Nebius Group has raised a $700 million strategic equity round, a $3.75 billion equity-plus-converts package, approximately $4.3375 billion and $5.0 billion convertible note offerings, and a $2 billion Nvidia equity investment tied to scaling more than 5GW by 2030. Anchor contracts include a $17.4 billion five-year Microsoft agreement expandable to up to $19.4 billion, anchored at Vineland, New Jersey, and Meta agreements of $3 billion and then $27 billion over five years. Contracted-power guidance has escalated to more than 4GW, with Q1 2026 group revenue of $399.0 million and capex of approximately $2.5 billion.
Reported and guided spending
Audited, reported and guided figures as the filing or release states them. Reported lines are what was spent, and guidance is what management expects. They sit side by side and are never combined.
| Period | Kind | Amount | As stated | Sources |
|---|---|---|---|---|
| Q1 2026 | reported | ~$2.5B | Q1 2026 capex approximately $2.5 billion; $6.3 billion of capital secured in the quarter, $2.3 billion positive operating cash flow, $9.3 billion ending cash |
|
| Q3 2025 | reported | $956M | Q3 2025 capex of $955.5 million against revenue of $146.1 million |
|
| FY2026 guidance | guidance | ≥$3.2B | 2026 revenue guidance of $3.0B-$3.4B (midpoint recorded) and $7B-$9B ARR; contracted-power guidance escalated from >1GW (Aug 2025) to >2.5GW, >3GW and currently >4GW |
Where Nebius Group builds
| Site | State | Place | Capital | MW | Status | Sources |
|---|---|---|---|---|---|---|
Highridge Business Park AI factory with PPL Electric Utilities |
Pennsylvania | Butler Township, Schuylkill County | n.a. | 1,200 | announced | |
Vineland build-to-suit facility with Microsoft |
New Jersey | Vineland | n.a. | 300 | announced | |
Independence AI factory campus Groundbreaking 12 May 2026 |
Missouri | Independence, Jackson County | n.a. | n.a. | construction | |
Kansas City colocation |
Missouri | Kansas City | n.a. | n.a. | announced |
Financing transactions
Transactions that name Nebius Group as a party or attach to one of its named sites. Amounts are as stated, and overlapping commitments are never summed.
| Parties | Instrument | Amount | Date | Site | Sources |
|---|---|---|---|---|---|
Nebius Group + Meta Second, far larger Meta agreement following the initial $3 billion deal. |
other | $27.0B | compute purchase beginning early 2027 |
n.a. |
|
Nebius Group + Microsoft AI infrastructure agreement anchored at the Vineland, New Jersey facility, with more than 100,000 GB300 units planned. |
other | $17.4B | September 2025 |
Vineland build-to-suit facility (NJ) |
|
Nebius Group Upsized private offering of convertible senior notes. Closed 24 August 2026 with aggregate principal of $5.75 billion after initial purchasers exercised options: $3.45 billion of 0.50% notes due 2030 and $2.3 billion of 4.50% notes due 2034. Holders exchanged $400 million of 2029 notes and $400 million of 2031 notes for approximately 15.8 million Class A shares |
convertible | ~$5.8B | Priced 19 August 2026; closed 24 August 2026 |
n.a. |
|
Nebius Group Private offering of convertible senior notes with aggregate gross proceeds of approximately $4.3 billion. |
convertible | ~$4.3B | closed March 20, 2026 |
n.a. |
|
Nebius Group Combined stock offering and convertible notes raise. |
convertible | $3.8B | September 2025 |
n.a. |
|
Nebius + Citi Nebius secured a $3.5 billion senior secured loan from Citi to fund data center buildout and GPU purchases. The loan has a 364-day term and an initial interest rate of Term SOFR plus 2.75%, potentially rising to 3.50%. It is Nebius’s second major capital raise in about two months. |
debt facility | $3.5B | October 22, 2026 (per Cryptopolitan) |
n.a. |
|
Nebius Group + Meta Initial Meta compute agreement, signed as Nebius described current available capacity as sold out. |
other | $3.0B | n.a. (reported alongside sold-out capacity commentary) |
n.a. |
|
Nvidia + Nebius + Nebius Group Nvidia committed $2 billion of equity to Nebius on March 11, 2026, under a partnership to scale more than 5GW by 2030, having also participated in Nebius's December 2024 round. |
equity raise | $2.0B | March 11, 2026; plus Dec 2024 round participation |
n.a. |
|
Industrial Development Funding + Oaktree + Bloom Energy + Nebius Group Industrial Development Funding and Oaktree agreed to invest $1.7 billion to deploy Bloom Energy fuel cells supplying dedicated behind-the-meter power to Nebius AI cloud infrastructure. The specific Nebius sites were not named in the fetched coverage. Nebius later adopted Bloom fuel cells in the approved plan for its Vineland, New Jersey campus |
project equity investment in behind-the-meter power | $1.7B | Announced 16 July 2026 |
n.a. |
|
AIB Data Centers Inc. (AIB CLT1 LLC) + Nebius AIB Data Centers signed a binding agreement with Nebius for 50 MW of critical IT capacity at its facility in the southeastern United States, delivered in two data halls and supported by AIB's 15-year Electric Service Agreement for 65 MW of utility load at the site. AIB's Form 10-Q identifies the 65,000 kVA agreement with its CLT-01 Campus in Spartanburg County, South Carolina, a former 40 MW bitcoin hosting facility being repurposed to about 65 MW. The release does not name the town. AIB's investor presentation says Nebius's guaranty backs the contract, rent commences hall by hall (two 25 MW halls targeted at about months 10 and 14), and the 12-year term runs from the first hall. |
lease | ≥$1.3B | Announced 30 September 2026 (AIB release via GlobeNewswire); contract value from AIB investor presentation furnished on Form 8-K 30 September 2026; ESA service scheduled to begin 1 October 2026 |
AIB Data Centers CLT-01 Campus (SC) |
|
Nebius Group + Reflection AI startup Reflection signed a deal worth more than $1 billion to secure computing capacity from Nebius, including access to Nvidia's latest chips. The agreement builds on Reflection's June 2026 compute agreement with SpaceX. Contract term and data center locations were not disclosed |
compute capacity agreement | ≥$1.0B | Announced 14 July 2026 |
n.a. |
|
Nvidia + CoreWeave + Nebius + Nscale + Lambda + Crusoe Nvidia backstops $860M of partner data center lease obligations, with $470M escrowed, across CoreWeave, Nebius, Nscale, Lambda and Crusoe. |
guarantee | $860M | Date n.a. in this part |
n.a. |
|
Nebius Group + MUFG + ABN AMRO + Bank of America + Deutsche Bank + HSBC Nebius raised its first secured debt, backed by deployed GPU infrastructure and contracted cash flows from an agreement with an investment-grade customer. MUFG was structuring agent and sole bookrunner; Citi, Credit Agricole CIB, ING and Morgan Stanley were senior lead arrangers, with Goldman Sachs also participating |
debt facility | $775M | Announced 17 July 2026 |
n.a. |
|
Nebius Group + Nvidia + Accel Strategic equity financing to accelerate roll-out of full-stack AI infrastructure. |
equity raise | $700M | December 2, 2024 |
n.a. |
Sourced facts on Nebius Group
- Q1 2026 group revenue reached $399.0 million (from $50.9 million a year earlier), with AI-cloud revenue of $389.7 million and group adjusted EBITDA of $129.5 million.
- Nebius plans to deploy more than 100,000 GB300 units for the Microsoft agreement, and described available capacity as sold out while targeting 2.5GW contracted and 800MW-1GW connected by end-2026.
How Nebius Group prices compare
Nebius Group's lowest price for each GPU beside the lowest price every other tracked provider lists for the same GPU, sold the same way. Typical is the middle provider, one price each.
NVIDIA H100On demand
All NVIDIA H100 prices →NVIDIA H100Spot
All NVIDIA H100 prices →NVIDIA H200On demand
All NVIDIA H200 prices →NVIDIA H200Spot
All NVIDIA H200 prices →NVIDIA B200On demand
All NVIDIA B200 prices →NVIDIA B200Spot
All NVIDIA B200 prices →NVIDIA B300On demand
All NVIDIA B300 prices →NVIDIA B300Spot
All NVIDIA B300 prices →Nebius Group prices
Every price the Index tracks for Nebius Group, in the provider's own words beside a normalized figure, with the date it was last checked. What AI Costs compares them across the market.
| GPU | Offer | Terms | Published price | Per GPU-hour | Change | Checked | Source |
|---|---|---|---|---|---|---|---|
| NVIDIA H100 | NVIDIA HGX H100 | on-demandList | $4.50 per GPU-hour, on-demand | $4.50 | +16.9% | On pageOct 27, 2026 | nebius.com ↗ |
| NVIDIA H100 | NVIDIA HGX H100 | spotSpot | $2.15 per GPU-hour, preemptible | $2.15 | No change | Not foundOct 27, 2026 | nebius.com ↗ |
| NVIDIA H200 | NVIDIA HGX H200 | on-demandList | $5.40 per GPU-hour, on-demand | $5.40 | +20% | On pageOct 27, 2026 | nebius.com ↗ |
| NVIDIA H200 | NVIDIA HGX H200 | spotSpot | $2.45 per GPU-hour, preemptible | $2.45 | No change | Not foundOct 27, 2026 | nebius.com ↗ |
| NVIDIA B200 | NVIDIA HGX B200 | on-demandList | $8.50 per GPU-hour, on-demand | $8.50 | +18.9% | On pageOct 27, 2026 | nebius.com ↗ |
| NVIDIA B200 | NVIDIA HGX B200 | spotSpot | $3.95 per GPU-hour, preemptible | $3.95 | No change | Not foundOct 27, 2026 | nebius.com ↗ |
| NVIDIA GB200 NVL72 | NVIDIA GB200 NVL72 | not publishedNot published | On-demand, GPU-hour" header, no value | Not published | No change | On pageOct 27, 2026 | nebius.com ↗ |
| NVIDIA B300 | NVIDIA HGX B300 | on-demandList | $7.85 per GPU-hour, on-demand | $7.85 | No change | RecheckingOct 27, 2026 | nebius.com ↗ |
| NVIDIA B300 | NVIDIA HGX B300 | spotSpot | $4.30 per GPU-hour, preemptible | $4.30 | No change | Not foundOct 27, 2026 | nebius.com ↗ |
| NVIDIA GB300 NVL72 | NVIDIA GB300 NVL72 | not publishedNot published | same | Not published | No change | On pageOct 27, 2026 | nebius.com ↗ |
| Seller | Model | Input | Cached input | Output | Revenue per GPU-hour at list | Other published prices | Change | Checked |
|---|---|---|---|---|---|---|---|---|
| Nebius Token Factory | DeepSeek V4-Pro-0813 | $1.32 | n.a. | $3.96 | n.a. | None published | No change | ResearchOct 27, 2026tokenfactory.nebius.com ↗ |
| Nebius Token Factory | gpt-oss-120b | $0.15 | n.a. | $0.60 | n.a. | None published | No change | ResearchOct 27, 2026tokenfactory.nebius.com ↗ |
| Nebius Token Factory | Llama-3.3-70B | $0.13 | n.a. | $0.40 | n.a. | None published | No change | ResearchOct 27, 2026tokenfactory.nebius.com ↗ |
Revenue per GPU-hour is SAVRN's calculation, not a price any seller charges: the 6.83 million input and 0.85 million output tokens one Vera Rubin GPU handles in an hour in CoreWeave's measured test, billed at this model's list prices. It puts a token price beside a GPU rental price; it says nothing about how fast this model actually runs.
Sources for Nebius Group
Every source cited on this page, once each.
- nebius.comNebius
- yahoo.comRepublican Herald via Yahoo News
- nebius.comNebius
- reuters.comReuters
- yahoo.comNJ.com via Yahoo News
- nbcphiladelphia.comNBC10 Philadelphia
- finance.yahoo.comYahoo Finance
- 247wallst.com24/7 Wall St.
- techtimes.comTech Times
- nebius.comNebius
- assets.nebius.comQ1 2026 shareholder letter
- datacenterdynamics.comDCD
- nebius.comNebius
- sec.govSEC EDGAR (Nebius 6-K)
- nebius.comNebius
- datacenterdynamics.comDCD
- sec.govsec.gov
- cryptopolitan.comCryptopolitan, 22 October 2026
- nebius.comNebius
- finance.yahoo.comReuters via Yahoo Finance
- finance.yahoo.comAIB Data Centers release (GlobeNewswire via Yahoo Finance)
- sec.govAIB Data Centers Form 10-Q for quarter ended 30 June 2026 (SEC)
- sec.govAIB Data Centers Form 8-K Exhibit 99.1, investor presentation Q3 2026 (SEC)
- thestar.com.myThe Star (Reuters)
- datacenterdynamics.comDCD
- nebius.comNebius
- nebius.comNebius
- nebius.comnebius.com
- tokenfactory.nebius.comtokenfactory.nebius.com
More in the Index
Capital figures come from the Capital Atlas, refreshed every Tuesday, Thursday and Saturday. Site commitments overlap reported capital expenditure and overlap one another, so each figure appears as its source states it and none are added into a single deployment number. Informational, not investment advice.
Seven references, one system