SAVRN Research · Capital Atlas · REIT and developer

SB Energy Data Center Capex and Sites

SB Energy is the SoftBank-backed developer of the PORTS-Pike Technology Campus in Pike County, Ohio, on the former Portsmouth Gaseous Diffusion Plant, a 5.4 square mile Department of Energy site. On 17 August 2026 SB Energy, NVIDIA and OpenAI announced that SB Energy will build, own and operate the campus under a 20-year lease to OpenAI, with NVIDIA as the exclusive AI compute provider and NVIDIA taking a $1.5 billion equity stake in SB Energy. OpenAI has contracted for approximately 8 IT-GW at the campus, of which 4.25 IT-GW is the initial deployment and 3.75 IT-GW an option. SB Energy and SoftBank committed at least $4.2 billion to new regional grid infrastructure with AEP Ohio. First capacity is expected to come online in phases beginning in 2028. On 1 September 2026 SB Energy, Inc. filed a Form S-1 registration statement for an initial public offering, disclosing a Data Center Contracted Portfolio of 8.8 GW-IT across the Cosmos Technology Campus in Travis County, Texas, the Milam County Data Center in Texas and the 8.0 GW-IT PORTS-Pike Technology Campus in Ohio, approximately $439 billion of backlog and approximately $178 billion of backlog-associated capex. No data center capacity is in operation.

Updated October 8, 2026 4 named sites 5 financing transactions 6 sourced facts 9 sources
SB Energy
REIT and developer
Financing regimeDeveloper capital plus a $1.5 billion NVIDIA equity investment, NVIDIA credit support on land, power and shell buildout for the initial phase, and a 20-year OpenAI lease as the contracted revenue base. Project-level financing to date includes $999.0 million of 8.875% senior secured notes due 2031 for Cosmos with a parent completion guaranty; the company had $3.9 billion of borrowings, net, from financial institutions at 30 June 2026 and states it plans to fund its capex with cash on hand, operating cash flow, newly raised corporate-level equity and newly raised project-level debt.
Named sites
4
Site-level commitments the atlas ties to SB Energy
Disclosed site capital
$999M
Sum of named sites with a stated dollar figure. Not a capex total; see the spending table
Disclosed capacity
4,300 MW
Sum of named sites with a stated megawatt figure
Financing transactions
5
Transactions naming SB Energy or tied to one of its sites
Spending

Reported and guided spending

Audited, reported and guided figures as the filing or release states them. Reported lines are what was spent; guidance is what management said it expects. They are shown side by side and never combined.

PeriodKindAmountAs statedSources
2026 equity $1.5B
NVIDIA equity investment in SB Energy announced 17 August 2026
2026 build ≥$4.2B
At least $4.2 billion committed by SB Energy and SoftBank to new regional grid infrastructure in partnership with AEP Ohio
as of the S-1 dated 1 September 2026 planned ~$178B
Backlog-associated capex of approximately $178 billion, measured on a cash basis from 30 June 2026, of which approximately $174 billion is attributable to the data center segment and $4 billion to the power segment. This is the company's own estimate of capital expenditure required to build its contracted projects and is not a committed or financed amount; it overlaps with the PORTS-Pike and Cosmos figures recorded elsewhere in this atlas and must not be added to them.
May 2026 debt $999M
$999.0 million of 8.875% senior secured notes due 2031 financing the Cosmos Technology Campus
Named sites

Where SB Energy builds

SiteStatePlaceCapitalMWStatusSources
Cosmos Technology Campus
with SoftBank
Texas Austin, Travis County $999M 50 construction
PORTS-Pike Technology Campus
with OpenAI, NVIDIA, SoftBank, AEP Ohio, U.S. Department of Energy
Ohio Piketon, Pike County n.a. 4,250 announced
Borden County campus (pipeline)
Disclosed in the Form S-1 filed 1 September 2026
Texas Borden County n.a. n.a. announced
Scurry County campus (pipeline)
Disclosed in the Form S-1 filed 1 September 2026
Texas Scurry County n.a. n.a. announced
Financing

Financing transactions

Transactions that name SB Energy as a party or attach to one of its named sites. Amounts are as stated; overlapping commitments are never summed.

PartiesInstrumentAmountDateSiteSources
NVIDIA + SB Energy + OpenAI
NVIDIA guaranteed SB Energy's PORTS-Pike Technology Campus in Pike County, Ohio to exclusively host NVIDIA AI compute. SB Energy will build, own and operate the campus under a 20-year lease to OpenAI, which has contracted for approximately 8 IT-GW: an initial 4.25 IT-GW plus a 3.75 IT-GW option. Capacity is expected to come online in phases from 2028. SB Energy's registration statement further discloses that the transmission expansion project enabling full planned campus capacity could alone require over $6 billion in credit support, in the form of guaranties or letters of credit.
guarantee ~$105B Announced 17 August 2026 PORTS-Pike Technology Campus (OH)
SB Energy + SoftBank + AEP Ohio
SB Energy and SoftBank committed at least $4.2 billion to new regional grid infrastructure in partnership with AEP Ohio to serve the PORTS-Pike Technology Campus, building power sources supporting 10 GW of energy. At the March 2026 announcement AEP Ohio said power should begin flowing to the campus in 2029, and Commerce Secretary Howard Lutnick called the plan, including 10 GW of new generation of which 9.2 GW is natural gas, a $33 billion power project.
other ≥$4.2B First announced 20 March 2026 by the U.S. Department of Energy, SB Energy and AEP Ohio; restated with the NVIDIA and OpenAI announcements of 17 August 2026 PORTS-Pike Technology Campus (OH)
NVIDIA + SB Energy
Alongside the PORTS-Pike guarantee, NVIDIA made a $1.5 billion equity investment in SB Energy, the SoftBank-backed developer that will build, own and operate the campus. SB Energy's Form S-1/A Amendment No. 2 (21 September 2026) states that NVIDIA has prepaid $1.5 billion under a forward contract to buy non-voting Class N common stock at 90% of the IPO price, settling on completion of the offering, and has separately committed to buy a further $1.5 billion of Class N stock in a concurrent private placement at the IPO price, contingent on and closing with the IPO. In total NVIDIA will invest $3.0 billion in connection with the offering. The amount on this record stays at $1.5 billion; the additional $1.5 billion is contingent on an IPO that was reported delayed on 21 September 2026.
equity raise $1.5B Announced 17 August 2026; terms restated in Form S-1/A Amendment No. 2 filed 21 September 2026 PORTS-Pike Technology Campus (OH)
SB Energy + SoftBank
SB Energy issued $999.0 million aggregate principal amount of 8.875% senior secured notes due 2031 in May 2026 to finance the Cosmos Technology Campus in Travis County, Texas, a facility of approximately 50 MW of critical IT capacity. One of the company's parent entities provided a completion guaranty for the benefit of the noteholders and the tenant. The campus is leased for a 15-year initial term to an affiliate of SoftBank on a triple-net basis with 100% operating expense pass-through and rent set as a percentage return on total project cost with annual escalators and limited tenant termination rights; expected aggregate rent over the initial term is approximately $2.5 billion.
senior notes $999M Issued May 2026, disclosed in the Form S-1 filed 1 September 2026 Cosmos Technology Campus (TX)
SB Energy, Inc. + SoftBank + OpenAI + NVIDIA
SB Energy, Inc. filed a Form S-1 registration statement for an initial public offering of Class A common stock on 1 September 2026. The filing discloses a Data Center Contracted Portfolio of 8.8 GW-IT, comprising 0.8 GW-IT under construction (the Cosmos Technology Campus and Milam County Buildings 1 and 2) and 8.0 GW-IT contracted but not under construction (the PORTS-Pike Technology Campus), against 5.5 GWac of power that is operating, under construction or contracted, of which approximately 2.2 GWac of solar and battery storage was in service at 30 June 2026. No data center capacity is in operation. The company reports approximately $439 billion of backlog ($430 billion data center segment, $10 billion power segment) and approximately $178 billion of backlog-associated capex ($174 billion data center, $4 billion power), and states that approximately $357 billion of the backlog is expected to be recognized beyond 96 months. SoftBank and OpenAI are strategic investors and customers; NVIDIA is a strategic investor and residual value guarantor at PORTS-Pike and is expected to become a holder of Class N common stock in connection with the offering, subject to closing of a concurrent private placement and settlement of a prepaid forward contract. Underwriters named on the cover include J.P. Morgan, Goldman Sachs & Co. LLC, Morgan Stanley, Citigroup and Mizuho. The registration statement records total revenue of $138.7 million and a net loss attributable to SB Energy, Inc. of $3,208.9 million for the six months ended 30 June 2026. SB Energy filed Amendment No. 2 to its Form S-1 on 21 September 2026, still leaving the offering size and price range blank and keeping the proposed Nasdaq and Nasdaq Texas symbol SBE. The amendment states that NVIDIA will invest $3.0 billion in total in connection with the offering, through a $1.5 billion private placement of Class N shares at the offering price and $1.5 billion already prepaid under a forward contract at 90 percent of that price, adds a Citibank agented revolving credit agreement whose $473.0 million initial borrowing is to repay the Hickory Facilities, and says the company targets up to 90 percent debt financing of $8 billion to $9 billion of capital expenditure per building at the PORTS-Pike Technology Campus. Reuters reported on 21 September 2026, citing The New York Times, that SB Energy had delayed its IPO; the company has not confirmed a postponement in any SEC filing.
equity raise n.a. Form S-1 filed 1 September 2026; Amendment No. 2 filed 21 September 2026; delay reported 21 September 2026 (Reuters citing The New York Times), not confirmed by the company n.a.
The record

Sourced facts on SB Energy

  • SB Energy will build, own and operate the PORTS-Pike campus under a 20-year lease to OpenAI, with NVIDIA as the exclusive AI compute provider.
  • OpenAI has contracted for approximately 8 IT-GW at PORTS-Pike: an initial 4.25 IT-GW plus a 3.75 IT-GW option, with first capacity expected in phases from 2028.
  • SB Energy reports a Data Center Contracted Portfolio of 8.8 GW-IT, comprising 0.8 GW-IT under construction (Cosmos and Milam County Buildings 1 and 2) and 8.0 GW-IT contracted but not under construction (PORTS-Pike), with no data center capacity in operation as of the S-1.
  • Backlog of approximately $439 billion, comprising approximately $430 billion in the data center segment and $10 billion in the power segment, with a weighted average remaining contract length of 19.6 years for data center projects and 16.6 years for power projects. The company describes the backlog as a hypothetical estimate based on management's assumptions and not necessarily indicative of future revenue; approximately $357 billion of it is expected to be recognized beyond 96 months.
  • Borden County and Scurry County, Texas together represent approximately 1.7 GW-IT of near-term critical IT capacity in ERCOT with secured interconnection, and are excluded from both the Data Center Contracted Portfolio and the backlog.
  • The company operates under a Foundation Agreement dated 9 January 2026 among OpenAI Infra Holdings, LLC, SB Energy Global and SoftBank Group Corp., amended and restated in its entirety on 17 August 2026.
Sources

Sources for SB Energy

Every source cited on this page, once each. The full atlas source register is at Capital Atlas sources.

REIT and developer: one page each

The figure beside each provider is its count of named sites in the atlas.

Part of the North American Data Center Capital Atlas, refreshed every Tuesday, Thursday and Saturday. Site commitments overlap reported capital expenditure and overlap one another, so this page shows each figure as its source states it and never adds them into a single deployment number. Informational, not investment advice.
The SAVRN reference set

Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.