July 31, 2027 In force
MansfieldBristol County—1 (1 in force)—Zoning bylaw barring data centers above 2 MW In force
NorthamptonHampshire County—1 (0 in force)—Proposed city moratorium on data centers Proposed
PlymouthPlymouth County + Plymouth County—1 (0 in force)—Proposed town moratorium on data centers Proposed
SalemEssex County—1 (1 in force)—Data center permit revocation upheld; citywide ban proposed In force
ShutesburyFranklin County—1 (1 in force)—Shutesbury data center moratorium In force
Southbridge——1 (0 in force)—Proposed town moratorium on data centers Proposed
SpencerWorcester County + Worcester County—1 (0 in force)—Proposed data center moratorium Proposed
WilmingtonMiddlesex County + Middlesex County—1 (0 in force)—Wilmington proposed zoning bylaw prohibiting data centers over 2 MW Proposed

Data center counts come from every facility on the SAVRN Data Center Map, counted in the county and the city or community where each building physically stands (Census boundaries), not its mailing address. Jurisdictions appear as the Moratorium Tracker records them.

The chain

Massachusetts, from generation to the household bill

1Grid operator

Data center projects in forecast framework
2 projects

2Generation pipeline

Operating capacity
14.0 GW
Planned, all types
727 MW
Under construction or built
252 MW
Planned gas
0 MW
Planned retirements 2026–30
1 MW
Net firm additions derived
250 MW

3Data center demand

Data centers identified
53
Operators
32
Load in tracked queues
—
Utility large-load projects
0
Commercial sales, YTD change
-0.2%
Industry share of state GDP
2.6%

4Jobs and pay

Unemployment, Aug 2026
4.3% (-0.2 pts y/y)
Construction jobs vs 2019
+2.4%
Manufacturing jobs vs 2019
-5.9%
Electrical contractor jobs 2019–25
+3.4%
Electrician median pay
$79,420
Electrician ÷ cashier pay
2.24×

5Household bill

Residential price, YTD Jul 2026
30.14¢/kWh
Change vs YTD 2025
-0.3%
All-sector price change
+3.2%
Total retail sales change
+1.0%

6Policy friction

State measures on record
5
Local measures (in force)
17 (10)
Watchlist projects
4
Lawsuits tracked
0
Announced capital, disclosed
—
Dedicated tax incentive
Yes
Generation

Planned power plants in Massachusetts

Every planned generator in Massachusetts in the August 2026 EIA-860M inventory, by technology, then the 15 largest units. Under construction or built covers status codes U, V and TS.

Planned generation by fuel 727 MW
Solar 55 MW 8%Battery storage 672 MW 92%
Under construction or built 252 MW
Solar 18 MW 7%Battery storage 234 MW 93%
TechnologyUnitsPlanned MWUnder construction or built
Battery storage17672 MW234 MW
Solar1455 MW18 MW

Largest planned generators

PlantCountyTechnologyMWStatusYearOwner
Energizar BESSSuffolkBatteries250 MWApprovals pending2027Energizar Storage LLC
Taft BESSWorcesterBatteries200 MWUnder construction (>50%)2027FE Taft LLC
Salt Cod BESSBristolBatteries168 MWApprovals pending2028Somerset Energy Storage, LLC
Town of Sharon Portfolio -Mt St LandfillNorfolkBatteries6 MWUnder construction (>50%)2027Mountain Street Solar Project 2019, LLC
Town of Sharon Portfolio -Mt St LandfillNorfolkSolar Photovoltaic5 MWUnder construction (>50%)2027Mountain Street Solar Project 2019, LLC
Logging Swamp SouthPlymouthSolar Photovoltaic5 MWApprovals received2027ReWild Renewables, LLC
Logging Swamp NorthPlymouthSolar Photovoltaic5 MWApprovals received2027ReWild Renewables, LLC
Clems Way SolarBristolSolar Photovoltaic5 MWApprovals received2027ReWild Renewables, LLC
Randall Lane SolarPlymouthSolar Photovoltaic5 MWApprovals pending2027ReWild Renewables, LLC
Randall Lane SolarPlymouthBatteries5 MWApprovals pending2027ReWild Renewables, LLC
Braley Hill North SolarPlymouthSolar Photovoltaic5 MWApprovals pending2027Agilitas Energy, Inc.
Braley Hill North SolarPlymouthBatteries5 MWApprovals pending2027Agilitas Energy, Inc.
Holyoke MA BESS 1HampdenBatteries5 MWUnder construction (≤50%)2026Holyoke MA BESS 1 LLC
Borrego - Highland AveBristolBatteries5 MWUnder construction (≤50%)2026Highland Ave Solar 1, LLC
Ipswich MA BESS 1EssexBatteries5 MWUnder construction (≤50%)2026Ipswich MA BESS 1 LLC
Supply chain

What the Massachusetts build-out runs on

Who is building generation in Massachusetts, which manufacturers and contractors have a plant, expansion or contract recorded here, and how long the critical equipment takes to arrive.

Developers and owners with planned generation

Developer or ownerUnitsPlanned MWBuilding MWMain technologyCounties
Energizar Storage LLC1250 MW—Battery storage1
FE Taft LLC1200 MW200 MWBattery storage1
Somerset Energy Storage, LLC1168 MW—Battery storage1
ReWild Renewables, LLC933 MW—Solar2
Agilitas Energy, Inc.418 MW—Battery storage1
Mountain Street Solar Project 2019, LLC211 MW11 MWBattery storage1
Highland Ave Solar 1, LLC210 MW10 MWSolar1
Uriel Renovables S.A210 MW10 MWBattery storage2
TJA 540R Main St. Acushnet, LLC26 MW—Solar1
Holyoke MA BESS 1 LLC15 MW5 MWBattery storage1
Ipswich MA BESS 1 LLC15 MW5 MWBattery storage1
Madison Energy Investments LLC15 MW5 MWSolar1
Solar Carver 1, LLC24 MW4 MWBattery storage1
Solar Carver 3, LLC22 MW2 MWBattery storage1

Manufacturers and contractors with a recorded Massachusetts footprint

No plant, expansion or contract in the manufacturer record names Massachusetts. The national suppliers below serve every state.

Order-by check derived

2 of the 2 planned units of 50 MW or more in Massachusetts that are not yet under construction (418 of 418 MW) are past the date their step-up transformer had to be ordered to meet the planned in-service date. These units hold their schedules only if the equipment is already on order.

PlantTechnologyMWPlanned in serviceTransformer order-byTurbine order-byOwner
Energizar BESSBattery storage250 MWSep 2027Aug 2024—Energizar Storage LLC
Salt Cod BESSBattery storage168 MWDec 2028Nov 2025—Somerset Energy Storage, LLC

Lead times, OEM backlogs and the national generation and grid contractors are on the national supply chain section.

Demand

Data center and large-load demand in Massachusetts

53 data centers run by 32 operators are identified in Massachusetts. The full list by city is on the Massachusetts Data Center Map page. Utilities report 0 large customer projects here to EEI.

No large customer projects reported to EEI for this state.

Jobs and pay

The Massachusetts jobs report, and who the build-out employs

Median pay, May 2025
Cashiers$35,520
Fast food and counter workers$35,850
Retail salespersons$36,610
All occupations$63,590
Construction laborers$63,390
Welders$62,570
HVAC mechanics$77,300
Plumbers and pipefitters$93,880
Electricians$79,420
Power plant operators$100,140
Power-line installers$110,210
Construction supervisors$97,850
Electrical engineers$127,720
Cashier median: $35,520

Payroll employment, August 2026 (preliminary)

IndustryJobsChange vs Aug 2025Change vs Aug 2019
Total nonfarm3,706.0k▲ 0.2%▼ 0.2% (-9.0k)
Construction167.9k▲ 1.4%▲ 2.4% (+4.0k)
Manufacturing229.7k▲ 1.8%▼ 5.9% (-14.4k)
Mining and logging1.1k▲ 10.0%▲ 10.0% (+0.1k)
Retail trade317.3k▼ 1.1%▼ 9.7% (-34.0k)

Power and data industries, 2019 to 2025

IndustryJobs 2019Jobs 2025ChangeAverage pay 2025
Data processing and hosting8,1229,960▲ 22.6%$292,029
Electrical contractors24,34225,179▲ 3.4%$103,755
Power and communication line construction3,2103,187▼ 0.7%$174,450
Electric power generation, transmission, distribution—8,605—$160,333
Transformer manufacturing—114—$132,808

Pay ladder, May 2025

OccupationEmploymentMedian annual payMultiple of cashier pay
Cashiers58,880$35,5201.00×
Fast food and counter workers85,810$35,8501.01×
Retail salespersons86,860$36,6101.03×
All occupations3,637,650$63,5901.79×
Construction laborers16,210$63,3901.78×
Welders2,830$62,5701.76×
HVAC mechanics8,200$77,3002.18×
Plumbers and pipefitters13,460$93,8802.64×
Electricians17,810$79,4202.24×
Power plant operators880$100,1402.82×
Power-line installers2,350$110,2103.10×
Construction supervisors18,330$97,8502.75×
Electrical engineers5,040$127,7203.60×

County-level contractor jobs and pay are in the county record above.

Economy

What the data center industry adds to Massachusetts

23,020
Direct data center jobs (2024)
99,120
Total jobs supported, in state
$20.4B
Total GDP contribution
2.6%
Share of state GDP
$1.9B
State and local taxes

PwC figures are modeled estimates commissioned by the industry.

Policy

The rules and the pipeline in Massachusetts

State measures 5

BillMeasureStatusDate
Executive Order No. 658Local approval and clean energy requirements for data centersIn force2026-09
Executive OrderHealey's New Data Center RulesIn force2026-09
Senate amendmentProposed one-year data-center moratoriumFailed / vetoed2026-07
Administrative hold (June 2026)Hold on data center sales and use tax exemption applicationsPaused2026-06
Massachusetts House (rejects Rep. Pease budget amendment for data center impact study commission)Massachusetts House rejected without debate a Republican budget amendment (Rep. Kelly Pease) that would have created a commission to study data centers'Failed / vetoed2026-05

Delay Watchlist projects 4

ProjectLocationStatusCauseMW
Markley Group Lowell ExpansionLowelllitigation activelitigationenvironmental review—
Markley Group Lowell Data Center Generator ExpansionLowelllitigation activelitigationcommunity opposition—
Westfield Data Center ($4B)Westfielddelayedcommunity opposition—
Servistar Realties WestfieldWestfielddelayedfinancing—

Local moratoria and restrictions (17) appear by county and city in the county-by-county section. Counts include every status in the weekly tracker feeds as of October 5, 2026. The Massachusetts Data Center Map page counts only active local pauses and delayed or blocked projects as of its September 2 rebuild, so its figures are lower. The difference is one of definition and date.

Nearby states

Massachusetts's neighbors

Questions

Massachusetts power, answered from the record

How much new power generation is planned in Massachusetts?

EIA's August 2026 inventory lists 727 MW of planned generators in Massachusetts, 252 MW of it under construction or built. By capacity the pipeline is battery storage 92%, solar 8%. The largest single unit is Energizar BESS (250 MW, Energizar Storage LLC). Owners plan to retire 1 MW from 2026 to 2030.

Who runs the power grid in Massachusetts?

ISO-NE serves most of Massachusetts as the regional wholesale market and grid operator. No data center load is tracked in its queues yet.

Are electricity prices rising in Massachusetts?

Residential electricity averaged 30.14¢/kWh from January to July 2026, -0.3% on a year earlier, one of the few jurisdictions where it fell. Commercial sales, the class that includes data centers, changed -0.2%.

Is planned generation in Massachusetts on schedule?

2 of 2 planned units of 50 MW or more not yet under construction are past the latest date to order a step-up transformer (more than 160 weeks) for their planned in-service date. They hold schedule only if equipment is already on order.

How much do data centers add to the Massachusetts economy?

PwC's 2026 study for the Data Center Coalition credits the industry with 99,120 in-state jobs, $20.4B of GDP (2.6% of the state economy, 10th of 51) and $1.9B in state and local taxes in 2024. These are modeled estimates commissioned by the industry.

Where are the data centers in Massachusetts?

53 data centers run by 32 operators are identified in Massachusetts. The largest clusters are in Middlesex County (22), Worcester County (8), Hampden County (7).

What do electricians earn in Massachusetts?

The median electrician in Massachusetts earned $79,420 in May 2025, 2.24 times the median cashier, and power-line installers earned $110,210 (BLS OEWS).

Does Massachusetts have a data center moratorium?

The SAVRN Moratorium Tracker holds 5 state-level measures (2 enacted) and 17 local moratoria or restrictions in Massachusetts, 10 of them in force, 27th most in the country.

Across SAVRN

Massachusetts across the SAVRN trackers

Sources

Sources for this page

Every figure links to its original source through the Sources buttons. Values marked derived are calculated from reported figures.