Tract Data Center Capex and Sites

Tract's land-banking model is documented at Morris Technology Park, Illinois (343 acres, 1 GW), Caldwell County, Texas (1,515 acres, 2 GW), and Pole Canyon, Utah (844 acres, 1,700 MW). Two of the largest documented losses in the dataset are Tract's: a $14B project in Goodyear/Buckeye, Arizona withdrawn in May 2024, and the $30.0B, 1.5 GW Mooresville, North Carolina project cancelled during due diligence after Mooresville Public Utilities denied capacity allocation, the single largest dollar figure in the cancellation dataset.

Updated October 8, 2026 6 named sites 1 financing transaction 2 sourced facts 9 sources
Tract
REIT and developer
Financing regimeland-banking developer model
Named sites
6
Site-level commitments the atlas ties to Tract
Disclosed site capital
$44.0B
Sum of named sites with a stated dollar figure. Not a capex total; see the spending table
Disclosed capacity
7,100 MW
Sum of named sites with a stated megawatt figure
Financing transactions
1
Transactions naming Tract or tied to one of its sites
Spending

Reported and guided spending

Tract has no reported or guided spending line in the atlas. Its position is recorded through its named sites, its transactions and its sourced facts below.
Named sites

Where Tract builds

SiteStatePlaceCapitalMWStatusSources
Tract Mooresville project
Q4 2024, impact realized 2025
North Carolina Mooresville, Iredell $30.0B 1,500 cancelled
Tract Goodyear/Buckeye project
withdrawn May 2024
Arizona n.a. $14.0B n.a. withdrawn
Tract Caldwell County technology park
Texas Caldwell n.a. 2,000 announced
Tract Pole Canyon technology tract
Utah n.a. n.a. 1,700 announced
Tract Morris Technology Park
Illinois Morris n.a. 1,000 announced
Tract Tuckahoe Creek Technology Park
Community meeting 23 July 2026; reported 28 July 2026
Virginia Goochland County (eastern, near West Creek), Goochland County n.a. 900 announced
Financing

Financing transactions

Transactions that name Tract as a party or attach to one of its named sites. Amounts are as stated; overlapping commitments are never summed.

PartiesInstrumentAmountDateSiteSources
Kodiak Gas Services + unnamed West Texas data center operator (contracted with an investment-grade hyperscaler; lease guaranteed by a GPU designer)
Kodiak Gas Services agreed to provide 76 MW of behind-the-meter, baseload power capacity, including balance of plant, to a West Texas data center for a six-year term, deploying about 40 reciprocating natural gas generation units. The customer is a data center operator contracted with an investment-grade-rated hyperscaler, with a GPU designer as guarantor of the data center lease. Deployment is expected to begin in Q4 2026 and scale into Q1 2027, with revenue recognition starting in Q1 2027. Kodiak said it is its second long-term contract to supply primary power to a data center and that about half of its power portfolio is now under long-term contracts; it targets two gigawatts of power generation capacity by 2030.
power supply agreement n.a. Announced 21 September 2026 (Kodiak release via Business Wire) n.a.
The record

Sourced facts on Tract

  • Tract's Buckeye position remained active as the company shifted focus toward Arizona, despite the withdrawn Goodyear/Buckeye project.
  • Morris Technology Park carries a ComEd transmission service agreement.
Sources

Sources for Tract

Every source cited on this page, once each. The full atlas source register is at Capital Atlas sources.

REIT and developer: one page each

The figure beside each provider is its count of named sites in the atlas.

Part of the North American Data Center Capital Atlas, refreshed every Tuesday, Thursday and Saturday. Site commitments overlap reported capital expenditure and overlap one another, so this page shows each figure as its source states it and never adds them into a single deployment number. Informational, not investment advice.
The SAVRN reference set

Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.