Vultr Data Center Capex and Sites

Vultr announced a financing at a $3.5 billion valuation in December 2024 with LuminArx Capital Management and AMD Ventures, with the round size reported as $333 million. In December 2025 it said it would invest more than $1 billion in a 50MW AI cluster in Springfield, Ohio using 24,000 AMD MI355 chips. Anchor customer contract values are n.a.

Updated October 8, 2026 1 named site 2 financing transactions 2 sourced facts 6 sources
Vultr logo
Vultr
NeoCloud and GPU cloud
Financing regimeprivate growth equity (LuminArx, AMD Ventures) funding balance-sheet AI cluster investment
Named sites
1
Site-level commitments the atlas ties to Vultr
Disclosed site capital
$1.0B
Sum of named sites with a stated dollar figure. Not a capex total; see the spending table
Disclosed capacity
50 MW
Sum of named sites with a stated megawatt figure
Financing transactions
2
Transactions naming Vultr or tied to one of its sites
Spending

Reported and guided spending

Audited, reported and guided figures as the filing or release states them. Reported lines are what was spent; guidance is what management said it expects. They are shown side by side and never combined.

PeriodKindAmountAs statedSources
Dec 2025 guidance ≥$1.0B
More than $1 billion investment in the Springfield, Ohio 50MW AI cluster
Named sites

Where Vultr builds

SiteStatePlaceCapitalMWStatusSources
Springfield AI cluster
with AMD
Ohio Springfield ≥$1.0B 50 announced
Financing

Financing transactions

Transactions that name Vultr as a party or attach to one of its named sites. Amounts are as stated; overlapping commitments are never summed.

PartiesInstrumentAmountDateSiteSources
Vultr + Hewlett Packard Enterprise + AMD
HPE announced at its networking investor day that it secured a $1.2 billion order from Vultr, which it calls the world's largest privately held cloud infrastructure company, to deploy AMD Helios AI Rack by HPE systems with HPE networking hardware and software. The release does not say where the systems will be deployed.
equipment order $1.2B Announced 30 September 2026 (HPE release, Form 8-K Exhibit 99.1) n.a.
Vultr + LuminArx Capital Management + AMD Ventures
Financing with LuminArx Capital Management and AMD Ventures.
equity raise $333M December 2024 n.a.
The record

Sourced facts on Vultr

  • The atlas notes the brief's '$3.5B Series A' conflates valuation with round size; the December 2024 round was reported at $333 million at a $3.5 billion valuation.
  • Anchor customer contract values are n.a. in the fetched record.
Sources

Sources for Vultr

Every source cited on this page, once each. The full atlas source register is at Capital Atlas sources.

NeoCloud and GPU cloud: one page each

The figure beside each provider is its count of named sites in the atlas.

Part of the North American Data Center Capital Atlas, refreshed every Tuesday, Thursday and Saturday. Site commitments overlap reported capital expenditure and overlap one another, so this page shows each figure as its source states it and never adds them into a single deployment number. Informational, not investment advice.
The SAVRN reference set

Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.

Have a specific address? Site Intelligence reads all seven references against one location, county, utility and grid operator included, and cites every finding.
Check an address →