Novva Data Centers Data Center Capex and Sites

Novva secured $2B of financing led by JPMorgan with Starwood participation for a 175 MW West Jordan, Utah campus, following an earlier $355M CIM Group equity round.

Updated October 8, 2026 1 named site 2 financing transactions 0 sourced facts 3 sources
Novva Data Centers
REIT and developer
Financing regimebank-led project financing (JPMorgan, Starwood) on CIM Group equity backing
Named sites
1
Site-level commitments the atlas ties to Novva Data Centers
Disclosed site capital
$2.0B
Sum of named sites with a stated dollar figure. Not a capex total; see the spending table
Disclosed capacity
175 MW
Sum of named sites with a stated megawatt figure
Financing transactions
2
Transactions naming Novva Data Centers or tied to one of its sites
Spending

Reported and guided spending

Audited, reported and guided figures as the filing or release states them. Reported lines are what was spent; guidance is what management said it expects. They are shown side by side and never combined.

PeriodKindAmountAs statedSources
n.a. raise $2.0B
$2B of financing led by JPMorgan with Starwood participation, for a 175 MW West Jordan, Utah campus
earlier raise $355M
earlier $355M CIM Group equity round
Named sites

Where Novva Data Centers builds

SiteStatePlaceCapitalMWStatusSources
Novva West Jordan campus
Utah West Jordan $2.0B 175 construction
Financing

Financing transactions

Transactions that name Novva Data Centers as a party or attach to one of its named sites. Amounts are as stated; overlapping commitments are never summed.

PartiesInstrumentAmountDateSiteSources
Novva Data Centers + JPMorgan + Starwood
Novva secured $2B of financing led by JPMorgan with Starwood participation for a 175 MW West Jordan, Utah campus.
debt facility $2.0B not dated in source Novva West Jordan campus (UT)
Novva Data Centers + CIM Group
An earlier $355M CIM Group equity round backed Novva's national expansion.
equity raise $355M earlier than the $2B financing n.a.
Sources

Sources for Novva Data Centers

Every source cited on this page, once each. The full atlas source register is at Capital Atlas sources.

REIT and developer: one page each

The figure beside each provider is its count of named sites in the atlas.

Part of the North American Data Center Capital Atlas, refreshed every Tuesday, Thursday and Saturday. Site commitments overlap reported capital expenditure and overlap one another, so this page shows each figure as its source states it and never adds them into a single deployment number. Informational, not investment advice.
The SAVRN reference set

Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.

Have a specific address? Site Intelligence reads all seven references against one location, county, utility and grid operator included, and cites every finding.
Check an address →