Bitdeer Technologies Group Data Center Capex and Sites
Bitdeer Technologies Group is a Singapore-headquartered, Nasdaq-listed operator converting bitcoin mining capacity to AI and high-performance computing infrastructure in North America. On 1 September 2026 it completed the purchase of approximately 200 acres of greenfield land in Milam County, Texas for approximately $100 million in cash, adjacent to its existing Rockdale facility on land formerly part of an Alcoa aluminum smelting plant. Following the transaction the company states it owns or operates approximately 255 acres and 742 MW of existing and pipeline power capacity in Milam County, against approximately 563 MW of interconnected grid capacity today.
Reported and guided spending
Audited, reported and guided figures as the filing or release states them. Reported lines are what was spent; guidance is what management said it expects. They are shown side by side and never combined.
| Period | Kind | Amount | As stated | Sources |
|---|---|---|---|---|
| 1 September 2026 | reported | ~$100M | Cash purchase price for approximately 200 acres of greenfield land in Milam County, Texas, stated as approximately $100 million |
Where Bitdeer Technologies Group builds
| Site | State | Place | Capital | MW | Status | Sources |
|---|---|---|---|---|---|---|
Rockdale AI/HPC campus (Milam County) Acquisition announced 1 September 2026 |
Texas | Rockdale, Milam County | n.a. | 563 | expansion | |
Bitdeer Massillon mining facility Partially operational as of July 2026; completion expected fall 2026; single-outlet report (The Canton Repository) |
Ohio | Massillon, Stark County | n.a. | 221 | partially operational |
Financing transactions
Transactions that name Bitdeer Technologies Group as a party or attach to one of its named sites. Amounts are as stated; overlapping commitments are never summed.
| Parties | Instrument | Amount | Date | Site | Sources |
|---|---|---|---|---|---|
Bitdeer Technologies Group + Barclays Capital Inc. + Cantor Fitzgerald & Co. + B. Riley Securities, Inc. + BTIG, LLC Bitdeer registered an at-the-market program of up to $1.0 billion of Class A ordinary shares through a syndicate of sales agents. The company said net proceeds, if any, would be used for datacenter expansion, HPC and AI cloud business expansion, and ASIC mining rig development and manufacture, as well as working capital. Bitdeer's North American AI/HPC development includes its Rockdale, Texas site |
at-the-market equity program | $1.0B | Prospectus supplement filed 10 August 2026 | n.a. | |
Bitdeer Technologies Group + U.S. Bank Trust Company, National Association (trustee) Bitdeer priced $325.0 million of 5.00% convertible senior notes due 2032 on 20 February 2026, up from $300.0 million, alongside a registered direct share offering; the initial conversion price is about $9.93 per share. The notes closed on 24 February 2026 and a further $50.0 million was issued on 26 February 2026 when the initial purchasers exercised their option in full. Proceeds paid about $29.2 million of capped calls and about $138.2 million to repurchase $135.0 million of the November 2029 convertible notes, with the remainder for data center expansion, HPC and AI cloud expansion, mining rig development and general corporate purposes. Bitdeer's data center footprint spans the United States and other countries; proceeds are not allocated by site. |
convertible | ~$375M | Backfill (not previously recorded). Priced 20 February 2026 (upsized from $300 million); closed 24 February 2026; option notes issued 26 February 2026 | n.a. | |
Bitdeer Technologies Group Bitdeer completed the acquisition of approximately 200 acres of greenfield property in Milam County, Texas for total consideration of approximately $100 million paid in cash. The parcel adjoins the existing Rockdale facility and was formerly part of an Alcoa aluminum smelting plant. Bitdeer states that following the transaction it owns or operates approximately 255 acres and 742 MW of existing and pipeline power capacity in Milam County, against approximately 563 MW of interconnected grid capacity today. |
acquisition | ~$100M | Announced 1 September 2026 | Rockdale AI/HPC campus (Milam County) (TX) |
Sourced facts on Bitdeer Technologies Group
- The Milam County sites, including the newly acquired parcel, carry approximately 563 MW of interconnected grid capacity with existing plans expected to scale to 742 MW, plus a dedicated water supply.
- The acquired parcel was formerly part of an aluminum smelting plant owned by Alcoa Corporation.
Sources for Bitdeer Technologies Group
Every source cited on this page, once each. The full atlas source register is at Capital Atlas sources.
- globenewswire.comBitdeer press release (GlobeNewswire)
- datacenterdynamics.comDCD
- aol.comThe Canton Repository via AOL, 15 July 2026
- yahoo.comThe Canton Repository via Yahoo, 10 July 2026
- sec.govSEC EDGAR (Bitdeer 424B5)
- sec.govSEC Form 6-K (Bitdeer)
- fool.comThe Motley Fool
- sec.govBitdeer pricing release, Form 6-K Exhibit 99.2 (SEC)
- sec.govBitdeer Form 6-K, 26 February 2026 (SEC)
- technode.globalTNGlobal
NeoCloud and GPU cloud: one page each
The figure beside each provider is its count of named sites in the atlas.
Seven references, one system
Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.