SAVRN Index · Data center developer

Equinix Data Center Capex and Sites

NASDAQ:EQIX equinix.com ↗
Follow this profile Is this your company? Send a correction

Equinix guided to $4-5B of capex per year through 2029, up from $3.3B in 2025, exceeding the $3-4B per year framing in the brief. It agreed to form a greater-than-$15B xScale joint venture with GIC and CPP Investments on a 37.5%/37.5%/25% split targeting more than 1.5 GW in the United States, with $15B planned, roughly $6B invested and 750+ MW committed as of its 2025 Analyst Day. It remains one of two developers still pursuing three proposed mega data centers in Seattle City Light territory that were captured by Seattle's one-year moratorium.

Updated October 8, 2026Capital record from the Capital Atlas
Named sites
2
Site commitments on record for Equinix
Disclosed site capital
$836M
Named sites with a stated dollar figure. A floor, not a capex total
Disclosed capacity
54 MW
Named sites with a stated megawatt figure
Financing transactions
3
Transactions naming Equinix or one of its sites
Sources
15
Every cited page, listed below
MarketMarket data from TradingView, delayed
Loading NASDAQ:EQIX from TradingView
Spending

Reported and guided spending

Audited, reported and guided figures as the filing or release states them. Reported lines are what was spent, and guidance is what management expects. They sit side by side and are never combined.

PeriodKindAmountAs statedSources
2026-2029 guidance $4.5B
superseded: guided to $4-5B per year through 2029 per S&P (June 2025); Equinix's own Q2 2026 release gives the prior outlook as $3-4B per year and raises it to $5-7B for 2027-2029
2027-2029 guidance $6.0B
Total capital expenditures annual range $5,000-7,000 million for 2027-2029, excluding M&A, real estate acquisitions and xScale JV investments; midpoint recorded; 2026 guided at $5.0-6.0 billion (Q2 2026 results, 29 July 2026)
FY2025 reported $3.3B
$3.3B in 2025
2025 Analyst Day aum ≥$15.0B
xScale: $15B planned, ~$6B invested, and 750+ MW committed
Named sites

Where Equinix builds

SiteStatePlaceCapitalMWStatusSources
Equinix DA12 data center (1550 West Mockingbird Lane)
with Margulies Hoelzli Architecture (design)
Texas Dallas, Dallas County ≥$836M n.a. under construction
Equinix proposed SoDo data center (nine-story, 54 MW)
Moratorium adopted 9 June 2026; project reported vested and advancing 3 October 2026 (environmental permit documents submitted to the state June 2026)
Washington Seattle n.a. 54 proposed
Financing

Financing transactions

Transactions that name Equinix as a party or attach to one of its named sites. Amounts are as stated, and overlapping commitments are never summed.

PartiesInstrumentAmountDateSiteSources
Equinix + GIC + CPP Investments
Equinix agreed to form a greater-than-$15B xScale joint venture with GIC and CPP Investments targeting more than 1.5 GW in the United States, with 750+ MW committed as of the 2025 Analyst Day.
jv equity $15.0B
agreement announced; as of 2025 Analyst Day $15B planned, ~$6B invested
n.a.
Equinix + Bank of America + BNP Paribas + Citibank + Goldman Sachs + HSBC + JPMorgan Chase + MUFG
Equinix entered a $5.5 billion revolving credit agreement with Bank of America as administrative agent. Proceeds are available for working capital, capital expenditures, acquisitions and general corporate purposes
debt facility $5.5B
Entered 27 July 2026
n.a.
Equinix + Equinix Europe 2 Financing Corporation LLC
Equinix and a finance subsidiary sold $3.0 billion of senior unsecured notes in four tranches under underwriting agreements dated 30 July 2026. The 2031 notes were issued by Equinix Europe 2 Financing Corporation and guaranteed by Equinix
project bond ~$3.0B
Priced 30 July 2026; issued 6 August 2026
n.a.
The record

Sourced facts on Equinix

  • Equinix and Prologis are the two remaining developers still pursuing three of five originally proposed mega data centers in Seattle City Light territory after two developers withdrew.
  • The Seattle projects sat inside the 369 MW that four companies asked Seattle City Light about in April 2026, and were captured by Seattle's one-year moratorium on data centers above 20 MVA, adopted 9-0 on June 9, 2026 with an option to extend six months.
  • Site-level Virginia, Texas and Chicago delay disclosures were n.a. in the fetched record.
Data center developer

More in the Index

Capital figures come from the Capital Atlas, refreshed every Tuesday, Thursday and Saturday. Site commitments overlap reported capital expenditure and overlap one another, so each figure appears as its source states it and none are added into a single deployment number. Informational, not investment advice.

The SAVRN reference set

Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.