SAVRN Index · NeoCloud

Nebius Group Data Centers, Capex and GPU Pricing

NASDAQ:NBIS nebius.com ↗
Follow this profile Is this your company? Send a correction

Nebius Group has raised a $700 million strategic equity round, a $3.75 billion equity-plus-converts package, approximately $4.3375 billion and $5.0 billion convertible note offerings, and a $2 billion Nvidia equity investment tied to scaling more than 5GW by 2030. Anchor contracts include a $17.4 billion five-year Microsoft agreement expandable to up to $19.4 billion, anchored at Vineland, New Jersey, and Meta agreements of $3 billion and then $27 billion over five years. Contracted-power guidance has escalated to more than 4GW, with Q1 2026 group revenue of $399.0 million and capex of approximately $2.5 billion.

Updated October 25, 2026Capital record from the Capital Atlas
Named sites
4
Site commitments on record for Nebius Group
Disclosed site capital
n.a.
Named sites with a stated dollar figure. A floor, not a capex total
Disclosed capacity
1,500 MW
Named sites with a stated megawatt figure
Financing transactions
14
Transactions naming Nebius Group or one of its sites
Prices tracked
13
5 confirmed on the provider's feed or page at the last check
Sources
29
Every cited page, listed below
MarketMarket data from TradingView, delayed
Loading NASDAQ:NBIS from TradingView
Spending

Reported and guided spending

Audited, reported and guided figures as the filing or release states them. Reported lines are what was spent, and guidance is what management expects. They sit side by side and are never combined.

PeriodKindAmountAs statedSources
Q1 2026 reported ~$2.5B
Q1 2026 capex approximately $2.5 billion; $6.3 billion of capital secured in the quarter, $2.3 billion positive operating cash flow, $9.3 billion ending cash
Q3 2025 reported $956M
Q3 2025 capex of $955.5 million against revenue of $146.1 million
FY2026 guidance guidance ≥$3.2B
2026 revenue guidance of $3.0B-$3.4B (midpoint recorded) and $7B-$9B ARR; contracted-power guidance escalated from >1GW (Aug 2025) to >2.5GW, >3GW and currently >4GW
Named sites

Where Nebius Group builds

SiteStatePlaceCapitalMWStatusSources
Highridge Business Park AI factory
with PPL Electric Utilities
Pennsylvania Butler Township, Schuylkill County n.a. 1,200 announced
Vineland build-to-suit facility
with Microsoft
New Jersey Vineland n.a. 300 announced
Independence AI factory campus
Groundbreaking 12 May 2026
Missouri Independence, Jackson County n.a. n.a. construction
Kansas City colocation
Missouri Kansas City n.a. n.a. announced
Financing

Financing transactions

Transactions that name Nebius Group as a party or attach to one of its named sites. Amounts are as stated, and overlapping commitments are never summed.

PartiesInstrumentAmountDateSiteSources
Nebius Group + Meta
Second, far larger Meta agreement following the initial $3 billion deal.
other $27.0B
compute purchase beginning early 2027
n.a.
Nebius Group + Microsoft
AI infrastructure agreement anchored at the Vineland, New Jersey facility, with more than 100,000 GB300 units planned.
other $17.4B
September 2025
Vineland build-to-suit facility (NJ)
Nebius Group
Upsized private offering of convertible senior notes. Closed 24 August 2026 with aggregate principal of $5.75 billion after initial purchasers exercised options: $3.45 billion of 0.50% notes due 2030 and $2.3 billion of 4.50% notes due 2034. Holders exchanged $400 million of 2029 notes and $400 million of 2031 notes for approximately 15.8 million Class A shares
convertible ~$5.8B
Priced 19 August 2026; closed 24 August 2026
n.a.
Nebius Group
Private offering of convertible senior notes with aggregate gross proceeds of approximately $4.3 billion.
convertible ~$4.3B
closed March 20, 2026
n.a.
Nebius Group
Combined stock offering and convertible notes raise.
convertible $3.8B
September 2025
n.a.
Nebius + Citi
Nebius secured a $3.5 billion senior secured loan from Citi to fund data center buildout and GPU purchases. The loan has a 364-day term and an initial interest rate of Term SOFR plus 2.75%, potentially rising to 3.50%. It is Nebius’s second major capital raise in about two months.
debt facility $3.5B
October 22, 2026 (per Cryptopolitan)
n.a.
Nebius Group + Meta
Initial Meta compute agreement, signed as Nebius described current available capacity as sold out.
other $3.0B
n.a. (reported alongside sold-out capacity commentary)
n.a.
Nvidia + Nebius + Nebius Group
Nvidia committed $2 billion of equity to Nebius on March 11, 2026, under a partnership to scale more than 5GW by 2030, having also participated in Nebius's December 2024 round.
equity raise $2.0B
March 11, 2026; plus Dec 2024 round participation
n.a.
Industrial Development Funding + Oaktree + Bloom Energy + Nebius Group
Industrial Development Funding and Oaktree agreed to invest $1.7 billion to deploy Bloom Energy fuel cells supplying dedicated behind-the-meter power to Nebius AI cloud infrastructure. The specific Nebius sites were not named in the fetched coverage. Nebius later adopted Bloom fuel cells in the approved plan for its Vineland, New Jersey campus
project equity investment in behind-the-meter power $1.7B
Announced 16 July 2026
n.a.
AIB Data Centers Inc. (AIB CLT1 LLC) + Nebius
AIB Data Centers signed a binding agreement with Nebius for 50 MW of critical IT capacity at its facility in the southeastern United States, delivered in two data halls and supported by AIB's 15-year Electric Service Agreement for 65 MW of utility load at the site. AIB's Form 10-Q identifies the 65,000 kVA agreement with its CLT-01 Campus in Spartanburg County, South Carolina, a former 40 MW bitcoin hosting facility being repurposed to about 65 MW. The release does not name the town. AIB's investor presentation says Nebius's guaranty backs the contract, rent commences hall by hall (two 25 MW halls targeted at about months 10 and 14), and the 12-year term runs from the first hall.
lease ≥$1.3B
Announced 30 September 2026 (AIB release via GlobeNewswire); contract value from AIB investor presentation furnished on Form 8-K 30 September 2026; ESA service scheduled to begin 1 October 2026
AIB Data Centers CLT-01 Campus (SC)
Nebius Group + Reflection
AI startup Reflection signed a deal worth more than $1 billion to secure computing capacity from Nebius, including access to Nvidia's latest chips. The agreement builds on Reflection's June 2026 compute agreement with SpaceX. Contract term and data center locations were not disclosed
compute capacity agreement ≥$1.0B
Announced 14 July 2026
n.a.
Nvidia + CoreWeave + Nebius + Nscale + Lambda + Crusoe
Nvidia backstops $860M of partner data center lease obligations, with $470M escrowed, across CoreWeave, Nebius, Nscale, Lambda and Crusoe.
guarantee $860M
Date n.a. in this part
n.a.
Nebius Group + MUFG + ABN AMRO + Bank of America + Deutsche Bank + HSBC
Nebius raised its first secured debt, backed by deployed GPU infrastructure and contracted cash flows from an agreement with an investment-grade customer. MUFG was structuring agent and sole bookrunner; Citi, Credit Agricole CIB, ING and Morgan Stanley were senior lead arrangers, with Goldman Sachs also participating
debt facility $775M
Announced 17 July 2026
n.a.
Nebius Group + Nvidia + Accel
Strategic equity financing to accelerate roll-out of full-stack AI infrastructure.
equity raise $700M
December 2, 2024
n.a.
The record

Sourced facts on Nebius Group

  • Q1 2026 group revenue reached $399.0 million (from $50.9 million a year earlier), with AI-cloud revenue of $389.7 million and group adjusted EBITDA of $129.5 million.
  • Nebius plans to deploy more than 100,000 GB300 units for the Microsoft agreement, and described available capacity as sold out while targeting 2.5GW contracted and 800MW-1GW connected by end-2026.
Against the market

How Nebius Group prices compare

Nebius Group's lowest price for each GPU beside the lowest price every other tracked provider lists for the same GPU, sold the same way. Typical is the middle provider, one price each.

NVIDIA H100On demand

All NVIDIA H100 prices →
Nebius Group$4.50per GPU-hour, on-demand
Rank14 of 2113% above typical
Typical$3.99middle of 21 providers
Lowest anywhere$1.99Voltage Park
Voltage Park1. H100 (single GPU, no contract) $1.99
GMI Cloud2. NVIDIA H100 $2.00
Vultr3. NVIDIA HGX H100 — Cloud GPU $2.30
Denvr Dataworks4. NVIDIA H100 SXM (8 GPUs, 208 vCPU) $2.45
Cirrascale5. 8X NVIDIA H100 (16-Node+ Clustered) $2.49
Massed Compute6. H100 (80 GB) ×1/×2/×4 $2.73
Runpod7. H100 PCIe / H100 NVL — Pods $2.89
Hyperbolic8. H100 SXM $3.19
Lambda9. NVIDIA H100 PCIe $3.29
Crusoe Cloud10. NVIDIA H100 $3.90
Nebius14. NVIDIA HGX H100 $4.50
Nebius GroupTypical $3.9910 more providers on the NVIDIA H100 page

NVIDIA H100Spot

All NVIDIA H100 prices →
Nebius Group$2.15per GPU-hour, spot
Rank2 of 57% below typical
Typical$2.30middle of 5 providers
Lowest anywhere$2.04Microsoft Azure
Microsoft Azure1. Standard_ND96is_H100_v5 (no InfiniBand variants incl. _noIB_, _flex_) $2.04
Nebius2. NVIDIA HGX H100 $2.15
Verda3. 1x H100 SXM5 80GB $2.30
CoreWeave4. NVIDIA HGX H100 $2.46
Google Cloud5. a3-megagpu-8g (A3 Mega) $5.99
Nebius GroupTypical $2.30

NVIDIA H200On demand

All NVIDIA H200 prices →
Nebius Group$5.40per GPU-hour, on-demand
Rank8 of 165% below typical
Typical$5.70middle of 16 providers
Lowest anywhere$2.60GMI Cloud
GMI Cloud1. NVIDIA H200 $2.60
Massed Compute2. H200 NVL (141 GB) ×8 $3.62
Hyperbolic3. H200 $3.99
Crusoe Cloud4. NVIDIA H200 $4.29
Runpod5. Clusters — H200 SXM $4.31
DigitalOcean6. NVIDIA HGX H200 (141 GB) $4.47
Cirrascale7. 8X H200 $4.54
Nebius8. NVIDIA HGX H200 $5.40
Together AI9. H200 (140 GB), 256–1,000 GPUs $5.99
Verda10. 1x H200 SXM5 141GB $6.01
Nebius GroupTypical $5.706 more providers on the NVIDIA H200 page

NVIDIA H200Spot

All NVIDIA H200 prices →
Nebius Group$2.45per GPU-hour, spot
Rank1 of 413% below typical
Typical$2.81middle of 4 providers
Lowest anywhere$2.45Nebius
Nebius1. NVIDIA HGX H200 $2.45
CoreWeave2. NVIDIA HGX H200 $2.62
Verda3. 1x H200 SXM5 141GB $3.00
Google Cloud4. a3-ultragpu-8g (A3 Ultra) $6.35
Nebius GroupTypical $2.81

NVIDIA B200On demand

All NVIDIA B200 prices →
Nebius Group$8.50per GPU-hour, on-demand
Rank10 of 165% above typical
Typical$8.12middle of 16 providers
Lowest anywhere$3.50Vultr
Vultr1. NVIDIA HGX B200 — Cloud GPU $3.50
GMI Cloud2. NVIDIA B200 $4.00
Massed Compute3. B200 SXM6 ×8 $5.43
Hyperbolic4. B200 $5.99
Cirrascale5. 8X B200 $5.99
Lambda6. NVIDIA B200 SXM6 $6.69
Runpod7. B200 (180 GB, 28 vCPU) — Pods $7.99
Google Cloud8. a4-highgpu-8g (A4) $8.06
Together AI9. HGX B200 (180 GB) $8.19
Nebius10. NVIDIA HGX B200 $8.50
Nebius GroupTypical $8.126 more providers on the NVIDIA B200 page

NVIDIA B200Spot

All NVIDIA B200 prices →
Nebius Group$3.95per GPU-hour, spot
Rank1 of 47% below typical
Typical$4.26middle of 4 providers
Lowest anywhere$3.95Nebius
Nebius1. NVIDIA HGX B200 $3.95
Verda2. 1x B200 SXM6 180GB $4.26
CoreWeave3. NVIDIA HGX B200 $4.26
Google Cloud4. a4-highgpu-8g (A4) $4.95
Nebius GroupTypical $4.26

NVIDIA B300On demand

All NVIDIA B300 prices →
Nebius Group$7.85per GPU-hour, on-demand
Rank3 of 1017% below typical
Typical$9.49middle of 10 providers
Lowest anywhere$6.60Massed Compute
Massed Compute1. B300 SXM6 ×8 (280 vCPU, 2800 GB) $6.60
TheAI Cloud2. B300 (8× B300 SXM6 · 288GB … whole node) $6.90
Nebius3. NVIDIA HGX B300 $7.85
Crusoe Cloud4. B300 $8.96
Runpod5. B300 (288 GB HBM3e, 32 vCPU) — Pods $8.99
Together AI6. HGX B300 (270 GB) $9.99
Verda7. 1x B300 SXM6 268GB $10.91
AWS8. p6-b300.48xlarge $14.04
Fireworks AI9. B300 288 GB $15.00
Oracle OCI10. BM.GPU.B300.8 $15.00
Nebius GroupTypical $9.49

NVIDIA B300Spot

All NVIDIA B300 prices →
Nebius Group$4.30per GPU-hour, spot
Rank1 of 34% below typical
Typical$4.48middle of 3 providers
Lowest anywhere$4.30Nebius
Nebius1. NVIDIA HGX B300 $4.30
CoreWeave2. NVIDIA HGX B300 $4.48
Verda3. 1x B300 SXM6 268GB $5.46
Nebius GroupTypical $4.48
Tracked prices

Nebius Group prices

Every price the Index tracks for Nebius Group, in the provider's own words beside a normalized figure, with the date it was last checked. What AI Costs compares them across the market.

GPUOfferTermsPublished pricePer GPU-hourChangeCheckedSource
NVIDIA H100 NVIDIA HGX H100 on-demandList $4.50 per GPU-hour, on-demand $4.50 +16.9% On pageOct 27, 2026 nebius.com ↗
NVIDIA H100 NVIDIA HGX H100 spotSpot $2.15 per GPU-hour, preemptible $2.15 No change Not foundOct 27, 2026 nebius.com ↗
NVIDIA H200 NVIDIA HGX H200 on-demandList $5.40 per GPU-hour, on-demand $5.40 +20% On pageOct 27, 2026 nebius.com ↗
NVIDIA H200 NVIDIA HGX H200 spotSpot $2.45 per GPU-hour, preemptible $2.45 No change Not foundOct 27, 2026 nebius.com ↗
NVIDIA B200 NVIDIA HGX B200 on-demandList $8.50 per GPU-hour, on-demand $8.50 +18.9% On pageOct 27, 2026 nebius.com ↗
NVIDIA B200 NVIDIA HGX B200 spotSpot $3.95 per GPU-hour, preemptible $3.95 No change Not foundOct 27, 2026 nebius.com ↗
NVIDIA GB200 NVL72 NVIDIA GB200 NVL72 not publishedNot published On-demand, GPU-hour" header, no value Not published No change On pageOct 27, 2026 nebius.com ↗
NVIDIA B300 NVIDIA HGX B300 on-demandList $7.85 per GPU-hour, on-demand $7.85 No change RecheckingOct 27, 2026 nebius.com ↗
NVIDIA B300 NVIDIA HGX B300 spotSpot $4.30 per GPU-hour, preemptible $4.30 No change Not foundOct 27, 2026 nebius.com ↗
NVIDIA GB300 NVL72 NVIDIA GB300 NVL72 not publishedNot published same Not published No change On pageOct 27, 2026 nebius.com ↗
SellerModelInputCached inputOutputRevenue per GPU-hour at listOther published pricesChangeChecked
Nebius Token Factory DeepSeek V4-Pro-0813 $1.32 n.a. $3.96 n.a. None published No change ResearchOct 27, 2026tokenfactory.nebius.com ↗
Nebius Token Factory gpt-oss-120b $0.15 n.a. $0.60 n.a. None published No change ResearchOct 27, 2026tokenfactory.nebius.com ↗
Nebius Token Factory Llama-3.3-70B $0.13 n.a. $0.40 n.a. None published No change ResearchOct 27, 2026tokenfactory.nebius.com ↗

Revenue per GPU-hour is SAVRN's calculation, not a price any seller charges: the 6.83 million input and 0.85 million output tokens one Vera Rubin GPU handles in an hour in CoreWeave's measured test, billed at this model's list prices. It puts a token price beside a GPU rental price; it says nothing about how fast this model actually runs.

Sources

Sources for Nebius Group

Every source cited on this page, once each.

NeoCloud

More in the Index

Capital figures come from the Capital Atlas, refreshed every Tuesday, Thursday and Saturday. Site commitments overlap reported capital expenditure and overlap one another, so each figure appears as its source states it and none are added into a single deployment number. Informational, not investment advice.

The SAVRN reference set

Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.

Have a specific address? Site Intelligence reads all seven references against one location, county, utility and grid operator included, and cites every finding.
Check an address →