SAVRN Research · Capital Atlas · Washington

Washington Data Center Investment Tracker

Washington carries 9 named site commitments, set against 22 projects blocked, delayed or restricted, 21 of them moratoria or delays, as of October 8, 2026.

Updated October 8, 2026 9 named sites 22 blocked, delayed or restricted 0 financing transactions 35 sources
Washington
WA
8 capital providers on record
Named sites
9
Site-level commitments the atlas records in Washington
Disclosed capital floor
n.a.
Sum of sites with a stated dollar figure. Sites without one are listed, not counted
Disclosed capacity
453 MW
Sum of sites with a stated megawatt figure
Blocked, delayed or restricted
22
$200M of announced capital in those projects
Who is investing

Who is investing in data centers in Washington?

The named commitments in Washington carry no disclosed dollar figure yet. The record is Voltage Park, Digital Realty Trust, Equinix, Microsoft (Azure), Sabey Data Centers, Vantage Data Centers.
Named sites

Named data center sites in Washington

Each row is one site-level commitment with its capital provider, the figure the source states, and the status the source gives it. Capital is shown as one compact figure; the verbatim wording is in the row's sources.

SiteCapital providerPlaceCapitalMWStatusSources
Merkle Standard data center, former Ponderay Newsprint papermill
PUD discussions since 2024; reported 25 September 2026 from records; no formal application; single outlet
Merkle Standard Infrastructure (owned by Allrise Capital Inc.)
with Pend Oreille County Public Utility District (power study)
Usk, Pend Oreille County n.a. 225 proposed
Vantage Quincy campus
Vantage Data Centers Quincy n.a. 89 operating
Sabey Quincy campus, 2200 M St NE
launched 2011; expansion completed 2023
Sabey Data Centers Quincy, Grant n.a. 85 operating
Equinix proposed SoDo data center (nine-story, 54 MW)
Moratorium adopted 9 June 2026; project reported vested and advancing 3 October 2026 (environmental permit documents submitted to the state June 2026)
Equinix Seattle n.a. 54 proposed
Digital Realty downtown Seattle data center (six-story)
Land-use permit application filed at the end of May 2026; reported vested and proceeding 3 October 2026; single-outlet report (The Seattle Times)
Digital Realty Trust Seattle, King County n.a. n.a. proposed
Prologis proposed Tukwila data center (75 MW, Seattle City Light territory)
moratorium adopted June 9, 2026
Prologis Tukwila n.a. n.a. paused
Puyallup facility
Voltage Park Puyallup n.a. n.a. operating
Quincy datacenters
2026
Microsoft (Azure) Quincy n.a. n.a. operating
Quincy facility
Voltage Park Quincy n.a. n.a. operating
Capital at risk

Blocked, delayed or restricted in Washington

Every project in Washington on the atlas's capital-at-risk record: the action taken, who took it, and the announced capital affected. Restarts and reversals are recorded with the same weight as blocks.

ProjectDeveloperJurisdictionActionCapitalSources
Bullfrog Flats DC
moratorium Jul 31 2026; capital stated as ~$200M
Blue Fern Development Cle Elum
Six-month emergency moratorium after proposal surfaced
~$200M
Avista-related project
moratorium Jun 22 2026
Avista Spokane
One-year citywide moratorium on new computer data center permits
n.a.
Burien data center moratorium
moratorium Enacted June 2026
n.a. Burien
Burien, Washington, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated June 2026. 12-month emergency moratorium, unanimous, effective immediately. The measure runs to 29 June 2027.
n.a.
Ellensburg six-month emergency data center moratorium
moratorium Approved unanimously the week of 5 October 2026 (reported 7 October 2026); in place until 5 April 2027
n.a. City of Ellensburg
The Ellensburg City Council voted unanimously to establish a six-month emergency moratorium on new data center proposals within city limits, effective immediately and in place until 5 April 2027, while staff evaluate zoning, permitting and environmental review rules. It follows six-month moratoriums in Cle Elum and Kittitas County.
n.a.
Federal Way 12-month data center moratorium
moratorium Adopted unanimously 7 July 2026; 12 months
Industrial Realty Group / Podium I-5 site owners referenced (neither proposing a data center) City of Federal Way
The Federal Way City Council voted unanimously on 7 July 2026 to impose a 12-month moratorium on data centers. The measure followed public concern that the planned 1,033,680-square-foot Podium I-5 industrial building on the former Wild Waves site could become a data center; the developer said he had no interest in building one. A public hearing on the moratorium was set for 1 September 2026.
n.a.
Five proposed "mega" data centers (Equinix, Prologis + 2 withdrawn)
moratorium Proposals April 2026; one-year moratorium approved 9 June 2026; vested Equinix and Digital Realty projects reported moving forward 3 October 2026
Equinix, Prologis, 2 unnamed Seattle (SoDo, Tukwila)
One-year moratorium on DCs >20 MVA approved 9-0, extendable 6 months. The Seattle Times reported on 3 October 2026 that two large projects are moving forward despite the moratorium because their permit applications predate it: a nine-story Equinix data center in Sodo (54 MW; environmental permits submitted to the state in June 2026) and a six-story Digital Realty data center downtown (40 MVA requested; land-use application filed at the end of May 2026), together nearly 100 MW of peak demand. The Seattle Department of Construction and Inspections said both are vested under the earlier rules. Seattle City Light said Prologis has neither submitted a service request nor withdrawn its interest in its 120 MW Sodo and 75 MW Tukwila proposals, which remain exploratory.
n.a.
Kittitas County data center application moratorium (extended)
moratorium Emergency moratorium 10 August 2026; six-month extension approved 15 September 2026 (total one year)
n.a. Kittitas County Board of Commissioners
Kittitas County commissioners approved an emergency six-month moratorium on data center land-use applications in August 2026, then on Tuesday 15 September 2026 approved a six-month extension, making it a year-long ban. Community Development Services Director Chad Bala said the county's codes do not adequately define or classify data centers. The pause covers siting, construction, expansion, conversion and operation of data centers in unincorporated areas while the county writes review criteria and mitigation measures.
n.a.
Klickitat County six-month data center moratorium motion (failed; former Columbia Gorge Aluminum site)
other Moratorium motion died for lack of a second 3 September 2026; explained at 8 September 2026 meeting
n.a. Klickitat County Board of Commissioners
Commissioner Todd Andrews moved for a six-month data center moratorium at a 3 September 2026 Klickitat County workshop, but neither of the other two commissioners seconded the motion. At the 8 September meeting Chair Ron Ihrig said the county has time to write an ordinance instead, and Commissioner Lori Zoller cited the time and cost of a moratorium. Both said no data center proposal would be ready to apply before an ordinance is adopted. A proposed site sits on the former Columbia Gorge Aluminum plant next to John Day Dam, where data centers are allowed outright.
n.a.
La Conner data center moratorium
moratorium Enacted July 2026
n.a. La Conner
La Conner, Washington, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated July 2026. Six-month moratorium on data center permit applications within town limits; no applications received; town reviewing whether any form of data center is appropriate. The measure runs to 29 January 2027 and covers permits.
n.a.
Lincoln County data center moratorium
moratorium Enacted September 2026
n.a. Lincoln County
Lincoln County, Washington, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated September 2026. Six-month moratorium on data centers and battery energy storage systems; covers facilities over 2,000 sqft or 2+ MW. The measure runs to 10 March 2027 and applies at a threshold of 2,000 sqft.
n.a.
Marysville data center moratorium
moratorium Enacted July 2026
n.a. Marysville
Marysville, Washington, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated July 2026. 6-month moratorium on buildings/facilities whose principal use is data management/transmission, unanimous. Mayor urged surrounding counties to follow suit. The measure runs to 14 January 2027.
n.a.
Moses Lake data center moratorium
moratorium Enacted January 2026
n.a. Moses Lake
Moses Lake, Washington, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated January 2026. Moratorium on new data center development; listed by MRSC (WA state municipal research service) among cities with moratoriums. The measure has a stated duration whose end date is not recorded.
n.a.
Mount Vernon data center moratorium
moratorium Enacted August 2026
n.a. Mount Vernon
Mount Vernon, Washington, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated August 2026. 6-month moratorium, 4-1, with no data center yet proposed. Planning staff to draft rules on electricity and water demand, stormwater and building in the Skagit River floodplain. The measure runs to 12 February 2027.
n.a.
Pasco data center moratorium
moratorium Enacted July 2026
n.a. Pasco
Pasco, Washington, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated July 2026. 6-month moratorium, 6-0. Extendable if officials don't have satisfactory answers. Developing data-center-specific land-use regulations. The measure runs to 20 January 2027.
n.a.
Pierce County data center moratorium
moratorium Enacted August 2026
n.a. Pierce County
Pierce County, Washington, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated August 2026. Emergency ordinance prohibiting new/expanded data centers over 10 MW in unincorporated Pierce County; one year unless extended or lifted. The measure runs to 25 August 2027 and applies at a threshold of 10 MW.
n.a.
Port Angeles six-month data center moratorium
moratorium Adopted Tuesday 1 September 2026; six months, renewable
n.a. City of Port Angeles
The Port Angeles City Council adopted a data center moratorium on 2 September 2026, effective immediately, with one member excused. It runs six months initially with potential renewal. Staff will spend the first 60 days developing a work plan covering utility and industrial-land impacts, and a public hearing is required within 60 days. Both the Peninsula Daily News and My Clallam County reported the council vote took place on Tuesday night, which was 1 September 2026, not 2 September.
n.a.
Renton one-year large data center moratorium
moratorium Approved unanimously 17 August 2026; up to one year
n.a. City of Renton
The Renton City Council unanimously approved a moratorium of up to one year on large data centers on 17 August 2026. It halts filing, acceptance, processing and approval of new applications and permits for siting, establishment or expansion. The ordinance cites impacts on electrical and water utility capacity, utility rates, land use, traffic, noise and air quality.
n.a.
Sedro-Woolley six-month data center moratorium
moratorium Adopted 9 September 2026 (reported 21 September 2026); six months
n.a. Sedro-Woolley City Council
After required public hearings, the Sedro-Woolley City Council on 9 September 2026 passed six-month moratoriums on data center projects and on accepting permit applications for major utility developments. The council can renew or extend them while staff draft permanent regulations, including possible land use map and zoning code amendments, for Planning Commission review.
n.a.
Spokane County four-month data center moratorium
moratorium Adopted August 2026
n.a. Spokane County
The Board of County Commissioners approved a four-month moratorium unanimously on Aug. 19, 2026, replacing an earlier nine-month proposal that had split the board 3-2, to give staff time to draft zoning rules.
n.a.
Unincorporated Skagit County
moratorium Jun 2026
n.a. Skagit County
Six-month moratorium approved Jun 1, extendable
n.a.
Winlock six-month data center moratorium
moratorium Enacted 23 September 2026; six months
n.a. Winlock City Council
The Winlock City Council unanimously enacted a six-month moratorium on data center development at a special meeting on Wednesday 23 September 2026. Mayor Victoria Marincin said the pause is meant to let the Planning and Park Commission draft updated commercial and industrial building codes covering water supply and noise, not to stop data centers entirely.
n.a.
Yakima County six-month data center moratorium
moratorium Approved unanimously at a Tuesday meeting, reported 12 August 2026; six months
n.a. Yakima County Board of Commissioners
Yakima County commissioners voted unanimously on a Tuesday to adopt a six-month moratorium preventing the county from accepting land use or building permits for data centers in unincorporated areas. The county has no data centers and no data-center-specific rules. The vote followed a work session at which dozens of residents opposed data centers over water, power rates and environmental impacts. Commissioner LaDon Linde said the pause gives time to gather information.
n.a.
Policy context

What governs a data center in Washington

Seattlecity
One-year moratorium on data centers >20 MVA, approved 9-0, extendable 6 months (Apr-Jun 9, 2026).
Five proposed mega data centers in SoDo and Tukwila (Equinix, Prologis, and two unnamed developers) had requested 369 MW; two of four developers withdrew before the moratorium passed.
Skagit Countycounty
Six-month moratorium covering data centers >2,000 sq ft in unincorporated Skagit County, approved June 1, 2026, extendable.
County commissioners approved a six-month pause on data centers larger than 2,000 square feet in unincorporated areas.
Washington (statewide summary)state
C.4 floors: 369 MW (Seattle) + 500 MW (Spokane, high end) + 20 MW (Cle Elum) paused or at risk; ~$200M identified; 4 named projects; 7 tracked actions.
Washington actions include the Seattle >20 MVA moratorium, a Spokane one-year citywide moratorium (Jun 22, 2026, Avista-related 125-500 MW), a Cle Elum six-month emergency moratorium (Jul 31, 2026), and the Skagit County pause. A source headline states a Washington statewide data center bill was killed before Seattle acted.

The policy layer for Washington lives in three companion references: the Washington Data Center Moratorium Tracker for every state measure and local moratorium on record, the Water Tracker for the water rules that touch a site, and the Grid Operator Watchlist for the large-load rules of the RTO or utility that decides whether it can energize.

On the map

Data centers in Washington

The US Data Center Map identifies 112 facilities run by 47 operators in Washington, each one placed from primary sources and listed by city and by operator, with this atlas record beside it.

Sources

Sources for Washington

Every source cited on this page, once each. The full atlas source register is at Capital Atlas sources.

The SAVRN reference set

Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.

Have a specific address? Site Intelligence reads all seven references against one location, county, utility and grid operator included, and cites every finding.
Check an address →